CN107237345B - Method and system for rapidly controlling settlement of building - Google Patents

Method and system for rapidly controlling settlement of building Download PDF

Info

Publication number
CN107237345B
CN107237345B CN201710453019.5A CN201710453019A CN107237345B CN 107237345 B CN107237345 B CN 107237345B CN 201710453019 A CN201710453019 A CN 201710453019A CN 107237345 B CN107237345 B CN 107237345B
Authority
CN
China
Prior art keywords
column
pile
original
steel
steel pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710453019.5A
Other languages
Chinese (zh)
Other versions
CN107237345A (en
Inventor
吴如军
唐颖
赵正兴
唐军
陈曦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Shengte Construction Technology Development Co ltd
Original Assignee
Guangzhou Shengte Construction Technology Development Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Shengte Construction Technology Development Co ltd filed Critical Guangzhou Shengte Construction Technology Development Co ltd
Priority to CN201710453019.5A priority Critical patent/CN107237345B/en
Publication of CN107237345A publication Critical patent/CN107237345A/en
Application granted granted Critical
Publication of CN107237345B publication Critical patent/CN107237345B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/48Foundations inserted underneath existing buildings or constructions
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • E02D27/14Pile framings, i.e. piles assembled to form the substructure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Foundations (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The method for rapidly controlling the settlement of the building comprises the following steps: step one, erecting a column-holding steel tray system on a column base of an original column at a larger sedimentation side, wherein the column-holding steel tray system consists of profile steel members which surround and are connected with the original column; a pile pressing hole is formed under the column holding type steel tray system, steel pipe piles are arranged in the pile pressing hole, the steel pipe piles are located on the periphery of an original foundation bearing platform, and pile pressing equipment is arranged between the top of each steel pipe pile and the column holding type steel tray system; pouring a new bearing platform on the periphery of the original basic bearing platform, wherein the steel pipe piles are embedded into the new bearing platform; and step four, dismantling the column-holding type steel tray system. The invention also provides a system for rapidly controlling the settlement of the building.

Description

Method and system for rapidly controlling settlement of building
Technical Field
The invention belongs to the technical field of controlling building settlement, and particularly relates to a method and a system for rapidly controlling building settlement.
Background
With the rapid development of the building industry in recent years, the situation that the building is inclined is quite common, and the engineering examples of correcting the inclination of the building at home and abroad are countless. Building inclination correction technology is more and more commonly applied at home and abroad, and the reasons for building inclination are various, such as geology, design, construction and use.
There are basically two ways to control building settlement: firstly, stabilizing the side with large sedimentation, and then trying to promote sedimentation of the side with small sedimentation, so that the sedimentation of a building is uniform; secondly, stabilizing the side with small sedimentation, then lifting the side with large sedimentation, and correcting the inclination of the building.
The defects of the prior art are: the construction process requires longer construction time and can not quickly control the settlement of the building.
Disclosure of Invention
In order to solve the technical problem of high building settlement speed in the prior art, the invention provides a method and a system for rapidly controlling the building settlement, namely, a primary column is fixed through a column-holding steel tray system, a steel pipe pile gradually enters a building foundation through the counterforce of the column-holding steel tray system, and after the building settlement is rapidly controlled, a newly-built bearing platform is permanently stable.
The method for rapidly controlling the settlement of the building comprises the following steps:
step one, erecting a column-holding steel tray system on a column base of an original column at a larger sedimentation side, wherein the column-holding steel tray system consists of profile steel members which surround and are connected with the original column;
a pile pressing hole is formed under the column holding type steel tray system, steel pipe piles are arranged in the pile pressing hole, the steel pipe piles are located on the periphery of an original foundation bearing platform, and pile pressing equipment is arranged between the top of each steel pipe pile and the column holding type steel tray system;
pouring a new bearing platform on the periphery of the original basic bearing platform, wherein the steel pipe piles are embedded into the new bearing platform;
and step four, dismantling the column-holding type steel tray system.
Preferably, the column-holding steel tray system is composed of four profile steel members surrounding the original column.
Preferably, the profile steel member is connected with the primary column through a split bolt.
Preferably, the steel pipe pile and the original foundation pile cap are fixed through pile locking and pile sealing.
Preferably, the steel pipe pile has a circular cross section.
The technical scheme of the system for rapidly controlling the settlement of the building comprises the following steps:
original post, original foundation cushion cap, embrace column type steel tray system, new cushion cap, steel-pipe pile and pile pressing equipment, wherein:
the column-holding type steel tray system is erected on the original column base at the larger sedimentation side and consists of profile steel components which surround and are connected with the original column;
a pile pressing hole is formed below the column-holding type steel pallet system, the steel pipe pile is arranged in the pile pressing hole, and the steel pipe pile is positioned at the periphery of the original foundation bearing platform;
the pile pressing equipment is arranged between the top of the steel pipe pile and the column-holding type steel tray system;
the new bearing platform is located at the periphery of the original basic bearing platform.
Preferably, the column-holding steel tray system is composed of four profile steel members surrounding the original column.
Preferably, the profile steel member is connected with the primary column through a split bolt.
Preferably, the steel pipe pile and the original foundation pile cap are fixed through pile locking and pile sealing.
Preferably, the steel pipe pile has a circular cross section.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings that are required to be used in the embodiments or the description of the prior art will be briefly described below, and it is obvious that the drawings in the following description are only embodiments of the present invention, and that other drawings can be obtained according to the provided drawings without inventive effort for a person skilled in the art.
FIG. 1 is a flow chart of a method for rapidly controlling settlement of a building according to the present invention;
FIG. 2 is a schematic illustration of building settlement;
FIG. 3 (a) (b) is a front view, top view of a system for rapidly controlling settlement of a building according to the present invention
Fig. 4 is a block diagram of the detached column steel pallet system of fig. 3.
Detailed Description
In order to solve the technical problem of high building settlement speed in the prior art, the invention provides a method and a system for rapidly controlling the building settlement, namely, a primary column is fixed through a column-holding steel tray system, a steel pipe pile gradually enters a building foundation through the counterforce of the column-holding steel tray system, and after the building settlement is rapidly controlled, a newly-built bearing platform is permanently stable.
The following description of the embodiments of the present invention will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present invention, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the invention without making any inventive effort, are intended to be within the scope of the invention.
Referring to fig. 1, a method for rapidly controlling settlement of a building according to the present invention includes:
101. erecting a column-holding steel tray system on the column base of the original column at the larger sedimentation side, wherein the column-holding steel tray system consists of profile steel members which surround and are connected with the original column;
in this embodiment, the section steel member and the column are connected by split bolts.
In addition, the primary column can be of a cube structure, and profile steel components are arranged at the peripheral edges of the primary column, and the primary column type steel tray system can be particularly composed of four profile steel components surrounding the primary column.
102. A pile pressing hole is formed under the column-holding type steel tray system, a steel pipe pile is arranged in the pile pressing hole, the steel pipe pile is positioned at the periphery of the original foundation bearing platform, and pile pressing equipment is arranged between the top of the steel pipe pile and the column-holding type steel tray system;
in this embodiment, the steel-pipe pile gradually gets into building foundation through the counter force of embracing column type steel tray braced system, and the steel-pipe pile is fixed through lock stake seal pile with former basic cushion cap, and the steel-pipe pile is circular cross-section.
103. Pouring a new bearing platform on the periphery of the original basic bearing platform, and embedding the steel pipe piles into the new bearing platform;
in this embodiment, the newly added pile is connected to the original pile cap through a lock pile or a seal pile.
104, dismantling the column type steel tray system.
In the embodiment, the column-holding type steel tray system is removed by removing the split bolts.
Referring to fig. 2 to 4, the technical scheme of the system for rapidly controlling settlement of a building according to the present invention includes:
original column 1, original foundation cushion cap 2, embrace column type steel tray system 3, new cushion cap 7, steel-pipe pile 4 and pile pressing equipment 5, wherein:
the column holding type steel tray system 3 is erected on the column foot of the original column 1 on the larger sedimentation side, the column holding type steel tray system 3 is composed of profile steel members 31 which surround and are connected with the original column 1, the concrete column holding type steel tray system 3 is composed of four profile steel members 31 which surround the original column 1, and the profile steel members 31 are connected with the original column 1 through split bolts 6.
Pile pressing holes are formed under the column holding type steel tray system 3, steel pipe piles 4 are arranged in the pile pressing holes, the steel pipe piles 4 are located on the periphery of the original foundation pile cap 2, the steel pipe piles 4 and the original foundation pile cap 2 are fixed through pile locking and pile sealing, and the steel pipe piles 4 are of circular cross section
The pile pressing device 5 is arranged between the top of the steel pipe pile 4 and the column holding type steel tray system 3;
the new platform 7 is located at the periphery of the original base platform 2.
The above embodiments are only for illustrating the technical solution of the present invention, and are not limiting; although the invention has been described in detail with reference to the foregoing embodiments, it will be understood by those of ordinary skill in the art that: the technical scheme described in the foregoing embodiments can be modified or some technical features thereof can be replaced by equivalents; such modifications and substitutions do not depart from the spirit and scope of the technical solutions of the embodiments of the present invention.

Claims (6)

1. A method for rapidly controlling settlement of a building, comprising:
step one, erecting a column-holding steel tray system on a column base of a primary column on a larger sedimentation side, wherein the column-holding steel tray system consists of four section steel members surrounding the primary column and connected with the primary column;
step two, arranging a pile pressing hole under the column-holding type steel tray system, arranging a steel pipe pile in the pile pressing hole, wherein the steel pipe pile is positioned at the periphery of an original foundation pile cap, the steel pipe pile and the original foundation pile cap are fixed through pile locking and pile sealing, the original foundation pile cap is positioned at the bottom of the original column, pile pressing equipment is arranged between the top of the steel pipe pile and the column-holding type steel tray system, and the steel pipe pile gradually enters a building foundation through the counterforce of the column-holding type steel tray system;
pouring a new bearing platform on the periphery of the original basic bearing platform, wherein the steel pipe piles are embedded into the new bearing platform;
and step four, dismantling the column-holding type steel tray system.
2. The method of quickly controlling settlement of buildings according to claim 1, wherein the section steel member and the primary column are connected by a split bolt.
3. The method of rapidly controlling settlement of a building according to claim 1, wherein the steel pipe pile has a circular cross section.
4. A system for rapid control of building settlement, characterized in that it is implemented based on the method for rapid control of building settlement according to any one of claims 1-3, comprising: original post, original foundation cushion cap, embrace column type steel tray system, new cushion cap, steel-pipe pile and pile pressing equipment, wherein:
the column-holding type steel tray system is erected on the original column base at the larger sedimentation side and consists of four section steel members surrounding the original column and connected with the original column;
the pile pressing hole is formed in the lower portion of the column-holding type steel tray system, the steel pipe pile is arranged in the pile pressing hole, the steel pipe pile is located on the periphery of the original foundation pile cap, the steel pipe pile and the original foundation pile cap are fixed through pile locking and pile sealing, and the original foundation pile cap is located at the bottom of the original column;
the pile pressing equipment is arranged between the top of the steel pipe pile and the column-holding steel tray system, and the steel pipe pile is used for gradually entering a building foundation through the counterforce of the column-holding steel tray system;
the new bearing platform is located at the periphery of the original basic bearing platform.
5. The system for rapid control of building settlement of claim 4, wherein said section steel member is connected to said primary column by means of split bolts.
6. The system for rapid control of building settlement of claim 4, wherein said steel pipe pile is circular in cross section.
CN201710453019.5A 2017-06-15 2017-06-15 Method and system for rapidly controlling settlement of building Active CN107237345B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710453019.5A CN107237345B (en) 2017-06-15 2017-06-15 Method and system for rapidly controlling settlement of building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710453019.5A CN107237345B (en) 2017-06-15 2017-06-15 Method and system for rapidly controlling settlement of building

Publications (2)

Publication Number Publication Date
CN107237345A CN107237345A (en) 2017-10-10
CN107237345B true CN107237345B (en) 2024-01-26

Family

ID=59986361

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710453019.5A Active CN107237345B (en) 2017-06-15 2017-06-15 Method and system for rapidly controlling settlement of building

Country Status (1)

Country Link
CN (1) CN107237345B (en)

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1111627C (en) * 1995-05-17 2003-06-18 广州市鲁班建筑防水补强专业公司 Method for connecting anchor-rod type supporting table
CN1078294C (en) * 1998-12-11 2002-01-23 北京市第七城市建设工程公司 Integral foundation underpinning technology for building added floor
RU2382146C1 (en) * 2008-08-04 2010-02-20 Владимир Николаевич Бронин Method for straightening of slant in building erected on pile foundation
CN103075020B (en) * 2013-02-04 2016-01-13 广州市胜特建筑科技开发有限公司 A kind of steel tray supports actuating system
CN106351270A (en) * 2016-11-16 2017-01-25 贵州正业工程技术投资有限公司 Self-locking steel pile structure for deviation correction and reinforcement of underpinned pile foundation
CN206844144U (en) * 2017-06-15 2018-01-05 广州市胜特建筑科技开发有限公司 A kind of system of quick control building settlement

Also Published As

Publication number Publication date
CN107237345A (en) 2017-10-10

Similar Documents

Publication Publication Date Title
US20180127938A1 (en) Water-permeable pipe pile system capable of accelerating soil consolidation and method of using the same
CN104018514A (en) Inverted installation method of embedded foundation bolts of large tower-type equipment foundation
CN103741817A (en) Enhancement method of X-shaped reinforcing bars for improving seismic resistance of special-shaped column nodes
CN103469732B (en) Construction method of preformed holes for foundation bolts of bridge support
CN104120802B (en) Simple method for mounting and locating seismic isolation support
CN108412223B (en) Deviation correcting structure and deviation correcting method for horizontal locking broken column
CN107938675A (en) A kind of Vertical spots concrete placings technique and device
CN103031892B (en) Steel truss brace and manufacturing method for steel truss platform
CN204703480U (en) A kind of integral supporting structure for building
CN107237345B (en) Method and system for rapidly controlling settlement of building
CN203238950U (en) Concrete beam formwork supported by trusses suspended in air
CN203213019U (en) Cast-in-situ construction bracket system of long cantilever bent cap
CN111980439A (en) Wall bearing replacement device and wall bearing replacement construction method
CN206844144U (en) A kind of system of quick control building settlement
CN206220534U (en) The pump line support meanss of concrete pumping equipment
CN202990418U (en) Slurry-leaking protection device preventing cast-in-place concrete column root from rotting
CN209082534U (en) Hanging operating platform sets up device in a kind of more piece open caisson
CN204112325U (en) A kind of for anchor jacked pile pile pressing device
CN103993612B (en) A kind of construction method of underwater concrete cushion cap
CN204715362U (en) A kind of deep foundation ditch embedded column base bracing frame
CN107806015A (en) A kind of unit construction bridge beam flange plate formwork for placing concrete system and construction method
CN207296393U (en) A kind of shed deckhead crack supporting construction
CN108104136B (en) Foundation pit supporting structure and construction method thereof
CN109098202A (en) Non- console mode tower crane foundation construction method
CN204780940U (en) Prop up supporting beam and go up interim year platform of piling of steel construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant