CN107386609A CN201710603174.0A CN201710603174A CN107386609A CN 107386609 A CN107386609 A CN 107386609A CN 201710603174 A CN201710603174 A CN 201710603174A CN 107386609 A CN107386609 A CN 107386609A
Authority
CN
China
Prior art keywords
stone
fixed
plate
exterior wall
hanging
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710603174.0A
Other languages
Chinese (zh)
Other versions
CN107386609B (en
Inventor
李月成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201710603174.0A priority Critical patent/CN107386609B/en
Publication of CN107386609A publication Critical patent/CN107386609A/en
Application granted granted Critical
Publication of CN107386609B publication Critical patent/CN107386609B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F21/00Implements for finishing work on buildings
    • E04F21/18Implements for finishing work on buildings for setting wall or ceiling slabs or plates
    • E04F21/1838Implements for finishing work on buildings for setting wall or ceiling slabs or plates for setting a plurality of similar elements
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/24Structural elements or technologies for improving thermal insulation
    • Y02A30/244Structural elements or technologies for improving thermal insulation using natural or recycled building materials, e.g. straw, wool, clay or used tires

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

A kind of exterior wall finishing stone material dry suspending boom hoisting, include loading plate, stone material mounting bracket top suspension mechanism, hoist engine and stone material clamping device, mounting hole is provided with the middle part of supporting plate main panel, above supporting plate on plate, hoist engine is provided with above mounting hole, the upper and lower ends of mounting hole are provided with two fixed otic placodes, connecting shaft is provided between two fixed otic placodes, the lower half of connecting shaft is arranged with compression spring, its first half is provided with stone material mounting bracket top suspension mechanism, the top of stone material mounting bracket top suspension mechanism is provided with the coiling roller corresponding with lifting drum, steel wire rope is arranged with lifting drum, steel wire rope is connected with stone material by coiling roller and accommodates mechanism.A kind of exterior wall finishing stone material dry suspending boom hoisting of the present invention and its application, its is reasonable in design, simple in construction, is easy to lift by crane, installs stone material, can effectively reduce dust caused by construction, improves operating efficiency, while can also save substantial amounts of fluid sealant.

Description

一种外墙装修石材干挂起吊装置及其应用A dry-hanging lifting device for exterior wall decoration stone and its application

技术领域technical field

本发明涉及建筑施工技术领域,尤其涉及一种外墙装修石材干挂起吊装置及其应用。The invention relates to the technical field of building construction, in particular to a device for dry-hanging stone materials for exterior wall decoration and its application.

背景技术Background technique

石材干挂法又名空挂法。是目前墙面装饰中一种新型的施工工艺。该工艺是利用耐腐蚀的螺栓和耐腐蚀的柔性连接件,将花岗石、人造大理石等饰面石材直接挂在建筑结构的外表面或空挂于钢架上,不需再灌浆粘贴。其原理是在主体结构上设置主要受力点,通过金属挂件将石材固定在建筑物上,形成石材装饰幕墙。石材与建筑结构之间留出40~50mm的空腔。用此工艺做成的饰面,在风力和地震力的作用下允许产生适量的变位,以吸收部分风力和地震力,而不致出现裂纹和脱落,当风力和地震力消失后,石材也随结构而复位。现阶段,石材在出厂时,通常在其侧面切割有安装槽,为了达到所需强度,降低运输过程中的损坏率,安装槽的口径较小,在实际施工过程中,由于石材质量大,安装时需要多人互相配合,施工难度高,且石材侧面的安装槽口径过小,很难与挂件对接,绝大多数工作人员在施工现场需要对安装槽进行扩槽,以便于将石材挂于挂件上,人工开槽费时费力,扬尘大,污染空气,同时每个槽口的差异性较大,工程质量难以保证。石材安装槽的口径扩大后,需要使用密封胶对安装槽进行密封,密封胶的使用量大,增加了施工成本。The dry hanging method of stone is also called the empty hanging method. It is a new type of construction technology in wall decoration. This process uses corrosion-resistant bolts and corrosion-resistant flexible connectors to hang granite, artificial marble and other decorative stones directly on the outer surface of the building structure or on the steel frame without grouting and pasting. The principle is to set the main stress points on the main structure, and fix the stone on the building through metal pendants to form a stone decorative curtain wall. Leave a cavity of 40-50mm between the stone and the building structure. The veneer made by this process is allowed to produce an appropriate amount of displacement under the action of wind and earthquake forces to absorb part of the wind and earthquake forces without cracks and falling off. When the wind and earthquake forces disappear, the stone will also follow The structure is reset. At this stage, stones are usually cut with installation grooves on their sides when they leave the factory. In order to achieve the required strength and reduce the damage rate during transportation, the diameter of the installation grooves is small. In the actual construction process, due to the large quality of stone materials, installation Many people need to cooperate with each other, the construction is difficult, and the diameter of the installation groove on the side of the stone is too small, it is difficult to dock with the pendant. Most of the workers need to expand the installation groove at the construction site so that the stone can be hung on the pendant In general, manual slotting is time-consuming and laborious, causing large dust and air pollution. At the same time, the difference between each slot is large, and the quality of the project is difficult to guarantee. After the caliber of the stone installation groove is enlarged, the installation groove needs to be sealed with a sealant, and the usage of the sealant is large, which increases the construction cost.

发明内容Contents of the invention

本发明的目的在于,克服现有技术的不足之处,提供一种外墙装修石材干挂起吊装置及其应用,其设计合理,结构简单,便于起吊、安装石材,省掉了石材安装槽扩槽这一工序,提升石材强度,能有效降低施工时产生的粉尘,减低工作强度,提高工作效率,同时还能节省大量的密封胶,提升经济效益。The object of the present invention is to overcome the deficiencies of the prior art and provide a dry-hanging lifting device for stone materials for exterior wall decoration and its application. The process of groove improves the strength of the stone, effectively reduces the dust generated during construction, reduces the work intensity, improves work efficiency, and at the same time saves a lot of sealant and improves economic benefits.

本发明所述的一种外墙装修石材干挂起吊装置,包括有承载板、石材安装架顶挂机构、卷扬机和石材夹持机构,所述的承载板为本发明的主体支撑部件,且为一槽形钢体结构,承托板主面板的中部设置有安装孔,在承托板的上面板上,即安装孔的上方设置有卷扬机,安装孔的上下两端,也是承托板主面板的正面设置有两个互相对应的固定耳板,两个固定耳板之间设置有连接轴,连接轴的下半部套设有压力弹簧,其上半部,即压力弹簧的上面设置有石材安装架顶挂机构,石材安装架顶挂机构的顶端设置有与卷扬机卷筒相对应的绕线滚轮,所述的卷扬机卷筒上绕设有钢丝绳,钢丝绳通过绕线滚轮连接有石材夹持机构。A dry-hanging lifting device for exterior wall decoration stone according to the present invention includes a bearing plate, a stone mounting frame top hanging mechanism, a hoist and a stone clamping mechanism. The bearing plate is the main body supporting part of the present invention, and is A trough-shaped steel body structure, the middle part of the main panel of the supporting plate is provided with a mounting hole, and a hoist is arranged on the upper plate of the supporting plate, that is, above the mounting hole, and the upper and lower ends of the mounting hole are also the main panel of the supporting plate There are two fixed lugs corresponding to each other on the front side, and a connecting shaft is set between the two fixed lugs. The lower half of the connecting shaft is set with a pressure spring, and the upper half, that is, the upper part of the pressure spring is set with a stone The top hanging mechanism of the installation frame, the top of the top hanging mechanism of the stone installation frame is provided with a winding roller corresponding to the hoist drum, and a steel wire rope is wound on the hoist drum, and the steel wire rope is connected to the stone clamping mechanism through the winding roller .

所述的石材安装架顶挂机构包括有顶压联动杆、固定钩联动杆、连接臂和固定钩,所述的固定钩联动杆为“L”形,其长边与承托板主面板的正面相对,竖直向上延伸,其短边为一管型结构,向承托板主面板的背面延伸,所述短边的中部设置有连接通孔,穿设于连接轴上,在固定钩联动杆的短边内设置有固定钩,所述的固定钩通过通孔也穿设于连接轴上,固定钩与承托板之间连接有伸缩弹簧,所述的顶压联动杆的底部设置有一连接槽体,连接轴穿过所述连接槽体,所述的固定钩联动杆短边的底面上设置有连接耳板,连接耳板的下部铰接在顶压联动杆上,固定钩联动杆长边的顶端铰接有连接臂,连接臂与顶压联动杆的上部铰接。The top hanging mechanism of the stone installation frame includes a top pressure linkage rod, a fixed hook linkage rod, a connecting arm and a fixed hook. The fixed hook linkage rod is "L" shaped, and its long side is connected to the main panel of the supporting plate. The fronts are opposite and extend vertically upwards. Its short side is a tubular structure extending to the back of the main panel of the supporting plate. The short side of the rod is provided with a fixed hook, and the fixed hook is also pierced on the connecting shaft through the through hole. A telescopic spring is connected between the fixed hook and the supporting plate. The bottom of the top pressure linkage rod is provided with a The connecting groove body, the connecting shaft passes through the connecting groove body, the bottom surface of the short side of the fixed hook linkage rod is provided with a connecting ear plate, the lower part of the connecting ear plate is hinged on the top pressure linkage rod, and the length of the fixed hook linkage rod is The top of the side is hinged with a connecting arm, and the connecting arm is hinged with the top of the top pressure linkage rod.

所述的顶压联动杆为横杆和竖杆两个部分组成,所述的横杆设置在安装孔内,其杆体上设置有连接槽体,所述的竖杆与承托板的正面相对,竖杆的底端与横杆的一端铰接,其顶端设置有与卷扬机卷筒相对应的绕线滚轮,所述的固定钩联动杆长边的上部与顶压联动杆竖杆的下部之间连接有拉伸弹簧。The top pressure linkage rod is composed of two parts, a horizontal rod and a vertical rod. The horizontal rod is arranged in the installation hole, and the rod body is provided with a connecting groove body. The vertical rod is opposite to the front of the supporting plate. , the bottom end of the vertical bar is hinged with one end of the cross bar, and the top end is provided with a winding roller corresponding to the hoist drum, between the upper part of the long side of the fixed hook linkage bar and the lower part of the top pressure linkage bar vertical bar Attached is a tension spring.

本发明所述的一种外墙装修石材干挂起吊装置及其应用,其设计合理,结构简单,便于起吊、安装石材,省掉了石材安装槽扩槽这一工序,提升石材强度,能有效降低施工时产生的粉尘,减低工作强度,提高工作效率,同时还能节省大量的密封胶,提升经济效益。The dry-hanging and lifting device for stone for exterior wall decoration and its application according to the present invention has reasonable design and simple structure, is convenient for lifting and installing stone, saves the process of expanding the stone installation groove, improves the strength of stone, and can effectively Reduce dust generated during construction, reduce work intensity, improve work efficiency, and at the same time save a lot of sealant and improve economic benefits.

附图说明Description of drawings

附图1是本发明所述的一种外墙装修石材干挂起吊装置及其应用的结构示意图。Accompanying drawing 1 is a kind of external wall decoration stone material dry-hanging lifting device and its application structure diagram according to the present invention.

附图2是本发明所述的一种外墙装修石材干挂起吊装置及其应用的左视结构示意图。Accompanying drawing 2 is a kind of external wall decoration stone material dry-hanging lifting device and its application according to the present invention, the left view structure schematic diagram.

附图3是本发明所述的一种外墙装修石材干挂起吊装置及其应用的右视结构示意图。Accompanying drawing 3 is a right-view structure schematic diagram of a kind of external wall decoration stone material dry-hanging lifting device and its application according to the present invention.

附图4是本发明所述的一种外墙装修石材干挂起吊装置及其应用的石材夹持机构结构示意图。Accompanying drawing 4 is a kind of outside wall decoration stone material dry-hanging lifting device and its applied stone material clamping structure schematic diagram according to the present invention.

1—承托板 2—滑轮 3—电机 4—外固定板 5—石材固定架顶挂机构 6—绕线滚轮 7—卷扬机 8—吊臂 9—连接轴 10—安装孔 11—压力弹簧 12—配重杆 13—固定耳板 14—顶压联动杆 15—固定钩联动杆 16—连接臂 17—固定钩 18—顶压滚轮 19—石材夹持机构 20—连接耳板 21—固定板 22—驱动齿轮 23—传动齿轮 24—转轴 25—固定夹臂 26—活动夹臂 27—固定环。1—supporting plate 2—pulley 3—motor 4—outer fixing plate 5—top hanging mechanism of stone fixing frame 6—winding roller 7—hoist 8—hanging arm 9—connecting shaft 10—installation hole 11—pressure spring 12— Counterweight rod 13—fixed ear plate 14—top pressure linkage rod 15—fixed hook linkage rod 16—connecting arm 17—fixed hook 18—top pressure roller 19—stone clamping mechanism 20—connecting ear plate 21—fixed plate 22— Drive gear 23—transmission gear 24—rotating shaft 25—fixed clamp arm 26—movable clamp arm 27—fixed ring.

具体实施方式detailed description

现参照附图1、附图2、附图3和附图4,结合具体实施例,说明如下:本发明所述的一种外墙装修石材干挂起吊装置,包括有承载板1、石材安装架顶挂机构5、卷扬机7和石材夹持机构19。所述的承载板1为本发明的主体支撑部件,且为一槽形钢体结构,承托板1主面板的中部设置有安装孔10,在承托板1的上面板上,即安装孔10的上方固定设置有卷扬机7,所述卷扬机7通过导线连接有电源。安装孔10的上下两端,也是承托板1主面板的正面固定设置有两个互相对应的固定耳板13,两个固定耳板13之间设置有连接轴9,连接轴9的下半部套设有压力弹簧11,其上半部,即压力弹簧11的上面设置有石材安装架顶挂机构5。石材安装架顶挂机构5的顶端设置有与卷扬机卷筒相对应的绕线滚轮6,所述的卷扬机卷筒上绕设有钢丝绳,钢丝绳通过绕线滚轮6连接有石材夹持机构19,所述的石材加持机构19用于夹持装修石材。Now referring to accompanying drawing 1, accompanying drawing 2, accompanying drawing 3 and accompanying drawing 4, in conjunction with specific embodiment, description is as follows: A kind of exterior wall decoration stone material dry-hanging lifting device of the present invention, comprises bearing plate 1, stone material installation Frame top hanging mechanism 5, winch 7 and stone clamping mechanism 19. The bearing plate 1 is the main body supporting part of the present invention, and is a trough-shaped steel body structure. The middle part of the main panel of the supporting plate 1 is provided with a mounting hole 10. On the upper panel of the supporting plate 1, the mounting hole The top of 10 is fixedly provided with hoist 7, and described hoist 7 is connected with power supply by wire. The upper and lower ends of the mounting hole 10, which are also the front of the main panel of the supporting plate 1, are fixedly provided with two corresponding fixed lugs 13, and a connecting shaft 9 is arranged between the two fixing lugs 13, and the lower half of the connecting shaft 9 The part is covered with a pressure spring 11, and its upper half, that is, the top of the pressure spring 11 is provided with a stone mounting frame top hanging mechanism 5. The top of the top hanging mechanism 5 of the stone installation frame is provided with a winding roller 6 corresponding to the hoist drum, and a steel wire rope is wound on the hoist drum, and the steel rope is connected with a stone clamping mechanism 19 through the winding roller 6, so The above-mentioned stone material holding mechanism 19 is used for clamping decorative stone materials.

所述的石材安装架顶挂机构5包括有顶压联动杆14、固定钩联动杆15、连接臂16和固定钩17。所述的固定钩联动杆15为“L”形,其长边与承托板1主面板的正面相对,竖直向上延伸,其短边为一管型结构,向承托板1主面板的背面延伸,所述短边的中部设置有连接通孔,穿设于连接轴9上。在固定钩联动杆15的短边内设置有固定钩17,所述的固定钩17通过通孔也穿设于连接轴9上,固定钩17与承托板1之间连接有伸缩弹簧,固定钩17可以在连接轴9上左右转动,并通过所述伸缩弹簧复位。所述的顶压联动杆14的底部设置有一连接槽体,连接轴9穿过所述连接槽体,所述的固定钩联动杆15短边的底面上固定设置有连接耳板20,连接耳板20的下部铰接在顶压联动杆14上,固定钩联动杆15长边的顶端铰接有连接臂16,连接臂16与顶压联动杆14的上部铰接。The top hanging mechanism 5 of the stone installation frame includes a top pressing link 14 , a fixed hook link 15 , a connecting arm 16 and a fixed hook 17 . The fixed hook linkage rod 15 is "L" shaped, its long side is opposite to the front of the main panel of the supporting plate 1, and extends vertically upwards, and its short side is a tubular structure, facing the front of the main panel of the supporting plate 1. The back side extends, and the middle part of the short side is provided with a connecting through hole, which is passed through the connecting shaft 9 . A fixed hook 17 is arranged in the short side of the fixed hook linkage rod 15, and the fixed hook 17 is also pierced on the connecting shaft 9 through a through hole. The hook 17 can rotate left and right on the connecting shaft 9, and reset by the telescopic spring. The bottom of the top pressure linkage rod 14 is provided with a connection groove body, the connecting shaft 9 passes through the connection groove body, and the bottom surface of the short side of the fixed hook linkage rod 15 is fixedly provided with a connection lug plate 20, and the connection lugs The bottom of plate 20 is hinged on the pressing link 14, and the top of fixed hook link 15 long sides is hinged with connecting arm 16, and connecting arm 16 is hinged with the top of pressing link 14.

所述的顶压联动杆14为横杆和竖杆两个部分组成,所述的横杆设置在安装孔10内,其杆体上设置有连接槽体,所述的竖杆与承托板1的正面相对,竖杆的底端与横杆的一端铰接,其顶端设置有与卷扬机卷筒相对应的绕线滚轮6,所述的固定钩联动杆15长边的上部与顶压联动杆14竖杆的下部之间连接有拉伸弹簧。The top pressure linkage rod 14 is composed of two parts, a horizontal rod and a vertical rod. The horizontal rod is arranged in the installation hole 10, and a connecting groove is provided on the rod body. The vertical rod and the supporting plate 1 The front of the vertical bar is opposite, the bottom end of the vertical bar is hinged with one end of the horizontal bar, and its top is provided with a winding roller 6 corresponding to the hoisting machine reel. Tension springs are connected between the lower parts of the vertical bars.

当石材夹持机构19没有载物时,在所述压力弹簧和拉伸弹簧的作用下,使石材安装架顶挂机构5位于连接轴9的上部,从而使固定钩17与石材安装架的横梁处于分离状态,此状态下本发明所述的一种外墙装修石材干挂起吊装置主要是通过顶压联动杆14挂接于石材安装架的横梁上,当石材夹持结构19夹持有装修石材后,在装修石材自身重力的作用下,通过钢丝绳和绕线滚轮6,使顶压联动杆14的竖杆下移,其横杆也会受到竖杆向下的作用力,继而使横杆朝向石材安装架的一端上翘,同时所述竖杆通过连接臂16使连接轴9上的固定钩联动杆15向下移动,从而使固定钩17下移,与石材安装架的横梁挂接,固定钩17与顶压联动杆14的横杆互相配合,使本起吊装置固定于石材安装架的横梁上。施工人员取出装修石材后,安装架顶挂机构5通过压力弹簧和拉伸弹簧复位。When the stone clamping mechanism 19 did not carry objects, under the action of the pressure spring and the tension spring, the top hanging mechanism 5 of the stone installation frame was positioned at the top of the connecting shaft 9, so that the fixed hook 17 and the crossbeam of the stone installation frame In the separated state, in this state, a kind of external wall decoration stone dry-hanging lifting device according to the present invention is mainly hooked on the beam of the stone installation frame through the top pressure linkage rod 14, when the stone clamping structure 19 clamps the decoration After the stone is finished, under the action of the gravity of the decoration stone itself, the vertical bar of the top pressure linkage bar 14 is moved down through the steel wire rope and the winding roller 6, and its horizontal bar will also be subjected to the downward force of the vertical bar, and then the horizontal bar will be pushed down. One end towards the stone mounting frame is upturned, and at the same time, the vertical bar moves the fixed hook linkage rod 15 on the connecting shaft 9 downward through the connecting arm 16, so that the fixed hook 17 moves down and is articulated with the crossbeam of the stone mounting frame. Fixed hook 17 cooperates with the cross bar of top pressure linkage bar 14, makes this hoisting device be fixed on the cross beam of stone material installation frame. After the construction workers take out the decoration stone, the top hanging mechanism 5 of the installation frame is reset by the pressure spring and the tension spring.

进一步的,所述的顶压联动杆14的底部,朝向承托板1背面的一端设置有顶压滚轮18。Further, the bottom of the pressing linkage rod 14 is provided with a pressing roller 18 at the end facing the back of the supporting plate 1 .

进一步的,所述的石材夹持机构19包括固定夹臂25、活动夹臂26两个部分组成。所述的固定夹臂25为一“冂”形支架,固定夹臂25的上端设置有导向轮,一侧支臂为固定臂,另一侧支臂的下部铰接有活动夹臂26。活动夹臂26的上部铰接有连接支架,连接支架连接有固定环27,以连接钢丝绳。所述活动夹臂26为椭圆形,其x轴大于y轴,其转动圆心在其椭圆形的下部。卷扬机卷筒内的钢丝绳沿导线轮的底面穿过所述连接支架,与固定环27固定连接。Further, the stone clamping mechanism 19 includes two parts: a fixed clamp arm 25 and a movable clamp arm 26 . Described fixed clamp arm 25 is a " 冂 " shape support, and the upper end of fixed clamp arm 25 is provided with guide wheel, and one side support arm is fixed arm, and the bottom of other side support arm is hinged with movable clamp arm 26. The top of the movable clamp arm 26 is hinged with a connecting bracket, and the connecting bracket is connected with a fixed ring 27 to connect the wire rope. The movable clamp arm 26 is elliptical, its x-axis is greater than the y-axis, and its center of rotation is at the lower part of its ellipse. The wire rope in the hoist drum passes through the connecting bracket along the bottom surface of the guide wheel, and is fixedly connected with the fixed ring 27.

进一步的,所述的承托板1上板面的两端分别设置有固定吊臂8,固定吊臂8上设置有滚轮。Further, the two ends of the upper surface of the support plate 1 are respectively provided with fixed booms 8 , and rollers are arranged on the fixed booms 8 .

进一步的,所述的承托板1主面板的两端分别设置有安装孔,安装孔内设置有滑轮2。Further, the two ends of the main panel of the supporting plate 1 are respectively provided with installation holes, and pulleys 2 are arranged in the installation holes.

进一步的,所述的承托板1上面板的一端设置有固定板21,承托板1主面板上设置有与固定板21相对应的外固定板4,所述的固定板21与外固定板4之间具有一定间距,外固定板4上设置有电机3,电机3通过导线连接有电源,所述的电机3的输出轴穿过外固定板4,并设置在外固定板4与固定板21之间的空间内,电机3的输出轴上连接有驱动齿轮22。所述的承托板1主面板上设置有连接孔,连接孔内设置有轴承,轴承内设置有转轴24,所述的转轴24的一端设置在外固定板4与固定板21之间的空间内,且连接有与驱动齿轮22相啮合的传动齿轮23,转轴24的另一端穿过承托板1的主面板连接有传动轮,承托板1主面板背面的一端设置有与传动轮相对应的从动轮。所述的固定钩17与石材安装架的横梁处于分离状态时,启动电机3,通过驱动轮和传动轮,即可使本起吊装置在石材安装架的横梁上横向移动,当固定钩17触碰到石材安装架的竖梁时,固定钩17以连接轴9为轴转动,从而使本起吊装置顺利通过石材安装架的竖梁,通过竖梁后在所述伸缩弹簧的作用下使固定钩17复位。Further, one end of the upper panel of the supporting plate 1 is provided with a fixed plate 21, and the main panel of the supporting plate 1 is provided with an external fixed plate 4 corresponding to the fixed plate 21, and the described fixed plate 21 is connected with the external fixed plate. There is a certain distance between the plates 4, the outer fixed plate 4 is provided with a motor 3, the motor 3 is connected to a power supply through a wire, the output shaft of the motor 3 passes through the outer fixed plate 4, and is arranged between the outer fixed plate 4 and the fixed plate In the space between 21, the output shaft of motor 3 is connected with driving gear 22. The main panel of the supporting plate 1 is provided with a connecting hole, a bearing is arranged in the connecting hole, and a rotating shaft 24 is arranged in the bearing, and one end of the rotating shaft 24 is arranged in the space between the outer fixing plate 4 and the fixing plate 21 , and is connected with the transmission gear 23 meshing with the drive gear 22, the other end of the rotating shaft 24 passes through the main panel of the supporting plate 1 and is connected with a transmission wheel, and one end of the back of the main panel of the supporting plate 1 is provided with a gear corresponding to the transmission wheel. driven wheel. When the fixed hook 17 is separated from the crossbeam of the stone installation frame, start the motor 3, and the lifting device can be moved laterally on the crossbeam of the stone installation frame through the driving wheel and the transmission wheel. When the fixed hook 17 touches the When reaching the vertical beam of the stone mounting frame, the fixed hook 17 is rotated with the connecting shaft 9 as an axis, so that the hoisting device passes through the vertical beam of the stone mounting frame smoothly, and the fixed hook 17 is made to move under the action of the telescopic spring after passing through the vertical beam. reset.

进一步的,所述的承托板1下面板的两端连接有配重杆13,配重杆13的底端设置有滚轮,所述的承托板1主面板正面的两端设置有磁吸部,其背面的两端设置有结构相同的磁吸部。Further, the two ends of the lower panel of the supporting board 1 are connected with a counterweight rod 13, the bottom end of the counterweight rod 13 is provided with rollers, and the two ends of the front of the main panel of the supporting board 1 are provided with magnetic attraction The two ends of the back are provided with magnetic attraction parts with the same structure.

本发明所述的一种外墙装修石材干挂起吊装置的应用方法为:首先是通过固定钩17和顶压联动杆14将本起吊装置固定在石材安装架的横梁上,用一连接绳沿滚轮的底面穿过固定吊臂8,并将连接绳固定于石材安装架上,防止本起吊装置掉落。当石材夹持机构19没有载物,固定钩17与石材安装架的横梁处于分离状态时,可以对本起吊装置的位置进行调整,启动电机3,即可调整本起吊装置横向位置,到达所需位置后,关闭电机3。通过石材夹持机构19夹住装修石材,启动卷扬机7,将装修石材提升到所需的位置,关闭卷扬机7,施工人员进行安装。The application method of a dry-hanging lifting device for exterior wall decoration stone of the present invention is as follows: firstly, the lifting device is fixed on the beam of the stone mounting frame through the fixing hook 17 and the top pressure linkage rod 14, The bottom surface of roller passes fixed boom 8, and connecting rope is fixed on the stone material installation frame, prevents that this hoisting device from falling. When the stone clamping mechanism 19 has no load and the fixed hook 17 is separated from the crossbeam of the stone installation frame, the position of the lifting device can be adjusted, and the motor 3 can be started to adjust the horizontal position of the lifting device to reach the desired position After that, turn off motor 3. The decoration stone is clamped by the stone clamping mechanism 19, the hoist 7 is started, the decoration stone is lifted to the required position, the hoist 7 is closed, and the construction personnel install it.

本发明所述的一种外墙装修石材干挂起吊装置及其应用,其设计合理,结构简单,便于起吊、安装石材,省掉了石材安装槽扩槽这一工序,提升石材强度,能有效降低施工时产生的粉尘,减低工作强度,提高工作效率,同时还能节省大量的密封胶,提升经济效益。The dry-hanging and lifting device for stone for exterior wall decoration and its application according to the present invention has reasonable design and simple structure, is convenient for lifting and installing stone, saves the process of expanding the stone installation groove, improves the strength of stone, and can effectively Reduce dust generated during construction, reduce work intensity, improve work efficiency, and at the same time save a lot of sealant and improve economic benefits.

Claims (10)

1.一种外墙装修石材干挂起吊装置,包括有承载板(1)、石材安装架顶挂机构(5)、卷扬机(7)和石材夹持机构(19),所述的承载板(1)为本发明的主体支撑部件,且为一槽形钢体结构,其特征在于:承托板(1)主面板的中部设置有安装孔(10),在承托板(1)的上面板上,即安装孔(10)的上方设置有卷扬机(7),安装孔(10)的上下两端,也是承托板(1)主面板的正面设置有两个互相对应的固定耳板(13),两个固定耳板(13)之间设置有连接轴(9),连接轴(9)的下半部套设有压力弹簧(11),其上半部,即压力弹簧(11)的上面设置有石材安装架顶挂机构(5),石材安装架顶挂机构(5)的顶端设置有与卷扬机卷筒相对应的绕线滚轮(6),所述的卷扬机卷筒上绕设有钢丝绳,钢丝绳通过绕线滚轮(6)连接有石材加持机构(19)。1. A stone dry-hanging device for exterior wall decoration, including a load-bearing plate (1), a top-hanging mechanism (5) for a stone installation frame, a hoist (7) and a stone clamping mechanism (19), the load-bearing plate ( 1) It is the main body supporting part of the present invention, and it is a channel-shaped steel body structure, which is characterized in that: the middle part of the main panel of the supporting plate (1) is provided with an installation hole (10), and the upper part of the supporting plate (1) On the panel, that is, above the installation hole (10), there is a hoist (7), and the upper and lower ends of the installation hole (10), which are also the support plate (1), are provided with two corresponding fixed ear plates ( 13), a connecting shaft (9) is set between the two fixed lugs (13), the lower half of the connecting shaft (9) is covered with a pressure spring (11), and the upper half, namely the pressure spring (11) There is a top hanging mechanism (5) of the stone installation frame on the top of the stone installation frame (5), and a winding roller (6) corresponding to the hoist drum is arranged on the top of the stone installation rack top hang mechanism (5). Steel wire rope is arranged, and steel wire rope is connected with stone material holding mechanism (19) by winding roller (6). 2.根据权利要求1所述的一种外墙装修石材干挂起吊装置,其特征在于:所述的石材安装架顶挂机构(5)包括有顶压联动杆(14)、固定钩联动杆(15)、连接臂(16)和固定钩(17),所述的固定钩联动杆(15)为“L”形,其长边与承托板(1)主面板的正面相对,竖直向上延伸,其短边为一管型结构,向承托板(1)主面板的背面延伸,所述短边的中部设置有连接通孔,穿设于连接轴(9)上,在固定钩联动杆(15)的短边内设置有固定钩(17),所述的固定钩(17)通过通孔也穿设于连接轴(9)上,固定钩(17)与承托板(1)之间连接有伸缩弹簧,所述的顶压联动杆(14)的底部设置有一连接槽体,连接轴(9)穿过所述连接槽体,所述的固定钩联动杆(15)短边的底面上设置有连接耳板(20),连接耳板(20)的下部铰接在顶压联动杆(14)上,固定钩联动杆(15)长边的顶端铰接有连接臂(16),连接臂(16)与顶压联动杆(14)的上部铰接。2. A dry-hanging lifting device for exterior wall decoration stone according to claim 1, characterized in that: the top-hanging mechanism (5) of the stone installation frame includes a top pressure linkage rod (14), a fixed hook linkage rod (15), connecting arm (16) and fixed hook (17), the fixed hook linkage rod (15) is "L" shape, its long side is opposite to the front of the main panel of the support plate (1), vertical Extending upwards, its short side is a tubular structure extending to the back of the main panel of the supporting plate (1). The middle part of the short side is provided with a connecting through hole, which is pierced on the connecting shaft (9). The short side of the linkage rod (15) is provided with a fixed hook (17), and the fixed hook (17) is also pierced on the connecting shaft (9) through the through hole, and the fixed hook (17) and the supporting plate (1 ) is connected with a telescopic spring, the bottom of the top pressure linkage rod (14) is provided with a connection groove body, the connection shaft (9) passes through the connection groove body, and the fixed hook linkage rod (15) is short The bottom surface of the side is provided with a connecting ear plate (20), the lower part of the connecting ear plate (20) is hinged on the top pressure linkage rod (14), and the top of the long side of the fixed hook linkage rod (15) is hinged with a connecting arm (16). , the connecting arm (16) is hinged with the upper part of the pressing linkage rod (14). 3.根据权利要求2所述的一种外墙装修石材干挂起吊装置,其特征在于:所述的顶压联动杆(14)为横杆和竖杆两个部分组成,所述的横杆设置在安装孔(10)内,其杆体上设置有连接槽体,所述的竖杆与承托板(1)的正面相对,竖杆的底端与横杆的一端铰接,其顶端设置有与卷扬机卷筒相对应的绕线滚轮(6),所述的固定钩联动杆(15)长边的上部与顶压联动杆(14)竖杆的下部之间连接有拉伸弹簧。3. A dry-hanging lifting device for exterior wall decoration stone according to claim 2, characterized in that: the top pressure linkage rod (14) is composed of two parts: a horizontal bar and a vertical bar, and the horizontal bar Set in the installation hole (10), the rod body is provided with a connecting groove, the vertical rod is opposite to the front of the support plate (1), the bottom end of the vertical rod is hinged with one end of the horizontal rod, and the top end is provided with For the winding roller (6) corresponding to the hoisting machine reel, a tension spring is connected between the upper part of the long side of the fixed hook linkage lever (15) and the lower part of the vertical bar of the top pressure linkage lever (14). 4.根据权利要求2所述的一种外墙装修石材干挂起吊装置,其特征在于:所述的顶压联动杆(14)的底部,朝向承托板(1)背面的一端设置有顶压滚轮(18)。4. The dry-hanging device for stone materials for exterior wall decoration according to claim 2, characterized in that: the bottom of the top pressure linkage rod (14) is provided with a top end facing the back of the support plate (1). Pressure roller (18). 5.根据权利要求1所述的一种外墙装修石材干挂起吊装置,其特征在于:所述的石材夹持机构(19)包括固定夹臂(25)、活动夹臂(26)两个部分组成,所述的固定夹臂(25)为一“冂”形支架,固定夹臂(25)的上端设置有导向轮,一侧支臂为固定臂,另一侧支臂的下部铰接有活动夹臂(26),活动夹臂(26)的上部铰接有连接支架,连接支架连接有固定环(27),以连接钢丝绳,所述活动夹臂(26)为椭圆形,其x轴大于y轴,其转动圆心在其椭圆形的下部。5. A dry hanging device for exterior wall decoration stone according to claim 1, characterized in that: the stone clamping mechanism (19) includes two fixed clamping arms (25) and movable clamping arms (26). Partially composed, the fixed clamp arm (25) is a "冂" shaped bracket, the upper end of the fixed clamp arm (25) is provided with a guide wheel, one side of the support arm is a fixed arm, and the lower part of the other side of the support arm is hinged with a The movable clamp arm (26), the upper part of the movable clamp arm (26) is hinged with a connecting bracket, and the connecting bracket is connected with a fixed ring (27) to connect the wire rope. The movable clamp arm (26) is elliptical, and its x axis is greater than The y-axis, whose center of rotation is at the lower part of its ellipse. 6.根据权利要求1所述的一种外墙装修石材干挂起吊装置,其特征在于:所述的承托板(1)上板面的两端分别设置有固定吊臂(8),固定吊臂(8)上设置有滚轮。6. A dry-hanging lifting device for exterior wall decoration stone according to claim 1, characterized in that: the two ends of the upper surface of the support plate (1) are respectively provided with fixed booms (8), fixed The boom (8) is provided with rollers. 7.根据权利要求1所述的一种外墙装修石材干挂起吊装置,其特征在于:所述的承托板(1)主面板的两端分别设置有安装孔,安装孔内设置有滑轮(2)。7. A dry-hanging lifting device for exterior wall decoration stone according to claim 1, characterized in that: the two ends of the main panel of the supporting plate (1) are respectively provided with installation holes, and pulleys are arranged in the installation holes (2). 8.根据权利要求1所述的一种外墙装修石材干挂起吊装置,其特征在于:所述的承托板(1)上面板的一端设置有固定板(21),承托板(1)主面板上设置有与固定板(21)相对应的外固定板(4),所述的固定板(21)与外固定板(4)之间具有一定间距,外固定板(4)上设置有电机(3),所述的电机(3)的输出轴穿过外固定板(4),并设置在外固定板(4)与固定板(21)之间的空间内,电机(3)的输出轴上连接有驱动齿轮(22),所述的承托板(1)主面板上设置有连接孔,连接孔内设置有轴承,轴承内设置有转轴(24),所述的转轴(24)的一端设置在外固定板(4)与固定板(21)之间的空间内,且连接有与驱动齿轮(22)相啮合的传动齿轮(23),转轴(24)的另一端穿过承托板(1)的主面板连接有传动轮,承托板(1)主面板背面的一端设置有与传动轮相对应的从动轮。8. A dry-hanging device for stone materials for exterior wall decoration according to claim 1, characterized in that: one end of the upper panel of the supporting plate (1) is provided with a fixing plate (21), and the supporting plate (1) ) The main panel is provided with an outer fixed plate (4) corresponding to the fixed plate (21), there is a certain distance between the fixed plate (21) and the outer fixed plate (4), and the outer fixed plate (4) A motor (3) is provided, the output shaft of the motor (3) passes through the outer fixing plate (4), and is arranged in the space between the outer fixing plate (4) and the fixing plate (21), the motor (3) The output shaft of the drive gear (22) is connected, the main panel of the support plate (1) is provided with a connecting hole, a bearing is arranged in the connecting hole, and a rotating shaft (24) is arranged in the bearing, and the rotating shaft ( One end of 24) is set in the space between the outer fixed plate (4) and the fixed plate (21), and is connected with the transmission gear (23) meshed with the drive gear (22), and the other end of the rotating shaft (24) passes through The main panel of the supporting plate (1) is connected with a driving wheel, and one end of the back of the main panel of the supporting plate (1) is provided with a driven wheel corresponding to the driving wheel. 9.根据权利要求1所述的一种外墙装修石材干挂起吊装置,其特征在于:所述的承托板(1)下面板的两端连接有配重杆(13),配重杆(13)的底端设置有滚轮,所述的承托板(1)主面板正面的两端设置有磁吸部,其背面的两端设置有结构相同的磁吸部。9. A dry-hanging lifting device for exterior wall decoration stone according to claim 1, characterized in that: the two ends of the lower panel of the support plate (1) are connected with a weight bar (13), and the weight bar The bottom end of (13) is provided with rollers, the two ends of the front of the main panel of the support plate (1) are provided with magnetic attraction parts, and the two ends of the back are provided with magnetic attraction parts with the same structure. 10.如权利要求1所述的一种外墙装修石材干挂起吊装置的应用方法,其特征在于:首先是通过固定钩(17)和顶压联动杆(14)本起吊装置固定在石材安装架的横梁上,用一连接绳沿滚轮的底面穿过固定吊臂(8),并将连接绳固定于石材安装架上,防止本起吊装置掉落,当石材夹持机构(19)没有载物,固定钩(17)与石材安装架的横梁处于分离状态时,可以对本起吊装置的位置进行调整,启动电机(3),即可调整本起吊装置横向位置,到达所需位置后,关闭电机(3),通过石材夹持机构(19)夹住装修石材,启动卷扬机(7),将装修石材提升到所需的位置,关闭卷扬机(7),施工人员进行安装。10. The application method of a stone dry-hanging lifting device for exterior wall decoration as claimed in claim 1, characterized in that: firstly, the lifting device is fixed on the stone installation through the fixing hook (17) and the top pressure linkage rod (14). On the beam of the frame, use a connecting rope to pass through the fixed boom (8) along the bottom surface of the roller, and fix the connecting rope on the stone mounting frame to prevent the lifting device from falling. When the stone clamping mechanism (19) is not loaded When the fixed hook (17) is separated from the crossbeam of the stone installation frame, the position of the lifting device can be adjusted. Start the motor (3) to adjust the lateral position of the lifting device. After reaching the desired position, turn off the motor (3), the decoration stone is clamped by the stone clamping mechanism (19), the hoist (7) is started, the decoration stone is lifted to the required position, the hoist (7) is closed, and the construction personnel carry out the installation.
CN201710603174.0A 2017-07-22 2017-07-22 A dry hanging device for exterior wall decoration stone and its application Expired - Fee Related CN107386609B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710603174.0A CN107386609B (en) 2017-07-22 2017-07-22 A dry hanging device for exterior wall decoration stone and its application

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710603174.0A CN107386609B (en) 2017-07-22 2017-07-22 A dry hanging device for exterior wall decoration stone and its application

Publications (2)

Publication Number Publication Date
CN107386609A true CN107386609A (en) 2017-11-24
CN107386609B CN107386609B (en) 2023-09-08

Family

ID=60336049

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710603174.0A Expired - Fee Related CN107386609B (en) 2017-07-22 2017-07-22 A dry hanging device for exterior wall decoration stone and its application

Country Status (1)

Country Link
CN (1) CN107386609B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109281455A (en) * 2018-11-07 2019-01-29 山东港基建设集团有限公司 A kind of vertical patch block device of construction facilitating feeding
CN111058604A (en) * 2019-12-28 2020-04-24 蒋昌俊 Construction method for dry hanging of building decoration facing stone

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103255892A (en) * 2013-05-09 2013-08-21 陈发城 Installing device of veneers or stone curtain walls and construction method for dry hanging veneers or stone curtain walls
CN205616495U (en) * 2016-05-11 2016-10-05 浙江中升建设有限公司 Hoist device for building small -size
CN208039763U (en) * 2017-07-22 2018-11-02 李月成 A kind of exterior wall finishing stone material dry suspending boom hoisting

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103255892A (en) * 2013-05-09 2013-08-21 陈发城 Installing device of veneers or stone curtain walls and construction method for dry hanging veneers or stone curtain walls
CN205616495U (en) * 2016-05-11 2016-10-05 浙江中升建设有限公司 Hoist device for building small -size
CN208039763U (en) * 2017-07-22 2018-11-02 李月成 A kind of exterior wall finishing stone material dry suspending boom hoisting

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109281455A (en) * 2018-11-07 2019-01-29 山东港基建设集团有限公司 A kind of vertical patch block device of construction facilitating feeding
CN111058604A (en) * 2019-12-28 2020-04-24 蒋昌俊 Construction method for dry hanging of building decoration facing stone

Also Published As

Publication number Publication date
CN107386609B (en) 2023-09-08

Similar Documents

Publication Publication Date Title
CN112340599A (en) Freely-adjustable assembly type hoisting device for building wallboard
CN209601999U (en) A kind of packaged type power-assisted pipeline boom hoisting
CN107386609B (en) A dry hanging device for exterior wall decoration stone and its application
CN206634962U (en) A kind of removable simple and easy hoisting equipment
CN108483212A (en) Cladding glass installation self-control electric hoist hanger system and its hanging method
CN201292222Y (en) Reciprocating swing machine
CN207406013U (en) A kind of FRAME ON THE ROOF OF HIGH-RISE BUILDING curtain wall lifting device
CN201785135U (en) Lifting bracket for installation
CN210505314U (en) Hoisting device for civil air defense equipment installation
CN210710521U (en) Elevating gear for construction
CN211806925U (en) Steel tensioning device for prefabricated parts
CN223088857U (en) Steel structure fixing frame for reinforcing type house interior decoration
CN208039763U (en) A kind of exterior wall finishing stone material dry suspending boom hoisting
CN201678398U (en) High-rise indoor object-suspending device
CN109368523B (en) GRC board hangs and draws supplementary installation device
CN208135724U (en) A kind of tubular pole suspender
CN214141329U (en) A high-efficiency auxiliary device for prefabricated flue lifting
CN219885608U (en) Hoisting platform in elevator well
CN220723343U (en) Mobile gantry crane hovering positioning and installing equipment
CN223495985U (en) A type of hoisting frame that is easy to install on exterior walls
CN118255244B (en) A kind of hoisting equipment for assembling prefabricated highway small box beam
CN220058768U (en) Pulley type hanging basket hanging device
CN222293383U (en) A heavy structural part lifting device
CN213356752U (en) Building materials hoisting accessory for building
CN224030525U (en) Material lifting device for constructional engineering

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20230908