CN107297598B CN201710451643.1A CN201710451643A CN107297598B CN 107297598 B CN107297598 B CN 107297598B CN 201710451643 A CN201710451643 A CN 201710451643A CN 107297598 B CN107297598 B CN 107297598B
Authority
CN
China
Prior art keywords
plate
composite
panel
fixture
bottom board
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710451643.1A
Other languages
Chinese (zh)
Other versions
CN107297598A (en
Inventor
金建伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Sheng Xing Metal Plate Co Ltd
Original Assignee
Jiangsu Sheng Xing Metal Plate Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Sheng Xing Metal Plate Co Ltd filed Critical Jiangsu Sheng Xing Metal Plate Co Ltd
Priority to CN201710451643.1A priority Critical patent/CN107297598B/en
Publication of CN107297598A publication Critical patent/CN107297598A/en
Application granted granted Critical
Publication of CN107297598B publication Critical patent/CN107297598B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23PMETAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
    • B23P15/00Making specific metal objects by operations not covered by a single other subclass or a group in this subclass
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K1/00Soldering, e.g. brazing, or unsoldering
    • B23K1/008Soldering within a furnace
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K1/00Soldering, e.g. brazing, or unsoldering
    • B23K1/20Preliminary treatment of work or areas to be soldered, e.g. in respect of a galvanic coating
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K1/00Soldering, e.g. brazing, or unsoldering
    • B23K1/20Preliminary treatment of work or areas to be soldered, e.g. in respect of a galvanic coating
    • B23K1/203Fluxing, i.e. applying flux onto surfaces
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K1/00Soldering, e.g. brazing, or unsoldering
    • B23K1/20Preliminary treatment of work or areas to be soldered, e.g. in respect of a galvanic coating
    • B23K1/206Cleaning
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16SCONSTRUCTIONAL ELEMENTS IN GENERAL; STRUCTURES BUILT-UP FROM SUCH ELEMENTS, IN GENERAL
    • F16S1/00Sheets, panels, or other members of similar proportions; Constructions comprising assemblies of such members

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Laminated Bodies (AREA)

Abstract

The invention belongs to cellular board technical fields, more particularly to the preparation process of no glue aluminum honeycomb plate, the following steps are included: 1. prepare composite panel, composite bottom board and honeycomb core, 2. in composite panel, composite bottom board surface coats scaling powder, 3. using fixture to composite panel, honeycomb core, composite bottom board is assembled, 4. in composite panel after assembly, honeycomb core, composite bottom board faying face sprays scaling powder again, 5. entering soldering oven to be brazed, obtain no glue cellular board, the present invention can be improved strength of brazed joint, prevent composite plate from deforming in high temperature brazing, improve cellular board Forming Quality.

Description

Preparation process without glue aluminum honeycomb plate
Technical field
The invention belongs to cellular board technical fields, and in particular to the preparation process without glue aluminum honeycomb plate.
Background technique
Cellular board is since light-weight, specific strength is high, rigidity is big, stability is good, heat-and sound-insulating and pollution-free etc. a series of Advantage is used widely in the fields such as aerospace, aircraft, train, ship, building.It is common both at home and abroad at present Cellular board either core material itself is still compound between panel and core material, is adhesive means, and connection type is physical bond, Its intensity, service life and the working environment of permission are largely restricted by Adhensive performance.The molding honeycomb of gluing Plate mechanical property is lower, structure built on the sand, moreover, pollution can be generated in the connection type reproduction of gluing, not environmentally.To understand Certainly problem, currently, mostly using method for welding formed honeycomb plate.
Soldering is to make solder using metal material more low-melting than base material, and weldment and solder heat are melted to higher than solder Point is lower than base material fusion temperature, soaks base material using liquid solder, fills play movement and realizes connection with base material phase counterdiffusion The method of weldment.Cellular board is aluminium sheet, and area when soldering is bigger, and aluminium sheet is very easy to deformation in the case where heated. The prior art is usually that aluminium sheet is sent directly into soldering oven with the cellular board for being coated with brazing flux to carry out high temperature brazing, although this method Simple process, but it is usually easy to happen aluminium sheet deformation, to influence the surface smoothness of composite plate, influence product quality.
Summary of the invention
The technical problem to be solved by the present invention is in view of the foregoing drawbacks, provide the preparation process of no glue aluminum honeycomb plate, The cellular board deformation of lead welding and shaping is small, and cellular board quality is high.
It is as follows that the technical scheme adopted by the invention to solve the technical problem:
Preparation process without glue aluminum honeycomb plate, which comprises the following steps:
A, panel, bottom plate and cellular sandwich are prepared: taking aluminium sheet to be cut into blocky spare, obtains panel, bottom plate, panel bottom plate is thick Degree is consistent;Aluminium foil strip is taken to be fabricated to cellular sandwich, cellular sandwich size and panel, bottom plate dimensional fits by mechanization;
B, composite panel, composite bottom board are prepared: solder layer being coated in panel lower surface obtained in step A, is answered Panel is closed, solder layer is coated in plate upper surface obtained in step A, obtains composite bottom board, solder layer thickness and panel are thick The ratio between degree is 20:3;
C, welding pretreatment: the surface of the composite panel obtained in cleaning solvent cleaning B, composite bottom board, and The surface of cellular sandwich obtained in step A is dried after cleaning;
D, scaling powder is sprayed for the first time: scaling powder is sprayed to lower surface, the composite bottom board of the composite panel after cleaning is dried Upper surface;
E, clamping:, will be obtained in step C by being placed on fixture upward of composite bottom board upper surface obtained in step D
Cellular sandwich row is located on composite bottom board upper surface, sets composite panel lower surface is directed downwardly obtained in step D It is pressed from both sides in honeycomb
On core, composite bottom board, cellular sandwich, the alignment of composite panel corner, clamp obtain clamping part;
F, scaling powder is sprayed again: by cellular sandwich of the scaling powder brushing after clamping and composite panel, composite bottom board
At abutted surface;
G, enter slice weldering: will be sent into soldering oven soldering after step F treated clamping part drying, it is preheated, heating is equal Temperature soldering, cooling, obtain no glue aluminum honeycomb plate;
H, surface clean, setting surface protection coating are carried out without glue aluminum honeycomb plate to obtained in step G.
Further, the solder layer in the step B is the solder layer of Al-Si eutectic composition, step D, helps weldering in F
Agent is to constitute brazing flux aqueous solution by Nocolok powdery brazing flux and water.
Further, the soldering oven in the step G is continuous tunnel furnace formula furnace brazing furnace, the heating samming pricker
The temperature of weldering is 600 DEG C -610 DEG C, and described being cooled to is air-cooled, and drying temperature is 300-550 DEG C, drying time period 5- 15min。
Further, the fixture of the step E includes upper fixture, lower fixture, and upper fixture includes upper bracket, upper porous Plate, upper porous plate are fixed on upper bracket surface, and upper bracket is made of the staggered cross tube in upper square box, upper square box, under Fixture includes lower bracket, lower porous plate, and lower porous plate is fixed on lower support surface, and upper porous plate, lower porous plate are opposite up and down, under Bracket is made of the staggered sheer pole in lower square box, lower square box, and upper square box, cross tube, lower square box, sheer pole are equal For the rectangular steel tube of Q235 carbon steel, upper porous plate, under the degree of porous plate thickness be 3mm, material is Q235 carbon steel, on The opposite face of porous plate, lower porous plate is equipped with multiple equally distributed high temperature springs, upper square box, four Bian Junshe of lower square box There is outwardly extending side lever, side lever is equipped with screw hole, and upper and lower side lever is connected by screw to locking.
Further, the cross tube unbalanced arrangement in shape frame inside above.
Further, the size of gained panel, bottom plate is 100cm*100cm in the step A
Further, the high reliablity of Welding, is not easy desoldering, stable connection, has cellular board more firm
Structure, cellular board have preferable mechanical property, can use in harsh environments, expand answering for cellular board With range,
Without glue connection, pollutant is not generated in production, more meets the requirement of environmental protection, scaling powder layer is arranged on solder surface, On the one hand just
In the operation of welding, the protectiveness of another aspect butt-welding fitting and solder is more preferable, and weldment and solder is avoided to be brazed It is aoxidized in journey,
Improve welding effect.
The beneficial effects of the present invention are: using the above scheme, simple process can effectively prevent composite plate to become in soldering
Shape greatly improves the quality of cellular board after molding, and cellular board plate face is smooth, sound construction, is suitble to the big ruler of manufacture Very little cellular board,
High production efficiency.
Detailed description of the invention
Through the following detailed description taken in conjunction with the accompanying drawings, present invention objects, features and advantages above-mentioned and other will become Obviously.
Fig. 1 is the top view of upper fixture in the present invention.
Fig. 2 is the cross-sectional view in the present invention at upper fixture porous plate.
Fig. 3 is a kind of embodiment schematic diagram of upper fixture bracket in the present invention.
Fig. 4 is the another embodiment schematic diagram of upper fixture bracket in the present invention.
Specific embodiment
The present invention will be further described with reference to the accompanying drawing.
Embodiment 1: design and manufacture of the production without glue aluminum honeycomb plate welding fixture:
Fixture includes upper fixture, lower fixture, and upper fixture, lower fixture clamp cellular board embryo material therebetween, upper fixture, under The structure of fixture is identical, is made of cross bar, the porous plate on bracket, bracket, take Q235 carbon steel rectangular steel tube, with And the open-work steel plate of 3mm thickness, the single pipe fitting that rectangular steel tube is cut into, open-work steel plate are cut into single porous plate, individually Pipe fitting includes frame tube, cross bar, frame tube progress split is welded into the upper bracket of frame type, lower bracket, referring to figs. 1 to Fig. 3 It is shown, cross bar is interweaved in length and breadth and is welded on upper bracket, on lower bracket, forms fenestral fabric, cross bar oblique weld upper bracket, On lower bracket, the sizing grid that cross bar is formed is different, and porous plate is welded on upper bracket, lower support surface, forms structure size All consistent upper fixture, lower fixture, porous plate surface are fixed with 50 high temperature springs, and high temperature spring is uniformly distributed, high temperature spring with Porous plate plate face keeps vertical, and the outwardly extending side lever of side edge welding of upper bracket, lower bracket, side lever is equipped with screw hole, It is connected by screw to locking between side lever, realizes the locking of upper fixture, lower fixture, upper fixture, lower fixture are by cellular board component clamping Afterwards, high temperature spring is tightly extruded in composite plate, is made composite plate entirety stress, composite plate can greatly be inhibited to become in soldering Shape improves the Forming Quality of cellular board.
Preparation process without glue aluminum honeycomb plate, comprising the following steps:
A, panel, bottom plate and cellular sandwich are prepared: 3003 rustproof aluminium sheets of 1mm thickness being taken to be cut into 100cm*100cm block Shape is spare, obtains the panel, bottom plate having a size of 100cm*100cm, panel, bottom plate consistency of thickness;Take 6061 swaged forging aluminium materials Thin-walled tube coupling, cutting stock is at the single tube coupling of 17mm high, and single size is 28 × 0.4 × 17mm of φ, in single joint Drilling processes core bore on side wall;
B, composite panel, composite bottom board are prepared: taking the solder of 400 model Al-Si eutectic compositions, solder composite molding is existed Panel, bottom plate surface, obtains composite panel, composite bottom board, solder layer with a thickness of 0.15mm, in panel, bottom plate table before welding Face elder generation composite soldering layer makes solder layer in the thickness uniformity of plate face, and convenient for the thickness of control solder layer, simplifies preparation Technique, while guaranteeing the reliable quality of soldering, the thickness of solder layer is big in the present invention, it is ensured that has enough fusing solders to fill Gap improves welded rate and avoids weld cracking, can not only fill out the gap between interlayer and panel, bottom plate after solder layer fusing It is full, and there may also be part and penetrate into the gap of interlayer and play welding, so as to promote the overall stiffness for being brazed cellular board.
C, welding pretreatment: the surface of composite panel, composite bottom board is cleaned with alcohol, and with the single tube coupling of alcohol washes Surface, remove stain after dry it is spare;
D, scaling powder is sprayed for the first time: taking Nocolok powder and water to be configured to scaling powder aqueous solution, scaling powder aqueous solution is sprayed Composite panel, composite bottom board are sprinkled upon on the surface of solder layer, the scaling powder aqueous solution that Nocolok powder is configured to is a kind of Almost free from corrosion fluoride chemical substance, can be configured to a certain proportion of aqueous solution, convenient for being coated in the brazing surface of workpiece On, it plays oxide film dissolving, improve wetting and capillary flow effect after brazing filler metal melts, and postwelding residue will not make component It at damaging destruction, is sprayed directly on solder layer, in welding, scaling powder can be merged preferably with solder, and raising helps The using effect of solder flux improves soldering effect;
E, clamping: the composite bottom board for having sprayed scaling powder aqueous solution is lain in a horizontal plane in lower fixture, composite bottom board is compound There is the side of solder layer upward, is arranged in what single tube coupling or so obtained in step C connected on composite bottom board, single tube coupling Cellular sandwich is formed after arrangement, single tube coupling inner cavity is then the single pocket of cellular sandwich, and the core bore on single tube coupling makes adjacent Pocket communicates, and can be bonded, is fixed by glue between single tube coupling, then composite panel is placed into cellular sandwich top, The side that composite panel is compounded with solder layer is downward, and upper fixture is placed into composite surface by composite panel, the alignment of composite bottom board corner On plate, and upper fixture, the connection locking of lower fixture are obtained into clamping part with screw;
