CN107269101A - The anemometer tower and its installation method of a kind of extension - Google Patents

The anemometer tower and its installation method of a kind of extension Download PDF

Info

Publication number
CN107269101A
CN107269101A CN201710478732.5A CN201710478732A CN107269101A CN 107269101 A CN107269101 A CN 107269101A CN 201710478732 A CN201710478732 A CN 201710478732A CN 107269101 A CN107269101 A CN 107269101A
Authority
CN
China
Prior art keywords
tower
pulley
hawser
middle level
fixture
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710478732.5A
Other languages
Chinese (zh)
Other versions
CN107269101B (en
Inventor
陆军
李光远
吴平平
张静波
马振军
陈�峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Jing Yin Ocean Engineering Co Ltd
Original Assignee
Guangdong Jing Yin Ocean Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Jing Yin Ocean Engineering Co Ltd filed Critical Guangdong Jing Yin Ocean Engineering Co Ltd
Priority to CN201710478732.5A priority Critical patent/CN107269101B/en
Publication of CN107269101A publication Critical patent/CN107269101A/en
Application granted granted Critical
Publication of CN107269101B publication Critical patent/CN107269101B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/18Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures movable or with movable sections, e.g. rotatable or telescopic
    • E04H12/182Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures movable or with movable sections, e.g. rotatable or telescopic telescopic
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/34Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Wind Motors (AREA)

Abstract

The present invention relates to meteorological observation equipment technical field, solve that anemometer tower installation effectiveness is low, and installer when anemometer tower is at sea installed on platform in face of dangerous installation environment the problem of.A kind of anemometer tower of extension, including at least three layers tower body, respectively bottom tower, middle level tower and top layer tower;The bottom tower and middle level tower be in three terrace with edges truss structure, the top layer tower be in triangular pyramid truss structure;The middle level tower is arranged in the bottom tower, and the top layer tower is arranged among the middle level tower;Also include pulley gear and fixing device;The pulley gear includes first pulley group, second pulley group and the 3rd assembly pulley and hawser group;The fixing device includes the first fixture and the second fixture.

Description

The anemometer tower and its installation method of a kind of extension
Technical field
The present invention relates to meteorological observation equipment technical field, and in particular to a kind of anemometer tower of extension and its installation side Method.
Background technology
At present, global every country all very pays close attention to the research and development of sustainable energy, and wind energy is used as renewable cleaning It is a kind of in the energy, there is huge development prospect.
Compared with land wind power plant, marine wind electric field has bigger advantage, and such as its development efficiency is high, environmental pollution Small, wind energy content is big and the area etc. that will not occupy cultivated land., typically all can cloth across the sea in order to study marine wind electric field Anemometer tower is put, can typically take following two modes to carry anemometer tower to infield, one kind is to install to transport again on land Defeated Attention problems position, but be due to that anemometer tower is elongate structure, up to 100 meters of height is lifted, installs and transported very Trouble, and the cost of transportation produced therewith is very high.Another is on the way to disassemble transport, then transports the marine peace specified Holding position and Assembling, can typically erect the pylon of bottom, then successively increase again during assembling, the installation of each layer of pylon It is required for layering to lift and then assemble, while each layer is required for being fixed with layback hawser, but uses which peace Installation effectiveness is very low during dress, with the rise of each layer of pylon, and the danger coefficient that installer faces also is continuously increased, and often One layer is required for being fixed with two hawsers, virtually increases space multistory installation site, certain wind is also brought along therewith Resistance, is that anemometer tower brings potential safety hazard.
The content of the invention
It is an object of the invention to for weak point of the prior art, there is provided a kind of installation effectiveness height, convenient installation Workman carries out the anemometer tower of the extension of installation exercise.
For up to this purpose, the present invention uses following technical scheme:A kind of anemometer tower of extension, including at least three layers tower Body, respectively bottom tower, middle level tower and top layer tower;
The bottom tower and middle level tower be in three terrace with edges truss structure, the top layer tower be in triangular pyramid truss knot Structure;The middle level tower is arranged in the bottom tower, and the top layer tower is arranged among the middle level tower;
Also include pulley gear and fixing device;
The pulley gear includes first pulley group, second pulley group and the 3rd assembly pulley and hawser group;Described first slides Wheel group is arranged on bottom tower at nearly top surface, and the second pulley group is arranged at the middle level Ta Shangjin bottom surfaces, and the described 3rd Assembly pulley is arranged on the middle level tower at nearly top surface;The hawser group successively bypasses the first pulley group, second cunning It is fixedly connected on after wheel group and the 3rd assembly pulley on the top layer tower;
The fixing device includes the first fixture and the second fixture;First fixture and the second fixture are The steel construction of hollow three terrace with edge, the endoporus of hollow three terrace with edge is also in three prismatic table shapes;First fixture is arranged at described In bottom tower, and the maximum end of its area of section is connected to the top surface of the bottom tower;Second fixture is arranged at described In the tower of middle level, and the maximum end of its area of section is connected to the top surface of the middle level tower.
It is preferred that, the first pulley group includes the first from left pulley and a right pulley;The first from left pulley and described right one is slided Wheel at nearly top surface and is oppositely arranged on the bottom tower;
The second pulley group includes the second from left pulley and right two pulley;The second from left pulley and right two pulley are located at institute State at the Ta Shangjin bottom surfaces of middle level and be oppositely arranged;
3rd pulley includes left three pulley and right three pulley;Left three pulley and right three pulley are located at described At nearly top surface and it is oppositely arranged on the tower of middle level;
The hawser group includes the first hawser and the second hawser;First hawser successively bypasses the first from left pulley, institute It is fixedly connected on after stating the second from left pulley and left three pulley on the top layer tower;Second hawser successively bypasses described right one It is fixedly connected on after pulley, right two pulley and right three pulley on the top layer tower.
It is preferred that, the hawser below hawser and a right pulley below the first from left pulley is arranged at the bottom tower Outside;
Hawser between the second from left pulley and left three pulley is arranged in the middle level tower, right two pulley and Hawser between right three pulley is arranged in the middle level tower;
It is preferred that, the altitude range of the bottom tower is 30-40m, and the altitude range of the middle level tower is 20-35m, described Top layer tower height degree scope is 10-25m;
The size dimension of the bottom surface of the bottom tower is 8.5m.
Using the installation method of the anemometer tower of extension described above, comprise the following steps:
Step 1:The bottom tower is welded on anemometer tower mounting platform;
Step 2:First hawser and second hawser have been cut with scissors respectively with two winches, until the top layer Taka enters Among first fixture, the middle level Taka enters among second fixture;
Step 3:First hawser and second hawser are fixed on the anemometer tower mounting platform.
Beneficial effects of the present invention:1st, in anemometer tower installation process, it is described that whole process does not all need installer to climb to On bottom tower, the middle level tower and the top layer tower, installer only needs to tense hawser on ground level, what it was in The relatively steady safety of environment is a lot, so that the safety of effective guarantee installer;
2nd, the middle level tower snaps onto first fixture when mounted, and the top layer tower is caught in when mounted To among second fixture, being connected between each layer tower is facilitated, is conducive to improving installation effectiveness;
3rd, the bottom tower and the middle level tower are in the truss of three shuttle table types, and the top layer tower is in the truss of Rhizoma Sparganii bevel-type, Its structure is evenly distributed than girder construction reasonable stress, and truss structure internal force, and the strength of materials can sufficiently be embodied, institute The wind and waves environment on sea is can adapt to it, it is not easy to collapsed by blowing.
Brief description of the drawings
The present invention is further described with reference to the accompanying drawings and examples.
Fig. 1 is the schematic diagram when anemometer tower of extension is not installed;
Fig. 2 is the schematic diagram after the anemometer tower installation of extension.
Wherein:Bottom tower 1, middle level tower 2, top layer tower 3, pulley gear 4, fixing device 5, first pulley group 41, second slides Wheel group 42, the 3rd assembly pulley 43, hawser group 44, the first fixture 51, the second fixture 52, the first from left pulley 411, a right pulley 412, the second from left pulley 421, right two pulley 422, left three pulley 431, right three pulley 432, the first hawser 441, the second hawser 442.
Embodiment
Further illustrate technical scheme below in conjunction with the accompanying drawings and by embodiment.
A kind of anemometer tower of extension, including at least three layers tower body, respectively bottom tower 1, middle level tower 2 and top layer tower 3;
The bottom tower 1 and middle level tower 2 be in three terrace with edges truss structure, the top layer tower 3 be in triangular pyramid purlin Frame structure;The middle level tower 2 is arranged in the bottom tower 1, and the top layer tower 3 is arranged among the middle level tower 2;
Also include pulley gear 4 and fixing device 5;
The pulley gear 4 includes first pulley group 41, the assembly pulley 43 of second pulley group 42 and the 3rd and hawser group 44;Institute State first pulley group 41 to be arranged on bottom tower 1 at nearly top surface, the second pulley group 42 is arranged on the middle level tower 2 nearly bottom At face, the 3rd assembly pulley 43 is arranged on the middle level tower 2 at nearly top surface;The priority of hawser group 44 bypasses described first It is fixedly connected on after assembly pulley 41, the second pulley group 42 and the 3rd assembly pulley 43 on the top layer tower 3;
The fixing device 5 includes the first fixture 51 and the second fixture 52;First fixture 51 and second is consolidated Determine the steel construction that part 52 is hollow three terrace with edge, the endoporus of hollow three terrace with edge is also in three prismatic table shapes;First fixture 51 are arranged in the bottom tower 1, and the maximum end of its area of section is connected to the top surface of the bottom tower 1;Described second consolidates Determine part 52 to be arranged in the middle level tower 2, and the maximum end of its area of section is connected to the top surface of the middle level tower 2.
Anemometer tower is arranged on offshore platform, is typically on the sea away from continent, often had due to offshore platform Boisterous situation, when installer climbs to progress installation exercise on anemometer tower, the wind-force faced is just more big, and order, which is installed, to be made Industry difficulty is increased, while its environment stayed is also more dangerous, fairly good risk just easily triggers security incident.To the extension When the anemometer tower of formula is lifted, the hawser group 44 is first progressively tightened up, the top layer tower 3 is caught in first fixture 51 and worked as In, continue to tighten up the hawser group 44, the middle level tower 2 is finally caught among second fixture 52, finally only need locking The hawser is that the installation to anemometer tower can be achieved.Because in installation process, it is described that whole process does not all need installer to climb to On bottom tower 1, the middle level tower 2 and the top layer tower 3, installer only needs to operate on ground level, what it was in The relatively steady safety of environment is a lot, so that the safety of effective guarantee installer.Moreover, the middle level tower 2 is card when mounted Enter to first fixture 51, the top layer tower 3 is snapped onto among second fixture 52 when mounted, they It need not be fixed to hawser auxiliary on ground, and exactly aid in fixed method to be that operation is quite cumbersome using hawser , and use the method operating process of clamping then easily a lot, facilitate being connected between each layer tower, be conducive to improving and pacify Fill efficiency.In addition, wind-force is very big on sea, the anemometer tower being made of common telescopic tube is subjected to examining for incessantly wind-force Test, occur being blown the phenomenon that folding is blown down, and the bottom tower 1 and the middle level tower 2 in the design are in the truss of three shuttle table types, The top layer tower 3 is in the truss of Rhizoma Sparganii bevel-type, and its structure is evenly distributed than girder construction reasonable stress, and truss structure internal force, The strength of materials can sufficiently be embodied, so it can adapt to the wind and waves environment on sea, it is not easy to collapsed by blowing.
Further, the first pulley group 41 includes the first from left pulley 411 and a right pulley 412;The first from left pulley 411 and a right pulley 412 at nearly top surface and be oppositely arranged on the bottom tower 1;
The second pulley group 42 includes the second from left pulley 421 and right two pulley 422;The second from left pulley 421 and the right side Two pulleys 422 at nearly bottom surface and are oppositely arranged on the middle level tower 2;
3rd pulley includes left three pulley 431 and right three pulley 432;Left three pulley 431 and described right three is slided Wheel 432 at nearly top surface and is oppositely arranged on the middle level tower 2;
The hawser group 44 includes the first hawser 441 and the second hawser 442;The priority of first hawser 441 bypasses described It is fixedly connected on after the first from left pulley 411, the second from left pulley 421 and left three pulley 431 on the top layer tower 3;Described The priority of two hawser 442 is fixedly connected on after bypassing a right pulley 412, right two pulley 422 and right three pulley 432 On the top layer tower 3.
Above-mentioned setting ensures the top layer tower 3 and the middle level tower 2 stable action, mean forced when mounted.Meanwhile, The anemometer tower is provided only with two hawsers, and every layer traditional of anemometer tower has the hawser of two, if being provided with three layers of survey wind Tower, the method being just fixed with six hawsers is compared, and it advantageously reduces windage, is also beneficial to reduce space mounting body Product.
Further, the hawser of the lower section of the first from left pulley 411 and the hawser of the lower section of a right pulley 412 are arranged at The outside of the bottom tower 1;
Hawser between the second from left pulley 421 and left three pulley 431 is arranged in the middle level tower 2, the right side Hawser between two pulleys 422 and right three pulley 432 is arranged in the middle level tower 2;
Because the bottom tower 1 is the foundation of bed rearrangement anemometer tower, whether whether it stable and firm determines bed rearrangement anemometer tower It is stable and firm, and the hawser of the lower section of the first from left pulley 411 and the hawser of the lower section of a right pulley 412 are arranged at the bottom During the outside of tower 1, because it forms triangle with the anemometer tower and ground, and triangle exactly has very high stability, So anemometer tower is less likely to occur to distort and deformed, so being conducive to ensureing firm.The wind-force that the top layer tower 3 is subject to is maximum, And the hawser of the second from left pulley 421 and left three pulley 431 is arranged in the middle level tower 2, the right He of two pulley 422 When the hawser of right three pulley 432 is arranged in the middle level tower 2, be conducive to preventing them from being swung by windage, So as to avoid impacting the stability of the top layer tower 3.
Further, the altitude range of the bottom tower 1 is 30-40m, and the altitude range of the middle level tower 2 is 20- 35m, the altitude range of top layer tower 3 is 10-25m;
The size dimension of the bottom surface of the bottom tower 1 is 8.5m.
The anemometer tower of the extension is because when it is not installed, maximum structure is bottom tower 1, compared with bed rearrangement anemometer tower Volume has been lacked much, is conducive to lifting and transports.Anemometer tower tower body in transportation within 40m, largely drops The cost and difficulty of low transport.The length of side of the bottom surface of the bottom tower 1 is very long, can make the floor space of the bottom tower 1 It is very big so that the bottom tower 1 can be fixedly secured on mounting platform, the peace of the anemometer tower can be further effectively ensured Entirely.
Using the installation method of the anemometer tower of extension described above, comprise the following steps:
Step 1:The bottom tower 1 is welded on anemometer tower mounting platform;
Step 2:First hawser 441 and second hawser 442 have been cut with scissors respectively with two winches, until the top layer Tower 3 is caught among first fixture 51, and the middle level tower 2 is caught among second fixture 52;
Step 3:First hawser 441 and second hawser 442 are fixed on the anemometer tower mounting platform.
The middle level tower 2 and the bottom tower 1 are when successively increasing, and each layer need not all be consolidated with layback hawser It is fixed, it is only necessary to which that installer operates winch, simple to operate, has saved in each layer of set-up time, has improved peace Fill efficiency.
Above content is only presently preferred embodiments of the present invention, for one of ordinary skill in the art, according to the present invention's Thought, will change in specific embodiments and applications, and this specification content should not be construed as to the present invention Limitation.

Claims (5)

1. a kind of anemometer tower of extension, including at least three layers tower body, respectively bottom tower, middle level tower and top layer tower;
The bottom tower and middle level tower be in three terrace with edges truss structure, the top layer tower be in triangular pyramid truss structure; The middle level tower is arranged in the bottom tower, and the top layer tower is arranged among the middle level tower;
It is characterized in that:Also include pulley gear and fixing device;
The pulley gear includes first pulley group, second pulley group and the 3rd assembly pulley and hawser group;The first pulley group It is arranged on bottom tower at nearly top surface, the second pulley group is arranged at the middle level Ta Shangjin bottom surfaces, the 3rd pulley Group is arranged on the middle level tower at nearly top surface;The hawser group successively bypasses the first pulley group, the second pulley group It is fixedly connected on after the 3rd assembly pulley on the top layer tower;
The fixing device includes the first fixture and the second fixture;First fixture and the second fixture are hollow The steel construction of three terrace with edges, the endoporus of hollow three terrace with edge is also in three prismatic table shapes;First fixture is arranged at the bottom In tower, and the maximum end of its area of section is connected to the top surface of the bottom tower;Second fixture is arranged at the middle level In tower, and the maximum end of its area of section is connected to the top surface of the middle level tower.
2. the anemometer tower of extension according to claim 1, it is characterised in that:The first pulley group includes the first from left pulley With a right pulley;The first from left pulley and a right pulley at nearly top surface and are oppositely arranged on the bottom tower;
The second pulley group includes the second from left pulley and right two pulley;The second from left pulley and right two pulley are in described At nearly bottom surface and it is oppositely arranged on layer tower;
3rd pulley includes left three pulley and right three pulley;Left three pulley and right three pulley are located at the middle level At nearly top surface and it is oppositely arranged on tower;
The hawser group includes the first hawser and the second hawser;First hawser successively bypasses the first from left pulley, the left side It is fixedly connected on after two pulleys and left three pulley on the top layer tower;Second hawser successively bypasses a right cunning It is fixedly connected on after wheel, right two pulley and right three pulley on the top layer tower.
3. the anemometer tower of extension according to claim 2, it is characterised in that:Hawser and institute below the first from left pulley State the outside that the hawser below a right pulley is arranged at the bottom tower;
Hawser between the second from left pulley and left three pulley is arranged in the middle level tower, right two pulley and described Hawser between right three pulleys is arranged in the middle level tower.
4. the anemometer tower of extension according to claim 3, it is characterised in that:The altitude range of the bottom tower is 30- 40m, the altitude range of the middle level tower is 20-35m, and the top layer tower height degree scope is 10-25m;
The size dimension of the bottom surface of the bottom tower is 8.5m.
5. the installation method of the anemometer tower using the extension described in any one of the claims 4, it is characterised in that including Following steps:
Step 1:The bottom tower is welded on anemometer tower mounting platform;
Step 2:Cut with scissors first hawser and second hawser respectively with two winches, until the top layer Taka enter it is described Among first fixture, the middle level Taka enters among second fixture;
Step 3:First hawser and second hawser are fixed on the anemometer tower mounting platform.
CN201710478732.5A 2017-06-22 2017-06-22 A kind of anemometer tower and its installation method of extension Active CN107269101B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710478732.5A CN107269101B (en) 2017-06-22 2017-06-22 A kind of anemometer tower and its installation method of extension

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710478732.5A CN107269101B (en) 2017-06-22 2017-06-22 A kind of anemometer tower and its installation method of extension

Publications (2)

Publication Number Publication Date
CN107269101A true CN107269101A (en) 2017-10-20
CN107269101B CN107269101B (en) 2019-08-13

Family

ID=60068184

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710478732.5A Active CN107269101B (en) 2017-06-22 2017-06-22 A kind of anemometer tower and its installation method of extension

Country Status (1)

Country Link
CN (1) CN107269101B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3217907A1 (en) * 1982-05-12 1983-11-24 Geroh GmbH Mechanische Systeme, 8551 Waischenfeld Telescopic mast having a device for the self-balancing bracing of the mast during its erection and extension
CN201486198U (en) * 2009-08-10 2010-05-26 深圳市海生机房技术有限公司 Lifting tower and mobile base station
CN102817341A (en) * 2012-08-23 2012-12-12 中国十七冶集团有限公司 Construction method for segmented installation of offshore anemometer tower and combination of high-altitude manufactured parts for assembly
US20140311057A1 (en) * 2013-03-05 2014-10-23 News Sports Microwave Rental Inc, dba NSM Surveillance Maximum Strength, Reduce Weight Telescoping Mast with Interlocking Structural Elements
WO2016120699A1 (en) * 2015-01-30 2016-08-04 Apollo Energy Services Corp. Transportable lighting system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3217907A1 (en) * 1982-05-12 1983-11-24 Geroh GmbH Mechanische Systeme, 8551 Waischenfeld Telescopic mast having a device for the self-balancing bracing of the mast during its erection and extension
CN201486198U (en) * 2009-08-10 2010-05-26 深圳市海生机房技术有限公司 Lifting tower and mobile base station
CN102817341A (en) * 2012-08-23 2012-12-12 中国十七冶集团有限公司 Construction method for segmented installation of offshore anemometer tower and combination of high-altitude manufactured parts for assembly
US20140311057A1 (en) * 2013-03-05 2014-10-23 News Sports Microwave Rental Inc, dba NSM Surveillance Maximum Strength, Reduce Weight Telescoping Mast with Interlocking Structural Elements
WO2016120699A1 (en) * 2015-01-30 2016-08-04 Apollo Energy Services Corp. Transportable lighting system

Also Published As

Publication number Publication date
CN107269101B (en) 2019-08-13

Similar Documents

Publication Publication Date Title
US20100219643A1 (en) Vertical-axis wind-powered electric power generator with photovoltaic cogeneration
EP3137763A2 (en) Device for controlling and steering traction kites or rotating flyer wheels for electricity generation
CN102797643B (en) A kind of wind power generation tower device
CN205669338U (en) A kind of split blade type bending head tower structure
KR20090103374A (en) Apparatus for preventing wind damage of a sunlight power generator
US11668278B2 (en) Mastless wind turbine for power generation
US10615738B2 (en) Photovoltaic solar array support structure
US20240060467A1 (en) Mastless wind turbine with stationary sails for improved power generation
CN107269101A (en) The anemometer tower and its installation method of a kind of extension
DE102012021697B4 (en) Support system for the stabilization of at least one mast
CN204282845U (en) Buildings in cold roof insulating structure
CN203769406U (en) Height-adjustable tower support for wireless private network equipment
CN103502547A (en) A wind turbine tower made of wood and a method of erection thereof
CN202450837U (en) Airport surface monitoring radar tower
CN104426413B (en) Wind power generation plant based on high frequency friction generator
CN205558428U (en) Marine anemometer tower
CN107939613B (en) Stacked tower system for wind gathering power generation
CN203285134U (en) Wire-bracing-type triangular truss wind measuring tower
CN221091721U (en) Building materials stacking device for construction
CN220014265U (en) Sunshade canopy
CN207553718U (en) A kind of wind resistance electric power tower
CN209261734U (en) A kind of interior pull-type tower and the Wind turbines including the tower
CN103375354B (en) Wind tower power generation bottom steel frame for wind
CN202391666U (en) Tower of truss structure
CN202645879U (en) Steel frame on wind power generation bottom of wind tower

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant