CN107288025A - The asymmetric span of formula is held in one kind mixing thrust CFST Arch Bridge - Google Patents

The asymmetric span of formula is held in one kind mixing thrust CFST Arch Bridge Download PDF

Info

Publication number
CN107288025A
CN107288025A CN201710639255.6A CN201710639255A CN107288025A CN 107288025 A CN107288025 A CN 107288025A CN 201710639255 A CN201710639255 A CN 201710639255A CN 107288025 A CN107288025 A CN 107288025A
Authority
CN
China
Prior art keywords
arch
main
bridge
span
bridge deck
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710639255.6A
Other languages
Chinese (zh)
Inventor
涂杨志
许三平
郗宏庆
林骋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Siyuan Survey and Design Group Co Ltd
Original Assignee
China Railway Siyuan Survey and Design Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Siyuan Survey and Design Group Co Ltd filed Critical China Railway Siyuan Survey and Design Group Co Ltd
Priority to CN201710639255.6A priority Critical patent/CN107288025A/en
Publication of CN107288025A publication Critical patent/CN107288025A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D4/00Arch-type bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

Holding the asymmetric span of formula the invention discloses one kind mixing has thrust CFST Arch Bridge.It includes bridge deck, the substructure of multiple support bridge decks and concrete-filled steel tube arch, the concrete-filled steel tube arch is symmetricly set in the both sides of bridge deck, concrete-filled steel tube arch includes the main span main arch of half-through and the end bay main arch of deck type, the arch springing at the main span main arch two ends is individually fixed in two neighboring substructure, the arch springing at the end bay main arch two ends is individually fixed in two neighboring substructure, and the span ratio of the main span main arch and end bay main arch is 0.3 0.55.The present invention combines half-through and Deck Arch Bridges arch, combined using a kind of span of asymmetric coordination than organically, form a kind of unique structure bridge-type structure attractive in appearance, to meet different site condition requirements, structure is novel, handsome in appearance, reasonable in design, easy construction, with good social and economic benefit.

Description

The asymmetric span of formula is held in one kind mixing thrust CFST Arch Bridge
Technical field
The invention belongs to technical field of bridge engineering, and in particular to the asymmetric span of formula is held in one kind mixing has thrust steel pipe to mix Solidifying soil arch bridge.
Background technology
On current existing municipal river course have thrust CFST Arch Bridge be mostly single deck type, half-through or Lower bearing arch bridge, Deck Arch Bridges refer to that bridge deck is located at the bridge of concrete-filled steel tube arch top of the trellis, and half-through arch bridge refers to bridge The bridge that face system passes through in the middle part of concrete filled steel tube bow member, lower bearing arch bridge refers to that bridge deck is located at concrete filled steel tube bow member bottom Bridge.Bridge type is generally single span freely supported structure bridge or three across Symmetric Rigid Frames arch bridge girder constructions.
The problem of arch bridge of above-mentioned single symmetric form is present:Not every site condition (such as river width) is all lucky Identical with the bridge length of design, some river widths are such as too big using single span, again too small using three across when spans, this When be accomplished by changing corresponding site condition to meet the bridge width of setting, cause construction cost to greatly increase.
The content of the invention
The purpose of the present invention is exactly that there is provided a kind of simple in construction, design in order to solve the deficiency of above-mentioned background technology presence The asymmetric span of formula is held in rational mixing thrust CFST Arch Bridge.
The technical solution adopted by the present invention is:The asymmetric span of formula is held in one kind mixing thrust CFST Arch Bridge, wraps Bridge deck, the substructure of multiple support bridge decks and concrete-filled steel tube arch are included, the concrete-filled steel tube arch is symmetricly set in bridge The both sides of face system, it is characterised in that:Concrete-filled steel tube arch includes the main span main arch of half-through and the end bay main arch of deck type, described The arch springing at main span main arch two ends is individually fixed in two neighboring substructure, and the arch springing at the end bay main arch two ends is fixed respectively In in two neighboring substructure, close to main span on the arch springing and end bay main arch of end bay main arch one end on the main span main arch The arch springing of main arch one end is fixed in same substructure, and the span ratio of the main span main arch and end bay main arch is 0.3- 0.55。
Further, the bridge deck includes floorings, crossbeam and longeron, and the floorings are supported in cross rail top, institute State crossbeam both sides and be respectively fixed with bracket, the longeron two ends are supported between adjacent beams on corresponding two brackets.
Further, the substructure includes pile foundation, cushion cap, skewback and the bridge pier being sequentially arranged from the bottom to top, institute State bridge deck and be supported in pier coping portion, the arch springing of the main span main arch and end bay main arch is fixed on skewback.
Further, the multiple substructure is included along vertical bridge to the first substructure, the second bottom being sequentially arranged Structure and the 3rd substructure, first substructure and the 3rd substructure are flexibly connected with bridge deck, under described second Portion's structure is fixedly connected with bridge deck.
Further, the main span main arch is located between the part above bridge deck and bridge deck and connected by suspension rod, hangs The crossbeam of bar bottom hung bridge deck, the main span main arch is located at vertical by first between the part below bridge deck and bridge deck Post is connected, the crossbeam of the first column top braces bridge deck.
Further, it is horizontal by the first intercostal between the position of the main span main arch of the bridge deck both sides and bridge deck connection Beam is connected, and is connected at the top of the bridge deck between the main span main arch of both sides by spaced multiple first stulls.
Further, it is connected, is propped up at the top of the second column with bridge deck by multiple second columns at the top of the end bay main arch Support the crossbeam of bridge deck.
Further, the second rib is passed through between the position of bridge deck connection at the top of the end bay main arch of the bridge deck both sides Between crossbeam connect, pass through spaced multiple second stulls between the end bay main arch of the bridge deck two bottom sides and connect.
Further, the arch rib of the main span main arch and end bay main arch is double-decker, including section is square arrangement Connected between four supervisors, four supervisors by cross bar and vertical pole, fill concrete in supervisor.
Further, the span ratio of the main span main arch and end bay main arch is 0.43.
The present invention combines half-through and Deck Arch Bridges arch, using a kind of span of asymmetric coordination than organic Ground is combined, and forms a kind of unique structure bridge-type structure attractive in appearance, to meet same site condition requirement not;Bridge deck is using light-duty The structural system of floatation type is engaged with the pile foundation of bottom and bridge pier, can improve the horizontal thrust of bridge, structure well Novelty, handsome in appearance, reasonable in design, easy construction, improves the harmony of bridge and environment, with good social and economy Benefit.
Brief description of the drawings
Fig. 1 is structural representation of the invention.
Fig. 2 is the schematic diagram of bridge deck of the present invention.
Fig. 3 is the schematic diagram of arch rib of the present invention.
Fig. 4 is the schematic diagram of substructure of the present invention.
In figure:1- bridge decks;1.1- floorings;1.2- crossbeam;1.3- longeron;1.4- bracket;2- substructures;2.1- stake Basis;2.2- cushion cap;2.3- skewback;2.4- bridge pier;3- main span main arch;4- end bay main arch;The substructures of 5- first;Under 6- second Portion's structure;The substructures of 7- the 3rd;8- suspension rods;The columns of 9- first;The columns of 10- second;11- the first intercostal crossbeams;The ribs of 12- second Between crossbeam;The stulls of 13- first;The stulls of 14- second;15- is responsible for;16- cross bars;17- vertical poles;18- bearings.
Embodiment
The present invention is described in further detail with specific embodiment below in conjunction with the accompanying drawings, is easy to that this hair is well understood It is bright, but they do not constitute restriction to the present invention.
As Figure 1-4, the present invention includes bridge deck 1, the substructure 2 of multiple support bridge decks and concrete filled steel tube Arch, the concrete-filled steel tube arch is symmetricly set in the both sides of bridge deck, and concrete-filled steel tube arch includes the He of main span main arch 3 of half-through The end bay main arch 4 of deck type, the arch springing at the two ends of main span main arch 3 is individually fixed in two neighboring substructure, the side Arch springing across the two ends of main arch 4 is individually fixed in two neighboring substructure, close to end bay main arch 4 one on the main span main arch 3 Arch springing on the arch springing and end bay main arch at end close to main span main arch one end is fixed in same substructure, the main span main arch 3 and the span ratio of end bay main arch 4 are 0.3-0.55, preferably 0.43, specific span ratio is decided according to the actual requirements.
In such scheme, bridge deck 1 includes floorings 1.1, crossbeam 1.2 and longeron 1.3, and the floorings 1.1 are supported in The top of crossbeam 1.2, the both sides of crossbeam 1.2 are respectively fixed with bracket 1.4, and adjacent beams 1.2 are fixed at the two ends of longeron 1.3 Between on relative two brackets 1.4.Floorings 1.1 are concrete slab, and main support is at the top of crossbeam 1.2, therefore floorings are set Count into height 36cm " π " shape mechanism.Crossbeam 1.2 uses steel box structure, crossbeam 1.2 and the formation steel of floorings 1.1 of steel construction Concrete Composite Beam, longeron 1.3 uses H-shaped steel construction, and longeron 1.3 is arranged between crossbeam 1.2 by bracket 1.4, crossbeam 1.2nd, longeron .3 and floorings 1.1 coordinate the bridge system structure that light-duty floatation type is integrally formed, and can be effectively improved pushing away for main arch Power problem.
In such scheme, substructure 2 includes the pile foundation 2.1 being sequentially arranged from the bottom to top, cushion cap 2.2, the and of skewback 2.3 Bridge pier 2.4, the bridge deck 1 is supported in the top of bridge pier 2.4, and the arch springing of the main span main arch 3 and end bay main arch 4 is fixed on skewback 2.3 on.This bridge type is due to being dissymmetrical structure, and foundation level power is slightly larger relative to vertical force, and pile foundation arrangement of reinforcement is more difficult, can adopt With the pile foundation of major diameter, method that is basic pre- eccentric and using larger concrete frame pier of conducting oneself with dignity is set to be improved. The pre- bias in basis is the center o of pile foundation 2.11With the cushion cap at the top of it, the center o of bridge pier2Not on same perpendicular, partially From with a certain distance from.
This bridge type is two bridge girder constructions of asymmetric formula, therefore multiple substructures 2 are included along vertical bridge to being sequentially arranged The first substructure 5, the second substructure 6 and the 3rd substructure 7, the arch springing at the two ends of main span main arch 3 is individually fixed in On the skewback of one substructure 5 and the second substructure 6, the arch springing at the two ends of end bay main arch 4 is individually fixed in the second bottom On the skewback of the substructure 7 of structure 6 and the 3rd.Wherein the first substructure 5 and the 3rd substructure 7 pass through work with bridge deck 4 Dynamic bearing is flexibly connected, and second substructure 6 is fixedly connected with bridge deck 4 by hold-down support (does not show activity in figure Bearing and hold-down support).
In such scheme, main span main arch 3 is located between the part above bridge deck and bridge deck to be connected by suspension rod 8, is hung The crossbeam of the bottom hung bridge deck 1 of bar 8, the main span main arch 3 is located between the part below bridge deck and bridge deck 1 by the One column 9 is connected, the crossbeam of the top braces bridge deck 1 of the first column 9.The main span main arch 3 of the both sides of bridge deck 1 connects with bridge deck 1 Connected between the position connect by the first intercostal crossbeam 11, pass through interval between the main span main arch 3 of the top both sides of bridge deck 1 Multiple first stulls 13 set are connected.
In such scheme, the top of end bay main arch 4 is connected by multiple second columns 10 with bridge deck 1, and the second column 10 is pushed up Portion supports the crossbeam of bridge deck 1.Pass through second between the position that the top of end bay main arch 4 of the both sides of bridge deck 1 and bridge deck 1 are connected Intercostal crossbeam 12 is connected, and passes through spaced multiple second stulls 14 between the end bay main arch 4 of the two bottom sides of bridge deck 1 Connection.First intercostal crossbeam 11 and the second intercostal crossbeam 12 are to support one of crossbeam of floorings bottom, because it is arranged on bridge floor The position that plate is connected with main arch, it plays connection bridge deck both sides main arch simultaneously, therefore forms intercostal crossbeam.Intercostal crossbeam with Bearing 18 is set between floorings.
In such scheme, the arch rib and the second stull 13 of main span main arch 3 and end bay main arch 4 and the second stull 14 are bilayer Structure, including section are square four of arrangement supervisors 15, are connected, are responsible for by cross bar 13 and vertical pole 17 between four supervisors 15 Fill concrete in 15.
This bridge-type structure is by main arch, suspension rod, bridge deck (crossbeam, longeron and floorings), bearing, bridge pier, spandrel column, arch Seat, cushion cap and pile foundation composition.Bridge deck directly bears bridge floor vehicle and Pedestrian Load, and main arch is passed to by suspension rod, or logical Cross bearing and pass to spandrel column, then pass to main arch;Bridge pier, cushion cap and base are directly passed to by bearing in pier location Plinth.Suspension rod and spandrel column load are passed to cushion cap and basis by main arch by skewback.The present invention encircles half-through and deck type Bridge arch is combined, and is combined using a kind of span of asymmetric coordination than organically, forms a kind of unique structure bridge attractive in appearance Type structure, to meet same site condition requirement not;Bridge deck is using the structural system of light-duty floatation type and the pile foundation of bottom And bridge pier is engaged, the horizontal thrust of bridge can be improved well, structure is novel, handsome in appearance, reasonable in design, construction party Just, the harmony of bridge and environment is improved, with good social and economic benefit.
The content not being described in detail in this specification belongs to prior art known to professional and technical personnel in the field.

Claims (10)

1. the asymmetric span of formula is held in one kind mixing thrust CFST Arch Bridge, including bridge deck (1), multiple support bridge decks Substructure (2) and concrete-filled steel tube arch, the concrete-filled steel tube arch is symmetricly set in the both sides of bridge deck, and its feature exists In:Concrete-filled steel tube arch includes the main span main arch (3) of half-through and the end bay main arch (4) of deck type, the main span main arch (3) two The arch springing at end is individually fixed in two neighboring substructure, and the arch springing at the end bay main arch two ends is individually fixed in two neighboring In substructure, close to main span main arch one end on the arch springing and end bay main arch of end bay main arch one end on the main span main arch Arch springing is fixed in same substructure, and the span ratio of the main span main arch (3) and end bay main arch (4) is 0.3-0.55.
2. the asymmetric span of formula is held in mixing according to claim 1 thrust CFST Arch Bridge, it is characterised in that:Institute Stating bridge deck (1) includes floorings (1.1), crossbeam (1.2) and longeron (1.3), and the floorings (1.1) are supported in crossbeam (1.2) top, crossbeam (1.2) both sides are respectively fixed with bracket (1.4), and longeron (1.3) two ends are supported on adjacent horizontal stroke Between beam on corresponding two brackets (1.4).
3. the asymmetric span of formula is held in mixing according to claim 1 thrust CFST Arch Bridge, it is characterised in that:Institute State pile foundation (2.1), cushion cap (2.2), skewback (2.3) and bridge pier that substructure (2) includes being sequentially arranged from the bottom to top (2.4), the bridge deck (1) is supported at the top of bridge pier (2.4), and the arch springing of the main span main arch (3) and end bay main arch (4) is fixed In on skewback (2.3).
4. the asymmetric span of formula is held in mixing according to claim 1 thrust CFST Arch Bridge, it is characterised in that:Institute Stating multiple substructures (2) is included along vertical bridge to the first substructure (5), the second substructure (6) and the 3rd being sequentially arranged Substructure (7), first substructure (5) and the 3rd substructure (7) are flexibly connected with bridge deck (1), and described second Substructure (6) is fixedly connected with bridge deck (1).
5. the asymmetric span of formula is held in mixing according to claim 1 thrust CFST Arch Bridge, it is characterised in that:Institute State and be connected by suspension rod (8) between part and bridge deck (1) of the main span main arch (3) above the bridge deck, suspension rod (8) bottom is outstanding The crossbeam of bridge deck (1) is hung, the main span main arch (3), which is located between the part below bridge deck and bridge deck (1), passes through first Column (9) is connected, the crossbeam of the first column (9) top braces bridge deck (1).
6. the asymmetric span of formula is held in mixing according to claim 1 thrust CFST Arch Bridge, it is characterised in that:Institute State between the position that the main span main arch (3) of bridge deck (1) both sides is connected with bridge deck (4) by the first intercostal crossbeam (11) even Connect, connected at the top of the bridge deck (1) between the main span main arch (3) of both sides by spaced multiple first stulls (13).
7. the asymmetric span of formula is held in mixing according to claim 1 thrust CFST Arch Bridge, it is characterised in that:Institute State and be connected at the top of end bay main arch (4) by multiple second columns (10) with bridge deck (1), the second column (10) top braces bridge floor It is the crossbeam of (1).
8. the asymmetric span of formula is held in mixing according to claim 1 thrust CFST Arch Bridge, it is characterised in that:Institute By the second intercostal crossbeam (12) between the position being connected at the top of the end bay main arch (4) for stating bridge deck (1) both sides with bridge deck (1) Between connection, the end bay main arch (4) of bridge deck (1) two bottom sides by spaced multiple second stulls (14) even Connect.
9. the asymmetric span of formula is held in mixing according to claim 1 thrust CFST Arch Bridge, it is characterised in that:Institute The arch rib for stating main span main arch (3) and end bay main arch (4) is double-decker, including section is square four supervisors (15) of arrangement, Connected between four supervisors 9 by cross bar (16) and vertical pole (17), fill concrete in supervisor.
10. the asymmetric span of formula is held in mixing according to claim 1 thrust CFST Arch Bridge, it is characterised in that: The span ratio of the main span main arch (3) and end bay main arch (4) is 0.43.
CN201710639255.6A 2017-07-31 2017-07-31 The asymmetric span of formula is held in one kind mixing thrust CFST Arch Bridge Pending CN107288025A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710639255.6A CN107288025A (en) 2017-07-31 2017-07-31 The asymmetric span of formula is held in one kind mixing thrust CFST Arch Bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710639255.6A CN107288025A (en) 2017-07-31 2017-07-31 The asymmetric span of formula is held in one kind mixing thrust CFST Arch Bridge

Publications (1)

Publication Number Publication Date
CN107288025A true CN107288025A (en) 2017-10-24

Family

ID=60103923

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710639255.6A Pending CN107288025A (en) 2017-07-31 2017-07-31 The asymmetric span of formula is held in one kind mixing thrust CFST Arch Bridge

Country Status (1)

Country Link
CN (1) CN107288025A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101977193B1 (en) * 2018-11-01 2019-05-10 지영호 Arch-Truss type Aqueduct
WO2022156157A1 (en) * 2021-01-21 2022-07-28 福州大学 Through arch bridge suspension bridge system reinforced by truss steel structure stiffened stringers and construction method therefor

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1904209A (en) * 2006-07-28 2007-01-31 中铁工程设计咨询集团有限公司 Three span continuous rigid structure steel arched bridge
CN200999322Y (en) * 2006-08-17 2008-01-02 铁道第四勘察设计院 V-shaped rigid frame arc combined bridge
CN103437296A (en) * 2013-08-28 2013-12-11 山东中宏路桥建设有限公司 Steel tube arch bridge towerless buckling three-section type double-rib folding hoisting construction method
CN204435195U (en) * 2014-12-31 2015-07-01 天津城建设计院有限公司 A kind of facade asymmetric space arch arch bridge structure
JP2016023523A (en) * 2014-07-24 2016-02-08 株式会社Ihiインフラシステム Construction method for arch bridge
CN205917585U (en) * 2016-07-29 2017-02-01 中铁第四勘察设计院集团有限公司 Steel pipe concrete has just constructed arched bridge
CN106758752A (en) * 2016-12-21 2017-05-31 北京建筑大学 Leaning tower oblique pull abnormity arch bridge and its construction method
CN207376437U (en) * 2017-07-31 2018-05-18 中铁第四勘察设计院集团有限公司 Formula asymmetry span is held in a kind of mixing thrust CFST Arch Bridge

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1904209A (en) * 2006-07-28 2007-01-31 中铁工程设计咨询集团有限公司 Three span continuous rigid structure steel arched bridge
CN200999322Y (en) * 2006-08-17 2008-01-02 铁道第四勘察设计院 V-shaped rigid frame arc combined bridge
CN103437296A (en) * 2013-08-28 2013-12-11 山东中宏路桥建设有限公司 Steel tube arch bridge towerless buckling three-section type double-rib folding hoisting construction method
JP2016023523A (en) * 2014-07-24 2016-02-08 株式会社Ihiインフラシステム Construction method for arch bridge
CN204435195U (en) * 2014-12-31 2015-07-01 天津城建设计院有限公司 A kind of facade asymmetric space arch arch bridge structure
CN205917585U (en) * 2016-07-29 2017-02-01 中铁第四勘察设计院集团有限公司 Steel pipe concrete has just constructed arched bridge
CN106758752A (en) * 2016-12-21 2017-05-31 北京建筑大学 Leaning tower oblique pull abnormity arch bridge and its construction method
CN207376437U (en) * 2017-07-31 2018-05-18 中铁第四勘察设计院集团有限公司 Formula asymmetry span is held in a kind of mixing thrust CFST Arch Bridge

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101977193B1 (en) * 2018-11-01 2019-05-10 지영호 Arch-Truss type Aqueduct
WO2022156157A1 (en) * 2021-01-21 2022-07-28 福州大学 Through arch bridge suspension bridge system reinforced by truss steel structure stiffened stringers and construction method therefor

Similar Documents

Publication Publication Date Title
CN102839678B (en) Structure for improving rigidity and stability of foundation pit steel support
CN204282199U (en) Pile-column concrete hollow pile bridge pier structure
CN101597918B (en) Prestressed giant brace-frame structure
CN100453737C (en) Steel-pipe concrete assembled pier
CN108412095B (en) Truss supporting structure of high-large-span curtain wall
CN201254694Y (en) Combination bridge deck
CN201933419U (en) Arch bridge arch rib cast-in-situ bracket
CN203247495U (en) Pedestrian rope bridge
CN203639807U (en) Y-shaped pier for concrete filled steel tube truss beam
CN205295953U (en) Long span steel case back of strideing across existing road pushes away system
CN201671050U (en) Through tie bar rigid frame arch bridge of inter-city express railway
CN107288025A (en) The asymmetric span of formula is held in one kind mixing thrust CFST Arch Bridge
CN206581147U (en) The support system constructed for bridge long-cantilever capping beam
CN202755370U (en) Structure for improving rigidity and stability of foundation pit steel support
CN207376437U (en) Formula asymmetry span is held in a kind of mixing thrust CFST Arch Bridge
CN202347828U (en) Bailey truss used during installation of steel structure
CN105544371B (en) Rail track traffic two-wire track girder is embraced in a kind of magnetic suspension
CN211815595U (en) Lower tower column tension and compression structure for cable tower
CN206034271U (en) Novel shelter bridge concrete foundation structure
CN207892037U (en) A kind of large-span steel-reinforced concrete is without column subway station
CN207314161U (en) A kind of temporary T structure of no bearing continuous rigid frame end bay beam section composition
CN211973058U (en) Arch bridge system
CN214424152U (en) Garage supporting component and garage
CN208604470U (en) A kind of half-through arch bridge
CN204530507U (en) Long span steel-concrete composite beam cable-stayed bridge limit steel case anchoring temporarily system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20171024