F, scaling powder is sprayed again: the scaling powder aqueous solution prepared in step D being sprayed on composite panel again, honeycomb presss from both sides Core, composite bottom board abutted surface at, spray scaling powder again, the abrasion of scaling powder layer caused by clamping process supplemented, Guarantee that scaling powder covers solder layer, oxidation film is removed to solder layer, improves soldering effect;
G, enter slice weldering: first clamping part being dried, using tunnel type drying equipment, clamping part is placed into dry On the transmission mechanism of dry equipment, clamping part is dried in operational process on tunnel type drying equipment in clamping part, is carried out Streamlined production, 150-260 DEG C of drying temperature, dry duration 5-15min, the clamping part after drying is sent into continuous tunnel furnace formula gas shielded Soldering oven carries out soldering processing, the clamping part after drying is placed on the transmission crawler belt of tunnel type furnace brazing furnace, clamping No colloid cellular board successively is obtained behind the preheating zone of tunnel type furnace brazing furnace, heating samming brazing area, cooling zone, is preheated The heat temperature in area is 300 DEG C, preheats duration 10min, and clamping part is forced to heat, is prepared for soldering, heating samming soldering Temperature be 605 DEG C, be brazed duration 15min, heating samming brazing area is passed through nitrogen and is protected, and the type of cooling after soldering is Using blower air blast cooling, cooling duration 20min comes out of the stove after cooling close to room temperature, carries out modularization, assembly line pricker to cellular board Weldering produces, and glue, environmental protection more is not used in life, and improve the integral strength of cellular board, panel, cellular sandwich, bottom plate Have in soldering and integrally wrapped by fixture, during soldering, fixture, which wraps the entirety of panel, bottom plate, effectively to be inhibited The deformation of panel, bottom plate, porous plate cooperate high temperature spring, carry out compacting tightly to panel, bottom plate plate face, both can guarantee high temperature Under clamped in thickness direction, and in-plane can be made to have certain flexible freedom degree, can avoid plate face bulge phenomenon in soldering, keep away Exempt to crack at soldering, welded rate is substantially improved, and compares prior art, and welded rate improves 70%-85%, and cellular board total quality obtains To significantly improving, solder layer thickness is big, not only meets the soldering demand between cellular sandwich and panel, bottom plate, and there are also parts to penetrate into Play welding in the joint of the single pipe fitting of cellular sandwich, gap, so as to promote the overall stiffness of soldering cellular board;
H, it will be removed from the molds obtained in step G without glue aluminum honeycomb plate, examine weld seam, panel, bottom plate deformation rate, The setting for carrying out surface clean, surface protection coating after qualification to cellular board, the clamping marking of fixture is removed by chemical cleaning, Setting coating makes cellular board have better rotproofness, improves surface quality.
Embodiment 2: design and manufacture of the production without glue aluminum honeycomb plate welding fixture:
Fixture includes upper fixture, lower fixture, and upper fixture, lower fixture clamp cellular board embryo material therebetween, upper fixture, under Clamp structure is consistent, takes the rectangular steel tube of Q235 carbon steel and the open-work steel plate of 3mm thickness, rectangular steel tube is cut into Single pipe fitting, open-work steel plate is cut into single porous plate, and single pipe fitting includes frame tube, cross bar, and frame tube is spelled Upper bracket, the lower bracket for being welded into frame type are closed, shown referring to Figure 2 to Figure 4, cross bar interweaves in length and breadth is welded on upper bracket, lower branch On frame, fenestral fabric is formed, sizing grid is consistent, porous plate is welded on upper bracket, lower support surface, in porous plate surface Uniformly 50 high temperature springs of welding, high temperature spring is vertical with porous plate holding, the phase up and down of the high temperature spring on upper and lower porous plate It is right, all consistent upper fixture of formation structure size, lower fixture, the outwardly extending side lever of side edge welding of upper bracket, lower bracket, Side lever is equipped with screw hole, and locking is connected by screw between side lever, realizes the locking of upper fixture, lower fixture.
Preparation process without glue aluminum honeycomb plate, comprising the following steps:
A, panel, bottom plate and cellular sandwich are prepared: 3003 rustproof aluminium sheets of 1mm thickness being taken to be cut into 100cm*100cm block Shape is spare, obtains the panel, bottom plate having a size of 100cm*100cm, panel, bottom plate consistency of thickness;Take 6061 swaged forging aluminium materials Thin-walled tube coupling, cutting stock is at the single tube coupling of 17mm high, and single size is 28 × 0.4 × 17mm of φ, in single joint Drilling processes core bore on side wall;
B, composite panel, composite bottom board are prepared: taking the solder of 400 model Al-Si eutectic compositions, solder composite molding is existed Panel, bottom plate surface, obtains composite panel, composite bottom board, solder layer with a thickness of 0.15mm, in panel, bottom plate table before welding Face elder generation composite soldering layer makes solder layer in the thickness uniformity of plate face, and convenient for the thickness of control solder layer, simplifies preparation Technique, while guaranteeing the reliable quality of soldering, the thickness of solder layer is big in the present invention, it is ensured that has enough fusing solders to fill Gap improves welded rate and avoids weld cracking, can not only fill out the gap between interlayer and panel, bottom plate after solder layer fusing It is full, and there may also be part and penetrate into the gap of interlayer and play welding, so as to promote the overall stiffness for being brazed cellular board.
C, welding pretreatment: the surface of composite panel, composite bottom board is cleaned with alcohol, and with the single tube coupling of alcohol washes Surface, remove stain after dry it is spare;
D, scaling powder is sprayed for the first time: taking Nocolok powder and water to be configured to scaling powder aqueous solution, scaling powder aqueous solution is sprayed Composite panel, composite bottom board are sprinkled upon on the surface of solder layer, the scaling powder aqueous solution that Nocolok powder is configured to is a kind of Almost free from corrosion fluoride chemical substance, can be configured to a certain proportion of aqueous solution, convenient for being coated in the brazing surface of workpiece On, it plays oxide film dissolving, improve wetting and capillary flow effect after brazing filler metal melts, and postwelding residue will not make component It at damaging destruction, is sprayed directly on solder layer, in welding, scaling powder can be merged preferably with solder, and raising helps The using effect of solder flux improves soldering effect;
E, clamping: the composite bottom board for having sprayed scaling powder aqueous solution is lain in a horizontal plane in lower fixture, composite bottom board is compound There is the side of solder layer upward, is arranged in what single tube coupling or so obtained in step C connected on composite bottom board, single tube coupling Cellular sandwich is formed after arrangement, single tube coupling inner cavity is then the single pocket of cellular sandwich, and the core bore on single tube coupling makes adjacent Pocket communicates, and can be bonded, is fixed by glue between single tube coupling, then composite panel is placed into cellular sandwich top, The side that composite panel is compounded with solder layer is downward, and upper fixture is placed into composite surface by composite panel, the alignment of composite bottom board corner On plate, and upper fixture, the connection locking of lower fixture are obtained into clamping part with screw;
F, scaling powder is sprayed again: the scaling powder aqueous solution prepared in step D being sprayed on composite panel again, honeycomb presss from both sides Core, composite bottom board abutted surface at, spray scaling powder again, the abrasion of scaling powder layer caused by clamping process supplemented, Guarantee that scaling powder covers solder layer, oxidation film is removed to solder layer, improves soldering effect;
G, enter slice weldering: first clamping part being dried, using tunnel type drying equipment, clamping part is placed into dry On the transmission mechanism of dry equipment, clamping part is dried in operational process on tunnel type drying equipment in clamping part, is carried out Streamlined production, 150-260 DEG C of drying temperature, dry duration 5-15min, the clamping part after drying is sent into continuous tunnel furnace formula gas shielded Soldering oven carries out soldering processing, the clamping part after drying is placed on the transmission crawler belt of tunnel type furnace brazing furnace, clamping Part successively obtains no colloid cellular board behind the preheating zone of tunnel type furnace brazing furnace, heating samming brazing area, cooling zone, in advance The heat temperature of hot-zone be 300 DEG C, preheat duration 10min, by clamping part force heat, for soldering prepare, heating samming pricker The temperature of weldering is 605 DEG C, is brazed duration 15min, heating samming brazing area be passed through nitrogen and protected, the cooling side after soldering Formula is the cooling duration 20min using blower air blast cooling, is come out of the stove after cooling close to room temperature, carries out modularization, flowing water to cellular board Line soldering production, glue, environmental protection more is not used in life, and improve the integral strength of cellular board, panel, cellular sandwich, Bottom plate has in soldering integrally to be wrapped by fixture, and during soldering, fixture wraps the entirety of panel, bottom plate can be effective Inhibit the deformation of panel, bottom plate, porous plate cooperates high temperature spring, carries out compacting tightly to panel, bottom plate plate face, both can guarantee It is clamped under high temperature in thickness direction, and in-plane can be made to have certain flexible freedom degree, it is existing to can avoid plate face bulge in soldering As avoiding cracking at soldering, welded rate is substantially improved, and compares prior art, and welded rate improves 70%-85%, and cellular board is whole Quality is improved significantly, and solder layer thickness is big, not only meets the soldering demand between cellular sandwich and panel, bottom plate, there are also portions It point penetrates into the joint of single pipe fitting of cellular sandwich, play welding in gap, so as to promote the entirety for being brazed cellular board Rigidity;
H, it will be removed from the molds obtained in step G without glue aluminum honeycomb plate, examine weld seam, panel, bottom plate deformation rate, The setting for carrying out surface clean, surface protection coating after qualification to cellular board, the clamping marking of fixture is removed by chemical cleaning, Setting coating makes cellular board have better rotproofness, improves surface quality.
The folder fixture that soldering oven in step G is further, described step E includes upper fixture, lower fixture, upper fixture Including upper bracket, upper porous plate, upper porous plate is fixed on upper bracket surface, and upper bracket is by the friendship in upper square box, upper square box Wrong cross tube is constituted, and lower fixture includes lower bracket, lower porous plate, and lower porous plate is fixed on lower support surface, upper porous plate, under Porous plate is opposite up and down, and lower bracket is made of the staggered sheer pole in lower square box, lower square box, upper square box, cross tube, Lower square box, sheer pole are the rectangular steel tube of Q235 carbon steel, upper porous plate, under the degree of porous plate thickness be 3mm, material It is Q235 carbon steel, the opposite face of upper porous plate, lower porous plate is equipped with multiple equally distributed high temperature springs, upper rectangular Frame, four side of lower square box are equipped with outwardly extending side lever, and side lever is equipped with screw hole, and upper and lower side lever is connected by screw to lock Tightly.
The above is only presently preferred embodiments of the present invention, not does limitation in any form to the present invention, it is all according to According to any simple modification to the above embodiments in technical spirit of the invention, equivalent variations, guarantor of the invention is each fallen within Within the scope of shield.

Claims (4)

1. the preparation process without glue aluminum honeycomb plate, which comprises the following steps:
A, panel, bottom plate and cellular sandwich are prepared: taking aluminium sheet to be cut into blocky spare, obtains panel, bottom plate, panel base plate thickness one It causes;Aluminium foil strip is taken to be fabricated to cellular sandwich, cellular sandwich size and panel, bottom plate dimensional fits by mechanization;
B, composite panel, composite bottom board are prepared: solder layer being coated in panel lower surface obtained in step A, obtains composite surface Solder layer is coated in plate upper surface obtained in step A, obtains composite bottom board by plate, solder layer thickness and plate thickness it Than for 20:3;
C, welding pretreatment: the composite panel obtained in cleaning solvent cleaning B, the surface of composite bottom board and step A Obtained in cellular sandwich surface, dried after cleaning;
D, scaling powder is sprayed for the first time: scaling powder being sprayed at the lower surface of composite panel after cleaning is dried, table on composite bottom board Face;
E, clamping: by being placed on fixture upward of composite bottom board upper surface obtained in step D, by honeycomb obtained in step C Sandwich row is located on composite bottom board upper surface, is placed in composite panel lower surface is directed downwardly obtained in step D on cellular sandwich, Composite bottom board, cellular sandwich, the alignment of composite panel corner, clamp obtain clamping part;
F, scaling powder is sprayed again: cellular sandwich of the scaling powder brushing after clamping and composite panel, composite bottom board are connected At face;
G, enter slice weldering: soldering oven soldering, preheated, heating samming pricker will be sent into after step F treated clamping part drying Weldering, cooling, obtain no glue aluminum honeycomb plate;
H, surface clean, setting surface protection coating are carried out without glue aluminum honeycomb plate to obtained in step G;
The fixture of the step E includes upper fixture, lower fixture, and upper fixture, lower fixture clamp cellular board embryo material therebetween, Upper fixture, the structure of lower fixture are identical, are made of cross bar, the porous plate on bracket, bracket, take the side of Q235 carbon steel The open-work steel plate of shape steel pipe and 3mm thickness, the single pipe fitting that rectangular steel tube is cut into, open-work steel plate are cut into single more Orifice plate, single pipe fitting include frame tube, cross bar, and frame tube progress split is welded into the upper bracket of frame type, lower bracket, will be horizontal Bar interweaves in length and breadth is welded on upper bracket, on lower bracket, forms fenestral fabric, cross bar oblique weld on upper bracket, lower bracket, The sizing grid that cross bar is formed is different, and porous plate is welded on upper bracket, lower support surface, formed structure size it is all consistent on Fixture, lower fixture, porous plate surface are fixed with high temperature spring, and high temperature spring is uniformly distributed, and high temperature spring and porous plate plate face are protected It holds vertically, the outwardly extending side lever of side edge welding of upper bracket, lower bracket, side lever is equipped with screw hole, passes through spiral shell between side lever Nail connection locking.
2. the preparation process of no glue aluminum honeycomb plate according to claim 1, it is characterised in that: in the step B Solder layer is the solder layer of Al-Si eutectic composition, and step D, the scaling powder in F is to constitute pricker by Nocolok powdery brazing flux and water Agent aqueous solution.
3. the preparation process of no glue aluminum honeycomb plate according to claim 1, it is characterised in that: in the step G Soldering oven is continuous tunnel furnace formula furnace brazing furnace, and the temperature of the heating samming soldering is 600 DEG C -610 DEG C, the cooling It is air-cooled.
4. the preparation process of no glue aluminum honeycomb plate according to claim 1, it is characterised in that: institute in the step A The size for obtaining panel, bottom plate is 100cm*100cm.
CN201710451643.1A 2017-06-15 2017-06-15 Preparation process without glue aluminum honeycomb plate Active CN107297598B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710451643.1A CN107297598B (en) 2017-06-15 2017-06-15 Preparation process without glue aluminum honeycomb plate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710451643.1A CN107297598B (en) 2017-06-15 2017-06-15 Preparation process without glue aluminum honeycomb plate

Publications (2)

Publication Number Publication Date
CN107297598A CN107297598A (en) 2017-10-27
CN107297598B true CN107297598B (en) 2019-06-14

Family

ID=60134883

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710451643.1A Active CN107297598B (en) 2017-06-15 2017-06-15 Preparation process without glue aluminum honeycomb plate

Country Status (1)

Country Link
CN (1) CN107297598B (en)

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108526638A (en) * 2018-04-16 2018-09-14 芜湖市泰能电热器具有限公司 A kind of application method of aluminium solder
CN108817638A (en) * 2018-07-25 2018-11-16 青岛归来科技有限公司 The preparation method of metal beehive core material and metal honeycomb plate
CN110732842B (en) * 2019-10-23 2021-02-02 佛山市桐立新材料科技有限公司 Preparation method of brazing aluminum honeycomb plate
CN110948188B (en) * 2019-12-20 2021-06-11 上海复合材料科技有限公司 High-precision honeycomb core processing method
CN111843098B (en) * 2020-07-23 2021-05-04 吉林大学 Clamp for brazing aluminum honeycomb panel and brazing process
CN113147107B (en) * 2021-03-09 2022-12-06 哈尔滨工业大学(威海) Honeycomb sandwich structure formed by C/C composite material and alloy and preparation method thereof
CN113733687A (en) * 2021-09-08 2021-12-03 河北工业大学 Manufacturing method of high-strength honeycomb composite board
CN114801409A (en) * 2022-04-26 2022-07-29 广州中樱汽车零部件有限公司 Production process of composite honeycomb board of automobile seat
CN116252019B (en) * 2023-04-18 2023-09-15 广东森铝科技有限公司 Clamp for brazing aluminum honeycomb plate for ship and brazing process

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3011254A (en) * 1959-04-06 1961-12-05 North American Aviation Inc Double differential pressure honeycomb sandwich panel brazing
CN101362297A (en) * 2008-09-16 2009-02-11 浙江大学 Pre-compressing device for processing and fixing the honeycomb flexible material
CN102489924A (en) * 2011-12-22 2012-06-13 浙江大学 Combined type flexible clamp for vacuum brazing of core body of plate-fin type aluminum heat exchanger
CN104148857A (en) * 2014-08-06 2014-11-19 安徽省芜湖仪器仪表研究所 Positioning mechanism for welding of cellular board capable of guaranteeing uniformity of forced convection flow field
CN205414768U (en) * 2015-08-05 2016-08-03 武船重型工程股份有限公司 Fixing device

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2548472B2 (en) * 1991-11-06 1996-10-30 住友軽金属工業株式会社 Welded brazed aluminum honeycomb panel and its coating method
US20030039856A1 (en) * 2001-08-15 2003-02-27 Gillispie Bryan A. Product and method of brazing using kinetic sprayed coatings
CN1876364A (en) * 2005-06-08 2006-12-13 巨科集团有限公司 Stainless steel, aluminum composite honeycomb panel and processing method
CN104607746A (en) * 2014-12-19 2015-05-13 江苏龙禾轻型材料有限公司 Self-bonding composite board and manufacturing process thereof
CN105562862A (en) * 2015-12-21 2016-05-11 天津大学 Intermediate temperature self-reaction brazing method for aluminum honeycomb boards
CN106256484A (en) * 2016-09-30 2016-12-28 张汉民 A kind of preparation technology of glue-free honeycomb core

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3011254A (en) * 1959-04-06 1961-12-05 North American Aviation Inc Double differential pressure honeycomb sandwich panel brazing
CN101362297A (en) * 2008-09-16 2009-02-11 浙江大学 Pre-compressing device for processing and fixing the honeycomb flexible material
CN102489924A (en) * 2011-12-22 2012-06-13 浙江大学 Combined type flexible clamp for vacuum brazing of core body of plate-fin type aluminum heat exchanger
CN104148857A (en) * 2014-08-06 2014-11-19 安徽省芜湖仪器仪表研究所 Positioning mechanism for welding of cellular board capable of guaranteeing uniformity of forced convection flow field
CN205414768U (en) * 2015-08-05 2016-08-03 武船重型工程股份有限公司 Fixing device

Also Published As

Publication number Publication date
CN107297598A (en) 2017-10-27

Similar Documents

Publication Publication Date Title
CN107297598B (en) Preparation process without glue aluminum honeycomb plate
CN108397679B (en) Sandwich metal plate
KR100264282B1 (en) A method of brazing
CN105665860B (en) Metal welds the welder and preparation method of honeycomb
CN110682029B (en) Active connecting agent for contact reaction of graphite and stainless steel and brazing method
CN105562862A (en) Intermediate temperature self-reaction brazing method for aluminum honeycomb boards
JP6049631B2 (en) Manufacturing method for producing brazed heat exchanger with reinforced parting sheet
CN101219494A (en) Method of welding foamed aluminium sandwich composite board
JP2007507355A5 (en)
CN101579766A (en) Preparation method of braze welding type metal honeycomb plate
CN102489813A (en) Vacuum active brazing process of molybdenum-copper alloys and stainless steel
CN108788356A (en) A kind of manufacturing method and cellular board of soldering cellular board
CN104907676A (en) Welding technology for aluminum alloy network cabinet
CN106181017A (en) A kind of friction stir welding method of corronil
CN111360366A (en) Welding method of full penetration overhead plate
CN101234446A (en) Aluminum alloy low temperature brazing method based on ultrasonic coating
CN108397680B (en) Sandwich metal plate
CN106513991A (en) Laser welding method for foamed aluminum alloy plate
CN105251971A (en) Interlayer vacuum coating method during blank manufacturing process of hot rolling composite plate
CN101992331B (en) Vacuum brazing process for super-Ni laminated material and Cr18-Ni8 stainless steel
CN108790296A (en) A kind of manufacturing method and cellular board of soldering cellular board
CN105694614A (en) Aluminum and steel plate for ships, method for welding aluminum and steel plate and method for preparing paint
CN103406627B (en) The method for welding of a kind of aluminum radiator hourglass pipe nitrogen protection
JP2002178178A (en) Laser lap welding method for metal with surface coating
CN102658465B (en) Manufacturing method of aluminum alloy composite corrugated board

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant