CN107387092B - 一种多个矩形顶管并联在复杂环境下形成地下空间的工法 - Google Patents
一种多个矩形顶管并联在复杂环境下形成地下空间的工法 Download PDFInfo
- Publication number
- CN107387092B CN107387092B CN201710623010.4A CN201710623010A CN107387092B CN 107387092 B CN107387092 B CN 107387092B CN 201710623010 A CN201710623010 A CN 201710623010A CN 107387092 B CN107387092 B CN 107387092B
- Authority
- CN
- China
- Prior art keywords
- rectangular top
- top pipe
- underground space
- jurisdiction
- parallel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/08—Lining with building materials with preformed concrete slabs
Abstract
本发明公开了一种多个矩形顶管并联在复杂环境下形成地下空间的工法,包括以下步骤:施做工作井;在工作井内对多个并联的矩形顶管交错顶进施工;在矩形顶管间的间隙及间隙的上下端部形成注浆加固体;在矩形顶管管片间不相邻部分的矩形顶管管片内侧施做二次衬砌;拆除矩形顶管管片间相邻的部分,完成剩余地下空间的内部结构二次衬砌施工。本发明可通过增加或减少并联矩形顶管的数量来满足开挖不同尺寸的地下空间,具有较好的适用性。通过对矩形顶管间的间隙及间隙的上下端部进行注浆加固,并采取分段渐进的施工方式,悬挑部分增加了钢支撑临时支撑,确保了拆除剩下矩形顶管管片间相邻部分时地下空间的稳定和安全。
Description
技术领域
本发明涉及地下工程技术领域,特别涉及一种多个矩形顶管并联在复杂环境下形成地下空间的工法。
背景技术
地下空间的合理开发是科学利用城市地下空间资源、适应城市现代化与可持续发展建设的重要体现。
目前,在软弱地质的条件下下穿敏感建构筑物和管线,上跨既有地铁线路,或在侧面临近重要建构筑物基础等情况下修建较大断面的地下通道时,较常采用的工法有新管幕法、洞桩法以及管幕法与冷冻法联合支护等。
新管幕法对设备以及对顶入钢管的精度控制要求较高,同时前期的支护肋梁体系需在施工空间极其狭窄的钢管内施做,工序复杂且工期较长。洞桩法施工场地狭窄,边桩等都需要在先期的导洞内施做,施工环境恶劣;同时开挖两个导洞之间的土体时,从根本上仍采用的是矿山法,地质不好时仍然存在较大沉降,因此风险较大。管幕法与冷冻法联合支护:当开挖断面较大时,需要冷冻的范围较大,导致造价特别高;同时,在高富水砂层类地层中或一些其他软弱地层中,若局部某一个点冷冻不到位,可能发生灾难性的后果,其安全性仍显不足。
因此,需要提出一种更加稳妥可行的工法。
发明内容
本发明所要解决的技术问题是提供一种施工方便且工期较短的、适用性好的以及安全性高的采用多个矩形顶管并联开挖地下空间的工法。
为解决上述技术问题所采用的技术方案:一种多个矩形顶管并联在复杂环境下形成地下空间的工法,包括以下步骤:
a.在地下空间的端部施做工作井;
b.在工作井内对多个并联的矩形顶管交错顶进施工;
c.位于矩形顶管管片转角处预留有注浆孔,注浆孔处可插入注浆管进行注浆,可在矩形顶管间的间隙及间隙的上下端部形成注浆加固体;
d.在矩形顶管管片间不相邻部分的矩形顶管管片内侧施做二次衬砌;
e.拆除矩形顶管管片间相邻的部分,完成剩余地下空间的内部结构二次衬砌施工。
进一步地,所述矩形顶管包括若干个依次相连的矩形顶管单元,所述矩形顶管单元由若干个矩形顶管管片首尾拼接而成。
进一步地,所述矩形顶管管片上预留有用于拉紧多个相连矩形单管单元的预应力索孔。
进一步地,所述步骤b中矩形顶管顶进施工的方式可采取单个交错顶进施工或多个间隔交错顶进施工。
进一步地,所述步骤d包括:在矩形顶管内部采用钢支撑对二次衬砌的顶、底板悬挑部分进行预支撑。
进一步地,所述步骤e包括:逐段拆除矩形顶管管片间相邻的部分并施工剩余部分内部结构的二次衬砌;待内部结构达到设计强度,拆除钢支撑,完成地下空间内部结构施工。
有益效果:本发明一种多个矩形顶管并联在复杂环境下形成地下空间的工法,可通过增加或减少并联矩形顶管的数量来满足开挖不同尺寸的地下空间,具有较好的适用性。同时,通过对矩形顶管间的间隙及间隙的上下端部进行注浆加固,形成有效的注浆加固体,并采取分段渐进的施工方式,外部有矩形顶管管片的包裹和支撑,内部除矩形顶管管片相邻处其余部分已施工完成二次衬砌,悬挑部分增加了钢支撑,确保了拆除剩下矩形顶管管片间相邻部分时地下空间的稳定和安全。
附图说明
下面结合附图和实施例对本发明做进一步的说明;
图1为本发明实施例工作井与三个矩形顶管之间的平面布置示意图;
图2为本发明实施例三个矩形管顶顶进施工后的分布示意图;
图3为本发明实施例采用三个矩形顶管并联开挖地下空间的剖面示意图;
图4为图3完成地下空间内部结构后的剖面示意图。
具体实施方式
参照图1至图4,本实施例一种采用三个大断面矩形顶管并联在复杂环境下形成地下空间的工法,包括以下步骤:
a.根据地下空间的规划布局以及现场土层的实际情况,设计由若干个矩形顶管单元10首尾连接组成的矩形顶管1在地下空间的分布位置,确定矩形顶管单元10的个数和尺寸、矩形顶管单元10转角处的矩形顶管管片11上预留注浆管12的数量和位置、相邻矩形顶管1间的间隙大小、以及位于地下空间两端的工作井2的位置和尺寸等参数,并预制矩形顶管单元10。
b.根据设计的位置和尺寸,在地下空间两侧施做的工作井2。
c.矩形顶管1顶进施工:在地下空间一侧的工作井2中,采用顶管机分别将位于图1顶部和底部的矩形顶管单元10逐个顶入土体至另一侧工作井2,直至形成顶部的矩形顶管1和底部的矩形顶管1,再采用顶管机将位于中间的矩形顶管单元10逐个顶入土体至另一侧工作井2,直至形成中间的矩形顶管1。其中,可同步施工左侧和右侧的矩形顶管1,有利于加快施工的进度。采取这种交叉顶入的方式,有效保证了同时顶入两根矩形顶管单元10至土体所需要的施工空间足够。并且,矩形顶管单元10的端部有防水密封装置,在若干个依次相连的矩形顶管单元10上的预应力索孔16内穿过锚索,并预紧固定,使矩形顶管1形成一个稳定的且防水的整体。
本发明一种多个矩形顶管并联在复杂环境下形成地下空间的工法,它可以通过增加或者减少并联矩形顶管1的数量来满足开挖地下空间尺寸的不同要求,因此具有比较好的适用性。
d.通过矩形顶管单元10转角处的矩形顶管管片11上预埋的注浆管12注入浆液,在相邻矩形顶管1间的间隙形成注浆加固体13,注浆加固体13填充矩形顶管管片11之间的空隙,同时也在矩形顶管1相邻位置的上下两端形成注浆加固体13,整体形成了有效的止水帷幕带,确保了拆除剩下矩形顶管管片11间相邻部分时地下空间稳定和安全。
e.在矩形顶管1内施做内部结构,具体步骤如下:
e1:在位于图2左侧的矩形顶管1内部的左侧面、以及上下面施工二次衬砌14以及内防水;在位于图2左(右)侧的矩形顶管1内部的左(右)侧面、以及上下面施工二次衬砌14、以及内防水;在位于图2中部的矩形顶管1内部的上下面施工二次衬砌14、以及内防水;三个矩形顶管1内作业面不交叉,可以同时进行施工,可缩短施工周期。
e2:矩形顶管1内二次衬砌14的顶、底板悬挑部分均采用钢支撑15进行预支撑;确保整体结构的强度和稳定,可有效防止在拆除矩形顶管管片11间相邻部分时矩形顶管1发生坍塌。
f.分别拆除矩形顶管管片11间相邻部分,并对拆除部分的顶面和底面施工二次衬砌14和内防水;待内部结构达到设计强度后,拆除钢支撑15,完成地下空间的最终结构形态。
上面结合附图对本发明的实施方式作了详细说明,但是本发明不限于上述实施方式,在所述技术领域普通技术人员所具备的知识范围内,还可以在不脱离本发明宗旨的前提下作出各种变化。
Claims (6)
1.一种多个矩形顶管并联在复杂环境下形成地下空间的工法,其特征在于,包括以下步骤:
a.在地下空间的端部施做工作井;
b.在工作井内对多个并联的矩形顶管交错顶进施工;
c.位于矩形顶管管片转角处预留有注浆孔,注浆孔处可插入注浆管进行注浆,可在矩形顶管间的间隙及间隙的上下端部形成注浆加固体;
d.在矩形顶管管片间不相邻部分的矩形顶管管片内侧施做二次衬砌;
e.拆除矩形顶管管片间相邻的部分,完成剩余地下空间的内部结构二次衬砌施工。
2.根据权利要求1所述的多个矩形顶管并联在复杂环境下形成地下空间的工法,其特征在于:所述矩形顶管包括若干个依次相连的矩形顶管单元,所述矩形顶管单元由若干个矩形顶管管片首尾拼接而成。
3.根据权利要求2所述的多个矩形顶管并联开挖地下空间的工法,其特征在于:所述矩形顶管管片上预留有用于拉紧多个相连矩形单管单元的预应力索孔。
4.根据权利要求1所述的多个矩形顶管并联在复杂环境下形成地下空间的工法,其特征在于:所述步骤b中矩形顶管顶进施工的方式可采取单个交错顶进施工或多个间隔交错顶进施工。
5.根据权利要求1所述的多个矩形顶管并联在复杂环境下形成地下空间的工法,其特征在于,所述步骤d包括:在矩形顶管内部采用钢支撑对二次衬砌的顶、底板悬挑部分进行预支撑。
6.根据权利要求1所述的多个矩形顶管并联在复杂环境下形成地下空间的工法,其特征在于,所述步骤e包括:逐段拆除矩形顶管管片间相邻的部分并施工剩余部分内部结构的二次衬砌;待内部结构达到设计强度,拆除钢支撑,完成地下空间内部结构施工。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710623010.4A CN107387092B (zh) | 2017-07-27 | 2017-07-27 | 一种多个矩形顶管并联在复杂环境下形成地下空间的工法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710623010.4A CN107387092B (zh) | 2017-07-27 | 2017-07-27 | 一种多个矩形顶管并联在复杂环境下形成地下空间的工法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107387092A CN107387092A (zh) | 2017-11-24 |
CN107387092B true CN107387092B (zh) | 2019-02-26 |
Family
ID=60341282
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710623010.4A Active CN107387092B (zh) | 2017-07-27 | 2017-07-27 | 一种多个矩形顶管并联在复杂环境下形成地下空间的工法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107387092B (zh) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111997662B (zh) * | 2020-09-07 | 2022-02-15 | 中铁工程装备集团有限公司 | 一种矩形或类矩形超大断面地下空间施工方法及施工体系 |
CN113898004B (zh) * | 2021-09-30 | 2023-06-30 | 中铁工程装备集团有限公司 | 一种地下空间施工方法 |
CN114165240A (zh) * | 2021-11-29 | 2022-03-11 | 苏交科集团股份有限公司 | 一种基于方形顶管的多层管幕结构及其施工方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102494188A (zh) * | 2011-12-06 | 2012-06-13 | 上海广联建设发展有限公司 | 矩形顶管管节的预应力装置及其施工方法 |
CN103742157A (zh) * | 2014-01-23 | 2014-04-23 | 岩土科技股份有限公司 | 用顶管法在地下新建地下空间的方法 |
CN203977941U (zh) * | 2014-07-11 | 2014-12-03 | 杭州南联地基基础工程有限公司 | 顶管式条状地下车库 |
CN104265321A (zh) * | 2014-08-06 | 2015-01-07 | 上海隧道工程有限公司 | 超大型全断面矩形顶管掘进施工方法 |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3425607B2 (ja) * | 1994-02-15 | 2003-07-14 | 株式会社竹中土木 | 超大断面矩形シールドトンネルの施工方法 |
-
2017
- 2017-07-27 CN CN201710623010.4A patent/CN107387092B/zh active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102494188A (zh) * | 2011-12-06 | 2012-06-13 | 上海广联建设发展有限公司 | 矩形顶管管节的预应力装置及其施工方法 |
CN103742157A (zh) * | 2014-01-23 | 2014-04-23 | 岩土科技股份有限公司 | 用顶管法在地下新建地下空间的方法 |
CN203977941U (zh) * | 2014-07-11 | 2014-12-03 | 杭州南联地基基础工程有限公司 | 顶管式条状地下车库 |
CN104265321A (zh) * | 2014-08-06 | 2015-01-07 | 上海隧道工程有限公司 | 超大型全断面矩形顶管掘进施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN107387092A (zh) | 2017-11-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102606167B (zh) | 浅埋暗挖隧道横向注浆导管沉降控制施工方法 | |
CN106907159A (zh) | 一种浅埋暗挖地铁车站分离开敞式结构及其施工方法 | |
KR101028535B1 (ko) | 근접병설터널 시공방법 | |
CN102606168B (zh) | 防止浅埋暗挖隧道开挖时沉降变形的施工方法 | |
CN107387092B (zh) | 一种多个矩形顶管并联在复杂环境下形成地下空间的工法 | |
CN104329095B (zh) | 一种既有隧道拓宽施工方法 | |
CN105201516A (zh) | 一种地铁车站主体结构及其四联拱pba暗挖施工方法 | |
CN113417649B (zh) | 一种地下隧道小断面至大断面的扩挖方法 | |
CN103362513A (zh) | 暗挖区间既有洞体改造施工工法 | |
CN108589771A (zh) | 一种已运营地下车站增层换乘节点施工方法 | |
CN108797641A (zh) | 一种地铁暗挖车站施工期间全车站止水的结构及其施工方法 | |
CN110159298A (zh) | 一种地铁暗挖车站初支扣拱施工方法 | |
CN107905798A (zh) | 采用中导洞法进行平顶直墙暗挖施工的方法 | |
CN104632245A (zh) | 一种用多导洞扩挖大直径盾构隧道建地铁车站的方法 | |
CN102817621B (zh) | 一种适用于不良地质隧道控制拱墙脚沉降的综合施工方法 | |
CN102410031B (zh) | 桩墙法建造地下空间结构 | |
CN206888990U (zh) | 一种浅埋暗挖地铁车站分离开敞式结构 | |
CN109372543A (zh) | 一种隧道衬砌欠厚补强构造及施工方法 | |
CN205036380U (zh) | 一种四联拱pba暗挖地铁车站主体结构 | |
CN105386779B (zh) | 浅埋岩层中修建大型地下结构物的拱柱法 | |
CN204851266U (zh) | 一种暗挖车站正上方竖井结构 | |
CN103437779A (zh) | 整治隧道衬砌渗水病害的施工方法 | |
CN207033463U (zh) | 海域中部矿山盾构交接隧道叠合型接头结构 | |
CN205036388U (zh) | 一种四联拱pba暗挖地铁车站的扣拱施工结构 | |
CN108756932B (zh) | 一种包含支护结构的隧道施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP03 | Change of name, title or address | ||
CP03 | Change of name, title or address |
Address after: 510060 East seat, No. 348 East Ring Road, Guangzhou, Guangdong, Yuexiu District Patentee after: Guangzhou municipal engineering design and Research Institute Co., Ltd. Address before: 510060 No. 348 East Ring Road, Guangzhou, Guangdong Patentee before: Guangzhou City Engineering Design studies total institute |