CN107366313A - 一种测斜管的埋设方法 - Google Patents

一种测斜管的埋设方法 Download PDF

Info

Publication number
CN107366313A
CN107366313A CN201710588264.7A CN201710588264A CN107366313A CN 107366313 A CN107366313 A CN 107366313A CN 201710588264 A CN201710588264 A CN 201710588264A CN 107366313 A CN107366313 A CN 107366313A
Authority
CN
China
Prior art keywords
inclinometer pipe
wire rope
steel wire
half button
button bowl
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710588264.7A
Other languages
English (en)
Other versions
CN107366313B (zh
Inventor
刘国良
管泽英
刘垚
张泽卫
许俊伟
逄锦伟
卢金栋
代昱昊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Tunnel Group Co Ltd CRTG
Original Assignee
China Railway Tunnel Group Co Ltd CRTG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Tunnel Group Co Ltd CRTG filed Critical China Railway Tunnel Group Co Ltd CRTG
Priority to CN201710588264.7A priority Critical patent/CN107366313B/zh
Publication of CN107366313A publication Critical patent/CN107366313A/zh
Application granted granted Critical
Publication of CN107366313B publication Critical patent/CN107366313B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

一种测斜管的埋设方法,通过在测斜管上安装固定装置使测斜管与钢筋笼连接,达到固定测斜管的目的,所述固定装置包括:包括上半扣碗和下半扣碗,所述上半扣碗和下半扣碗的外侧均设有两个钢丝绳收纳器,所述钢丝绳收纳器内设有钢丝绳,从而保证测斜管绑扎的平顺,保证测量数据的精度准确。

Description

一种测斜管的埋设方法
技术领域:
本发明属于基坑监测技术领域,主要提出一种测斜管的埋设方法。
背景技术:
基坑围护结构施工中,为监测围护结构的变形情况,需埋设测斜管,测斜埋设分预埋式和钻孔埋设两种,钻孔式在连续墙或桩施工完成后对其进行取芯进行测斜管的埋设,预埋式测斜管是预先绑扎在连续墙或桩的钢筋笼内部,绑扎主要通过铁丝或扎丝将测斜管与钢筋笼进行连接,但绑扎平顺度差,造成测斜管弯折,影响监测数据精度,严重时测斜管无法使用,降低对基坑风险的预测的准确性。怎样有效的解决测斜管绑扎的平顺已至关重的要。
目前对于测斜管绑扎主要通过铁丝或扎丝将测斜管与钢筋笼进行连接,以达到测斜管预埋的目的,因绑扎时测斜管与钢筋直接接触,接触面不平整,造成测斜管平顺度低,影响监测数据精度,严重时测斜管无法使用。
发明内容:
为了克服上述的不足,本发明提供了一种测斜管的埋设方法,通过在测斜管上安装固定装置使测斜管与钢筋笼连接,达到固定测斜管的目的,保证测斜管绑扎的平顺。
本发明解决其技术问题所采用的技术方案:
一种测斜管的埋设方法,包括如下步骤:
A、将2m或4m一节的测斜管通过接头管连接,用四颗自功螺丝将接头管与测斜管固定好,使测斜管连接到要求长度;
B、在步骤A中连接好的测斜管上每隔1.5-2米的间距设置固定装置,所述固定装置包括上半扣碗和下半扣碗,所述上半扣碗和下半扣碗的外侧均设有两个钢丝绳收纳器,所述钢丝绳收纳器内设有钢丝绳;
C、通过钢丝绳收纳器中的钢丝绳将测斜管固定在钢筋笼上,再调整好测斜管位置后,将钢丝绳固定;
D、重复步骤B和C,将整根测斜管完全固定。
所述钢丝绳的长度1米。
所述上半扣碗和下半扣碗均呈半圆形,二者通过螺栓或者卡扣固定在测斜管上。
由于采用如上所述的技术方案,本发明具有如下优越性:
本发明所述的一种测斜管的埋设方法,通过在测斜管上安装固定装置使测斜管与钢筋笼连接,达到固定测斜管的目的,保证测斜管绑扎的平顺,保证测量数据的精度准确。
附图说明:
图1为采用本发明测斜管固定装置剖面示意图。
图2为采用本发明测斜管固定装置与钢筋连接剖面图示意图。
图3为采用本发明测斜管固定装置平面示意图。
图中:1、测斜管,2、上半扣碗,3、下半扣碗,4、钢丝绳收纳器,5、钢筋笼,6、钢丝绳,7、固定装置。
具体实施方式:
通过下面实施例可以更详细的解释本发明,公开本发明的目的旨在保护本发明范围内的一切变化和改进,本发明并不局限于下面的实施例;
如图所示的一种测斜管的埋设方法,包括如下步骤:
A、将2m或4m一节的测斜管1通过接头管连接,用四颗自功螺丝将接头管与测斜管1固定好,使测斜管连接到要求长度;
B、在步骤A中连接好的测斜管上每隔1.5-2米的间距设置固定装置7,所述固定装置7包括上半扣碗2和下半扣碗3,所述上半扣碗2和下半扣碗3的外侧均设有两个钢丝绳收纳器4,所述钢丝绳收纳器4内设有钢丝绳6;
C、通过钢丝绳收纳器4中的钢丝绳6将测斜管1固定在钢筋笼5上,再调整好测斜管1位置后,将钢丝绳6固定;
D、重复步骤B和C,将整根测斜管完全固定。
所述钢丝绳6的长度1米。
所述上半扣碗2和下半扣碗3均呈半圆形,二者通过螺栓或者卡扣固定在测斜管上。
以上内容中未细述部份为现有技术,故未做细述。

Claims (3)

1.一种测斜管的埋设方法,其特征在于:包括如下步骤:
A、将2m或4m一节的测斜管通过接头管连接,用四颗自功螺丝将接头管与测斜管固定好,使测斜管连接到要求长度;
B、在步骤A中连接好的测斜管上每隔1.5-2米的间距设置固定装置,所述固定装置包括上半扣碗和下半扣碗,所述上半扣碗和下半扣碗的外侧均设有两个钢丝绳收纳器,所述钢丝绳收纳器内设有钢丝绳;
C、通过钢丝绳收纳器中的钢丝绳将测斜管固定在钢筋笼上,再调整好测斜管位置后,将钢丝绳固定;
D、重复步骤B和C,将整根测斜管完全固定。
2.根据权利要求1所述的一种测斜管的埋设方法,其特征在于:所述钢丝绳的长度1米。
3.根据权利要求1所述的一种测斜管的埋设方法,其特征在于:所述上半扣碗和下半扣碗均呈半圆形,二者通过螺栓或者卡扣固定在测斜管上。
CN201710588264.7A 2017-07-19 2017-07-19 一种测斜管的埋设方法 Active CN107366313B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710588264.7A CN107366313B (zh) 2017-07-19 2017-07-19 一种测斜管的埋设方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710588264.7A CN107366313B (zh) 2017-07-19 2017-07-19 一种测斜管的埋设方法

Publications (2)

Publication Number Publication Date
CN107366313A true CN107366313A (zh) 2017-11-21
CN107366313B CN107366313B (zh) 2020-08-28

Family

ID=60308148

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710588264.7A Active CN107366313B (zh) 2017-07-19 2017-07-19 一种测斜管的埋设方法

Country Status (1)

Country Link
CN (1) CN107366313B (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109900237A (zh) * 2017-12-11 2019-06-18 上海岩土工程勘察设计研究院有限公司 一种多节钢筋笼地墙测斜管连接装置及安装方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005061985A (ja) * 2003-08-12 2005-03-10 Shimizu Corp 地中変位計測システム
JP2010150810A (ja) * 2008-12-25 2010-07-08 Nishimatsu Constr Co Ltd 傾斜測定用冶具及び傾斜測定方法
CN203357324U (zh) * 2013-07-29 2013-12-25 中国矿业大学(北京) 超长测斜管的埋设装置
CN205399505U (zh) * 2016-02-26 2016-07-27 上海中测行工程检测咨询有限公司 一种测斜管的固定装置
CN206205012U (zh) * 2016-09-30 2017-05-31 中设设计集团股份有限公司 一种smw工法桩测斜管布设装置

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005061985A (ja) * 2003-08-12 2005-03-10 Shimizu Corp 地中変位計測システム
JP2010150810A (ja) * 2008-12-25 2010-07-08 Nishimatsu Constr Co Ltd 傾斜測定用冶具及び傾斜測定方法
CN203357324U (zh) * 2013-07-29 2013-12-25 中国矿业大学(北京) 超长测斜管的埋设装置
CN205399505U (zh) * 2016-02-26 2016-07-27 上海中测行工程检测咨询有限公司 一种测斜管的固定装置
CN206205012U (zh) * 2016-09-30 2017-05-31 中设设计集团股份有限公司 一种smw工法桩测斜管布设装置

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109900237A (zh) * 2017-12-11 2019-06-18 上海岩土工程勘察设计研究院有限公司 一种多节钢筋笼地墙测斜管连接装置及安装方法

Also Published As

Publication number Publication date
CN107366313B (zh) 2020-08-28

Similar Documents

Publication Publication Date Title
CN102607488B (zh) 一种监测滑坡滑动面位移变形的装置及方法
KR101072721B1 (ko) 말뚝 정재하 시험장치
CN103243747B (zh) 预应力混凝土管桩桩基的纠偏方法
CN103711151B (zh) 波压力传感器预埋装置及其埋设方法
CN105735374B (zh) 一种高应变法测试桩的承载力的方法
CN105672314B (zh) 一种半逆作法钢管立柱桩施工方法
CN203337138U (zh) 一种水平测斜仪的牵引辅助装置
CN111254920B (zh) 一种逆作工程钢管混凝土柱安装施工方法和逆作工程钢管混凝土柱施工结构
CN102788569A (zh) 一种地质变形及滑塌预警系统
CN109797782A (zh) 一种沉管隧道接头张开量监测装置及方法
CN202974148U (zh) 一种输电线杆底盘卡盘埋深探测工具
CN208721064U (zh) 一种城市隧道上跨既有地铁隧道的实时监测系统
CN105350488A (zh) 一种新型板桩码头的试验装置及其制作方法和试验方法
KR100955599B1 (ko) 지하수위 자동계측 장치
CN201865111U (zh) 海上自升式钻井平台插桩及拔桩自动控制装置
CN214747897U (zh) 一种建筑施工监测系统
CN107366313A (zh) 一种测斜管的埋设方法
KR101191131B1 (ko) 흙막이 가시설 구조물의 변위 계측장치
CN206529812U (zh) 一种直埋式测试系统
CN113605377A (zh) 一种岩石地层超深钢管柱与抗拔桩联合施工工艺
CN209894167U (zh) 一种隧道顶板围岩位移测量装置
CN105547248A (zh) 一种快装自动测斜管及监测方法
CN205296219U (zh) 钢管柱液压抱紧和垂直插入工法机
CN207214967U (zh) 一种管幕超前支护条件下管节水平位移的监测装置
CN217174960U (zh) 一种监测不同深度水平位移的埋入式测量装置

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant