CN107292452A - A kind of distribution power automation terminal Optimal Configuration Method suitable for mountain area power distribution network - Google Patents

A kind of distribution power automation terminal Optimal Configuration Method suitable for mountain area power distribution network Download PDF

Info

Publication number
CN107292452A
CN107292452A CN201710603350.0A CN201710603350A CN107292452A CN 107292452 A CN107292452 A CN 107292452A CN 201710603350 A CN201710603350 A CN 201710603350A CN 107292452 A CN107292452 A CN 107292452A
Authority
CN
China
Prior art keywords
allocation
reliability index
distribution network
automation terminal
mountain area
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710603350.0A
Other languages
Chinese (zh)
Inventor
郑欢
林红阳
唐元春
林文钦
陈力
林长锥
冷正龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Fujian Electric Power Co Ltd
Economic and Technological Research Institute of State Grid Fujian Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Fujian Electric Power Co Ltd
Economic and Technological Research Institute of State Grid Fujian Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Fujian Electric Power Co Ltd, Economic and Technological Research Institute of State Grid Fujian Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201710603350.0A priority Critical patent/CN107292452A/en
Publication of CN107292452A publication Critical patent/CN107292452A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/70Smart grids as climate change mitigation technology in the energy generation sector
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Theoretical Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Marketing (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Quality & Reliability (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Development Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The present invention relates to a kind of distribution power automation terminal Optimal Configuration Method suitable for mountain area power distribution network, including calculate comprehensive cost and reliability index when not configuring automation, the allocation optimum scheme under calculating different condition, output allocation optimum scheme.The comprehensive cost and reliability index when not configuring automation are calculated, according to distribution network track data, is calculated not configuring comprehensive cost and reliability index during automation;The allocation optimum scheme under different condition is calculated, respectively in the whole config failure indicators of key node, and when backbone block switch and distant tie switches allocation wireless three, the allocation optimum scheme under fault detector difference configuration number in addition to key node is calculated;Allocation optimum scheme is exported, the allocation optimum scheme under the different condition obtained by calculating is compared, and allocation plan is exported according to actual conditions.The present invention provides method accurately, efficiently, easy for the planning of solution mountain area distribution power automation terminal and optimization allocation.

Description

A kind of distribution power automation terminal Optimal Configuration Method suitable for mountain area power distribution network
Technical field
It is especially a kind of suitable for mountain area power distribution network the present invention relates to a kind of distribution power automation terminal Optimal Configuration Method Distribution power automation terminal Optimal Configuration Method.
Background technology
With the fast development of economic society, user proposes more intelligent, relatively reliable, more economical to distribution system Required etc. many.Related data shows, power distribution automation be improve power supply reliability, expand power supply capacity, improve power supply quality, Realize the important means of power distribution network high-efficiency and economic operation, be new electricity change under policy power grid enterprises improve distribution network automated level, Strengthen the necessary condition of itself market competitiveness.
In recent years, developing rapidly with computer technology, information and the communication technology, the Distribution Automation Construction of China takes Significant progress was obtained, and progresses into practical stage.China's mountain and sea feature is obvious, although Southern Power Grid Company and state's household electrical appliances Net company puts into effect in succession《Distribution network automated planning directive/guide》With《Distribution automation planning designing technique directive/guide》, for difference The terminal Configuration Type of power supply area has carried out clear and definite regulation, but in specific operation process, because network structure, equipment are joined Had nothing in common with each other in terms of number, load level, reliability requirement, planning personnel is difficult the configuration result for finding a total optimization.
The content of the invention
It is an object of the invention to provide a kind of distribution power automation terminal Optimal Configuration Method suitable for mountain area power distribution network, To overcome defect present in prior art.
To achieve the above object, the technical scheme is that:A kind of power distribution automation suitable for mountain area power distribution network is whole Optimal Configuration Method is held, is realized in accordance with the following steps:
Step S1:Calculate the comprehensive cost and reliability index when not configuring distribution power automation terminal;Input distribution network circuit Data, and calculate not configuring comprehensive cost and reliability index during distribution power automation terminal;
Step S2:Calculate the allocation optimum scheme under different condition;
First state is provided:In the whole config failure indicators of key node;
And second state:It is distant, former in the configuration of remaining key node in backbone block switch and tie switches allocation wireless three Hinder indicator;
Calculate under the first state and under second state, in addition to key node, fault detector difference configuration number Under allocation optimum scheme;Wherein, key node is backbone block switch, interconnection switch and big branch line breaker;
Step S3:Export allocation optimum scheme;Allocation optimum scheme under different condition obtained by calculating is compared, and root Allocation plan is exported according to actual conditions.
In an embodiment of the present invention, in the step S2, for the first state and second state, lead to Cross following steps and calculate allocation optimum scheme:
Step S21:Note is in addition to key node, and fault detector configuration number is 0, calculates comprehensive cost and reliability index;
Step S22:Note is in addition to key node, and fault detector configuration number is 1, and calculating now optimal using genetic algorithm matches somebody with somebody Put scheme and corresponding comprehensive cost and reliability index;
Step S23:Increase the fault detector configuration number in addition to key node successively, and calculated;Match somebody with somebody if gained is optimal Put the corresponding comprehensive cost rising of scheme and reliability index lifting amplitude is less than preset threshold value, then terminate to calculate, obtain Allocation optimum scheme under different faults indicator configuration number.
In an embodiment of the present invention, the reliability index in the step S3 according to actual conditions by being taken House, genetic algorithm does not regard reliability index as constraints described in the step S2.
In an embodiment of the present invention, in the step S22, the genetic algorithm is used as optimization so that comprehensive cost is minimum Target.
In an embodiment of the present invention, the key node includes:Backbone block switch, interconnection switch and big branch line Breaker.
In an embodiment of the present invention, the comprehensive cost includes:Equipment investment, operating cost and interruption cost.
In an embodiment of the present invention, in the step S3, according to acquired allocation optimum scheme, judge whether to deposit Meeting the scheme of reliability index requirements;If in the presence of the optimal allocation plan of output integrated expense;It is defeated if being not present All allocation optimum schemes gone out under different condition, are transmitted to planning personnel.
Compared to prior art, the invention has the advantages that:The present invention proposes a kind of suitable for mountain area power distribution network Distribution power automation terminal Optimal Configuration Method, referred to according to given network structure, track data, load level and reliability Mark, determines distribution power automation terminal installation site optimal under the conditions of specific circuit and Setup Type so that the circuit is as far as possible On the premise of meeting power supply area reliability requirement, line walking difficulty is reduced, the fault insulation and resume time is greatly reduced, shows money The maximum service efficiency of gold.The present invention provides an alignment to solve the planning of mountain area distribution power automation terminal with optimization allocation Really, method efficiently, easy.
Brief description of the drawings
Fig. 1 for the present invention in be applied to mountain area power distribution network distribution power automation terminal Optimal Configuration Method flow chart.
Fig. 2 is example conspectus in one embodiment of the invention.
Fig. 3 (a) is comprehensive cost result of calculation contrast schematic diagram in one embodiment of the invention.
Fig. 3 (b) is reliability index result of calculation contrast schematic diagram in one embodiment of the invention.
Embodiment
Below in conjunction with the accompanying drawings, technical scheme is specifically described.
The present invention proposes a kind of distribution power automation terminal Optimal Configuration Method suitable for mountain area power distribution network, including synthesis Consider the influence factors such as distribution net work structure, power load distributing, construction investment, fault outage loss and reliability requirement, set up optimization Model simultaneously uses genetic algorithm for solving, determines the Configuration Type of distribution power automation terminal, quantity and position in the power distribution network of mountain area.
Further, in the present embodiment, according to distribution network track data, first to not configuring synthesis during automation Expense and reliability index are calculated;Secondly, respectively in the whole config failure indicators of key node, and backbone segmentation When switch and tie switches allocation wireless three are distant, optimal the matching somebody with somebody under fault detector difference configuration number in addition to key node is calculated Put scheme;Finally, the allocation optimum scheme under the different condition obtained by calculating is compared, if in the presence of meeting constraints Optimal solution, then export optimal solution, if being not present, and lists the allocation optimum scheme under different condition.
In order to allow those skilled in the art to further appreciate that a kind of matching somebody with somebody suitable for mountain area power distribution network proposed by the invention The terminal optimized collocation method of electric automation, is illustrated with reference to specific implementation.
As shown in figure 1, a kind of distribution power automation terminal suitable for mountain area power distribution network proposed in the present embodiment optimizes Collocation method, including calculate comprehensive cost and reliability index 1 when not configuring automation, optimal matching somebody with somebody of calculating under different condition Put scheme 2,3 three parts of output allocation optimum scheme.
Further, calculating comprehensive cost and reliability index 1 when not configuring automation includes:Input power distribution network winding thread Circuit-switched data, and calculate not configuring comprehensive cost and reliability index during automation.Comprehensive cost include equipment investment, Operating cost and interruption cost.
Further, the allocation optimum scheme 2 calculated under different condition includes:Respectively in the whole config failures of key node Indicator, and backbone block switch and tie switches allocation wireless three is distant, remaining key node config failure indicator when, The allocation optimum scheme under fault detector difference configuration number in addition to key node is calculated, wherein key node is backbone point Duan Kaiguan, interconnection switch and big branch line breaker.By taking whole config failure indicators at key node as an example, assume initially that Fault detector configuration number is 0 in addition to key node, calculates comprehensive cost and reliability index;Secondly assume to remove key node Outer fault detector configuration number is 1, using genetic algorithm calculate allocation optimum scheme now and corresponding comprehensive cost with Reliability index;Increase the configuration number of the fault detector in addition to key node successively and calculated, if gained allocation optimum The corresponding comprehensive cost of scheme rises and reliability index lifting amplitude is less than given threshold, then terminates to calculate, obtain different events Hinder the allocation optimum scheme under indicator configuration number.Backbone block switch and tie switches allocation are obtained using same procedure Wireless three is distant, remaining key node config failure indicator when different faults indicators configuration number under allocation optimum scheme.
Further, the genetic algorithm optimization target that the allocation optimum scheme 2 under calculating different condition is used is synthesis Expense is minimum, because mountain area power distribution network still suffers from the high failure long transmission line in part, it is impossible to meet reliability index requirements, therefore at this Genetic algorithm employed in embodiment is not using reliability index as constraints, and reliability index is in output allocation optimum side The part of case 3 is considered.
Further, output allocation optimum scheme 3 includes:Judgement is in the allocation optimum scheme of gained at different conditions It is no to there is the scheme for meeting reliability index requirements.If in the presence of the optimal allocation plan of output integrated expense;If being not present, All allocation optimum schemes under different condition are then listed, are selected by planning personnel according to actual conditions.
Further, in the present embodiment, it is applied to the distribution power automation terminal of mountain area power distribution network with reference to Fig. 2 ~ 3 pair Optimal Configuration Method carries out sample calculation analysis.
Example circuit and relevant parameter employed in the present embodiment are illustrated in figure 2, the overhead transmission line is somewhere mountain area The high failure long transmission line of power distribution network typical case, has 6, branch line, load point 50,400, shaft tower, about 40 kilometers of total line length.Figure Numeral is bar number in middle black box, and black open squares are interconnection switch, and solid black square frame is with electrode difference protection function Breaker, failure can automatic separating fault after occurring.Basic parameter sets as follows:According to the actual traffic-operating period of local power distribution network, Load simultaneity factor 0.6,37.3 secondary/hundred kilometers, wireless three distant 20,000 yuan/group of terminal, maintenance cost of overhead transmission line fault rate are set 0.1 ten thousand yuan/year, 0.4 ten thousand yuan/group of fault detector, yuan/year of maintenance cost 217;Population in Genetic Algorithms scale 100, iterations 100, crossover probability is 0.9, and mutation probability is 0.1;Unit loss of outage is 0.8 yuan/kilowatt hour, and the fault outage time, which accounts for, always to stop Electric time scale is 30%, and reliability index lifting amplitude set threshold value is 0.01%, and reliability program target is 99.726%;Not When configuring distribution power automation terminal, the fault outage time is trouble shooting time and the time sum that restores electricity, during trouble shoot Between be that, with the time of 4 kilometers/hour of speed line walking, the time that restores electricity is 0.5 hour from circuit top;Distribution is installed automatic Change after terminal, trouble shooting time is in the indicating fault interval time with 4 kilometers/hour of speed line walking, if backbone point Duan Kaiguan and tie switches allocation wireless three are distant, then the time that restores electricity is 0.
Further, it is adaptable to which the result of calculation contrast of the distribution power automation terminal Optimal Configuration Method of mountain area power distribution network is shown It is intended to as shown in Fig. 3 (a) and Fig. 3 (b).Fig. 3(a)Middle unit is/ten thousand yuan, Fig. 3(b)In be percentage.With fault detector The increase of number is configured, reliability index is gradually lifted, and reliability index during key node whole config failure indicator Consistently lower than backbone block switch and reliability index during distant tie switches allocation wireless three;Key node all configuration events When hindering indicator, comprehensive cost is minimum when the fault detector configuration number in addition to key node is 3;Backbone block switch and Tie switches allocation is wireless three it is distant when, in addition to key node fault detector configuration number be 2 when comprehensive cost it is minimum;Except pass When fault detector configuration number outside key node is more than 2, comprehensive cost during key node whole config failure indicator is low Comprehensive cost when backbone block switch and tie switches allocation wireless three is distant.When terminal configuration number is more than 5, the line The reliability index lifting amplitude on road is less than given threshold, and EP (end of program) is calculated, and the reliability of gained allocation optimum scheme refers to Mark is below reliability program target 99.726%, now lists all allocation optimum schemes under different condition, for planning people Member is selected according to actual conditions.
Above is presently preferred embodiments of the present invention, all changes made according to technical solution of the present invention, produced function is made During with scope without departing from technical solution of the present invention, protection scope of the present invention is belonged to.

Claims (7)

1. a kind of distribution power automation terminal Optimal Configuration Method suitable for mountain area power distribution network, it is characterised in that according to following step It is rapid to realize:
Step S1:Calculate the comprehensive cost and reliability index when not configuring distribution power automation terminal;Input distribution network circuit Data, and calculate not configuring comprehensive cost and reliability index during distribution power automation terminal;
Step S2:Calculate the allocation optimum scheme under different condition;
First state is provided:In the whole config failure indicators of key node;
And second state:It is distant, former in the configuration of remaining key node in backbone block switch and tie switches allocation wireless three Hinder indicator;
Calculate under the first state and under second state, in addition to key node, fault detector difference configuration number Under allocation optimum scheme;Wherein, key node is backbone block switch, interconnection switch and big branch line breaker;
Step S3:Export allocation optimum scheme;Allocation optimum scheme under different condition obtained by calculating is compared, and root Allocation plan is exported according to actual conditions.
2. a kind of distribution power automation terminal Optimal Configuration Method suitable for mountain area power distribution network according to claim 1, its It is characterised by, in the step S2, for the first state and second state, calculates as follows optimal Allocation plan:
Step S21:Note is in addition to key node, and fault detector configuration number is 0, calculates comprehensive cost and reliability index;
Step S22:Note is in addition to key node, and fault detector configuration number is 1, and calculating now optimal using genetic algorithm matches somebody with somebody Put scheme and corresponding comprehensive cost and reliability index;
Step S23:Increase the fault detector configuration number in addition to key node successively, and calculated;Match somebody with somebody if gained is optimal Put the corresponding comprehensive cost rising of scheme and reliability index lifting amplitude is less than preset threshold value, then terminate to calculate, obtain Allocation optimum scheme under different faults indicator configuration number.
3. a kind of distribution power automation terminal Optimal Configuration Method suitable for mountain area power distribution network according to claim 2, its It is characterised by, in the step S22, the genetic algorithm is used as optimization aim using comprehensive cost minimum.
4. a kind of distribution power automation terminal Optimal Configuration Method suitable for mountain area power distribution network according to claim 2, its It is characterised by, the reliability index is accepted or rejected in by the step S3, and genetic algorithm described in the step S2 Reliability index is not regard it as constraints.
5. a kind of distribution power automation terminal Optimal Configuration Method suitable for mountain area power distribution network according to claim 2, its It is characterised by, the key node includes:Backbone block switch, interconnection switch and big branch line breaker.
6. a kind of distribution power automation terminal side of distributing rationally suitable for mountain area power distribution network according to claim 1,2 or 5 Method, it is characterised in that the comprehensive cost includes:Equipment investment, operating cost and interruption cost.
7. a kind of distribution power automation terminal Optimal Configuration Method suitable for mountain area power distribution network according to claim 1, its It is characterised by, in the step S3, according to acquired allocation optimum scheme, judges whether that meeting reliability index wants The scheme asked;If in the presence of the optimal allocation plan of output integrated expense;It is all under output different condition if being not present Allocation optimum scheme, is transmitted to planning personnel.
CN201710603350.0A 2017-07-22 2017-07-22 A kind of distribution power automation terminal Optimal Configuration Method suitable for mountain area power distribution network Pending CN107292452A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710603350.0A CN107292452A (en) 2017-07-22 2017-07-22 A kind of distribution power automation terminal Optimal Configuration Method suitable for mountain area power distribution network

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710603350.0A CN107292452A (en) 2017-07-22 2017-07-22 A kind of distribution power automation terminal Optimal Configuration Method suitable for mountain area power distribution network

Publications (1)

Publication Number Publication Date
CN107292452A true CN107292452A (en) 2017-10-24

Family

ID=60102702

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710603350.0A Pending CN107292452A (en) 2017-07-22 2017-07-22 A kind of distribution power automation terminal Optimal Configuration Method suitable for mountain area power distribution network

Country Status (1)

Country Link
CN (1) CN107292452A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114218727A (en) * 2021-12-15 2022-03-22 国家电网有限公司 Power distribution network frame planning and multi-module intelligent terminal configuration joint optimization method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105356610A (en) * 2015-11-26 2016-02-24 江苏省电力公司南京供电公司 Configuration method of distribution automation terminal of intelligent power distribution network
CN105868869A (en) * 2016-05-10 2016-08-17 华南理工大学 Dynamic distribution automation terminal layout optimization planning method taking reliability and economic cost of power supply into account
CN106786531A (en) * 2016-12-26 2017-05-31 国网天津市电力公司 A kind of distribution terminal Optimal Configuration Method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105356610A (en) * 2015-11-26 2016-02-24 江苏省电力公司南京供电公司 Configuration method of distribution automation terminal of intelligent power distribution network
CN105868869A (en) * 2016-05-10 2016-08-17 华南理工大学 Dynamic distribution automation terminal layout optimization planning method taking reliability and economic cost of power supply into account
CN106786531A (en) * 2016-12-26 2017-05-31 国网天津市电力公司 A kind of distribution terminal Optimal Configuration Method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
刘大雷: ""配电网可靠性分析及分段开关和故障指示器优化配置的研究"", 《中国优秀硕士学位论文全文数据库 工程科技辑》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114218727A (en) * 2021-12-15 2022-03-22 国家电网有限公司 Power distribution network frame planning and multi-module intelligent terminal configuration joint optimization method

Similar Documents

Publication Publication Date Title
CN101673965B (en) Automatic switching control method for wide-area emergency power source of electric power system
CN106021596B (en) A kind of analysis method of electric network fault rush of current topological diagram
CN103354353B (en) Intelligent power-distribution-network whole-line quick-reacting main protection and determination system and method
CN104599067B (en) Powered based on mountain area power distribution network the novel index evaluation system construction method of model
CN110808633B (en) Distribution automation terminal optimal configuration method for active distribution network
CN109146124B (en) Power distribution terminal transformation decision method based on time-varying failure rate
CN103219727B (en) Partition power grid structure dynamics method of adjustment based on PMU actual measurement
CN105576660A (en) Region power distribution network on-line simulation analysis device and system
CN109858663A (en) Distribution network failure power failure INFLUENCING FACTORS analysis based on BP neural network
CN102289731A (en) Method for maintaining state of power transmission equipment based on system risk
CN109949178B (en) Method for judging and complementing power failure event of medium-voltage distribution network based on support vector machine
CN103607042A (en) Power distribution network fault processing method for suburb long overhead line-oriented fault indicator
CN108710099A (en) Capacitance type potential transformer monitoring alarm method and system
Sun et al. Optimal allocation of smart substations in a distribution system considering interruption costs of customers
CN107453354A (en) A kind of weak link recognition methods of power distribution network
CN112001686A (en) Overhead line power failure studying and judging system
CN105337314A (en) Multisource coordination control fault treatment method based on distributed power supply black start technology
CN101969234B (en) Optimization control method of transformer load of transformer substation automation system
CN112766738B (en) Optimal configuration method for distribution network automation terminal
CN105404933A (en) Computing system for enhancing power supply reliability for power distribution network and computing method thereof
CN107292452A (en) A kind of distribution power automation terminal Optimal Configuration Method suitable for mountain area power distribution network
CN106372764A (en) 10kV distribution network and 10kV distribution network coordination configuration method
CN104319779B (en) Regional power grid reactive voltage control method
CN108847656B (en) Distribution network grounding line selection protection system based on self-adaptive dynamic contribution rate
CN115224687A (en) Power failure overhaul safety checking method and system for power transmission and transformation equipment below 220KV

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20171024