CN107403278A - A kind of Engineering Settlement Whole Process Cost dynamic management approach and system - Google Patents

A kind of Engineering Settlement Whole Process Cost dynamic management approach and system Download PDF

Info

Publication number
CN107403278A
CN107403278A CN201710649849.5A CN201710649849A CN107403278A CN 107403278 A CN107403278 A CN 107403278A CN 201710649849 A CN201710649849 A CN 201710649849A CN 107403278 A CN107403278 A CN 107403278A
Authority
CN
China
Prior art keywords
project
engineering
whole process
construction
process cost
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710649849.5A
Other languages
Chinese (zh)
Inventor
蒲兰芝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hefei Zhe Cheng Project Management Co Ltd
Original Assignee
Hefei Zhe Cheng Project Management Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hefei Zhe Cheng Project Management Co Ltd filed Critical Hefei Zhe Cheng Project Management Co Ltd
Priority to CN201710649849.5A priority Critical patent/CN107403278A/en
Publication of CN107403278A publication Critical patent/CN107403278A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0633Workflow analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • General Business, Economics & Management (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Data Mining & Analysis (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Game Theory and Decision Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of Engineering Settlement Whole Process Cost dynamic management approach and system, pass through Dynamic comparison, analysis, cost plan actual expenses are compared item by item, and analysis deviation, find out deviation place and its reason, satisfactory after correcting is taken according to analysis result, ensures that big deviation will not occur for actual building cost;Engineering is tracked, and Site visa-an important chain system is performed when change in the work occurs, it is ensured that construction quality standard.

Description

A kind of Engineering Settlement Whole Process Cost dynamic management approach and system
Technical field
The present invention relates to Engineering Settlement technical field, specifically a kind of Engineering Settlement Whole Process Cost dynamic management approach and System.
Background technology
Engineering Settlement is directly connected to the vital interests of construction unit and unit in charge of construction.During the editing of clearing due to Status, position residing for editing personnel and purpose are different, and edit and revise the working level of personnel there is also difference, thus edit and revise knot It is sheerly normal different degrees of gap to be present in fruit.But difference is too big, just forces down cost or the possibility of exorbitant estimation and calculation intentionally.
Cost Management is content important in Engineering Settlement, due to total project cost activity it is more, involve a wide range of knowledge, influence because Element is more, only goes analyzing influence factor with system, comprehensive, dynamic viewpoint, and influence factor is implemented to control, can be only achieved The target of engineering construction cost Control pipe, it is rational to determine cost and efficiently control cost.Therefore, the present invention proposes to be directed to item Mesh builds the pricing management of overall process, in the hope of more reasonably carrying out comprehensively, effectively managing to total project cost.
The content of the invention
It is an object of the invention to provide a kind of Engineering Settlement Whole Process Cost dynamic management approach and system, with solution State the problem of being proposed in background technology.
To achieve the above object, the present invention provides following technical scheme:
A kind of Engineering Settlement Whole Process Cost dynamic management approach, comprises the following steps:
S1, predetermined engineering project planned amount invested, and listed subdivision project in the form of form;
S2, investment actual value is contrasted with planned value;
S3, judge that investing actual value and planned value whether there is deviation, if so, then return to step S1, predetermined engineering again Project plan investment, if it is not, then performing step S4;
S4, analysis deviation reason, and use satisfactory after correcting;
S5, follow the trail of project progress;
S6, collect investment actual expenses data;
S7, judge whether invest actual expenses data and planned amount invested has deviation, if so, then performing change examination & approval journey Sequence, if without deviation, carry out project decision.
As the further scheme of the present invention:The change examination and approval procedures are realized by following steps:
The project content for needing visa is reported unit in charge of construction by S91, construction party after construction completion and by self-test;
S92, job site confirms visa project content, and reports engineering management department and project supervision;
S93, project signature list (three parts) is made a report on by unit in charge of construction, and report unit in charge of construction;
S94, project signature list is checked, perform step S95 if confirmation is errorless, otherwise return to step S92, again Confirm visa action and change;
S95, examination & verification is finished to project signature list Unified number, registration, backup, and transfers to unit in charge of construction, engineering management department With each portion of project supervision.
As the further scheme of the present invention:In step S94, by engineering management department and project supervision simultaneously to engineering label Card is singly checked.
As the further scheme of the present invention:After engineering management department and project supervision are simultaneously errorless to the review of project signature list Should be signed confirmation respectively, and be affixed one's seal.
A kind of Engineering Settlement Whole Process Cost dynamic management system, including following four:Organiztion measure, economic measure, skill Art measure and contract measures, the organiztion measure are used for people, task and the function that cost Control is implemented in project management group The division of labor;
The economic measure be used for Dynamic comparison cost planned value and actual value, in work progress carry out cost with Track;
The technical measures are used to carry out arrangement and method for construction technical economic analysis, and close scrutiny supervises the design in each stage;
The contract measures provide construction of contract, and the claim for that may occur provides foundation.
As the further scheme of the present invention:The organiztion measure also include be used for work out the cost Control plan of this stage and Workflow.
As the further scheme of the present invention:The economic measure is based on market competitive bidding comprehensive unit price establishment use of funds meter Draw, it is determined that decomposing control targe, basis is provided for dynamic contrast.
Compared with prior art, the beneficial effects of the invention are as follows:
1st, Dynamic comparison, analysis, cost plan actual expenses are compared item by item, and analysis deviation, find out deviation institute And its reason, satisfactory after correcting is taken according to analysis result, ensures that big deviation will not occur for actual building cost;
2nd, engineering is tracked, and Site visa-an important chain system is performed when change in the work occurs, it is ensured that construction quality mark It is accurate.
Brief description of the drawings
Fig. 1 is a kind of schematic flow sheet of Engineering Settlement Whole Process Cost dynamic management approach.
Fig. 2 is the schematic flow sheet that examination and approval procedures are changed in a kind of Engineering Settlement Whole Process Cost dynamic management approach.
Fig. 3 is a kind of principle schematic of Engineering Settlement Whole Process Cost dynamic management system.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Site preparation describes, it is clear that described embodiment is only part of the embodiment of the present invention, rather than whole embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art are obtained every other under the premise of creative work is not made Embodiment, belong to the scope of protection of the invention.
Refer to Fig. 1~2, in the embodiment of the present invention, a kind of Engineering Settlement Whole Process Cost dynamic management approach, including with Lower step:
S1, predetermined engineering project planned amount invested, and listed subdivision project in the form of form;
S2, investment actual value is contrasted with planned value;
S3, judge that investing actual value and planned value whether there is deviation, if so, then return to step S1, predetermined engineering again Project plan investment, if it is not, then performing step S4;
S4, analysis deviation reason, and use satisfactory after correcting;
S5, follow the trail of project progress;
S6, collect investment actual expenses data;
S7, judge whether invest actual expenses data and planned amount invested has deviation, if so, then performing change examination & approval journey Sequence, if without deviation, carry out project decision.
Change examination and approval procedures are realized by following steps:
The project content for needing visa is reported unit in charge of construction by S91, construction party after construction completion and by self-test;
S92, job site confirms visa project content, and reports engineering management department and project supervision;
S93, project signature list (three parts) is made a report on by unit in charge of construction, and report unit in charge of construction;
S94, project signature list is checked, perform step S95 if confirmation is errorless, otherwise return to step S92, again Confirm visa action and change;
S95, examination & verification is finished to project signature list Unified number, registration, backup, and transfers to unit in charge of construction, engineering management department With each portion of project supervision.
In step S94, project signature list is checked simultaneously by engineering management department and project supervision.
Should sign confirmation respectively after engineering management department and project supervision are simultaneously errorless to the review of project signature list, and affix one's seal.
Refering to Fig. 3,
A kind of Engineering Settlement Whole Process Cost dynamic management system, including following four:Organiztion measure 1, economic measure 2, Technical measures 3 and contract measures 4, the organiztion measure 1 be used to implementing in project management group the people of cost Control, task and Functional division;
Economic measure 2 is used for the planned value and actual value of Dynamic comparison cost, and cost tracking is carried out in work progress;
Technical measures 3 are used to carry out arrangement and method for construction technical economic analysis, and close scrutiny supervises the design in each stage;
Contract measures 4 provide construction of contract, and the claim for that may occur provides foundation.
Organiztion measure 1 also includes being used to work out the cost Control plan of this stage and workflow.
Economic measure 2 is based on market competitive bidding comprehensive unit price establishment fund using plan, it is determined that control targe is decomposed, for dynamic Contrast provides basis.
It is obvious to a person skilled in the art that the invention is not restricted to the details of above-mentioned one exemplary embodiment, Er Qie In the case of without departing substantially from spirit or essential attributes of the invention, the present invention can be realized in other specific forms.Therefore, no matter From the point of view of which point, embodiment all should be regarded as exemplary, and be nonrestrictive, the scope of the present invention is by appended power Profit requires rather than described above limits, it is intended that all in the implication and scope of the equivalency of claim by falling Change is included in the present invention.Any reference in claim should not be considered as to the involved claim of limitation.
Moreover, it will be appreciated that although the present specification is described in terms of embodiments, not each embodiment is only wrapped Containing an independent technical scheme, this narrating mode of specification is only that those skilled in the art should for clarity Using specification as an entirety, the technical solutions in the various embodiments may also be suitably combined, forms those skilled in the art It is appreciated that other embodiment.

Claims (7)

1. a kind of Engineering Settlement Whole Process Cost dynamic management approach, it is characterised in that comprise the following steps:
S1, predetermined engineering project planned amount invested, and listed subdivision project in the form of form;
S2, investment actual value is contrasted with planned value;
S3, judge that investing actual value and planned value whether there is deviation, if so, then return to step S1, predetermined engineering project again Planned amount invested, if it is not, then performing step S4;
S4, analysis deviation reason, and use satisfactory after correcting;
S5, follow the trail of project progress;
S6, collect investment actual expenses data;
S7, judge whether invest actual expenses data and planned amount invested has deviation, if so, change examination and approval procedures are then performed, if There is no deviation, then carry out project decision.
A kind of 2. Engineering Settlement Whole Process Cost dynamic management approach according to claim 1, it is characterised in that the change More examination and approval procedures are realized by following steps:
The project content for needing visa is reported unit in charge of construction by S91, construction party after construction completion and by self-test;
S92, job site confirms visa project content, and reports engineering management department and project supervision;
S93, project signature list (three parts) is made a report on by unit in charge of construction, and report unit in charge of construction;
S94, project signature list is checked, perform step S95 if confirmation is errorless, otherwise return to step S92, reaffirm Visa action is simultaneously changed;
S95, examination & verification is finished to project signature list Unified number, registration, backup, and transfers to unit in charge of construction, engineering management department and work Each portion of journey management.
A kind of 3. Engineering Settlement Whole Process Cost dynamic management approach according to claim 2, it is characterised in that:In step In S94, project signature list is checked simultaneously by engineering management department and project supervision.
A kind of 4. Engineering Settlement Whole Process Cost dynamic management approach according to claim 3, it is characterised in that:Engineering pipe Should sign confirmation respectively after reason portion and project supervision are simultaneously errorless to the review of project signature list, and affix one's seal.
5. a kind of Engineering Settlement Whole Process Cost dynamic management system, it is characterised in that including following four:Organiztion measure (1), Economic measure (2), technical measures (3) and contract measures (4), the organiztion measure (1) are used to implement in project management group People, task and the Functional division of cost Control;
The economic measure (2) is used for the planned value and actual value of Dynamic comparison cost, and cost tracking is carried out in work progress;
The technical measures (3) are used to carry out arrangement and method for construction technical economic analysis, and close scrutiny supervises the design in each stage;
The contract measures (4) provide construction of contract, and the claim for that may occur provides foundation.
A kind of 6. Engineering Settlement Whole Process Cost dynamic management system according to claim 5, it is characterised in that:Described group Knitting measure (1) also includes being used to work out the cost Control plan of this stage and workflow.
A kind of 7. Engineering Settlement Whole Process Cost dynamic management system according to claim 5, it is characterised in that:The warp Ji measure (2) is based on market competitive bidding comprehensive unit price establishment fund using plan, it is determined that decomposing control targe, is provided for dynamic contrast Basis.
CN201710649849.5A 2017-08-02 2017-08-02 A kind of Engineering Settlement Whole Process Cost dynamic management approach and system Pending CN107403278A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710649849.5A CN107403278A (en) 2017-08-02 2017-08-02 A kind of Engineering Settlement Whole Process Cost dynamic management approach and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710649849.5A CN107403278A (en) 2017-08-02 2017-08-02 A kind of Engineering Settlement Whole Process Cost dynamic management approach and system

Publications (1)

Publication Number Publication Date
CN107403278A true CN107403278A (en) 2017-11-28

Family

ID=60402570

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710649849.5A Pending CN107403278A (en) 2017-08-02 2017-08-02 A kind of Engineering Settlement Whole Process Cost dynamic management approach and system

Country Status (1)

Country Link
CN (1) CN107403278A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108256821A (en) * 2017-12-14 2018-07-06 中国航空规划设计研究总院有限公司 A kind of management method of construction project overall process various dimensions cost management system
CN111080239A (en) * 2019-11-29 2020-04-28 中国电力企业联合会电力建设技术经济咨询中心 Real-time dynamic tracking method and device for construction cost
CN111523928A (en) * 2019-03-21 2020-08-11 广州翔实工程咨询有限公司 Automatic pre-settlement system and method for single-party settlement
CN111724141A (en) * 2020-06-29 2020-09-29 张群 Dynamic management method for construction cost in whole process of engineering cost settlement
CN112036815A (en) * 2020-08-20 2020-12-04 湖北四位元电力有限公司 Method for establishing power distribution network engineering cost index system

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108256821A (en) * 2017-12-14 2018-07-06 中国航空规划设计研究总院有限公司 A kind of management method of construction project overall process various dimensions cost management system
CN111523928A (en) * 2019-03-21 2020-08-11 广州翔实工程咨询有限公司 Automatic pre-settlement system and method for single-party settlement
CN111080239A (en) * 2019-11-29 2020-04-28 中国电力企业联合会电力建设技术经济咨询中心 Real-time dynamic tracking method and device for construction cost
CN111080239B (en) * 2019-11-29 2021-03-26 中国电力企业联合会电力建设技术经济咨询中心 Real-time dynamic tracking method and device for construction cost
CN111724141A (en) * 2020-06-29 2020-09-29 张群 Dynamic management method for construction cost in whole process of engineering cost settlement
CN112036815A (en) * 2020-08-20 2020-12-04 湖北四位元电力有限公司 Method for establishing power distribution network engineering cost index system

Similar Documents

Publication Publication Date Title
CN107403278A (en) A kind of Engineering Settlement Whole Process Cost dynamic management approach and system
CN114493213A (en) Carbon emission data acquisition and processing method based on Internet of things
Franks et al. Cumulative social impacts
CN108537519A (en) A kind of architectural design method based on BIM
CN107169709A (en) The one-stop management method of building trade and its management platform
CN113112233A (en) BIM-based intelligent management method and platform for full life cycle of wind power project
Gade A proposed solution to the problem of construction industry overruns: lean construction techniques and linear programming
Liu Research on the management system of enterprises using modern logistics supply chain theory
CN105512814A (en) Online data analysis method for material supply chain
Alotabi et al. Identification of social responsibility factors within mega construction projects
CN117078209A (en) Method, system and device for managing supervision project and computer storage medium
Nhung et al. Deepening Analysis on Internal Control Procedures of Cost Estimation Design in Road and Bridge Construction Units-and the Relation with Internal Audit
Paucar et al. Development of a Lean Manufacturing and SLP-based System for a Footwear Company
Saad et al. Fundamentals of construction project management
Kamalan et al. Root Cause Analysis of Delays in Dam Construction (Case Studies: Karun-3, Marun, Shafaroud and Jamishan Dams)
Weng et al. Quality data collection and management technology of aerospace complex product assembly process
Ali et al. Evaluating risk management practices in the pakistani construction industry: The current state of play
Ostadi et al. A practical self-assessment framework for evaluation of maintenance management system based on RAMS model and maintenance standards
Brander et al. Greenhouse gas emissions and infrastructure investment decisions
Khoa et al. Investigating the impact of social capital on SC resilience and SC performance.
Vijayan et al. A Study of Implementing Lean & Fast Tracking in Construction Project Management
Furtado et al. Improving the production process for a medical device manufacturing company using Monte Carlo simulation
Borkowski A framework for risk analysis in infrastructure projects
Koppenhoefer et al. Managing and Controlling Decentralized Corporate Energy Systems-Transferring Best-practice Methods to the Energy Domain
Jayadi et al. The Development of 4D BIM Based Infrastructure Construction Time Planning Standard Operating Procedure to Enhance Communication Quality from Infrastructure Contractor Perspective

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20171128