CN105804388A CN201610170798.3A CN201610170798A CN105804388A CN 105804388 A CN105804388 A CN 105804388A CN 201610170798 A CN201610170798 A CN 201610170798A CN 105804388 A CN105804388 A CN 105804388A
Authority
CN
China
Prior art keywords
steel pipe
pop
board
groove
collar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610170798.3A
Other languages
Chinese (zh)
Other versions
CN105804388B (en
Inventor
祁术洪
光辉
曹立梅
孙小菊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201610170798.3A priority Critical patent/CN105804388B/en
Publication of CN105804388A publication Critical patent/CN105804388A/en
Application granted granted Critical
Publication of CN105804388B publication Critical patent/CN105804388B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G7/00Connections between parts of the scaffold
    • E04G7/02Connections between parts of the scaffold with separate coupling elements
    • E04G7/06Stiff scaffolding clamps for connecting scaffold members of common shape
    • E04G7/20Stiff scaffolding clamps for connecting scaffold members of common shape for ends of members only, e.g. for connecting members in end-to-end relation
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G7/00Connections between parts of the scaffold
    • E04G7/02Connections between parts of the scaffold with separate coupling elements
    • E04G7/06Stiff scaffolding clamps for connecting scaffold members of common shape
    • E04G7/22Stiff scaffolding clamps for connecting scaffold members of common shape for scaffold members in end-to-side relation

Abstract

The invention relates to a scaffold for building construction. The problems that a traditional scaffold is low in structure safety and has no safety protection measures are effectively solved. According to the technical scheme for solving the problems, the scaffold comprises first steel pipes and second steel pipes, each first steel pipe is provided with annular grooves, an annular convex piece is arranged below each annular groove, and fixing holes are formed in the bottom face of each annular groove. U-shaped grooves are formed in the outer wall of each first steel pipe, lantern rings are arranged at the two ends of each second steel pipe and provided with U-shaped blocks, and pin holes are formed in the U-shaped blocks. A popup plate is arranged between every two annular convex pieces, and a safety net is arranged below each popup plate. Steel wire grooves are formed in the two ends of each second steel pipe, and a fixed pulley is fixed above each second steel pipe. By means of the scaffold, safety of workers during construction operation is guaranteed.

Description

Construction scaffold
Technical field
The present invention relates to technical field of building construction, particularly a kind of construction scaffold.
Background technology
Scaffold refers to that job site is operative and solves vertically and horizontally to transport the various supports set up.The generic term on building circle, refers to be used in the higher place that cannot directly construct of exterior wall, inside fitting or floor height on construction site.Mainly for the upper and lower operation of workmen or perimeter security net are gone along with sb. to guard him and high-altitude installation component etc., plainly building a framework exactly, scaffold makes material generally to be had: bamboo and wood, steel pipe or synthetic material etc..Some engineering also with scaffold when template uses, the department such as this external advertising, municipal administration, traffic road and bridge, mine is also extensively used.
In the Chinese patent that the patent No. is 201410327376.3, disclosing a kind of new-type protection type attachment type raise scaffold, the purpose of this invention is in that to provide a kind of safety coefficient high, new-type protection type attachment type raise scaffold easy to assembly.The advantage of this invention is in that: 1, the protective net apparatus in the present invention is expanded metal lath, and it has bigger structural strength and stronger wind resistance load-carrying ability, it is adaptable to the execution conditions of existing attachment type raise scaffold and security protection requirement;2, the protective net apparatus in the present invention includes multiple protection network unit that split is arranged, and each protection network unit can individually be carried, and therefore need not lift by large-scale hanging device, saves construction cost;3, the protective net apparatus in the present invention adopts the first connecting bolt of wedge shape to make the first union joint be connected with location-plate, and fastening strength is high, and easy to assembly;4, the location-plate in the present invention can be separately provided, it is possible to utilizes existing spigot-and-socket button dish as location dish, saves working procedure and material;5, pass through to add fixing bolt between the adjacent framework in the present invention to be fastenedly connected, further increase the safety of protective net apparatus;6, the protective net apparatus in the present invention adopts rectangular frame, arranges reinforcing horizontal edge and/or reinforces vertical edge and/or reinforce hypotenuse, further increase the structural strength of steel plate dictyosome in rectangular frame;7, the setting of the first mark scale in the present invention, the second mark scale and the 3rd mark scale ensure that when installation foot hand cradle, what vertical rod, steel plate dictyosome, cross bar and brace were consolidated is assembled together, unnecessary structure need not be increased, it can be ensured that the security performance of scaffold;8, the first anti-loose hole in the present invention, the second anti-loose hole and the 3rd anti-loose hole the firm performance having ensured scaffold further is set.
Along with the number of plies of building increases, the height of scaffold also increases, the scaffold quantity used also increases significantly, people also increase than several years ago to some extent at the probability of high aerial work, but the structure of scaffold does not still change, still transverse direction is used, vertically, the steel pipe in oblique three directions, climbers through three kinds of directions link together, scaffold is upwards superposition rising constantly, along with security risk also with lifting, when workman constructs on scaffold, although workman self is provided with protection network with safety device and scaffold, but the security incident that annual building trade occurs from scaffold can be found everywhere.
The generation one of this security incident is owing to the process of safety device is improperly worked as, more importantly scaffold itself does not have safety device, scaffold is inadequate it may be said that play the effect that safety is fixing through the climbers that bolt is fixing, but the effect that it plays is each fastener for connection, to reach the effect raising and extending.
The problem that the safety problem of building trade becomes developer's headache already, also it is an important leverage to construction worker's safety simultaneously, scaffold is while playing fixing interconnection function, whether can also having the safety prevention measure device of self, we will continue its structure of detailed fractional analysis and use below.
