CN107327148A - A kind of lower jacking ready-package hoisting platform and construction method - Google Patents

A kind of lower jacking ready-package hoisting platform and construction method Download PDF

Info

Publication number
CN107327148A
CN107327148A CN201710425822.8A CN201710425822A CN107327148A CN 107327148 A CN107327148 A CN 107327148A CN 201710425822 A CN201710425822 A CN 201710425822A CN 107327148 A CN107327148 A CN 107327148A
Authority
CN
China
Prior art keywords
building
cushion cap
platform
jack
standard knot
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710425822.8A
Other languages
Chinese (zh)
Other versions
CN107327148B (en
Inventor
李荣岩
杜春阳
王似松
荣士宇
肖扬
苏伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Tianjin Electric Power Transmission and Transformation Engineering Corp
Original Assignee
State Grid Corp of China SGCC
Tianjin Electric Power Transmission and Transformation Engineering Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Tianjin Electric Power Transmission and Transformation Engineering Corp filed Critical State Grid Corp of China SGCC
Priority to CN201710425822.8A priority Critical patent/CN107327148B/en
Publication of CN107327148A publication Critical patent/CN107327148A/en
Application granted granted Critical
Publication of CN107327148B publication Critical patent/CN107327148B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/163Jacks specially adapted for working-up building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/166Landings, receiving platforms

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The present invention relates to a kind of lower jacking ready-package hoisting platform, interval is fixed with assembling type steel structure basis in the ground base of the original cushion cap side of building, assembling type steel structure basis upper end is fixed with jack-up system, the longitudinally coaxial stacking of jack-up system is provided with multiple standard knots, the upper end of standard knot is highly identical with the original cushion cap of building, standard knot upper end is fixed with a lifting bolster, in standard knot top side, cantilevered is provided with an extended position bearing platform, and the cantilever end of the extended position bearing platform is flushed with the original cushion cap upper end of building to be docked;Pull bar is connected between the side of lifting bolster and building.The present invention is marched into the arena using ready-package hoisting platform progress indoor substation electrical equipment after construction, avoid equipment and topple over the risk caved in platform, substantially increase efficiency of construction simultaneously, the platform time of 10 hours originally is foreshortened to 2 hours, this platform can be used repeatedly, suitable for the lifting transhipment of various height, construction cost is greatly reduced.

Description

A kind of lower jacking ready-package hoisting platform and construction method
Technical field
The invention belongs to power construction auxiliary equipment field, especially a kind of lower jacking ready-package hoisting platform and construction party Method.
Background technology
When Substation Electric Equipment is marched into the arena indoors, because the hoisting platform that building is reserved in itself is often set by site space Restriction in terms of meter, greatly reduces the efficiency that equipment is marched into the arena, while have some equipment bigger than normal due to the size of itself, it is difficult to from Outdoor is directly transferred to the installation region of two layers and the above.
It is main using two methods of scaffold hoisting platform or sleeper platform for lining are set up at present in practical operation, no Only low construction efficiency, and all there is the serious risk that lifting risk and platform collapse.
The content of the invention
It is an object of the invention to overcome the deficiencies of the prior art and provide a kind of lower jacking ready-package hoisting platform and construction Method,.
The present invention solves its technical problem and takes following technical scheme to realize:
A kind of lower jacking ready-package hoisting platform, including assembling type steel structure basis, jack-up system, pull bar bracing wire, standard Section, extended position bearing platform and lifting bolster, the side for leaving equipment importation building are fixedly installed at the upper part with the original cushion cap of building, It is characterized in that:Interval is fixed with assembling type steel structure basis, the dress in the ground base of the original cushion cap side of building Jack-up system is fixed with formula steel structure base upper end, the longitudinally coaxial stacking of jack-up system is provided with multiple standard knots, standard knot Upper end it is highly identical with the original cushion cap of building, standard knot upper end is fixed with a lifting bolster, outstanding in standard knot top side Arm-type to be provided with an extended position bearing platform, the cantilever end of the extended position bearing platform is flushed with the original cushion cap upper end of building to be docked; Pull bar is connected between the side of lifting bolster and building.
Moreover, the opposite side of the lifting bolster is connected with one end of bracing wire, the other end oblique pull of bracing wire is fixed to earth anchor Or the pre-buried facility of transformer station.
Moreover, the bracing wire is many.
Moreover, the jack-up system includes two jacking cylinders and petrol station.
Moreover, assembling type steel structure basis including basis with case, Weight plate, foundation anchor point by constituting, case water is matched somebody with somebody on basis It is flat to be fixedly mounted with the ground, ensure stability built with equipped plate with case on basis, basis is provided with and jack-up system with case upper end The basic anchor point that installation site matches.
Moreover, the construction method of this platform:
(1) the size of the measurement original cushion cap of building and position, select the ground with the original cushion cap coaxial spaced position of building Face sets assembling type steel structure basis;
(2) jack-up system is installed on the basis of assembling type steel structure, and by jack-up system successively jack-up standard knot, and Standard knot is fixedly mounted with bolt is stable, it is ensured that standard knot reaches the original cushion cap height of building;
(3) expansion extended position bearing platform is docked with the original cushion cap of building;
(4) lifting cushion cap is installed in the upper end of standard knot, and lifts installing connecting rods between cushion cap and building lateral wall, The opposite side connecting stay wire of cushion cap is lifted, bracing wire is connected to earth anchor or the pre-buried facility of transformer station;
(5) electrical equipment is lifted in standard knot, the height of equipment importation on building is reached, then by deploying to stretch Equipment is sent into installation region in building by formula bearing platform and the original cushion cap of building, is completed equipment and is installed.
Advantages and positive effects of the present invention are:
1st, this platform is for indoor substation equipment mobilization and lifting construction characteristic and requires R & D design, stands on equipment Import builds side by assembling type base, adheres to hard pull bar for building, and consolidated platform from other directions with bracing wire It is fixed.
2nd, the present invention is marched into the arena after construction using ready-package hoisting platform progress indoor substation electrical equipment, it is to avoid equipment Topple over the risk caved in platform, while substantially increasing efficiency of construction, the platform time of 10 hours originally is foreshortened to 2 Hour, and this platform can be used repeatedly, it is adaptable to the lifting transhipment of various height, greatly reduce construction cost.
Brief description of the drawings
Fig. 1 is structural representation of the invention.
Embodiment
Below in conjunction with the accompanying drawings and the invention will be further described by specific embodiment, following examples are descriptive , it is not limited, it is impossible to which protection scope of the present invention is limited with this.
A kind of lower jacking ready-package hoisting platform, including assembling type steel structure basis 10, jack-up system 9, pull bar 2, bracing wire 7th, standard knot 6, extended position bearing platform 4 and lifting bolster 5, the side for leaving equipment importation building 1 is fixedly installed at the upper part with building The original cushion cap 3 of thing, innovation of the invention is:
Interval is fixed with assembling type steel structure basis, the assembled in the ground base of the original cushion cap side of building Steel structure base upper end is fixed with jack-up system, and the longitudinally coaxial stacking of jack-up system is provided with multiple standard knots, standard knot it is upper End is highly identical with the original cushion cap of building, and standard knot upper end is fixed with a lifting bolster 5,
In order to ensure to dock continuity, in standard knot top side, cantilevered is provided with an extended position bearing platform, the stretching, extension The cantilever end of formula bearing platform is flushed with the original cushion cap upper end of building and docked;
In order to ensure that platform steadiness sets pull bar wire drawing system, it is connected between the side of lifting bolster and building Pull bar 2, pull bar is designed as adjustable F shapes " pipe wrench " form, is fixed on building masonry wall, is prevented before platform during platform building After topple over;The opposite side of lifting bolster is connected with one end of a bracing wire 7, and the other end oblique pull of bracing wire is fixed to earth anchor 8, can also consolidated Due to the pre-buried facility of transformer station, the present embodiment is provided with two bracing wires, it is main pull direction be parallel to building direction, Predominantly prevent platform swaying style;
Jack-up system includes two jacking cylinders and petrol station, and the jacking of standard knot can be achieved, platform building is efficiently completed, Jack-up system has more structure in construction, concrete structure is not defined herein.
Assembling type steel structure basis including basis with case, Weight plate, foundation anchor point by being constituted, and basis is fixedly mounted with case level On the ground, stability is ensured built with equipped plate with case on basis, basis is provided with and jack-up system installation position with case upper end Put the basic anchor point matched.
The standard knot of the present embodiment includes 0.5 meter, 1 meter, 2 meters three kinds prefabricated standard assembling steel constructions, for assembling Hoisting platform and adjustment height is realized, also can realize the fine setting of podium level by symmetrically increasing correcting wedge.
Extended position bearing platform is made up of load-bearing shaped steel, platform steel plate, the extensible splicing of platform steel plate, can be stacked during placement, It is the crucial ring for completing convenient transport.
The construction method of this platform:
(1) the size of the measurement original cushion cap of building and position, select the ground with the original cushion cap coaxial spaced position of building Face sets assembling type steel structure basis;
(2) jack-up system is installed on the basis of assembling type steel structure, and by jack-up system successively jack-up standard knot, and Standard knot is fixedly mounted with bolt is stable, it is ensured that standard knot reaches the original cushion cap height of building;
(3) expansion extended position bearing platform is docked with the original cushion cap of building;
(4) lifting cushion cap is installed in the upper end of standard knot, and lifts installing connecting rods between cushion cap and building lateral wall, The opposite side connecting stay wire of cushion cap is lifted, bracing wire is connected to earth anchor or the pre-buried facility of transformer station;
(5) electrical equipment is lifted in standard knot, the height of equipment importation on building is reached, then by deploying to stretch Equipment is sent into installation region in building by formula bearing platform and the original cushion cap of building, is completed equipment and is installed.
Although disclosing embodiments of the invention and accompanying drawing for the purpose of illustration, those skilled in the art can manage Solution:Do not departing from the present invention and spirit and scope of the appended claims in, it is various replace, change and modifications all be it is possible, Therefore, the scope of the present invention is not limited to embodiment and accompanying drawing disclosure of that.

Claims (6)

1. a kind of lower jacking ready-package hoisting platform, including assembling type steel structure basis, jack-up system, pull bar bracing wire, standard knot, Extended position bearing platform and lifting bolster, the side for leaving equipment importation building are fixedly installed at the upper part with the original cushion cap of building, its It is characterised by:Interval is fixed with assembling type steel structure basis, the assembling in the ground base of the original cushion cap side of building Formula steel structure base upper end is fixed with jack-up system, and the longitudinally coaxial stacking of jack-up system is provided with multiple standard knots, standard knot Upper end is highly identical with the original cushion cap of building, and standard knot upper end is fixed with a lifting bolster, in standard knot top side cantilever Formula is provided with an extended position bearing platform, and the cantilever end of the extended position bearing platform is flushed with the original cushion cap upper end of building to be docked; Lift and be connected with pull bar between the side of bolster and building.
2. lower jacking ready-package hoisting platform according to claim 1, it is characterised in that:The opposite side of the lifting bolster One end of bracing wire is connected with, the other end oblique pull of bracing wire is fixed to earth anchor or the pre-buried facility of transformer station.
3. lower jacking ready-package hoisting platform according to claim 2, it is characterised in that:The bracing wire is many.
4. lower jacking ready-package hoisting platform according to claim 1, it is characterised in that:The jack-up system includes two Jacking cylinder and petrol station.
5. lower jacking ready-package hoisting platform according to claim 1, it is characterised in that:Assembling type steel structure basis is by wrapping Include basis with case, Weight plate, foundation anchor point composition, basis with case level be fixedly mounted with the ground, basis match somebody with somebody case built with Fill plate and ensure stability, basis is provided with the basic anchor point matched with jack-up system installation site with case upper end.
6. lower jacking ready-package hoisting platform according to claim 1, it is characterised in that:The construction method of this platform:
(1) the size of the measurement original cushion cap of building and position, select the ground with the original cushion cap coaxial spaced position of building to set Put assembling type steel structure basis;
(2) jack-up system is installed on the basis of assembling type steel structure, and by jack-up system successively jack-up standard knot, and use spiral shell Bolt is stable to be fixedly mounted with standard knot, it is ensured that standard knot reaches the original cushion cap height of building;
(3) expansion extended position bearing platform is docked with the original cushion cap of building;
(4) lifting cushion cap is installed in the upper end of standard knot, and lifts installing connecting rods between cushion cap and building lateral wall, is lifted The opposite side connecting stay wire of cushion cap, bracing wire is connected to earth anchor or the pre-buried facility of transformer station;
(5) electrical equipment is lifted in standard knot, the height of equipment importation on building is reached, is then held by deploying extended position Equipment is sent into installation region in building by weight platform and the original cushion cap of building, is completed equipment and is installed.
CN201710425822.8A 2017-06-08 2017-06-08 The lower jacking ready-package hoisting platform of one kind and construction method Active CN107327148B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710425822.8A CN107327148B (en) 2017-06-08 2017-06-08 The lower jacking ready-package hoisting platform of one kind and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710425822.8A CN107327148B (en) 2017-06-08 2017-06-08 The lower jacking ready-package hoisting platform of one kind and construction method

Publications (2)

Publication Number Publication Date
CN107327148A true CN107327148A (en) 2017-11-07
CN107327148B CN107327148B (en) 2019-12-03

Family

ID=60194516

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710425822.8A Active CN107327148B (en) 2017-06-08 2017-06-08 The lower jacking ready-package hoisting platform of one kind and construction method

Country Status (1)

Country Link
CN (1) CN107327148B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201649668U (en) * 2009-09-22 2010-11-24 中冶成工上海五冶建设有限公司 Lattice column lifting frame
CN102635225A (en) * 2012-04-05 2012-08-15 广东省工业设备安装公司 Equipment hoisting platform and method for super high-rise buildings
CN203079590U (en) * 2012-12-28 2013-07-24 徐州重型机械有限公司 Tower crane and jacking device thereof
CN103738891A (en) * 2013-12-27 2014-04-23 柳州欧维姆机械股份有限公司 Standard knot jacking device and construction method for continuously and automatically jacking standard knots thereof
CN203654755U (en) * 2013-12-06 2014-06-18 中铁建设集团有限公司 Shaping aluminous spliced discharge platform of construction elevator
CN103982040A (en) * 2014-05-06 2014-08-13 中建三局集团有限公司 Vertical comprehensive transportation device for super high-rise building construction
CN104724643A (en) * 2015-03-26 2015-06-24 国家电网公司 Double-oil-cylinder down jacking system and jacking construction method thereof

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201649668U (en) * 2009-09-22 2010-11-24 中冶成工上海五冶建设有限公司 Lattice column lifting frame
CN102635225A (en) * 2012-04-05 2012-08-15 广东省工业设备安装公司 Equipment hoisting platform and method for super high-rise buildings
CN203079590U (en) * 2012-12-28 2013-07-24 徐州重型机械有限公司 Tower crane and jacking device thereof
CN203654755U (en) * 2013-12-06 2014-06-18 中铁建设集团有限公司 Shaping aluminous spliced discharge platform of construction elevator
CN103738891A (en) * 2013-12-27 2014-04-23 柳州欧维姆机械股份有限公司 Standard knot jacking device and construction method for continuously and automatically jacking standard knots thereof
CN103982040A (en) * 2014-05-06 2014-08-13 中建三局集团有限公司 Vertical comprehensive transportation device for super high-rise building construction
CN104724643A (en) * 2015-03-26 2015-06-24 国家电网公司 Double-oil-cylinder down jacking system and jacking construction method thereof

Also Published As

Publication number Publication date
CN107327148B (en) 2019-12-03

Similar Documents

Publication Publication Date Title
US8584429B2 (en) Tower erection system and method
US20100281818A1 (en) Method for building wind turbine tower
AU2014283227B2 (en) Wind turbine foundation
CN105544590A (en) Base used for power transmission and transformation project tower and capable of being continuously adjusted as whole
CN105863042A (en) All-steel structure building and construction method thereof
CN109607399B (en) Hoisting process for installing roof net rack
CN205894049U (en) A first pitching pile formula jacket structure for marine booster station
CN111997043A (en) Segmented reinforcement cage and diaphragm wall construction method under low-clearance high-voltage line
CN103669952B (en) The Cang Ding construction platform of diameter Silo and construction method
CN103806735B (en) Based on to the electric pole replacing options in electric power pipe network
CN102094524B (en) Construction method of high-altitude large-span beam-slab template steel support system
CN107327148A (en) A kind of lower jacking ready-package hoisting platform and construction method
CN201817817U (en) Integral continuously-adjustable foundation for power transmission and transformation tower (pole)
WO2023126974A1 (en) Portable footing based telecom tower
CN215055324U (en) High-rise structure construction device
CN214194626U (en) Mountain area transmission tower anchor rope assembled basis
CN105951896B (en) A kind of architecture foundation pile dead-load detection device
CN212002582U (en) Communication tower with high stability
CN203613856U (en) Top construction platform for large-diameter silo
CN202450838U (en) Assembling type iron tower base station
CN205676935U (en) A kind of architecture foundation pile dead-load detection device
CN207149995U (en) A kind of preassembled transformer station mounting structure
CN206219080U (en) A kind of tower crane
CN206941426U (en) A kind of viaduct pile foundation underpinning structure
CN201512803U (en) Structural layer used for preventing building from sinking and bottom layer structure in transformer substation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant