CN107288125A - Prefabricated pile stake core anti-blocking method - Google Patents

Prefabricated pile stake core anti-blocking method Download PDF

Info

Publication number
CN107288125A
CN107288125A CN201710521054.6A CN201710521054A CN107288125A CN 107288125 A CN107288125 A CN 107288125A CN 201710521054 A CN201710521054 A CN 201710521054A CN 107288125 A CN107288125 A CN 107288125A
Authority
CN
China
Prior art keywords
otic placode
pile
prefabricated pile
plugging plate
blocking method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710521054.6A
Other languages
Chinese (zh)
Inventor
康建元
殷永艺
王明雄
许伟杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Shanghai Ershiye Construction Co Ltd
Original Assignee
China MCC20 Group Corp Ltd
Shanghai Ershiye Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd, Shanghai Ershiye Construction Co Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201710521054.6A priority Critical patent/CN107288125A/en
Publication of CN107288125A publication Critical patent/CN107288125A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/30Prefabricated piles made of concrete or reinforced concrete or made of steel and concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The present invention relates to pile foundation construction field, specifically a kind of prefabricated pile stake core anti-blocking method;It is characterized in that:The pre-buried otic placode including step 1, in prefabricated pile, the otic placode is embedded in below pile end plate;Step 2, before piling one plugging plate is connected by screw with pre-buried otic placode;Step 3, progress piling work;Step 4, after piling completes earth excavation to stake top absolute altitude, plugging plate is removed, and will prominent internal diameter otic placode gas cutting or tie.This anti-blocking method is easy to implement, with strong points, simple to operate, it can prevent prefabricated pile foreign matter during work progress and foundation construction from, to the landfill of stake core, the inconvenience that borehole cleaning is brought is saved, so as to reduce construction cost, the duration is saved, efficiency of construction is improved, it is ensured that construction quality.

Description

Prefabricated pile stake core anti-blocking method
Technical field
The present invention relates to pile foundation construction field, specifically a kind of prefabricated pile stake core anti-blocking method.
Background technology
Typically in multilayer or high building project, through frequently with prefabricated tubular pile as pile foundation, and in construction often There is prefabricated tubular pile stake core to be filled by foreign matter or soil, processing method is extremely complex, and for example stone is directly clamped among stake to some foreign matters Inside core, it is impossible to rejected, manually can only be processed to using light instrument using equipment, and for example during earth excavation A large amount of soil fill up stake core, secondary need to carry out borehole cleaning to stake core, waste a large amount of manpower and materials, and influence duration.
The content of the invention
It is an object of the present invention to provide preventing the method that stake core is filled by foreign matter during a kind of construction of prefabricated piles.
In order to achieve the above object, the present invention is realized in:
A kind of prefabricated pile stake core anti-blocking method, including
Step 1, the pre-buried otic placode in prefabricated pile, the otic placode are embedded in below pile end plate;
Step 2, before piling one plugging plate is connected by screw with pre-buried otic placode;
Step 3, progress piling work;
Step 4, after piling completes earth excavation to stake top absolute altitude, plugging plate is removed, and will prominent internal diameter otic placode gas cutting Or tie.
The prefabricated pile stake core anti-blocking method, otic placode and prefabricated pile one-shot forming;Specifically, by ear before prefabricated forming pile Plate is embedded in inside pile body in advance, and otic placode exposes the hole in advance fixed screw a core position and interior screw thread is completed, screw thread hole It need to be matched with the closure board size of installation.
The prefabricated pile stake core anti-blocking method, plugging plate is combined with the screw hole internal thread deduction of points portion size of otic placode, sealed Closure plate is U-shaped, and outside dimension must not exceed prefabricated pile stake core internal diameter size, and plugging plate adds spring shim and otic placode by screw It is connected.
This anti-blocking method is easy to implement, with strong points, simple to operate, can prevent prefabricated pile from being applied in work progress and basis Foreign matter saves the inconvenience that borehole cleaning is brought to the landfill of stake core during work, so as to reduce construction cost, saves the duration, raising is applied Work efficiency rate, it is ensured that construction quality.
Brief description of the drawings
The pre-buried schematic diagram of Fig. 1 otic placodes.
Fig. 2 otic placode processing dimension figures.
Fig. 3 perforation plugging plate scheme of installations.
Fig. 4 perforation plugging plate processing dimension figures.
Fig. 5, perforation plugging plate are removed and otic placode processing schematic diagram one.
Fig. 6, perforation plugging plate are removed and otic placode processing schematic diagram two.
Embodiment
The present invention is further illustrated below by way of specific embodiment.
A kind of prefabricated pile stake core anti-blocking method, including;
As shown in figure 1, below the end plate 3 of prefabricated pile 2 pre-buried otic placode 1 totally 8, uniform branch in pile body internal diameter, otic placode 1 with it is pre- During forming pile processed it is synchronous it is pre-buried pours completions, pre-buried exposed stake holes the inner of otic placode 1 need to beat internal thread hole 7, using M6 screws 5 and Plugging plate is connected.
As shown in Fig. 2 otic placode 1 is processed into " 7 " font using the thick galvanized steel plain sheets of 3mm, 7 dozens of internal thread hole 6mm of revealed section, so as to Subsequently it is connected with plugging plate.
As shown in figure 3, perforation plugging plate 4 and the engineering of otic placode 1 complete plugging effect, therefore plugging plate 4 is connected with otic placode 1 Screw hole 7 should be corresponded to strictly, uniform branch, and the diameter control of hole 8 is in 8mm, to ensure that stake reduces air during suppressing Damage of the pressure to pile body, therefore uniformly beat diameter 10mm holes 6, the spacing 50mm of hole 6 in the plate face of plugging plate 4.
As shown in figure 4, the diameter D of plugging plate 4 is processed into U-shaped, sheet metal thickness 2mm according to actual size, the space of a whole page is according to spacing 50mm size uniforms perforate 6, the diameter 10mm of hole 6 alleviates stake holes inner air pressure, and the diameter of perimeter perforate 8 is not less than 8mm, and should being connected with otic placode internal thread hole branch, it is ensured that connection coincide.
As shown in Figure 5, Figure 6, pile driving construction is treated to designed elevation, and earth excavation is to bottom of foundation ditch, prefabricated pile end plate 3 is all After exposed, stake in-core plugging plate 4 is removed, then picked the otic placode 1 of exposed stake core inner using gas welding cutting or corresponding tool It is flat;So as to prevent piling or earth excavation process medium-and-large-sized hard thing or soil etc. from being clogged to stake holes.