Summary of the invention
For above-mentioned situation, for overcoming the defect of prior art, the purpose of the present invention is just to provide a kind of construction scaffold, effectively solves traditional scaffolding structure safety low, it does not have the problem of safety precautions.
The technical scheme of its solution is, including solid vertical first steel pipe and horizontal second steel pipe, first steel pipe is provided with multiple annular groove, the annular lug being connected with being integrated with the first steel pipe connecting of annular groove, the size of annular lug is sequentially reduced from centre to two ends, the bottom surface of annular groove is provided with multiple circumferentially uniform fixing hole, the outer wall of the first steel pipe is provided with the vertical U-lag being placed in annular groove both sides, one end of first steel pipe is provided with stretches out post, stretch out post and be provided with fixture block, the other end of the first steel pipe is provided with and stretches out the recessed post groove that post mates, the concave block groove with card Block-matching it is provided with in recessed post groove;
The two ends of the second steel pipe are provided with the collar being connected as a single entity with it, the collar is provided with the U-shaped block matched with U-lag, U-shaped block is provided with the pin-and-hole corresponding with fixing hole, alignment pin it is inserted with in pin-and-hole, constitute the collar and can be enclosed within the first steel pipe, U-shaped block mates with U-lag, the second steel pipe is made to be moved downward to the structure at annular groove place along U-lag, and constitute the collar and be stuck in the structure that the annular located finger setting in lug place is fixing, the diameter of the collar is provided with the collar of different size size according to different size of annular lug, constitute the collar and can be respectively provided at the structure at different rings connected in star place;
Multiple ejection groove being placed on the first outer wall of steel pipe it is provided with between each two annular lug, eject in groove and be provided with pop-up board, pop-up board is connected with the rotating shaft being placed in the first steel pipe through the first spring, constituting pop-up board under free state can from ejecting the structure routed up in groove, the alignment pin pressing above it of the top of ejection groove, when composition alignment pin loses efficacy, the structure that pop-up board ejects at once;
Pop-up board be connected with safety net, the safety net the second Spring Card through being completely stretched is on four the first steel pipes of surrounding, when pop-up board is placed in ejection groove, be connected to same fixing plate below with rotating shaft, when constituting pop-up board ejection, the structure of axis of rotation followed by fixing plate, fixing plate is connected plate and connects L-shaped connecting rod, connecting plate is connected through moving fastening with connecting rod, no matter constituting how connecting plate rotates, connecting rod is in the immovable structure in direction all the time;
The termination of the second steel pipe is provided with built-in multiple first flat thin magnet, and the upper surface of pop-up board is provided with multiple the second built-in flat thin magnet, ejects groove inwall and is provided with exhausted magnetosphere;
Two ends on second steel pipe are provided with steel wire trough, both sides the second steel pipe be fixedly arranged above fixed pulley, fixed pulley both sides are connected in steel wire trough through steel wire rope, are provided with the little spring being connected with steel wire rope near the second steel pipe place, when being used for constituting normal condition, the second steel pipe is not had the structure of pulling force by steel wire rope.
Present configuration is ingenious, improved by the design structure of scaffold itself, the safety and the security performance that further enhance scaffolding structure are greatly improved, thus ensure that workman's safety guarantee when construction operation, being enterprise and workman favors jointly.
Accompanying drawing explanation
Fig. 1 is the present invention the first steel pipe and the second steel pipe exploded perspective view.
Fig. 2 is the present invention the first steel pipe front view.
Fig. 3 is the present invention the first steel pipe axonometric chart.
Fig. 4 is the present invention the first steel pipe, the second steel pipe, safety net sectional view.
Fig. 5 is fixed pulley of the present invention and the second fastener for connection front view.
Fig. 6 is fixed pulley of the present invention and the second fastener for connection top view.
Fig. 7 is the present invention the first steel pipe and the first fastener for connection schematic perspective view.
Detailed description of the invention
Below in conjunction with accompanying drawing, the specific embodiment of the present invention is described in further detail.
Provided by Fig. 1 to Fig. 7, the present invention includes solid vertical first steel pipe 1 and horizontal second steel pipe 2, first steel pipe 1 is provided with multiple annular groove 3, the annular lug 4 being connected with being connected as a single entity with the first steel pipe 1 of annular groove 3, the size of annular lug 4 is sequentially reduced from centre to two ends, the bottom surface of annular groove 3 is provided with multiple circumferentially uniform fixing hole 5, the outer wall of the first steel pipe 1 is provided with the vertical U-lag 6 being placed in annular groove 3 both sides, one end of first steel pipe 1 is provided with stretches out post 30, stretch out post 30 and be provided with fixture block 31, the other end of the first steel pipe 1 is provided with and stretches out the recessed post groove 32 that post 30 mates, the concave block groove 33 mated with fixture block 31 it is provided with in recessed post groove 32;
The two ends of the second steel pipe 2 are provided with the collar 7 being connected as a single entity with it, the collar 7 is provided with the U-shaped block 8 matched with U-lag 6, U-shaped block 8 is provided with the pin-and-hole 9 corresponding with fixing hole 5, alignment pin 10 it is inserted with in pin-and-hole 9, constitute the collar 7 and can be enclosed within the first steel pipe 1, U-shaped block 8 mates with U-lag 6, the second steel pipe 2 is made to be moved downward to the structure at annular groove 3 place along U-lag 6, and constitute the collar 7 and be stuck in the structure that located pin 10 location, annular lug 4 place is fixing, the diameter of the collar 7 is provided with the collar 7 of different size size according to different size of annular lug 4, constitute the collar 7 and can be respectively provided at the structure at different rings connected in star 3 place;
Multiple ejection groove 11 being placed on the first steel pipe 1 outer wall it is provided with between each two annular lug 4, eject in groove 11 and be provided with pop-up board 12, pop-up board 12 is connected with the rotating shaft 14 being placed in the first steel pipe 1 through the first spring 13, constituting pop-up board 12 under free state can from ejecting the structure routed up in groove 11, the top of ejection groove 11 alignment pin 10 above it presses, when composition alignment pin 10 loses efficacy, the structure that pop-up board 12 ejects at once;
Pop-up board 12 be connected with safety net 15, the safety net 15 second spring 16 through being completely stretched is stuck on four the first steel pipes 1 of surrounding, when pop-up board 12 is placed in ejection groove 11, same fixing plate 17 it is connected to below with rotating shaft 14, when composition pop-up board 12 ejects, the structure that rotating shaft 14 rotates followed by fixing plate 17, fixing plate 17 is connected plate 18 and connects L-shaped connecting rod 19, connecting plate 18 is connected through moving fastening 20 with connecting rod 19, no matter constituting how connecting plate 18 rotates, connecting rod 19 is in the immovable structure in direction all the time;
The termination of the second steel pipe 2 is provided with built-in multiple first flat thin magnet 25, and the upper surface of pop-up board 12 is provided with multiple the second built-in flat thin magnet 26, ejects groove 11 inwall and is provided with exhausted magnetosphere 27;
Two ends on second steel pipe 2 are provided with steel wire trough 21, both sides the second steel pipe 2 be fixedly arranged above fixed pulley 22, fixed pulley 22 both sides are connected in steel wire trough 21 through steel wire rope 23, it is provided with the little spring 24 being connected with steel wire rope 23 near the second steel pipe 2 place, when being used for constituting normal condition, the second steel pipe 2 is not had the structure of pulling force by steel wire rope 23.
Between two second steel pipes 2 of described fixed pulley 22 side fixed thereon.
The described rear ejecting groove 11 is provided with and is horizontally through the second steel pipe 2 and is detachably fixed support bar 28, and the two ends of support bar 28 are fixed with dismountable baffle plate 29, and baffle plate 29 is placed in the both sides above when pop-up board 12 ejects.
The vertical U-lag 6 of described each two is not on the same line.
Described pop-up board 12 and the outer wall of the first steel pipe 1 are in same cambered surface.
The second described spring 16 is stuck on L-shaped connecting rod 19 through snap ring 34.
Described alignment pin 10 is connected rope 35 and is connected with the second steel pipe 2.
Described pop-up board 12 is groove type pop-up board.
When the present invention uses,
First steel pipe 1 of the present invention and the second steel pipe 2 literary style are solid steel pipe, actually going up inside still has multi-section to be divided into used hollow steel pipe, simply a portion structure is solid, but in order to literary style is convenient, first steel pipe and the second steel pipe are first write as solid steel pipe, concrete hollow part and solid position have a detailed description at concrete structure place.
First on the first steel pipe 1, offer multiple annular groove 3, it is provided with the annular lug 4 concentric with the first steel pipe 1 at the position of fluting, so the diameter of annular lug 4 is greater than the diameter of the first steel pipe 1, and annular groove 3 quantity has multiple, thus annular lug 4 has multiple, but when arranging, annular lug 4 diameter being middle is maximum, it is sequentially reduced to the annular lug 4 of both sides, that so design in order that meet the installation of the second steel pipe 2.
Because the collar 7 of the second steel pipe 2 is when coordinating with the first steel pipe 1, first to mate U-lag 6 with U-shaped block 8, second steel pipe 2 moves down along U-lag 6, and the fixed position of the second steel pipe 2 can select different annular groove 6 positions according to actual needs, now, due to varying in size of annular lug 4, so the diameter of the collar 7 is also different, the collar 7 selecting suitable size can pass sequentially through little annular lug 4, then move to suitable annular groove 3 place, because if the size of annular lug 4 is identical, so the collar 7 move to annular lug 4 place will by annular lug 4 stop, thus cannot pass through to next annular groove 3 place.
Annular lug 4 is just used to stop that the collar 7 passes through, thus being fixed on this position, when the collar 7 chooses suitable annular groove 3, rotate the collar 7, select suitable hole, location 5, then its collar 7 and the first steel pipe 1 are fixed by alignment pin 10, now complete the first steel pipe 1 and be connected with the second the fixing of steel pipe 2.
The present invention is primarily intended to the problem solving potential safety hazard, all there is certain danger in anything, can not safety very, and for the present invention, comparatively speaking, relatively holding accident-prone place is in the junction of the second steel pipe 2 with the collar 7, the collar 7 is blocked by annular lug 4, it is not easy to come off, but As time goes on, through long-term pressure, the corrosion exposed to the weather, it is understood that there may be the fracture at the collar 7 and the second steel pipe 2 place.
And once the collar 7 and the second steel pipe 2 rupture; fixed pulley 22 above it can first through little spring 24; second steel pipe 2 is applied pulling force upwards; second steel pipe 2 of side keeps balance corresponding thereto; guarantee that the second steel pipe 2 does not come off; the present invention first passes through the connection of steel wire rope 23 and fixed pulley 22; second steel pipe 2 is carried out the safeguard protection of the first step; when second steel pipe 2 is come off; second steel pipe 2 is applied pulling force upwards through little spring 24 by the steel pipe of its opposite side; thus keeping balance, then find steel pipe fracture when maintenance, thus being replaced maintenance.
And the effect of little spring 24 is to maintain under normal condition, second steel pipe 2 of both sides is not possessed the effect of pulling force by fixed pulley 22, thus reducing the active force to the second steel pipe 2, extend the life-span that the second steel pipe 2 is fixing, it is only when the second steel pipe 2 has downward movement tendency, little spring 24 plays a role, and at once it is carried out active force upwards.
Further, if do not found in time after the second steel pipe 2 fracture, the fixing of the second steel pipe 2 all maintains by steel wire rope 23, As time goes on, the abrasion of steel wire rope 23, add second steel pipe 2 other end do not stop rock, cause the second steel pipe 2 to come off downwards.
When second steel pipe 2 comes off downwards, being connected rope 10 1 active forces upwards of 35 alignment pins, once the active force of alignment pin 10 reduces, pop-up board 12, through the structure of the first spring 13 with rotating shaft 14, can eject at once in ejection groove 11.
Because can eject at once when losing alignment pin 10 to its active force at pop-up board 12, and the second steel pipe 2 is certain to along with alignment pin 10 is moved up when coming off, so the second steel pipe 2 is when coming off, pop-up board 12 will necessarily first eject, so that when the second steel pipe 2 comes off downwards, drop on pop-up board 12, be ejected plate 12 and stop.
During in order to ensure that the second steel pipe 2 drops on pop-up board 12, will not occur roll or do not drop out pop-up board 12, pop-up board 12 can be designed to groove shapes, when pop-up board 12 drops, drop in the groove of spill pop-up board 12, or be embedded with the first flat thin magnet 25 in the termination of the second steel pipe 2, pop-up board 12 is embedded with the second flat thin magnet 26, first flat thin magnet 25 and the second flat thin magnet 26 attract each other, and are used for ensureing to drop out pop-up board 12 when the second steel pipe 2 drops.
Further, in order to prevent the second steel pipe 2 from dropping out pop-up board 12, it is arranged over baffle plate 29 in the both sides of pop-up board 12.
And connecting and fixing of baffle plate 29 must be dismountable, so just will not stop installation and the use of the collar 7, after treating that all process steps is installed, the first steel pipe 1 be installed detachable support bar 28, then dismountable block plate 29 is installed on support bar 28.
First steel pipe 1 is connected with the vertical of the first steel pipe 1, in order to better reinforce the stability of the first steel pipe 1, be set as at the two ends of the first steel pipe 1 can mate stretch out post 30 and recessed post groove 32, rotate in recessed post groove 32 to prevent it from stretching out post 30, so using fixture block 31 to be stuck in block groove 33, avoiding it freely rotatable, thus reaching to consolidate further the effect of the first steel pipe 1, finally using scaffold climbers to connect.
Further, if workman constructs on scaffold, the danger brought to workman to prevent scaffold from coming off, further safety precautions has been done at this.
nullIt is connected with the structure of pop-up board 12,It is being connected to fixing plate 17 with rotating shaft 14,When pop-up board 12 ejects downwards,Now fix plate 17 to follow rotating shaft 14 and rotate,Connecting plate 18 is followed fixing plate 17 and is rotated,But L-shaped connecting rod 19 follow mobile in,L-shaped connecting rod 19 is simply followed and is moved over to the left,But do not change its direction,That is,Because connecting plate 18 is connected through moving fastening 20 with L-shaped connecting rod 19,The result being finally reached is,L-shaped connecting rod 19 moves over to the left,But the structure direction state before remaining on,And the snap ring 34 of the second spring 16 is stuck on L-shaped connecting rod 19,Now L-shaped connecting rod 19 is deviate from snap ring 34,The second spring 16 moment being completely stretched is caused to lose tensile force,Second spring 16 starts to stretch safety net 15,Safety net 15 becomes extended state from contraction state,And then ensure the safety of workman.
In the present invention, one end of solid first steel pipe 1 is cavity, is recessed post groove 32, and the other end is solid is stretch out post 30, and the two ends of annular groove 3 are solid, is cavity between U-shaped connecting rod 19 place and ejection groove 11, is used for making the movement of U-shaped connecting rod 19.
The present invention is when installing and use, convenient and swift, and has significantly high security performance guarantee, by the structural design of steel wire rope, pop-up board, safety net on fixed pulley, thus layer by layer it being carried out safeguard protection, adds safety and the stability of scaffold.
Being closely connected between each structural design of the present invention, it is not possible to individually compare, can not pass judgment on separately as a branch, not only structure is closely connected, and the effect reached also is transmission impact mutually, it should comprehensive from general direction assurance.
Such as, the collar and the first steel pipe, U-shaped block and U-lag, hole, location and pin-and-hole and alignment pin, annular lug and the collar, pop-up board and fixing plate, fixing plate and safety net, alignment pin and pop-up board, the first magnetic sheet and second magnetic sheet etc., all connect each other, pull one hair and move the whole body.
Present configuration is ingenious, improved by the design structure of scaffold itself, the safety and the security performance that further enhance scaffolding structure are greatly improved, thus ensure that workman's safety guarantee when construction operation, being enterprise and workman favors jointly.

Claims (8)

  1. null1. a construction scaffold,Including solid vertical first steel pipe (1) and horizontal second steel pipe (2),It is characterized in that,First steel pipe (1) is provided with multiple annular groove (3),The annular lug (4) being connected with being connected as a single entity with the first steel pipe (1) of annular groove (3),The size of annular lug (4) is sequentially reduced from centre to two ends,The bottom surface of annular groove (3) is provided with multiple circumferentially uniform fixing hole (5),The outer wall of the first steel pipe (1) is provided with the vertical U-lag (6) being placed in annular groove (3) both sides,One end of first steel pipe (1) is provided with stretches out post (30),Stretch out post (30) and be provided with fixture block (31),The other end of the first steel pipe (1) is provided with and stretches out the recessed post groove (32) that post (30) mates,The concave block groove (33) mated with fixture block (31) it is provided with in recessed post groove (32);
    nullThe two ends of the second steel pipe (2) are provided with the collar (7) being connected as a single entity with it,The collar (7) is provided with the U-shaped block (8) matched with U-lag (6),U-shaped block (8) is provided with the pin-and-hole (9) corresponding with fixing hole (5),Alignment pin (10) it is inserted with in pin-and-hole (9),Constitute the collar (7) can be enclosed within the first steel pipe (1),U-shaped block (8) mates with U-lag (6),The second steel pipe (2) is made to be moved downward to the structure at annular groove (3) place along U-lag (6),And constitute the collar (7) and be stuck in the structure that the annular located pin in lug (4) place (10) location is fixing,The diameter of the collar (7) is provided with the collar (7) of different size size according to different size of annular lug (4),Constitute the collar (7) and the structure at different rings connected in star (3) place can be respectively provided at;
    Multiple ejection groove (11) being placed on the first steel pipe (1) outer wall it is provided with between each two annular lug (4), eject in groove (11) and be provided with pop-up board (12), pop-up board (12) is connected with the rotating shaft (14) being placed in the first steel pipe (1) through the first spring (13), constituting pop-up board (12) under free state can from ejecting the structure routed up in groove (11), alignment pin (10) pressing above it of the top of ejection groove (11), when composition alignment pin (10) loses efficacy, the structure that pop-up board (12) ejects at once;
    Pop-up board (12) be connected with safety net (15), the safety net (15) the second spring (16) through being completely stretched is stuck on four the first steel pipes (1) of surrounding, pop-up board (12) be placed in ejection groove (11) interior time, same fixing plate (17) it is connected to below with rotating shaft (14), when constituting pop-up board (12) ejection, the structure that rotating shaft (14) rotates followed by fixing plate (17), fixing plate (17) is connected plate (18) and connects L-shaped connecting rod (19), connecting plate (18) is connected through moving fastening (20) with connecting rod (19), no matter constituting how connecting plate (18) rotates, connecting rod (19) is in the immovable structure in direction all the time;
    The termination of the second steel pipe (2) is provided with built-in multiple first flat thin magnet (25), and the upper surface of pop-up board (12) is provided with multiple built-in the second flat thin magnet (26), ejects groove (11) inwall and is provided with exhausted magnetosphere (27);
    Two ends on second steel pipe (2) are provided with steel wire trough (21), both sides the second steel pipe (2) be fixedly arranged above fixed pulley (22), fixed pulley (22) both sides are connected in steel wire trough (21) through steel wire rope (23), it is provided with the little spring (24) being connected with steel wire rope (23) near the second steel pipe (2) place, when being used for constituting normal condition, the second steel pipe (2) is not had the structure of pulling force by steel wire rope (23).
  2. 2. a kind of construction scaffold according to claim 1, it is characterised in that between two second steel pipes (2) of described fixed pulley (22) side fixed thereon.
  3. 3. a kind of construction scaffold according to claim 1, it is characterized in that, the rear of described ejection groove (11) is provided with and is horizontally through the second steel pipe (2) and is detachably fixed support bar (28), the two ends of support bar (28) are fixed with dismountable baffle plate (29), and baffle plate (29) is placed in the both sides above when pop-up board (12) ejects.
  4. 4. a kind of construction scaffold according to claim 1, it is characterised in that the vertical U-lag of described each two (6) is not on the same line.
  5. 5. a kind of construction scaffold according to claim 1, it is characterised in that the outer wall of described pop-up board (12) and the first steel pipe (1) is in same cambered surface.
  6. 6. a kind of construction scaffold according to claim 1, it is characterised in that described the second spring (16) is stuck on L-shaped connecting rod (19) through snap ring (34).
  7. 7. a kind of construction scaffold according to claim 1, it is characterised in that described alignment pin (10) is connected rope (35) and is connected with the second steel pipe (2).
  8. 8. a kind of construction scaffold according to claim 1, it is characterised in that described pop-up board (12) is groove type pop-up board.
CN201610170798.3A 2016-03-24 2016-03-24 scaffold for building construction Expired - Fee Related CN105804388B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610170798.3A CN105804388B (en) 2016-03-24 2016-03-24 scaffold for building construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610170798.3A CN105804388B (en) 2016-03-24 2016-03-24 scaffold for building construction

Publications (2)

Publication Number Publication Date
CN105804388A true CN105804388A (en) 2016-07-27
CN105804388B CN105804388B (en) 2017-04-19

Family

ID=56454818

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610170798.3A Expired - Fee Related CN105804388B (en) 2016-03-24 2016-03-24 scaffold for building construction

Country Status (1)

Country Link
CN (1) CN105804388B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107386658A (en) * 2017-03-20 2017-11-24 广州珠江工程建设监理有限公司 A kind of construction method of large steel net frame integral hoisting platform

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001220902A (en) * 2000-02-08 2001-08-17 Kazuhiko Kishida Bracing device for concrete form
CN101824904A (en) * 2009-03-05 2010-09-08 卢兴明 Integral-scaffold supporting elevation method and double-track double-anti-dropping hydraulic lifting integral scaffold thereof
CN202990393U (en) * 2012-10-15 2013-06-12 门晓红 Tool type steel mesh attached elevating scaffold

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001220902A (en) * 2000-02-08 2001-08-17 Kazuhiko Kishida Bracing device for concrete form
CN101824904A (en) * 2009-03-05 2010-09-08 卢兴明 Integral-scaffold supporting elevation method and double-track double-anti-dropping hydraulic lifting integral scaffold thereof
CN202990393U (en) * 2012-10-15 2013-06-12 门晓红 Tool type steel mesh attached elevating scaffold

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107386658A (en) * 2017-03-20 2017-11-24 广州珠江工程建设监理有限公司 A kind of construction method of large steel net frame integral hoisting platform

Also Published As

Publication number Publication date
CN105804388B (en) 2017-04-19

Similar Documents

Publication Publication Date Title
CN103206074B (en) Elevator shaft template construction method, platform and support
CN110094049B (en) Quick early-dismantling support for constructional engineering
CN105803944B (en) scaffold for road and bridge construction
CN209780183U (en) Scaffold for building engineering
CN105804388A (en) Scaffold for building construction
CN211548713U (en) A suspension type scaffold frame for square chimney
CN201221365Y (en) Front cantilever temporary support
CN213626572U (en) Tool type external cantilever operation platform
CN211114737U (en) A construction operation platform in elevator well for tower crane promotes
CN211473327U (en) Building external climbing type building construction operation platform
CN208310302U (en) A kind of new reinforcing steel bar processing protection canopy
CN215829972U (en) Scaffold frame for engineering construction convenient to equipment
CN210947630U (en) Scaffold with hard isolation structure for construction of exterior wall dry-hanging marble
CN209891750U (en) Elevator shaft protective screening mechanism convenient to disassemble and assemble
CN210195457U (en) Safety protective guard is used in civil engineering
CN210598063U (en) Cross rod structure for column edge connection
CN201730306U (en) Light-weight scaffold
CN110344748A (en) A kind of Domestic staircase that durability is high
CN214739838U (en) Dish knot formula scaffold frame based on BIM
CN207905343U (en) A kind of fastener locking device for scaffold
CN202831591U (en) Special-shaped truss operation platform capable of hoisting to super high space
CN110565929B (en) Scaffold for construction of large-specification wall paving piece of building outer wall
CN213174721U (en) Climbing frame positioned by inclined top support
CN211341656U (en) Support frame that construction fitment was used
CN101575908A (en) Light scaffold

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 451191 Longhu, Henan, Xinzheng Town, Wenchang Road, No. 1, No.

Applicant after: Qi Shuhong

Applicant after: Guang Hui

Applicant after: Cao Limei

Applicant after: Sun Xiaoju

Address before: 450000 Zhengzhou, Jinshui District, Henan, North Ring Road, No. 36 attached to No. 2003

Applicant before: Qi Shuhong

Applicant before: Guang Hui

Applicant before: Cao Limei

Applicant before: Sun Xiaoju

COR Change of bibliographic data
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170419

Termination date: 20200324

CF01 Termination of patent right due to non-payment of annual fee