CN107394890A CN201710532276.8A CN201710532276A CN107394890A CN 107394890 A CN107394890 A CN 107394890A CN 201710532276 A CN201710532276 A CN 201710532276A CN 107394890 A CN107394890 A CN 107394890A
Authority
CN
China
Prior art keywords
electricity
target
time section
history
period
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710532276.8A
Other languages
Chinese (zh)
Inventor
滕智帆
马小珊
粟世玮
夏良宇
高顿
曹成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Three Gorges University CTGU
Original Assignee
China Three Gorges University CTGU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Three Gorges University CTGU filed Critical China Three Gorges University CTGU
Priority to CN201710532276.8A priority Critical patent/CN107394890A/en
Publication of CN107394890A publication Critical patent/CN107394890A/en
Pending legal-status Critical Current

Links

Classifications

    • H02J13/0006

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

A kind of electricity dispatching method and device, when needing to dispatch electricity to target area in target time section, obtain the season where target time section;Obtain the history dispatched in target time section in historical process, within season to target area and averagely dispatch electricity;Electricity is averagely dispatched according to history and determines target dispatch electricity;In the initial time of target time section, start to dispatch electricity to target area regulation goal.Because different seasons is in a period of time inconsistent using electricity, therefore, the present invention has gathered the season where target time section, and then compared to prior art, power demand of the target area in target time section can accurately be determined, and then accurately electricity is dispatched to target area in target time section, be not in waste electricity or the not enough situation of electricity occur.

Description

A kind of electricity dispatching method and device
Technical field
The present invention relates to Dispatch of electric net and electric power technical field, specifically a kind of electricity dispatching method and device.
Background technology
Dispatch of electric net and electric power is to ensure power network safety operation, external reliable power supply, the work of all kinds of power generations The management means for carrying out and using in order.Currently, power network is generally divided into multiple regions, in any one period, when need When giving a certain subdispatch electricity, typically according in historical process in the period, the average electricity to the subdispatch Measure to determine currently to need the electricity to the subdispatch in the period.For example, in historical process daily 12 points ~ 13 points it Between, it is 10000W to the average electricity dispatched in the region, then gives subdispatch 10000W's between 12 points ~ 13 points today Electricity.However, determined currently in the time to the average electricity of the subdispatch in the period according in historical process When section needs the electricity to the subdispatch, the inaccurate situation of the electricity of scheduling usually occurs, such as:The electricity mistake of scheduling It is cause to waste electricity more;Or the electricity of scheduling not enough influences normal work and life.
The content of the invention
In order to solve the above technical problems, the present invention provides a kind of electricity dispatching method and device, target time section is gathered The season at place, and then compared to prior art, can accurately determine power demand of the target area in target time section. Accurately electricity is dispatched to target area in target time section, is not in waste electricity or the not enough feelings of electricity occurs Condition.
The technical scheme that the present invention takes is:
A kind of electricity dispatching method, comprises the following steps:
When needing to dispatch electricity to target area in target time section, the season where the target time section is obtained;
Obtain the history dispatched in the target time section in historical process, within the season to the target area Averagely dispatch electricity;
Electricity is averagely dispatched according to the history and determines target dispatch electricity;
In the initial time of the target time section, start to dispatch the target dispatch electricity to the target area.
Further, obtain pre-set with the target area and the season simultaneously the corresponding, period with History averagely dispatches the corresponding relation between electricity, and the history corresponding with the target time section is searched in corresponding relation and is put down Dispatch electricity.
During the target dispatch electricity is dispatched to the target area, the target area is obtained in the mesh Mark the actual use electricity in the first sub- period in the period;
History of the target area in historical process in the first sub- period in the target time section is obtained to be averaged Use electricity;
If the history that actual use electricity was less than in the first sub- period averagely uses electricity, in the described first sub- period The scheduling electricity to the target area is reduced in the second sub- period afterwards;
If the history that actual use electricity was more than in the first sub- period averagely uses electricity, in the described first sub- period Increase the scheduling electricity to the target area in the second sub- period afterwards.
In the finish time of the target time section, count in the target time section to the reality of the target area Dispatch electricity in border;
Electricity and actual schedule electricity are averagely dispatched according to the history, update in the corresponding relation with the object time The corresponding history of section averagely dispatches electricity.
A kind of electricity dispatching device, the device include:
First acquisition module, for when needing to dispatch electricity to target area in target time section, obtaining the object time Season where section;
Second acquisition module, for obtaining in the target time section in historical process, within the season to described The history of target area scheduling averagely dispatches electricity;
Determining module, target dispatch electricity is determined for averagely dispatching electricity according to the history;
Scheduler module, for the initial time in the target time section, start to dispatch the target tune to the target area Spend electricity.
Second acquisition module includes:
Acquiring unit, for obtain pre-set with the target area and the season simultaneously the corresponding, period with History averagely dispatches the corresponding relation between electricity;
Searching unit, electricity is averagely dispatched for searching the history corresponding with the target time section in the corresponding relation Amount.
The device includes:
3rd acquisition module, for during the target dispatch electricity is dispatched to the target area, obtaining the mesh Mark actual use electricity of the region in the first sub- period in the target time section;
4th acquisition module, for obtaining first period of the day from 11 p.m. to 1 a.m of the target area in historical process in the target time section Between history in section averagely use electricity;
Module is reduced, if being less than the history in the first sub- period for the actual use electricity averagely uses electricity, The scheduling electricity to the target area is reduced in the second sub- period after the described first sub- period;
Increase module, if being more than the history in the first sub- period for the actual use electricity averagely uses electricity, Increase the scheduling electricity to the target area in the second sub- period after the described first sub- period.
Second acquisition module includes:
Statistic unit, in the finish time of the target time section, counting in the target time section to the mesh Mark the actual schedule electricity in region;
Updating block, for averagely dispatching electricity and the actual schedule electricity according to the history, update the corresponding relation In the history corresponding with the target time section averagely dispatch electricity.
A kind of electricity dispatching method of the present invention and device, when needing to dispatch electricity to target area in target time section, Obtain the season where target time section;Obtain in target time section in historical process, within season to target area The history of scheduling averagely dispatches electricity;Electricity is averagely dispatched according to history and determines target dispatch electricity;In rising for target time section Begin the moment, start to dispatch electricity to target area regulation goal.Because different seasons is use in a period of time Electricity is inconsistent, and therefore, the present invention has gathered the season where target time section, and then compared to prior art, Ke Yijing Power demand of the target area in target time section is determined accurately, and then is dispatched accurately to target area in target time section Electricity, be not in waste electricity or the not enough situation of electricity occur.
Brief description of the drawings
Accompanying drawing herein is merged in specification and forms the part of this specification, shows the implementation for meeting the present invention Example, and be used to together with specification to explain the principle of the embodiment of the present invention.
Fig. 1 is a kind of flow chart of electricity dispatching method according to an exemplary embodiment;
Fig. 2 is a kind of flow chart of electricity dispatching method according to an exemplary embodiment;
Fig. 3 is a kind of block diagram of electricity dispatching device according to an exemplary embodiment.
Embodiment
A kind of electricity dispatching method, comprises the following steps:
When needing to dispatch electricity to target area in target time section, the season where the target time section is obtained;
Obtain the history dispatched in the target time section in historical process, within the season to the target area Averagely dispatch electricity;
Electricity is averagely dispatched according to the history and determines target dispatch electricity;
In the initial time of the target time section, start to dispatch the target dispatch electricity to the target area.
Further:Obtain pre-set with the target area and the season simultaneously the corresponding, period with History averagely dispatches the corresponding relation between electricity, and the history corresponding with the target time section is searched in corresponding relation and is put down Dispatch electricity.
During the target dispatch electricity is dispatched to the target area, the target area is obtained in the mesh Mark the actual use electricity in the first sub- period in the period;
History of the target area in historical process in the first sub- period in the target time section is obtained to be averaged Use electricity;
If the history that actual use electricity was less than in the first sub- period averagely uses electricity, in the described first sub- period The scheduling electricity to the target area is reduced in the second sub- period afterwards;
If the history that actual use electricity was more than in the first sub- period averagely uses electricity, in the described first sub- period Increase the scheduling electricity to the target area in the second sub- period afterwards.
In the finish time of the target time section, count in the target time section to the reality of the target area Dispatch electricity in border;
Electricity and actual schedule electricity are averagely dispatched according to the history, update in the corresponding relation with the object time The corresponding history of section averagely dispatches electricity.
A kind of electricity dispatching device, the device include:
First acquisition module 11, for when need target time section to target area dispatch electricity when, when obtaining the target Between season where section;
Second acquisition module 12, for obtaining in the target time section in historical process, within the season to institute The history for stating target area scheduling averagely dispatches electricity;
Determining module 13, target dispatch electricity is determined for averagely dispatching electricity according to the history;
Scheduler module 14, for the initial time in the target time section, start to dispatch the target to the target area Dispatch electricity.
Second acquisition module 12 includes:
Acquiring unit, for obtain pre-set with the target area and the season simultaneously the corresponding, period with History averagely dispatches the corresponding relation between electricity;
Searching unit, electricity is averagely dispatched for searching the history corresponding with the target time section in the corresponding relation Amount.
The device includes:
3rd acquisition module, for during the target dispatch electricity is dispatched to the target area, obtaining the mesh Mark actual use electricity of the region in the first sub- period in the target time section;
4th acquisition module, for obtaining first period of the day from 11 p.m. to 1 a.m of the target area in historical process in the target time section Between history in section averagely use electricity;
Module is reduced, if being less than the history in the first sub- period for the actual use electricity averagely uses electricity, The scheduling electricity to the target area is reduced in the second sub- period after the described first sub- period;
Increase module, if being more than the history in the first sub- period for the actual use electricity averagely uses electricity, Increase the scheduling electricity to the target area in the second sub- period after the described first sub- period.
Second acquisition module 12 includes:
Statistic unit, in the finish time of the target time section, counting in the target time section to the mesh Mark the actual schedule electricity in region;
Updating block, for averagely dispatching electricity and the actual schedule electricity according to the history, update the corresponding relation In the history corresponding with the target time section averagely dispatch electricity.
Fig. 1 is a kind of flow chart of electricity dispatching method according to an exemplary embodiment, as shown in figure 1, the party Method is used in terminal, and this method comprises the following steps.
In step S101, when needing to dispatch electricity to target area in target time section, target time section institute is obtained Season;
In embodiments of the present invention, season includes spring, summer, fall and winter.
Target time section can be day, hour or minute etc..For example, a target time section is 1 day, or, one day Include 24 target time sections, each target time section is 1 hour etc..The embodiment of the present invention is using target time section as one Illustrated within one hour in it, but not as the limitation to protection domain of the embodiment of the present invention.
Wherein, the date that the different seasons that technical staff in advance can be in being locally located 1 year include.For example, respectively Date set corresponding to four seasons is set, by the date storage that each season includes in the corresponding date gathers.For example, , can be by date storage that summer includes in date set corresponding to summer for summer.
In this way, when needing to dispatch electricity to target area in target time section, where can obtaining target time section Date.Then the date is searched in gathering four dates, using season corresponding to the date set for being stored with the date as mesh Mark the season where the period.For example, it is assumed that target time section is 12 points ~ 13 points, the date where target time section is June 13 Day, if finding June 13 in date set corresponding to summer, using summer as the season where target time section, If finding June 13 in date set corresponding to spring, using spring as the season where target time section, if June is found in corresponding date set 13, then using autumn as the season where target time section, if in the winter in the fall June is found in date set corresponding to season 13, then using winter as the season where target time section.
In step s 102, obtain in target time section in historical process, within season and dispatched to target area History averagely dispatch electricity;
For any one season, each target time section in historical process, within the season can be counted in advance The scheduling electricity inside dispatched respectively to target area, then calculate what is dispatched respectively to target area in each target time section The average value of electricity is dispatched, electricity is averagely dispatched as the history dispatched in the target time section within the season to target area Amount, and target time section and the history being calculated averagely are dispatched into electricity and form a record, and be stored in locally in advance What is set averagely dispatches the corresponding relation between electricity with target area and the season while corresponding, period and history In.
In this way, in this step, can obtain pre-set with target area and season corresponding, period simultaneously The corresponding relation between electricity is averagely dispatched with history;Then the history corresponding with target time section is searched in corresponding relation Averagely dispatch electricity.
In step s 103, electricity is averagely dispatched according to history and determines target dispatch electricity;
In an embodiment of the invention, history can averagely be dispatched to electricity directly as target dispatch electricity.
In an alternative embodiment of the invention, obtain target area in Current Temperatures, obtain it is in historical process, in season History mean temperature in target time section in section;
When Current Temperatures are more than history mean temperature, if the season where target time section is summer, due in order to cool, Using the customer volume increase of air-conditioning, therefore in order that electricity is obtained enough using, it is necessary on the basis of history averagely dispatches electricity Increase scheduling electricity, to obtain target dispatch electricity.For example, history averagely to be dispatched to electricity and a multiplication, mesh is obtained Mark scheduling electricity, coefficient can be 1.1,1.2 or 1.25 etc., and the embodiment of the present invention is not limited to this.If during target Between season where section be winter, then heated without using air-conditioning, therefore, in order to avoid wasting electricity, it is necessary to be put down in history Electricity is dispatched in reduction on the basis of dispatching electricity, to obtain target dispatch electricity.For example, history is averagely dispatched into electricity and one Individual multiplication, target dispatch electricity is obtained, coefficient can be 0.9,0.8 or 0.85 etc., and the embodiment of the present invention is not added with to this To limit.
When Current Temperatures are less than history mean temperature, if the season where target time section is summer, due in order to It is warming, using the customer volume increase of air-conditioning, therefore in order that electricity is obtained enough using, it is necessary to averagely dispatch the base of electricity in history Increase scheduling electricity on plinth, to obtain target dispatch electricity.For example, history averagely to be dispatched to electricity and a multiplication, obtain To target dispatch electricity, coefficient can be 1.1,1.2 or 1.25 etc., and the embodiment of the present invention is not limited to this.If mesh Season where marking the period is winter, then cools without using air-conditioning, therefore, in order to avoid wasting electricity, it is necessary to go through History reduces scheduling electricity on the basis of averagely dispatching electricity, to obtain target dispatch electricity.For example, history is averagely dispatched into electricity With a multiplication, target dispatch electricity is obtained, coefficient can be 0.9,0.8 or 0.85 etc., and the embodiment of the present invention is to this It is not limited.
When Current Temperatures are equal to history mean temperature, then no matter the season where target time section be summer, spring, the autumn Season or winter, can be directly by history all without increasing or decreasing scheduling electricity on the basis of history averagely dispatches electricity Electricity is averagely dispatched directly as target dispatch electricity.
In step S104, in the initial time of target time section, start to dispatch electricity to target area regulation goal.
Further, in order to dispatch electricity to target area in target time section afterwards exactly, in target , it is necessary to count in target time section to the actual schedule electricity of target area during the finish time of period;Put down according to history Electricity and actual schedule electricity are dispatched, the history corresponding with target time section updated in corresponding relation averagely dispatches electricity Amount.
In embodiments of the present invention, when needing to dispatch electricity to target area in target time section, the object time is obtained Season where section;The history dispatched to target area in target time section in historical process, within season is obtained to put down Dispatch electricity;Electricity is averagely dispatched according to history and determines target dispatch electricity;In the initial time of target time section, start to Target area regulation goal scheduling electricity.Because different seasons is in a period of time inconsistent using electricity, Therefore, the season where set of embodiment of the present invention target time section, and then compared to prior art, can accurately determine Go out power demand of the target area in target time section, and then accurately electricity is dispatched to target area in target time section, no Waste electricity occurs or the not enough situation of electricity occurs.
Further, in an alternative embodiment of the invention, in order to avoid dispatching electricity to target area regulation goal During, electricity may be more accurately dispatched, avoids wasting electricity or the not enough situation of electricity occurs, should referring to Fig. 2 Method also includes:
In step s 201, during electricity is dispatched to target area regulation goal, target area is obtained in the object time The actual use electricity in the first sub- period in section;
In embodiments of the present invention, target time section can be divided into multiple adjacent sub- periods, each sub- period it Between it is misaligned.For example, it is assumed that target time section is 12 points ~ 13 points, then 12 points 0 minute ~ 12: 15 can be allocated as a period of the day from 11 p.m. to 1 a.m Between section, 12 points 15 minutes ~ 12: 30 were allocated as a sub- period, 12 points 30 minutes ~ 12: 45 were allocated as a sub- period, 12 points 45 minutes ~ 13: 0 were allocated as a sub- period.Or using every 5 minutes as a sub- period.
In embodiments of the present invention, target area can Real-time Feedback actual use electricity.At the end of the first sub- period, Count the actual use electricity within the first sub- period.
In step S202, the target area in historical process is obtained in the first sub- period in target time section History averagely uses electricity;
In embodiments of the present invention, for any one season, can count in advance target area in historical process, at this The history in each sub- period in each target time section in season averagely actually uses electricity, and is stored in this Ground.Therefore, can be from the local target area directly obtained in historical process in the first sub- period in target time section History averagely use electricity.
In step S203, if the history that actual use electricity was less than in the first sub- period averagely uses electricity, The scheduling electricity to target area is reduced in the second sub- period after the first sub- period;
Wherein, if the history that actual use electricity was less than in the first sub- period averagely uses electricity, illustrate in the first son The history in the first sub- period that power demand in period is less than in historical process averagely uses electricity, in order to avoid wave Power-consuming amount, then it can reduce the scheduling electricity to target area.
In step S204, if the history that actual use electricity was more than in the first sub- period averagely uses electricity, Increase the scheduling electricity to target area in the second sub- period after the first sub- period.
Wherein, if the history that actual use electricity was more than in the first sub- period averagely uses electricity, illustrate the The history in the first sub- period that power demand in one sub- period is more than in historical process averagely uses electricity, in order to full Sufficient power demand, then it can increase the scheduling electricity to target area.
Fig. 3 is a kind of block diagram of electricity dispatching device according to an exemplary embodiment.Reference picture 3, the device bag Include:
First acquisition module 11, for when need target time section to target area dispatch electricity when, when obtaining the target Between season where section;
Second acquisition module 12, for obtaining in the target time section in historical process, within the season to institute The history for stating target area scheduling averagely dispatches electricity;
Determining module 13, target dispatch electricity is determined for averagely dispatching electricity according to the history;
Scheduler module 14, for the initial time in the target time section, start to dispatch the target to the target area Dispatch electricity.
Wherein, second acquisition module 12 includes:
Acquiring unit, for obtain pre-set with the target area and the season simultaneously the corresponding, period with History averagely dispatches the corresponding relation between electricity;
Searching unit, electricity is averagely dispatched for searching the history corresponding with the target time section in the corresponding relation Amount.
Further, described device includes:
3rd acquisition module, for during the target dispatch electricity is dispatched to the target area, obtaining the mesh Mark actual use electricity of the region in the first sub- period in the target time section;
4th acquisition module, for obtaining first period of the day from 11 p.m. to 1 a.m of the target area in historical process in the target time section Between history in section averagely use electricity;
Module is reduced, if being less than the history in the first sub- period for the actual use electricity averagely uses electricity, The scheduling electricity to the target area is reduced in the second sub- period after the described first sub- period;
Increase module, if being more than the history in the first sub- period for the actual use electricity averagely uses electricity, Increase the scheduling electricity to the target area in the second sub- period after the described first sub- period.
Further, second acquisition module 12 also includes:
Statistic unit, in the finish time of the target time section, counting in the target time section to the mesh Mark the actual schedule electricity in region;
Updating block, for averagely dispatching electricity and the actual schedule electricity according to the history, update the corresponding relation In the history corresponding with the target time section averagely dispatch electricity.
In embodiments of the present invention, when needing to dispatch electricity to target area in target time section, the object time is obtained Season where section;The history dispatched to target area in target time section in historical process, within season is obtained to put down Dispatch electricity;Electricity is averagely dispatched according to history and determines target dispatch electricity;In the initial time of target time section, start to Target area regulation goal scheduling electricity.Because different seasons is in a period of time inconsistent using electricity, Therefore, the season where set of embodiment of the present invention target time section, and then compared to prior art, can accurately determine Go out power demand of the target area in target time section, and then accurately electricity is dispatched to target area in target time section, no Waste electricity occurs or the not enough situation of electricity occurs.
On the device in above-described embodiment, wherein modules perform the concrete mode of operation in relevant this method Embodiment in be described in detail, explanation will be not set forth in detail herein.
Those skilled in the art will readily occur to the present invention its after considering specification and putting into practice invention disclosed herein Its embodiment.The application is intended to any modification, purposes or the adaptations of the embodiment of the present invention, these modifications, Purposes or adaptations follow the general principle of the embodiment of the present invention and including undocumented skills of the embodiment of the present invention Common knowledge or conventional techniques in art field.Description and embodiments are considered only as exemplary, the embodiment of the present invention True scope and spirit pointed out by appended claim.
It should be appreciated that the accurate knot that the embodiment of the present invention is not limited to be described above and is shown in the drawings Structure, and various modifications and changes can be being carried out without departing from the scope.The scope of the embodiment of the present invention is only by appended right It is required that to limit.

Claims (8)

1. a kind of electricity dispatching method, it is characterised in that comprise the following steps:
When needing to dispatch electricity to target area in target time section, the season where the target time section is obtained;
Obtain the history dispatched in the target time section in historical process, within the season to the target area Averagely dispatch electricity;
Electricity is averagely dispatched according to the history and determines target dispatch electricity;
In the initial time of the target time section, start to dispatch the target dispatch electricity to the target area.
A kind of 2. electricity dispatching method according to claim 1, it is characterised in that:Obtain pre-setting with the target area Domain and the season while corresponding, period and history averagely dispatch the corresponding relation between electricity, in corresponding relation Search the history corresponding with the target time section and averagely dispatch electricity.
A kind of 3. electricity dispatching method according to claim 1, it is characterised in that:The mesh is being dispatched to the target area During mark scheduling electricity, obtain the target area actually makes in the first sub- period in the target time section Power consumption;
History of the target area in historical process in the first sub- period in the target time section is obtained to be averaged Use electricity;
If the history that actual use electricity was less than in the first sub- period averagely uses electricity, in the described first sub- period The scheduling electricity to the target area is reduced in the second sub- period afterwards;
If the history that actual use electricity was more than in the first sub- period averagely uses electricity, in the described first sub- period Increase the scheduling electricity to the target area in the second sub- period afterwards.
A kind of 4. electricity dispatching method according to claim 1, it is characterised in that:In the finish time of the target time section When, count in the target time section to the actual schedule electricity of the target area;
Electricity and actual schedule electricity are averagely dispatched according to the history, update in the corresponding relation with the object time The corresponding history of section averagely dispatches electricity.
5. a kind of electricity dispatching device, it is characterised in that the device includes:
First acquisition module(11), for when needing to dispatch electricity to target area in target time section, obtaining the target Season where period;
Second acquisition module(12), for obtain in the historical process, target time section within the season to The history of the target area scheduling averagely dispatches electricity;
Determining module(13), target dispatch electricity is determined for averagely dispatching electricity according to the history;
Scheduler module(14), for the initial time in the target time section, start to dispatch the mesh to the target area Mark scheduling electricity.
A kind of 6. electricity dispatching device according to claim 5, it is characterised in that second acquisition module(12)Including:
Acquiring unit, for obtain pre-set with the target area and the season simultaneously the corresponding, period with History averagely dispatches the corresponding relation between electricity;
Searching unit, electricity is averagely dispatched for searching the history corresponding with the target time section in the corresponding relation Amount.
7. a kind of electricity dispatching device according to claim 5, it is characterised in that the device includes:
3rd acquisition module, for during the target dispatch electricity is dispatched to the target area, obtaining the mesh Mark actual use electricity of the region in the first sub- period in the target time section;
4th acquisition module, for obtaining first period of the day from 11 p.m. to 1 a.m of the target area in historical process in the target time section Between history in section averagely use electricity;
Module is reduced, if being less than the history in the first sub- period for the actual use electricity averagely uses electricity, The scheduling electricity to the target area is reduced in the second sub- period after the described first sub- period;
Increase module, if being more than the history in the first sub- period for the actual use electricity averagely uses electricity, Increase the scheduling electricity to the target area in the second sub- period after the described first sub- period.
A kind of 8. electricity dispatching device according to claim 5, it is characterised in that second acquisition module(12)Including:
Statistic unit, in the finish time of the target time section, counting in the target time section to the mesh Mark the actual schedule electricity in region;
Updating block, for averagely dispatching electricity and the actual schedule electricity according to the history, update the corresponding relation In the history corresponding with the target time section averagely dispatch electricity.
CN201710532276.8A 2017-07-03 2017-07-03 A kind of electricity dispatching method and device Pending CN107394890A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710532276.8A CN107394890A (en) 2017-07-03 2017-07-03 A kind of electricity dispatching method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710532276.8A CN107394890A (en) 2017-07-03 2017-07-03 A kind of electricity dispatching method and device

Publications (1)

Publication Number Publication Date
CN107394890A true CN107394890A (en) 2017-11-24

Family

ID=60334186

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710532276.8A Pending CN107394890A (en) 2017-07-03 2017-07-03 A kind of electricity dispatching method and device

Country Status (1)

Country Link
CN (1) CN107394890A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103489077A (en) * 2013-09-30 2014-01-01 无锡清华信息科学与技术国家实验室物联网技术中心 Electric appliance task dispatching method and electric appliance task dispatching device
CN103530701A (en) * 2013-10-12 2014-01-22 国家电网公司 User month electricity consumption predicating method and system based on seasonal index method
CN104392274A (en) * 2014-10-29 2015-03-04 南京南瑞集团公司 Urban short-term electrical load prediction method based on trend of electrical load and temperature
CN104467029A (en) * 2014-11-25 2015-03-25 国家电网公司 Regional small hydropower and wind power day combined optimization and dispatching method
CN104504619A (en) * 2015-01-05 2015-04-08 国家电网公司 Temperature/ economic growth factor considered monthly total electricity consumption predication method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103489077A (en) * 2013-09-30 2014-01-01 无锡清华信息科学与技术国家实验室物联网技术中心 Electric appliance task dispatching method and electric appliance task dispatching device
CN103530701A (en) * 2013-10-12 2014-01-22 国家电网公司 User month electricity consumption predicating method and system based on seasonal index method
CN104392274A (en) * 2014-10-29 2015-03-04 南京南瑞集团公司 Urban short-term electrical load prediction method based on trend of electrical load and temperature
CN104467029A (en) * 2014-11-25 2015-03-25 国家电网公司 Regional small hydropower and wind power day combined optimization and dispatching method
CN104504619A (en) * 2015-01-05 2015-04-08 国家电网公司 Temperature/ economic growth factor considered monthly total electricity consumption predication method

Similar Documents

Publication Publication Date Title
JP6193400B2 (en) Electric power demand prediction system, electric power demand prediction method, customer profiling system, and customer profiling method
CN110378522A (en) Method, apparatus, storage medium and the electronic equipment of prediction dispatching status information
US10223167B2 (en) Discrete resource management
CN103927616B (en) Collector associates the method with electric energy meter rotation
JP3783929B2 (en) Energy saving effect estimation method and apparatus
CN107133713A (en) A kind of photovoltaic plant intelligently cleans the method for building up of decision system
CN105446122B (en) Clock of power meter calibration method
US11585549B1 (en) Thermal modeling technology
MX2013008835A (en) System and method for estimating and providing dispatchable operating reserve energy capacity through use of active load management.
US20150346741A1 (en) Method and apparatus for distributed control of thermostatic electric loads using high-granularity energy usage data
CN107246705B (en) A kind of air-conditioning power consumption estimation method and device
CN112730938B (en) Electricity larceny user judging method based on electricity utilization acquisition big data
US20150019023A1 (en) Heat pump system energy management device
CN101929721B (en) Predicting method of central air conditioner energy-conservation control autoregressive (AR) model load predicting system
CN104346839B (en) A kind of employee's electronic attendance system based on LAN
CN104463344A (en) Power grid short-term load forecasting method and system
JP2016019358A (en) Demand prediction apparatus, computer program, smart meter and power storage device
JP6617476B2 (en) Demand power prediction apparatus, demand power prediction method, and computer program
JP2004164388A (en) Demand forecast system
CN110738380A (en) Thermal load control method, device and system
CN106229969A (en) Electric network element based on cumulative statistics line loss per unit loss abnormality judgment method
CN104898084A (en) Electric energy metering device operation state monitoring method
JP2017146815A (en) Power demand prediction device and method
JP2014220971A (en) Power demand prediction device, power demand prediction method, and power demand prediction program
CN110084496A (en) A kind of resource allocation methods and device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20171124