Claims (3)

1. a kind of prefabricated pile stake core anti-blocking method, it is characterized in that:Including
Step 1, the pre-buried otic placode in prefabricated pile, the otic placode are embedded in below pile end plate;
Step 2, before piling one plugging plate is connected by screw with pre-buried otic placode;
Step 3, progress piling work;
Step 4, after piling completes earth excavation to stake top absolute altitude, plugging plate is removed, and will prominent internal diameter otic placode gas cutting Or tie.
2. according to claim 1 prefabricated pile stake core anti-blocking method, it is characterized in that:Otic placode and prefabricated pile one-shot forming;Specifically It is to be embedded in otic placode inside pile body in advance before prefabricated forming pile, and otic placode exposes the hole that screw is in advance fixed in a core position And interior screw thread is completed, screw thread hole need to match with the closure board size of installation.
3. according to claim 1 prefabricated pile stake core anti-blocking method, it is characterized in that:The screw hole internal thread of plugging plate and otic placode Deduction of points portion size is combined, and plugging plate is U-shaped, and outside dimension must not exceed prefabricated pile stake core internal diameter size, and plugging plate passes through Screw adds spring shim to be connected with otic placode.
CN201710521054.6A 2017-06-30 2017-06-30 Prefabricated pile stake core anti-blocking method Pending CN107288125A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710521054.6A CN107288125A (en) 2017-06-30 2017-06-30 Prefabricated pile stake core anti-blocking method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710521054.6A CN107288125A (en) 2017-06-30 2017-06-30 Prefabricated pile stake core anti-blocking method

Publications (1)

Publication Number Publication Date
CN107288125A true CN107288125A (en) 2017-10-24

Family

ID=60098824

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710521054.6A Pending CN107288125A (en) 2017-06-30 2017-06-30 Prefabricated pile stake core anti-blocking method

Country Status (1)

Country Link
CN (1) CN107288125A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110374084A (en) * 2019-06-28 2019-10-25 中国一冶集团有限公司 Prefabricated tubular pile stomidium plugging device and method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103643682A (en) * 2013-11-28 2014-03-19 杭州江润科技有限公司 Pre-stressed hollow pipe pile foundation pit support structure and construction method
CN203855960U (en) * 2014-03-19 2014-10-01 江苏弘发建设工程有限公司 Pile top mud-preventing pile cap applied to pre-stressing concrete pipe pile
CN104131556A (en) * 2014-07-22 2014-11-05 冠鲁建设股份有限公司 Soft-and-hard interlayer alternation foundation drainage prestressed pipe pile and construction method
KR101494239B1 (en) * 2012-09-28 2015-03-02 주식회사 제이에스그린 The artificial structure of natural stone type using soil nail to be able to make a hole
CN105507235A (en) * 2015-08-20 2016-04-20 喻良军 Prefabricated pile for expressway bridge
CN205636735U (en) * 2016-04-26 2016-10-12 江苏仪征苏中建设有限公司 But secondary is used as in advance stake hole guard plate that core layer board was filled out to stress tube stake pile bolck

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101494239B1 (en) * 2012-09-28 2015-03-02 주식회사 제이에스그린 The artificial structure of natural stone type using soil nail to be able to make a hole
CN103643682A (en) * 2013-11-28 2014-03-19 杭州江润科技有限公司 Pre-stressed hollow pipe pile foundation pit support structure and construction method
CN203855960U (en) * 2014-03-19 2014-10-01 江苏弘发建设工程有限公司 Pile top mud-preventing pile cap applied to pre-stressing concrete pipe pile
CN104131556A (en) * 2014-07-22 2014-11-05 冠鲁建设股份有限公司 Soft-and-hard interlayer alternation foundation drainage prestressed pipe pile and construction method
CN105507235A (en) * 2015-08-20 2016-04-20 喻良军 Prefabricated pile for expressway bridge
CN205636735U (en) * 2016-04-26 2016-10-12 江苏仪征苏中建设有限公司 But secondary is used as in advance stake hole guard plate that core layer board was filled out to stress tube stake pile bolck

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110374084A (en) * 2019-06-28 2019-10-25 中国一冶集团有限公司 Prefabricated tubular pile stomidium plugging device and method

Similar Documents

Publication Publication Date Title
CN103967028A (en) Immersed tube drainage structure and method for handling suddenly-produced foundation pit water bursting and fountains through immersed tube drainage structure
CN108612111B (en) Steel pipe pile, foundation pit support structure and construction method of foundation pit support structure
CN109403347B (en) Frame type double-row pile cement soil wall foundation pit support structure and construction method thereof
CN108086308B (en) Construction method for punching cast-in-place pile on local buried sludge bag in sea-filling area
CN107288125A (en) Prefabricated pile stake core anti-blocking method
CN105350555B (en) A kind of rapid constructing method of dewatering well
JP3733533B2 (en) Foundation reinforcement method under pressure of existing structures
CN203855960U (en) Pile top mud-preventing pile cap applied to pre-stressing concrete pipe pile
EP2650446A1 (en) Method of creating a foundation for a offshore structure
CN110206481A (en) Dewatering well constructing device
CN214061716U (en) Testing arrangement of cement soil mud lateral pressure
CN102400564A (en) Temporary underpinning system for masonry structure bearing wall rear opening and construction method thereof
CN106051316B (en) A kind of pipeline wears the construction method in pond
CN105332375A (en) Fixing method for base of pile driver for static-pressed pile by anchor rods
JP2017057616A (en) Steel pipe concrete composite pile, its manufacturing method and pile head processing method
CN104532832A (en) Steel retaining cylinder and application method thereof
CN204370413U (en) A kind of steel pile casting
JP3219993B2 (en) Piling method in pit structure
EP2432984B1 (en) Wave chamber for a wave power plant, and method for producing the same
CN205444484U (en) Wall lacing wire subassembly
CN205604251U (en) A slip casting system that is used for pier, bridge pile steel pipe
CN204898673U (en) Make things convenient for drilling equipment in advance of engineering construction
CN110173113A (en) A kind of Lin Qiang hangs hole constructing structure and method
DE102014112787A1 (en) Method for connecting an upper pipe end of a foundation structure with a lower pipe end of a structural element for the construction of an offshore wind turbine
CN112832253B (en) Treatment method for piping of steel sheet pile support foundation pit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20171024