CN107255981A - 一种基于bim的超高层建筑物材料运输管理系统 - Google Patents

一种基于bim的超高层建筑物材料运输管理系统 Download PDF

Info

Publication number
CN107255981A
CN107255981A CN201710447317.3A CN201710447317A CN107255981A CN 107255981 A CN107255981 A CN 107255981A CN 201710447317 A CN201710447317 A CN 201710447317A CN 107255981 A CN107255981 A CN 107255981A
Authority
CN
China
Prior art keywords
bim
rise building
transport
conveying arrangement
conveying mechanism
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710447317.3A
Other languages
English (en)
Inventor
周江峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu Zhi Jian New Architectural Design Consulting Co Ltd
Original Assignee
Chengdu Zhi Jian New Architectural Design Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Zhi Jian New Architectural Design Consulting Co Ltd filed Critical Chengdu Zhi Jian New Architectural Design Consulting Co Ltd
Priority to CN201710447317.3A priority Critical patent/CN107255981A/zh
Publication of CN107255981A publication Critical patent/CN107255981A/zh
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/04Programme control other than numerical control, i.e. in sequence controllers or logic controllers
    • G05B19/048Monitoring; Safety

Abstract

本发明公开了一种基于BIM的超高层建筑物材料运输管理系统,包括监控系统和运输系统;监控系统包括监控室,监控室内设置有控制器,控制器连接有显示屏,控制器还连接有摄像头和报警装置;运输系统包括运输装置和输送机构,所述运输装置和输送机构的设计包括以下步骤:1)、获得超高层建筑的高度,判断在该高度下有可能出现的危险和故障信息;2)、利用BIM技术建立不同的BIM模型,将BIM模型模拟应用于超高层建筑的材料运输,获得所有BIM模型的模拟结果;3)、根据模拟结果进行选择,选择最佳模拟结果BIM模型中设计的运输装置和输送机构进行制造与安装。本发明解决了现有施工方法中因运输装置设计不合理导致发生故障甚至产生危险的问题。

Description

一种基于BIM的超高层建筑物材料运输管理系统
技术领域
本发明涉及建筑施工技术领域,具体涉及一种基于BIM的超高层建筑物材料运输管理系统。
背景技术
在现代化城市建设中,建筑物的高度越来越高,因此,在建筑施工中,常常会涉及到超高层建筑,通常是指建筑高度超过100米的建筑施工。在建筑施工中会涉及到将物料运输至高层,由于高度较高,向超高层运输物料时不仅具有一定的危险性,而且容易发生故障,为了避免上述问题,在运输材料的过程中,要设计合理的运输装置。
现有技术中,通常是根据施工经验进行运输装置的设计,易因设计不合理导致发生故障甚至产生危险。
发明内容
本发明的目的在于提供一种基于BIM的超高层建筑物材料运输管理系统,以解决现有施工方法中因运输装置设计不合理导致发生故障甚至产生危险的问题。
本发明通过下述技术方案实现:
一种基于BIM的超高层建筑物材料运输管理系统,包括监控系统和运输系统;
所述监控系统包括监控室,所述监控室内设置有控制器,所述控制器连接有显示屏,所述控制器还连接有摄像头和报警装置,所述摄像头和报警装置均设置在施工现场;
所述运输系统包括运输装置和输送机构,所述运输装置和输送机构的设计包括以下步骤:
1)、获得超高层建筑的高度,判断在该高度下有可能出现的危险和故障信息;
2)、结合步骤1)获得的信息,利用BIM技术建立运输装置和输送机构的不同BIM模型,将BIM模型模拟应用于超高层建筑的材料运输,获得所有BIM模型的模拟结果;
3)、根据模拟结果进行选择,选择最佳模拟结果BIM模型中设计的运输装置和输送机构进行制造与安装。
现有技术中,通常是根据施工经验进行运输装置的设计,易因设计不合理导致发生故障甚至产生危险。
本发明通过利用BIM技术建立运输装置和输送机构的不同的BIM模型,将BIM模型模拟应用于超高层建筑的材料运输,获得所有BIM模型的模拟结果,然后选择最优结果进行运输装置和输送机构的制造与安装,避免故障的发生,同时降低危险性。
进一步地,将所述模拟结果录入数据库,通过数据库进行分析选择。
进一步地,报警装置按照危险源的不同设置不同类型的报警器。
本发明与现有技术相比,具有如下的优点和有益效果:
本发明通过利用BIM技术建立运输装置和输送机构的不同的BIM模型,将BIM模型模拟应用于超高层建筑的材料运输,获得所有BIM模型的模拟结果,然后选择最优结果进行运输装置和输送机构的制造与安装,避免故障的发生,同时降低危险性。
附图说明
此处所说明的附图用来提供对本发明实施例的进一步理解,构成本申请的一部分,并不构成对本发明实施例的限定。在附图中:
图1是本发明的原理框图。
具体实施方式
为使本发明的目的、技术方案和优点更加清楚明白,下面结合实施例和附图,对本发明作进一步的详细说明,本发明的示意性实施方式及其说明仅用于解释本发明,并不作为对本发明的限定。
实施例:
如图1所示,一种基于BIM的超高层建筑物材料运输管理系统,包括监控系统和运输系统;
所述监控系统包括监控室,所述监控室内设置有控制器,所述控制器连接有显示屏,所述控制器还连接有摄像头和报警装置,所述报警装置按照危险源的不同设置不同类型的报警器,所述摄像头和报警装置均设置在施工现场;
所述运输系统包括运输装置和输送机构,所述运输装置和输送机构的设计包括以下步骤:
1)、获得超高层建筑的高度,判断在该高度下有可能出现的危险和故障信息;
2)、结合步骤1)获得的信息,利用BIM技术建立运输装置和输送机构的不同BIM模型,将BIM模型模拟应用于超高层建筑的材料运输,获得所有BIM模型的模拟结果;
3)、将所述模拟结果录入数据库,通过数据库进行分析选择,选择最佳模拟结果BIM模型中设计的运输装置和输送机构进行制造与安装。
以上所述的具体实施方式,对本发明的目的、技术方案和有益效果进行了进一步详细说明,所应理解的是,以上所述仅为本发明的具体实施方式而已,并不用于限定本发明的保护范围,凡在本发明的精神和原则之内,所做的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。

Claims (3)

1.一种基于BIM的超高层建筑物材料运输管理系统,其特征在于,包括监控系统和运输系统;
所述监控系统包括监控室,所述监控室内设置有控制器,所述控制器连接有显示屏,所述控制器还连接有摄像头和报警装置,所述摄像头和报警装置均设置在施工现场;
所述运输系统包括运输装置和输送机构,所述运输装置和输送机构的设计包括以下步骤:
1)、获得超高层建筑的高度,判断在该高度下有可能出现的危险和故障信息;
2)、结合步骤1)获得的信息,利用BIM技术建立运输装置和输送机构的不同BIM模型,将BIM模型模拟应用于超高层建筑的材料运输,获得所有BIM模型的模拟结果;
3)、根据模拟结果进行选择,选择最佳模拟结果BIM模型中设计的运输装置和输送机构进行制造与安装。
2.根据权利要求1所述的一种基于BIM的超高层建筑物材料运输管理系统,其特征在于,将所述模拟结果录入数据库,通过数据库进行分析选择。
3.根据权利要求1所述的一种基于BIM的超高层建筑物材料运输管理系统,其特征在于,所述报警装置按照危险源的不同设置不同类型的报警器。
CN201710447317.3A 2017-06-14 2017-06-14 一种基于bim的超高层建筑物材料运输管理系统 Pending CN107255981A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710447317.3A CN107255981A (zh) 2017-06-14 2017-06-14 一种基于bim的超高层建筑物材料运输管理系统

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710447317.3A CN107255981A (zh) 2017-06-14 2017-06-14 一种基于bim的超高层建筑物材料运输管理系统

Publications (1)

Publication Number Publication Date
CN107255981A true CN107255981A (zh) 2017-10-17

Family

ID=60023171

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710447317.3A Pending CN107255981A (zh) 2017-06-14 2017-06-14 一种基于bim的超高层建筑物材料运输管理系统

Country Status (1)

Country Link
CN (1) CN107255981A (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108732979A (zh) * 2018-05-15 2018-11-02 浙江大学 一种基于bim技术的施工安全管控系统
CN109388879A (zh) * 2018-09-30 2019-02-26 河北建设集团股份有限公司 基于bim技术的构件装运方法
CN109948853A (zh) * 2019-03-21 2019-06-28 湖北工业大学 一种基于bim技术自动出渣装置运输物料的方法

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101916970A (zh) * 2010-07-29 2010-12-15 广州电力设计院 变电站的室内通风系统及变电站的室内通风系统设计方法
US20110218777A1 (en) * 2010-03-03 2011-09-08 Honeywell International Inc. System and method for generating a building information model
CN202522896U (zh) * 2012-05-14 2012-11-07 东北石油大学 工程现场施工状态的管理监测系统
CN103500371A (zh) * 2013-08-08 2014-01-08 机械工业第六设计研究院有限公司 基于bim的变更控制方法
CN104899378A (zh) * 2015-06-10 2015-09-09 上海大学 基于bim和三维测量的高层钢结构数字化安装方法
CN105426601A (zh) * 2015-11-11 2016-03-23 深圳市华阳国际工程设计股份有限公司 一种基于bim的多样性设计方案汇报方法及其系统
CN106013798A (zh) * 2016-06-12 2016-10-12 江苏宜安建设有限公司 一种基于bim的标准层施工方法
CN106326536A (zh) * 2016-08-17 2017-01-11 上海交通建设总承包有限公司 基于bim的水工预制构件标准化施工方法
CN106642508A (zh) * 2015-10-29 2017-05-10 西安丁子电子信息科技有限公司 一种基于bim模型的水源热泵热水空调系统
CN106815415A (zh) * 2016-12-30 2017-06-09 中建三局第建设工程有限责任公司 基于bim的工程桩施工方法

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20110218777A1 (en) * 2010-03-03 2011-09-08 Honeywell International Inc. System and method for generating a building information model
CN101916970A (zh) * 2010-07-29 2010-12-15 广州电力设计院 变电站的室内通风系统及变电站的室内通风系统设计方法
CN202522896U (zh) * 2012-05-14 2012-11-07 东北石油大学 工程现场施工状态的管理监测系统
CN103500371A (zh) * 2013-08-08 2014-01-08 机械工业第六设计研究院有限公司 基于bim的变更控制方法
CN104899378A (zh) * 2015-06-10 2015-09-09 上海大学 基于bim和三维测量的高层钢结构数字化安装方法
CN106642508A (zh) * 2015-10-29 2017-05-10 西安丁子电子信息科技有限公司 一种基于bim模型的水源热泵热水空调系统
CN105426601A (zh) * 2015-11-11 2016-03-23 深圳市华阳国际工程设计股份有限公司 一种基于bim的多样性设计方案汇报方法及其系统
CN106013798A (zh) * 2016-06-12 2016-10-12 江苏宜安建设有限公司 一种基于bim的标准层施工方法
CN106326536A (zh) * 2016-08-17 2017-01-11 上海交通建设总承包有限公司 基于bim的水工预制构件标准化施工方法
CN106815415A (zh) * 2016-12-30 2017-06-09 中建三局第建设工程有限责任公司 基于bim的工程桩施工方法

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108732979A (zh) * 2018-05-15 2018-11-02 浙江大学 一种基于bim技术的施工安全管控系统
CN109388879A (zh) * 2018-09-30 2019-02-26 河北建设集团股份有限公司 基于bim技术的构件装运方法
CN109388879B (zh) * 2018-09-30 2023-02-28 河北建设集团股份有限公司 基于bim技术的构件装运方法
CN109948853A (zh) * 2019-03-21 2019-06-28 湖北工业大学 一种基于bim技术自动出渣装置运输物料的方法

Similar Documents

Publication Publication Date Title
CN107255981A (zh) 一种基于bim的超高层建筑物材料运输管理系统
Swuste A ‘normal accident’with a tower crane? An accident analysis conducted by the Dutch Safety Board
CN106095519B (zh) 一种使用Ambari在大数据组件管理中扩展自定义服务的方法
CN105555638B (zh) 双重安全关键的分布式系统中的非关键部件的软件更新
CN104268658A (zh) 一种桥梁结构安全监测数据的预测方法
US20120284077A1 (en) Automated work order generation for maintenance
CN104836699A (zh) 设备状态处理方法与设备状态处理系统
WO2017051576A1 (ja) プラント運転システム及びプラント運転方法
CN106651074A (zh) 一种地下管线智能管理系统
CN106056400A (zh) 预测新增用户数的方法、装置及系统
CN106056302A (zh) 基于石化企业工业现场危险源及风险信息的建模方法
CN103901845A (zh) 一种油田生产现场物联设备远程智能管理方法及系统
CN105260491A (zh) 管道综合布管建模方法
CN105119237A (zh) 继电保护操作校核的方法
CN103440168B (zh) 一种程序变更方法及系统
CN103257638A (zh) 面向复杂制造过程的可重入工艺路径建模方法
CN107292012A (zh) 一种基于bim向高层建筑运输物料的方法
CN108120475A (zh) 一种管廊的数据监测方法和装置
US10637239B2 (en) Utility network monitoring device
CN204883348U (zh) 干法水泥生产线安全监控系统
CN110704921A (zh) 一种基于bim的变电站暖通与给排水设计方法
EP4002079A1 (en) Information processing method, information processing system and program
JP7342526B2 (ja) 修理工事優先順位決定方法
CN104821898B (zh) 一种降低司法社区矫正管理系统越界误报率的方法
Yuan et al. Real-time Cyber-Physical Systems (CPS)-based monitoring of temporary structures: A scaffolding system example

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20171017