CN107386658A - A kind of construction method of large steel net frame integral hoisting platform - Google Patents

A kind of construction method of large steel net frame integral hoisting platform Download PDF

Info

Publication number
CN107386658A
CN107386658A CN201710167782.1A CN201710167782A CN107386658A CN 107386658 A CN107386658 A CN 107386658A CN 201710167782 A CN201710167782 A CN 201710167782A CN 107386658 A CN107386658 A CN 107386658A
Authority
CN
China
Prior art keywords
fitting
steel
capital
built
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710167782.1A
Other languages
Chinese (zh)
Other versions
CN107386658B (en
Inventor
蔡志新
张向党
钟伟
姚志新
于洪涛
徐鹏飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Pearl River Construction Supervision Co Ltd
Original Assignee
Guangzhou Pearl River Construction Supervision Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Pearl River Construction Supervision Co Ltd filed Critical Guangzhou Pearl River Construction Supervision Co Ltd
Priority to CN201710167782.1A priority Critical patent/CN107386658B/en
Publication of CN107386658A publication Critical patent/CN107386658A/en
Application granted granted Critical
Publication of CN107386658B publication Critical patent/CN107386658B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a kind of construction method of large steel net frame integral hoisting platform, large steel net frame integral hoisting platform includes concrete foundation and top steel frame, capital built-in fitting installed in concrete bottom column top, and it is welded on the support frame on the built-in fitting of capital, using the construction method of this large steel net frame integral hoisting platform, working procedure can be reduced, accelerating construction progress, reduce material, artificial use, reduce the danger of operating personnel's work high above the ground, avoid having an impact finishing process.

Description

A kind of construction method of large steel net frame integral hoisting platform
Technical field
The invention belongs to build steel mesh frame lifting field, and in particular to a kind of construction of large steel net frame integral hoisting platform Method.
Background technology
Conventional steel mesh frame lifting platform embedded part is mainly disposed to post side, adds rack welding engineering amount and manually makes With adding the danger of work high above the ground, and influence is caused on follow-up post finishing process.
In order to accelerate progress, quality and the safety of rack lifting, my supervision office tissue owner, designing unit and unit in charge of construction Hold symposium, it is proposed that lifter platform measure embedded part is changed to share with capital bearing embedded part by unit in charge of construction, can be reduced Working procedure, accelerating construction progress, ensure construction quality, safety is in controllable state, and reduces the shadow to fitting up process later Ring.This suggestion has obtained the consistent accreditation of participant.
The content of the invention
The technical assignment of the present invention is to provide a kind of large steel net frame for above-mentioned the deficiencies in the prior art and integrally carry The construction method of peaceful.
A kind of construction method of large steel net frame integral hoisting platform, large steel net frame integral hoisting platform include concrete Foundation and top steel frame, the capital built-in fitting installed in concrete bottom column top, and the branch being welded on the built-in fitting of capital Support frame frame, is characterised by:The pre-buried angle steel support of concrete foundation, capital built-in fitting, capital built-in fitting are welded in angle steel support It is firm by spot welding with the lengthways main steel bar of concrete foundation, capital built-in fitting include embedded board and auxiliary steel bracket, embedded board with Aid in steel bracket welding, auxiliary steel bracket is buried into concrete foundation top, the lengthways main steel bar of embedded board and concrete foundation it Between be provided with steel plate washer, and fixed by spot welding, embedded board is located at concrete foundation center position, and the upper surface of embedded board with Concrete bottom capital face is equal, and antidetonation hinged-support, Vibration-resistant hinge holder top erecting and welding tumbler bearing, tumbler bearing are installed on embedded board Steel frame at the top of upper installation.
In addition, hydraulic rockshaft is installed on lifting platform, for lifting large steel net frame.
It is characterized in that carry out according to the following steps:Exterior sheathing wouldn't be removed after the completion of step 1), post concrete lower sections pour, The installation that 2m is highly used for capital built-in fitting, the support of pre-plugged angle steel, the peace of preparation capital built-in fitting are reserved at the top of pillar Dress;Step 2), installation capital built-in fitting, using live civil engineering tower crane or truck crane, auxiliary steel bracket is lifted to installation site, Embedded board is soldered to auxiliary steel bracket welding afterwards, forms capital built-in fitting, the auxiliary steel bracket of capital built-in fitting uses dowel Welded with crab-bolt, and be both needed to plug welding of perforating, the top surface of embedded board is polished, the dowel and crab-bolt of built-in fitting are in support column Construction carries out Embedment Construction after meeting pre-buried condition;Step 3), by angle steel support adjustment absolute altitude capital built-in fitting is determined Position, capital built-in fitting bottom are welded in angle steel support, and steel cushion block is set in capital built-in fitting bottom, after measurement and positioning, post The bottom of top built-in fitting is fixed with lengthways main steel bar spot welding;Step 4), colligation reserve position stirrup and the reserved position template of laying, bury Position template is reserved using corner brace clamping at the top of plate, and with template fixation, casting concrete;Step 5), concreting Finish, built-in fitting position and absolute altitude after concreting are checked using GPS positioning system, after errorless, treat that concrete reaches and tears open Form removal during mould requirement, and erection support ring-shaped baffle, carry out bearing installation and prepare;Step 6), grouting are poured, and grouting material is adopted With high-strength, early strong, shrinkage-free gravitational grouting material, irrigated after the installation of bearing ring baffle;Step 7), concrete strength reach age Antidetonation hinged-support is installed on embedded board afterwards, and using line traffic control installation site is positioned, after antidetonation hinged-support installs, upper Portion's erecting and welding ball hinged support;Step 8), after ball hinged support installs, then carry out lifted platform top steel frame peace Dress is fixed, and eventually forms steel net frame integral hoisting platform.
In addition, in step 4), the corner brace that is set on capital is pre-buried is steel angle hitch, and steel angle hitch is stupefied by neck and template Checkpost connects, and forms the capital built-in fitting plane of armored concrete parcel, embedded board and the phase at the top of concrete column of capital built-in fitting It is flat.The middle part of ball hinged support described in the step 7) is rubber hinged-support.
The lifting platform of the technical program, for the support platform as lifting lifting, each lifts platform in operation Column top be provided with suspension centre, and configure hydraulic rockshaft.
Using above-mentioned technical proposal, the beneficial effects of the invention are as follows:
The present invention is improved for existing rack lifting platform.Original lifting platform measure embedded part is arranged on post side To, my supervision office finds that lateral embedded part shares with capital embedded part when checking at the scene, can reduce working procedure, quickening construct into Degree, material, artificial use are reduced, reduce the danger of operating personnel's work high above the ground, avoid having an impact finishing process.
Brief description of the drawings
The accompanying drawing for forming the part of the present invention is used for providing a further understanding of the present invention, schematic reality of the invention Apply example and its illustrate to be used to explain the present invention, do not form inappropriate limitation of the present invention.In the accompanying drawings:
Fig. 1 is the lifting platform schematic diagram of prior art
Fig. 2 is the schematic diagram for the step 1) for lifting platform construction method
Fig. 3 is to lift the step 2) of platform construction method to the schematic diagram of step 3)
Fig. 4 is the schematic diagram for the step 4) for lifting platform construction method
Fig. 5 is the schematic diagram for the step 5) for lifting platform construction method
Fig. 6 is to lift the step 6) of platform construction method to the schematic diagram of step 7)
Drawing reference numeral
1st, lengthways main steel bar;2nd, angle steel supports;3rd, stirrup;4th, concrete bottom column template;5th, capital built-in fitting;6th, steel plate washer; 7th, cage bar built-in fitting;8th, steel angle hitch;9th, rubber hinged-support;10th, ball hinged support
Embodiment
It should be noted that in the case where not conflicting, the feature in embodiment and embodiment in the present invention can phase Mutually combination.Describe the present invention in detail below with reference to the accompanying drawings and in conjunction with the embodiments.
Embodiments of the invention are elaborated below in conjunction with the accompanying drawings.
A kind of construction method of large steel net frame integral hoisting platform, large steel net frame integral hoisting platform include concrete Foundation and top steel frame, the capital built-in fitting 5 installed in concrete bottom column top, and be welded on capital built-in fitting 5 Support frame, it is characterised by:The pre-buried angle steel support 2 of concrete foundation, welds capital built-in fitting 5, capital is pre- in angle steel support 2 The lengthways main steel bar 1 of embedded part 5 and concrete foundation is firm by spot welding, and capital built-in fitting 5 includes embedded board and auxiliary steel bracket, in advance Buried plate is buried into concrete foundation top, the longitudinal direction of embedded board and concrete foundation with auxiliary steel bracket welding, auxiliary steel bracket Steel plate washer 6 is provided between cage bar 1, and is fixed by spot welding, embedded board is located at concrete foundation center position, and embedded board Upper surface is equal with concrete bottom capital face, and antidetonation hinged-support, Vibration-resistant hinge holder top erecting and welding ball branch are installed on embedded board Seat 10, installation top steel frame on tumbler bearing.The middle part of described ball hinged support 10 is rubber hinged-support 9.
In addition, hydraulic rockshaft is installed on lifting platform, for lifting large steel net frame.
Carry out according to the following steps:Exterior sheathing wouldn't be removed after the completion of step 1), post concrete lower sections pour, at the top of pillar Reserved 2m is highly used for the installation of capital built-in fitting, the support of pre-plugged angle steel, prepares the installation of capital built-in fitting;Step 2), Capital built-in fitting is installed, using live civil engineering tower crane or truck crane, auxiliary steel bracket is lifted to installation site, after by embedded board Auxiliary steel bracket welding is soldered to, forms capital built-in fitting, the auxiliary steel bracket of capital built-in fitting is carried out using dowel and crab-bolt Welding, and plug welding of perforating is both needed to, the top surface of embedded board is polished, the dowel and crab-bolt of built-in fitting meet in advance in support column construction Embedment Construction is carried out after underground layering part;Step 3), by angle steel support adjustment absolute altitude capital built-in fitting is positioned, capital is pre-buried Part bottom is welded in angle steel support, and steel cushion block is set in capital built-in fitting bottom, after measurement and positioning, the bottom of capital built-in fitting Portion is fixed with lengthways main steel bar spot welding;Step 4), colligation reserve position stirrup and the reserved position template of laying, and angle is used at the top of buried plate Code clamping reserve position template, and with template fixation, casting concrete;Step 5), concreting finish, using GPS Alignment system checks built-in fitting position and absolute altitude after concreting, after errorless, is removed when concrete reaches form removal requirement Template, and erection support ring-shaped baffle, carry out bearing installation and prepare;Step 6), grouting pour, grouting material using it is high-strength, early strong, Shrinkage-free gravitational grouting material, irrigated after the installation of bearing ring baffle;Step 7), concrete strength reach after age on embedded board Antidetonation hinged-support is installed, and using line traffic control installation site is positioned, after antidetonation hinged-support installs, in top erecting and welding ball Hinged-support;Step 8), after ball hinged support installs, then lifted the installation of top steel frame of platform and fix, finally Form steel net frame integral hoisting platform.
In addition, in step 4), the corner brace that is set on capital is pre-buried is steel angle hitch, and steel angle hitch is stupefied by neck and template Checkpost connects, and forms the capital built-in fitting plane of armored concrete parcel, embedded board and the phase at the top of concrete column of capital built-in fitting It is flat.The middle part of ball hinged support described in the step 7) is rubber hinged-support.
The lifting platform of the technical program, for the support platform as lifting lifting, each lifts platform in operation Column top be provided with suspension centre, and configure hydraulic rockshaft.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all essences in the present invention God any modification, equivalent substitution and improvements made etc., should be included in the scope of the protection with principle.

Claims (3)

1. a kind of construction method of large steel net frame integral hoisting platform, including concrete foundation and top steel frame, are arranged on The capital built-in fitting of concrete bottom column top, and the support frame being welded on the built-in fitting of capital, are characterised by:Concrete bottom The pre-buried angle steel support of post, welds capital built-in fitting, the lengthways main steel bar of capital built-in fitting and concrete foundation leads in angle steel support It is firm to cross spot welding, capital built-in fitting includes embedded board and auxiliary steel bracket, embedded board and auxiliary steel bracket welding, aids in steel bracket Bury into concrete foundation top, be provided with steel plate washer between embedded board and the lengthways main steel bar of concrete foundation, and pass through spot welding Fixed, embedded board is located at concrete foundation center position, and the upper surface of embedded board is equal with concrete bottom capital face, embedded board Upper installation antidetonation hinged-support, Vibration-resistant hinge holder top erecting and welding tumbler bearing, installation top steel frame on tumbler bearing;
It is characterized in that carry out according to the following steps:Exterior sheathing wouldn't be removed after the completion of step 1), post concrete lower sections pour, in post The sub- reserved 2m in top is highly used for the installation of capital built-in fitting, the support of pre-plugged angle steel, prepares the installation of capital built-in fitting;Step It is rapid 2), installation capital built-in fitting, using live civil engineering tower crane or truck crane, auxiliary steel bracket is lifted to installation site, after will Embedded board is soldered to auxiliary steel bracket welding, forms capital built-in fitting, the auxiliary steel bracket of capital built-in fitting uses dowel and anchor Bolt is welded, and is both needed to plug welding of perforating, and the top surface of embedded board is polished, and the dowel and crab-bolt of built-in fitting are constructed in support column Embedment Construction is carried out after meeting pre-buried condition;Step 3), by angle steel support adjustment absolute altitude capital built-in fitting is positioned, post Top built-in fitting bottom is welded in angle steel support, and steel cushion block is set in capital built-in fitting bottom, and after measurement and positioning, capital is pre-buried The bottom of part is fixed with lengthways main steel bar spot welding;Step 4), colligation reserve position stirrup and the reserved position template of laying, buried plate top Using corner brace clamping reserve position template, and with template fixation, casting concrete;Step 5), concreting finish, and adopt Built-in fitting position and absolute altitude after concreting are checked with GPS positioning system, after errorless, when concrete reaches form removal requirement Form removal, and erection support ring-shaped baffle, carry out bearing installation and prepare;Step 6), grouting pour, grouting material using it is high-strength, Early strong, shrinkage-free gravitational grouting material, irrigated after the installation of bearing ring baffle;Step 7), concrete strength reach after age pre- Antidetonation hinged-support is installed on buried plate, and using line traffic control installation site is positioned, after antidetonation hinged-support installs, installed on top Weld ball hinged support;Step 8), after ball hinged support installs, then lifted the installation of top steel frame of platform and consolidate It is fixed, eventually form steel net frame integral hoisting platform.
2. the construction method of a kind of large steel net frame integral hoisting platform according to claim 2, it is characterised in that described The antidetonation hinged-support of ball hinged support bottom in step 7) is rubber hinged-support.
A kind of 3. construction method of large steel net frame integral hoisting platform according to claim 3, it is characterised in that step 4) in, the corner brace set on capital is pre-buried is steel angle hitch, and steel angle hitch is connect by the stupefied checkpost of neck and template, forms reinforcing bar and mixes The capital built-in fitting plane of solidifying soil parcel, the embedded board of capital built-in fitting are equal with the top of concrete column.
CN201710167782.1A 2017-03-20 2017-03-20 A kind of construction method of large steel net frame integral hoisting platform Active CN107386658B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710167782.1A CN107386658B (en) 2017-03-20 2017-03-20 A kind of construction method of large steel net frame integral hoisting platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710167782.1A CN107386658B (en) 2017-03-20 2017-03-20 A kind of construction method of large steel net frame integral hoisting platform

Publications (2)

Publication Number Publication Date
CN107386658A true CN107386658A (en) 2017-11-24
CN107386658B CN107386658B (en) 2018-07-20

Family

ID=60337898

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710167782.1A Active CN107386658B (en) 2017-03-20 2017-03-20 A kind of construction method of large steel net frame integral hoisting platform

Country Status (1)

Country Link
CN (1) CN107386658B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108086695A (en) * 2017-12-15 2018-05-29 浙江精工钢结构集团有限公司 A kind of attached shell type promotes frock and construction method
CN110792265A (en) * 2019-10-31 2020-02-14 中建六局第三建筑工程有限公司 Integral synchronous jacking equipment for large-span combined type overweight eccentric slope angle steel structure
CN111945774A (en) * 2020-08-21 2020-11-17 方志兰 Installation and construction method for embedded part of large steel structure fixed foundation
CN112554345A (en) * 2020-11-27 2021-03-26 中国二冶集团有限公司 Ground splicing and integral lifting construction method for large-span welding ball net rack
CN113123608A (en) * 2021-04-12 2021-07-16 中建科工集团有限公司 Unloading method and unloading device for grid structure spherical hinge support

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH600099A5 (en) * 1975-09-19 1978-06-15 Self Lock Echafaudages
CN2178757Y (en) * 1994-02-19 1994-10-05 成志全 Plug-in multifunction scaffold
CN2318319Y (en) * 1996-03-06 1999-05-12 程舒 Connecting frame body and its of scaffold coupling bar
CN2506729Y (en) * 2001-07-13 2002-08-21 于国杰 Multifunctional inserting disc type scaffold
CN2568752Y (en) * 2001-04-10 2003-08-27 高鹏 Directly inserting double self-locking multifunctional scaffold
CN1796703A (en) * 2004-12-20 2006-07-05 久纳利彦 Working surface construction system of slope, working surface construction apparatus and working panel
CN105804388A (en) * 2016-03-24 2016-07-27 祁术洪 Scaffold for building construction

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH600099A5 (en) * 1975-09-19 1978-06-15 Self Lock Echafaudages
CN2178757Y (en) * 1994-02-19 1994-10-05 成志全 Plug-in multifunction scaffold
CN2318319Y (en) * 1996-03-06 1999-05-12 程舒 Connecting frame body and its of scaffold coupling bar
CN2568752Y (en) * 2001-04-10 2003-08-27 高鹏 Directly inserting double self-locking multifunctional scaffold
CN2506729Y (en) * 2001-07-13 2002-08-21 于国杰 Multifunctional inserting disc type scaffold
CN1796703A (en) * 2004-12-20 2006-07-05 久纳利彦 Working surface construction system of slope, working surface construction apparatus and working panel
CN105804388A (en) * 2016-03-24 2016-07-27 祁术洪 Scaffold for building construction

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108086695A (en) * 2017-12-15 2018-05-29 浙江精工钢结构集团有限公司 A kind of attached shell type promotes frock and construction method
CN108086695B (en) * 2017-12-15 2020-08-21 浙江精工钢结构集团有限公司 Auxiliary sleeve type lifting tool and construction method
CN110792265A (en) * 2019-10-31 2020-02-14 中建六局第三建筑工程有限公司 Integral synchronous jacking equipment for large-span combined type overweight eccentric slope angle steel structure
CN110792265B (en) * 2019-10-31 2021-08-06 中建六局安装工程有限公司 Integral synchronous jacking equipment for large-span combined type overweight eccentric slope angle steel structure
CN111945774A (en) * 2020-08-21 2020-11-17 方志兰 Installation and construction method for embedded part of large steel structure fixed foundation
CN112554345A (en) * 2020-11-27 2021-03-26 中国二冶集团有限公司 Ground splicing and integral lifting construction method for large-span welding ball net rack
CN113123608A (en) * 2021-04-12 2021-07-16 中建科工集团有限公司 Unloading method and unloading device for grid structure spherical hinge support

Also Published As

Publication number Publication date
CN107386658B (en) 2018-07-20

Similar Documents

Publication Publication Date Title
CN107386658B (en) A kind of construction method of large steel net frame integral hoisting platform
CN106223360B (en) Using the open cut cast in place and precast construction subway station construction method of stake supporting system
CN101838968B (en) Double track bridge construction process crossing existing railway operational lines
CN106013172A (en) Double row pile and diagonal brace combined soft soil deep foundation pit supporting structure and construction method
CN102031756A (en) Support assembly and construction method of cast-in-place box girder
CN106869548B (en) A kind of newel frame assembled underground parking structural system and construction method
CN103498425A (en) Full-dismounting combination type multifunctional bracket supporting structure and construction method thereof
CN106930194A (en) Inter-tie and pier stud global formation construction method and template used support
CN107013033A (en) A kind of concrete side wall formwork for placing and its construction method
CN110397148A (en) A kind of prefabricated assembled catch pit structure and construction method
CN105649248B (en) Prefabricated PC concrete core slab and Cast-in-situ Beam integral construction method
CN109797777A (en) Assembled is constructed from sealing underground pipe gallery and construction method
CN108951683A (en) A kind of prefabricated cushion cap of land superposed type and its production and installation method
CN207047881U (en) The prefabricated cushion cap of core is filled with joint bar
CN211074115U (en) A double-column pier prefabricated cap structure
CN109811787A (en) It is a kind of to use the additional elevator structure of pin-connected panel foundation precast elements and its construction method
CN207891904U (en) A kind of prefabricated basic component of additional elevator of existing building
CN206752699U (en) A kind of concrete filled steel tube column connected node
CN110219366A (en) Assembled architecture heat preserving formwork integral structure and construction method
CN109895239A (en) A kind of assembly concrete stair delay platform beam slab and its method of construction
CN109083184A (en) A kind of prefabricated cushion cap of land sectional type and its production and installation method
CN113373815A (en) Construction method for on-site wet joint of prefabricated bent cap
CN109137990A (en) A kind of prefabricated cushion cap of land delay-pour joint sectional type and its production and installation method
CN207620184U (en) A kind of superimposed sheet construction system
CN105178356B (en) Setting-up construction method for vertical joint bars of columns in reverse building method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant