CN107330585A - A kind of method that shipbuilding data integrated system and auxiliary build ship - Google Patents
A kind of method that shipbuilding data integrated system and auxiliary build ship Download PDFInfo
- Publication number
- CN107330585A CN107330585A CN201710451253.4A CN201710451253A CN107330585A CN 107330585 A CN107330585 A CN 107330585A CN 201710451253 A CN201710451253 A CN 201710451253A CN 107330585 A CN107330585 A CN 107330585A
- Authority
- CN
- China
- Prior art keywords
- information
- shipbuilding
- product
- information database
- integrated system
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 67
- 238000003466 welding Methods 0.000 claims abstract description 31
- 238000004519 manufacturing process Methods 0.000 claims abstract description 28
- 238000007726 management method Methods 0.000 claims abstract description 27
- 238000005516 engineering process Methods 0.000 claims abstract description 16
- 230000008569 process Effects 0.000 claims abstract description 15
- 238000010276 construction Methods 0.000 claims description 20
- 238000012217 deletion Methods 0.000 claims description 12
- 230000037430 deletion Effects 0.000 claims description 12
- 230000011218 segmentation Effects 0.000 claims description 12
- 230000009471 action Effects 0.000 claims description 10
- 230000008439 repair process Effects 0.000 claims description 7
- 238000012545 processing Methods 0.000 claims description 6
- 238000003860 storage Methods 0.000 claims description 6
- 238000004458 analytical method Methods 0.000 claims description 4
- 239000002184 metal Substances 0.000 claims description 4
- 238000012986 modification Methods 0.000 claims description 3
- 230000004048 modification Effects 0.000 claims description 3
- 239000000463 material Substances 0.000 claims description 2
- 238000005259 measurement Methods 0.000 claims description 2
- 230000008859 change Effects 0.000 claims 1
- 238000011160 research Methods 0.000 abstract description 5
- 230000008901 benefit Effects 0.000 abstract description 3
- 230000002452 interceptive effect Effects 0.000 abstract description 3
- 230000000454 anti-cipatory effect Effects 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 238000013461 design Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000008014 freezing Effects 0.000 description 1
- 238000007710 freezing Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/04—Manufacturing
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/30—Computing systems specially adapted for manufacturing
Landscapes
- Business, Economics & Management (AREA)
- Engineering & Computer Science (AREA)
- Human Resources & Organizations (AREA)
- Strategic Management (AREA)
- Entrepreneurship & Innovation (AREA)
- Economics (AREA)
- General Business, Economics & Management (AREA)
- General Physics & Mathematics (AREA)
- Marketing (AREA)
- Theoretical Computer Science (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Health & Medical Sciences (AREA)
- General Health & Medical Sciences (AREA)
- Development Economics (AREA)
- Educational Administration (AREA)
- Manufacturing & Machinery (AREA)
- Game Theory and Decision Science (AREA)
- Primary Health Care (AREA)
- Data Mining & Analysis (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- General Factory Administration (AREA)
Abstract
This hair discloses a kind of shipbuilding data integrated system, including the method that basic information database, technique information database, production information database, precision controlling information database, Product Information Management module, resource management module, technique views module, production views module and accuracy standard management module and auxiliary build ship.The disclosed of the present invention utilizes the method that the shipbuilding data integrated system auxiliary ship station is built.The present invention is built using Computer Aided Ship, and shipbuilding process is information-based, is solved the Research on Interactive Problem between assembly technology, welding procedure, building technology etc., is reduced time and the cost of shipbuilding, improve shipbuilding benefit.
Description
Technical field
The invention belongs to shipbuilding technical management field, it is related to a kind of shipbuilding data integrated system and auxiliary is built
The method of shipbuilding oceangoing ship.
Background technology
Shipbuilding is a complicated engineering project, the features such as with small lot, tight cycle, many work post products.With
Modular shipbuilding pattern progressively comes into effect in China's shipyard, and sectional construction turns into the Main Patterns of China's shipyard shipbuilding.
Since 1990s, shipbuilding developed country conducts a research in terms of digital shipbuilding at first, particularly pair
The research of virtual ship design and ship emulation technology.At present, the digital shipbuilding of the shipbuilding enterprise such as South Korea and Japan and virtual
Emulation technology is maintained the leading position in international shipbuilding market, and China's digital shipbuilding, virtual shipbuilding etc. are started late, near several
Year is gradually paid close attention to by each universities and colleges and shipyard.In addition, in order to reach the quality requirement constantly lifted and technological requirement, solving dress
With the Research on Interactive Problem between technique, welding procedure, building technology etc., it is also desirable to which formation process is information-based, to reduce shipbuilding
Time and cost, improve shipbuilding benefit.
The content of the invention
Goal of the invention:The problem of existing for prior art, the present invention provide a kind of shipbuilding data integrated system and
The method that auxiliary builds ship, in real time to the real-time tracking of construction progress, realizes assembly technology, welding procedure, building technology etc.
Between collaboration.
The content of the invention:The present invention provides a kind of shipbuilding integrated system, including basic information database, technique information number
According to storehouse, production information database, precision controlling information database, Product Information Management module, resource management module, technique view
Module, production views module and accuracy standard management module;
The basic information database is used to preserving product information involved during shipbuilding and builds resource base
Plinth information, the product include block, segmentation and part, the construction resource base information include building equipment resource information,
Technological document information, place resource information, establishment officer's information;
The technique information database is used to store assembly technology information and welding procedure information;
The production information database is used to preserve job-shop scheduling plan and yard planning;
The precision controlling information database is used to store product precision control information;
The Product Information Management module is used to obtain the product information in basic information database, and it is added
Plus, delete, update, deletion action;
The resource management module is used to obtain the construction resource base information in basic information database, and it is carried out
Addition, deletion, renewal, deletion action;
The technique views module is used for the assembling process of products and welding procedure information for obtaining technique information database, and
It is added, updated, is deleted, operation is exported;
The production views module is used for product cell plan, the marshalling plan information for obtaining production information database, and
It is added, updated, is deleted, operation is exported;
The accuracy standard module is used for the product precision control information for obtaining accuracy standard database, and it is added
Plus, update, delete, output operation.
The method built using above-mentioned shipbuilding data integrated system auxiliary ship station, is comprised the following steps:
Step 1, Product Information Management module are interacted with basic information database, obtain shipbuilding product (such as block, point
Section and portion's part) information, and product information is increased, changed, deletion action;Resource management module and essential information data
Storehouse is interacted, and obtains the construction resource base information needed for shipbuilding, and increased building resource base information, changed,
Deletion action;
Step 2, shipbuilding assembling and welding process views module are interacted with technique information database, obtain based on boat segmental,
The assembling process of products and welding procedure information of part, and assembling process of products and welding procedure information are increased, changed,
Delete, output is operated;
Step 3, shipbuilding production views module are interacted with production information database, are obtained and are based on boat segmental, part
Product cell schedule job information and yard job information, and product cell schedule job and yard operation are believed
Breath is increased, changed, being deleted, exporting operation;
Step 4, shipbuilding accuracy standard views module are interacted with shipbuilding control information database, are obtained and are based on ship
Oceangoing ship block, the shipbuilding precision controlling information of segmentation, and product precision control information is increased, changes, delete, exporting
Operation.
Beneficial effect:Built using Computer Aided Ship, shipbuilding process is information-based, solve assembly technology, welding
Research on Interactive Problem between technique, building technology etc., reduces time and the cost of shipbuilding, improves shipbuilding benefit.
Brief description of the drawings
Fig. 1 is shipbuilding data integrated system structural representation;
Fig. 2 is building equipment resource management flow chart;
Fig. 3 is production plan management flow chart.
Embodiment
Below in conjunction with the accompanying drawings and specific embodiment, the invention will be further described.
Shipbuilding integrated system as shown in Figure 1, including basic information database, technique information database, production letter
Breath database, precision controlling information database, Product Information Management module, resource management module, technique views module, production are regarded
Module and accuracy standard management module;The basic information database is used to preserve involved product during shipbuilding
Information and construction resource base information, the product include block, segmentation and part, and the construction resource base information includes building
Manufacturing apparatus resource information, technological document information, place resource information, establishment officer's information;The technique information database is used for
Store assembly technology information and welding procedure information;The production information database is used to preserve job-shop scheduling plan and stockyard is adjusted
Degree plan;The precision controlling information database is used to store product precision control information;The Product Information Management module is used
In obtain basic information database in product information, and it is added, deleted, is updated, deletion action;The resource pipe
Reason module is used to obtain the construction resource base information in basic information database, and it is added, delete, update, deleted
Division operation;The technique views module is used for the assembling process of products and welding procedure information for obtaining technique information database, and
It is added, updated, is deleted, operation is exported;The production views module is used for the product for obtaining production information database
Workshop plan, marshalling plan information, and it is added, updated, is deleted, operation is exported;The accuracy standard module is used for
The product precision control information of accuracy standard database is obtained, and it is added, updated, is deleted, operation is exported.
The product information includes digital numbering, production code member, product size, product weight and Product processing state.Institute
Stating Product processing state includes:Part processing, part making, block assembly, ssection fitting-out, block combination, block outfitting, building berth
General assembly, berth fitting-out.
The building equipment resource information includes device numbering, device name, number of devices and equipment control state;It is described
Technological document information includes document code, document title and document content;The place resource information includes site location, place
Size and place use state information;Establishment officer's information includes personnel's job number, name and its affiliated unit's information.It is described
Equipment control state includes:Application purchase, application arrival, be put in storage, receive, receive returns, borrow, borrow return, normal loss,
Damage, send and repair, send and repair return.
The assembly technology information includes digital numbering, name of product, initial link, Assembly sequences number, sequence number, starting point structure
Part, starting point assembling element, terminal component, terminal assembling element;The welding procedure information is numbered including numeral, mother metal is numbered,
Mother metal thickness, welding position, welding method, groove type, welding material, weld diameter, welding current, weldingvoltage and welding
Speed.
The job-shop scheduling plan include digital numbering, name of product, build the side, with reference to abscissa, with reference to ordinate,
Tire date, plan lower tire date on construction direction, plan;The yard planning includes digital numbering, name of product, stockyard
Title, with reference to abscissa, with reference to ordinate, build direction, into the stockyard date, leave the stockyard date.
The product precision control information is responsible for including digital numbering, total number of engineering, report name, unit in charge of construction, construction
People, surveyor, check mode, analysis result, measurement date and the analysis of causes.
The method built using above-mentioned shipbuilding data integrated system auxiliary ship station, is comprised the following steps:
Step 1, Product Information Management module are interacted with basic information database, obtain shipbuilding product (such as block, point
Section and portion's part) information, and product information is increased, changed, deletion action;Resource management module and essential information data
Storehouse is interacted, and obtains the construction resource base information needed for shipbuilding, and increased building resource base information, changed,
Deletion action;
Step 2, shipbuilding assembling and welding process views module are interacted with technique information database, obtain based on boat segmental,
The assembling process of products and welding procedure information of part, and assembling process of products and welding procedure information are increased, changed,
Delete, output is operated;
Step 3, shipbuilding production views module are interacted with production information database, are obtained and are based on boat segmental, part
Product cell schedule job information and yard job information, and product cell schedule job and yard operation are believed
Breath is increased, changed, being deleted, exporting operation;
Step 4, shipbuilding accuracy standard views module are interacted with shipbuilding control information database, are obtained and are based on ship
Oceangoing ship block, the shipbuilding precision controlling information of segmentation, and product precision control information is increased, changes, delete, exporting
Operation.
Wherein, the process step of managing construction device resource such as Fig. 2, be specially:
Step 1, to building equipment resource node attribute carry out application purchase operation, then be transferred to wait and apply to purchase arrival state;
After completing to apply to purchase arrival operation, then wait binning state is transferred to;After in-stockroom operation is clicked on, storage is completed;
After step 2, completion equipment storage, borrow operation is carried out to nodal community, then is transferred to wait and borrows return state;When
Complete to borrow and return after operation, complete the return binning state of equipment;
After step 3, completion equipment storage, nodal community is carried out to receive operation, then is transferred to wait and receives return state;When
Completion is received after return operation, completes the return binning state of equipment;
Step 4, complete after equipment storage, normal loss is carried out to nodal community or is damaged to operate, then is transferred to wait and send and repair
State;When complete equipment send repair operation after, then be transferred to wait and send and repair return state;After completion, which is sent, repaiies return operation, complete to set
Standby return binning state.
Process step such as Fig. 3 of job scheduling plan is managed, is specially:
Step 1, job scheduling plan information of the reading based on product, check segmentation in building course respectively in workshop, heap
Field two-part plan starting date, scheduled completion date, position coordinates, construction direction etc., into planning management state;
Its original plan information and the corresponding modification of work are checked in step 2, the segmentation to not freezing, not sending work or multiple segmentations,
It is final to preserve rational modification result;
Step 3, the rational segmentation progress freeze operation of selection in fractional anticipatory message structure tree, wait and plan to send work simultaneously
Perform;
Step 4, in fractional anticipatory message structure tree frozen plan is carried out sending work, generation job order simultaneously assigns work
Industry task;
Step 5, the segmentation progress Job Completion registration completed to operation, the record hit the target.
Claims (9)
1. a kind of shipbuilding integrated system, it is characterised in that including basic information database, technique information database, production
Information database, precision controlling information database, Product Information Management module, resource management module, technique views module, production
Views module and accuracy standard management module;
The basic information database is used to preserving product information involved during shipbuilding and builds resource base letter
Breath, the product includes block, segmentation and part, and the construction resource base information includes building equipment resource information, technology
Fileinfo, place resource information, establishment officer's information;
The technique information database is used to store assembly technology information and welding procedure information;
The production information database is used to preserve job-shop scheduling plan and yard planning;
The precision controlling information database is used to store product precision control information;
The Product Information Management module is used to obtain the product information in basic information database, and it is added, deleted
Remove, update, deletion action;
The resource management module is used to obtain the construction resource base information in basic information database, and it is added
Plus, delete, update, deletion action;
The technique views module is used for the assembling process of products and welding procedure information for obtaining technique information database, and to it
It is added, updates, deleting, exports operation;
The production views module is used for product cell plan, the marshalling plan information for obtaining production information database, and to it
It is added, updates, deleting, exports operation;
The accuracy standard module is used to obtaining the product precision control information of accuracy standard database, and it is added,
Update, delete, output is operated.
2. shipbuilding integrated system according to claim 1, it is characterised in that the product information includes numeral and compiled
Number, production code member, product size, product weight and Product processing state.
3. shipbuilding integrated system according to claim 2, it is characterised in that the Product processing state includes:Zero
Part processing, part making, block assembly, ssection fitting-out, block combination, block outfitting, building berth general assembly, berth fitting-out.
4. shipbuilding integrated system according to claim 1, it is characterised in that the building equipment resource information includes
Device numbering, device name, number of devices and equipment control state;The technological document information includes document code, document name
Claim and document content;The place resource information includes site location, place size and place use state information;The tissue
Personal information includes personnel's job number, name and its affiliated unit's information.
5. shipbuilding integrated system according to claim 4, it is characterised in that the equipment control state includes:Shen
It please buy, apply for arrival, be put in storage, receive, receive return, borrow, borrow return, normal loss, damage, send and repair, send and repair return.
6. shipbuilding integrated system according to claim 1, it is characterised in that the assembly technology information includes numeral
Numbering, name of product, initial link, Assembly sequences number, sequence number, starting point component, starting point assembling element, terminal component, terminal dress
With element;The welding procedure information includes digital numbering, mother metal numbering, mother metal thickness, welding position, welding method, groove
Form, welding material, weld diameter, welding current, weldingvoltage and speed of welding.
7. shipbuilding integrated system according to claim 1, it is characterised in that the job-shop scheduling plan includes numeral
Numbering, name of product, build the side, with reference to abscissa, with reference to ordinate, built direction, plan upper tire date, plan and play tire day
Phase;The yard planning include digital numbering, name of product, stockyard title, with reference to abscissa, with reference to ordinate, construction
Direction, into the stockyard date, leave the stockyard date.
8. shipbuilding integrated system according to claim 1, it is characterised in that the product precision control information includes
Digital numbering, total number of engineering, report name, unit in charge of construction, construction director, surveyor, check mode, analysis result, measurement
Date and the analysis of causes.
9. the method built using the shipbuilding data integrated system auxiliary ship station described in claim 1-8 any one, its
It is characterised by, comprises the following steps:
Step 1, Product Information Management module are interacted with basic information database, obtain shipbuilding product (such as block, segmentation and
Portion's part) information, and product information is increased, changed, deletion action;Resource management module is handed over basic information database
Mutually, the construction resource base information needed for shipbuilding is obtained, and is increased building resource base information, is changed, deletes
Operation;
Step 2, shipbuilding assembling and welding process views module are interacted with technique information database, are obtained and are based on boat segmental, part
Assembling process of products and welding procedure information, and assembling process of products and welding procedure information are increased, changes, delete
Remove, export operation;
Step 3, shipbuilding production views module are interacted with production information database, obtain the production based on boat segmental, part
Product Job-Shop job information and yard job information, and product cell schedule job and yard job information are entered
Row increase, modification, deletion, output operation;
Step 4, shipbuilding accuracy standard views module are interacted with shipbuilding control information database, obtain total based on ship
Section, the shipbuilding precision controlling information of segmentation, and product precision control information is increased, change, delete, exports behaviour
Make.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710451253.4A CN107330585A (en) | 2017-06-15 | 2017-06-15 | A kind of method that shipbuilding data integrated system and auxiliary build ship |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710451253.4A CN107330585A (en) | 2017-06-15 | 2017-06-15 | A kind of method that shipbuilding data integrated system and auxiliary build ship |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107330585A true CN107330585A (en) | 2017-11-07 |
Family
ID=60194866
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710451253.4A Pending CN107330585A (en) | 2017-06-15 | 2017-06-15 | A kind of method that shipbuilding data integrated system and auxiliary build ship |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107330585A (en) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108256027A (en) * | 2018-01-10 | 2018-07-06 | 圣泓工业设计创意有限公司 | A kind of ship technique manufactures micro-system |
CN109460606A (en) * | 2018-11-08 | 2019-03-12 | 上海船舶工艺研究所(中国船舶工业集团公司第十研究所) | Calculation method when a kind of Welder based on boat segmental mode of construction |
CN110427647A (en) * | 2019-06-28 | 2019-11-08 | 江南造船(集团)有限责任公司 | Technique synergy emulation method, electronic device and storage medium |
CN110659844A (en) * | 2019-09-30 | 2020-01-07 | 哈尔滨工程大学 | Optimization method for assembly resource scheduling of mail-carrier outfitting workshop |
CN110990663A (en) * | 2019-12-04 | 2020-04-10 | 中船黄埔文冲船舶有限公司 | Ship process knowledge management method, device and system |
CN111667140A (en) * | 2020-04-26 | 2020-09-15 | 招商局重工(深圳)有限公司 | Method for building large cutter suction dredger |
CN111815286A (en) * | 2020-07-15 | 2020-10-23 | 厦门船舶重工股份有限公司 | Welding process information system |
CN111917836A (en) * | 2020-07-13 | 2020-11-10 | 成都鹦鹉螺大数据科技有限公司 | Industrial equipment cloud thing allies oneself with system |
CN113792385A (en) * | 2021-09-22 | 2021-12-14 | 江南造船(集团)有限责任公司 | Construction method, device, storage medium and system of ship cooperative basic resource library |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101976288A (en) * | 2010-10-30 | 2011-02-16 | 上海交通大学 | Ship subsection manufacture analog system |
CN103049620A (en) * | 2013-01-09 | 2013-04-17 | 江南造船(集团)有限责任公司 | Ship simulating system and ship simulating method used during shipbuilding |
CN106056286A (en) * | 2016-06-01 | 2016-10-26 | 江苏科技大学 | Ship sectional construction workshop operation scheduling system and scheduling method thereof |
CN106802990A (en) * | 2017-01-06 | 2017-06-06 | 江南造船(集团)有限责任公司 | A kind of shipbuilding human engineering method of tire and system |
-
2017
- 2017-06-15 CN CN201710451253.4A patent/CN107330585A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101976288A (en) * | 2010-10-30 | 2011-02-16 | 上海交通大学 | Ship subsection manufacture analog system |
CN103049620A (en) * | 2013-01-09 | 2013-04-17 | 江南造船(集团)有限责任公司 | Ship simulating system and ship simulating method used during shipbuilding |
CN106056286A (en) * | 2016-06-01 | 2016-10-26 | 江苏科技大学 | Ship sectional construction workshop operation scheduling system and scheduling method thereof |
CN106802990A (en) * | 2017-01-06 | 2017-06-06 | 江南造船(集团)有限责任公司 | A kind of shipbuilding human engineering method of tire and system |
Non-Patent Citations (1)
Title |
---|
陈旭东: "船舶分段堆场调度系统开发与关键技术研究", 《中国优秀硕士学位论文全文数据库 信息科技Ⅱ辑》 * |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108256027A (en) * | 2018-01-10 | 2018-07-06 | 圣泓工业设计创意有限公司 | A kind of ship technique manufactures micro-system |
CN109460606A (en) * | 2018-11-08 | 2019-03-12 | 上海船舶工艺研究所(中国船舶工业集团公司第十研究所) | Calculation method when a kind of Welder based on boat segmental mode of construction |
CN110427647A (en) * | 2019-06-28 | 2019-11-08 | 江南造船(集团)有限责任公司 | Technique synergy emulation method, electronic device and storage medium |
CN110427647B (en) * | 2019-06-28 | 2022-11-29 | 江南造船(集团)有限责任公司 | Process collaborative simulation method, electronic device and storage medium |
CN110659844A (en) * | 2019-09-30 | 2020-01-07 | 哈尔滨工程大学 | Optimization method for assembly resource scheduling of mail-carrier outfitting workshop |
CN110990663A (en) * | 2019-12-04 | 2020-04-10 | 中船黄埔文冲船舶有限公司 | Ship process knowledge management method, device and system |
CN110990663B (en) * | 2019-12-04 | 2023-03-24 | 中船黄埔文冲船舶有限公司 | Ship process knowledge management method, device and system |
CN111667140A (en) * | 2020-04-26 | 2020-09-15 | 招商局重工(深圳)有限公司 | Method for building large cutter suction dredger |
CN111917836A (en) * | 2020-07-13 | 2020-11-10 | 成都鹦鹉螺大数据科技有限公司 | Industrial equipment cloud thing allies oneself with system |
CN111815286A (en) * | 2020-07-15 | 2020-10-23 | 厦门船舶重工股份有限公司 | Welding process information system |
CN113792385A (en) * | 2021-09-22 | 2021-12-14 | 江南造船(集团)有限责任公司 | Construction method, device, storage medium and system of ship cooperative basic resource library |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107330585A (en) | A kind of method that shipbuilding data integrated system and auxiliary build ship | |
KR101179800B1 (en) | Piping fabrication and installation process visualization system | |
CN108268715B (en) | Steel bridge deck pavement construction simulation method based on BIM technology | |
CN104281729A (en) | BIM (building information model) method for digital processing and manufacturing of steel structure buildings | |
CN109460606B (en) | Welding man-hour calculation method based on ship section construction mode | |
CN104679954A (en) | Method and system for lightening BIM (Building Information Modeling) model | |
CN112232683A (en) | Comprehensive pipe gallery full-period construction management system based on BIM | |
CN110008591A (en) | A kind of continuous rigid frame bridge construction management control method based on BIM | |
CN106056286A (en) | Ship sectional construction workshop operation scheduling system and scheduling method thereof | |
CN111581804B (en) | Method for generating minimum part repair scheme based on actual measurement model | |
CN105204472A (en) | Single-piece discrete type production operation scheduling optimization method | |
CN108274187A (en) | A kind of complex curved surface parts defect repair system and restorative procedure | |
CN105069604A (en) | Tobacco logistics information collaborative management system based on Internet of Things | |
CN106203905A (en) | The material in-out-storehouse management method that engineering construction is on-the-spot | |
CN110287604A (en) | A kind of Bridge Management & Maintenance system based on BIM-GIS | |
CN104850954A (en) | System and method for processing construction information of architectural decoration project | |
SANIUK et al. | Management of production orders in metalworking production | |
CN115048699A (en) | Construction management method based on BIM | |
CN107576503A (en) | Aero-engine high accuracy assembly quality detector device people's system | |
CN106951621B (en) | A kind of simulation optimization method carrying Plan rescheduling for ship | |
CN112288384A (en) | Application of P-BIAS-based fabricated building full-life-cycle management | |
CN115393560A (en) | BIM model drawing marking method, device, equipment and readable storage medium | |
CN110837541A (en) | Prefabricated component factory production management system based on GIS + BIM system | |
CN108153244A (en) | A kind of Control During Paint Spraying by Robot orbit generation method based on ROS platforms | |
Sharma et al. | Location-based highway construction planning using geographic information systems |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20171107 |
|
RJ01 | Rejection of invention patent application after publication |