CN107237333A CN201710633942.7A CN201710633942A CN107237333A CN 107237333 A CN107237333 A CN 107237333A CN 201710633942 A CN201710633942 A CN 201710633942A CN 107237333 A CN107237333 A CN 107237333A
Authority
CN
China
Prior art keywords
fixed disk
backfill
construction
buried rod
rammed earth
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710633942.7A
Other languages
Chinese (zh)
Other versions
CN107237333B (en
Inventor
刘学刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Wuzhou Construction Group Co., Ltd.
Su Huojin
Original Assignee
Huaibei Qing Rong High Building Science And Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huaibei Qing Rong High Building Science And Technology Co Ltd filed Critical Huaibei Qing Rong High Building Science And Technology Co Ltd
Priority to CN201710633942.7A priority Critical patent/CN107237333B/en
Priority to CN201811419378.XA priority patent/CN109680693A/en
Publication of CN107237333A publication Critical patent/CN107237333A/en
Application granted granted Critical
Publication of CN107237333B publication Critical patent/CN107237333B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/18Making embankments, e.g. dikes, dams
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/046Improving by compacting by tamping or vibrating, e.g. with auxiliary watering of the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/11Improving or preserving soil or rock, e.g. preserving permafrost soil by thermal, electrical or electro-chemical means

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

Pre-buried rod is used the invention discloses a kind of construction backfill rammed earth auxiliary, belongs to the realm of building construction.A kind of construction backfill rammed earth auxiliary uses pre-buried rod, the fixed disk of through hole is offered including center, the fixed disk is hollow-core construction, dividing plate is connected with the fixed disk, the dividing plate will be separated out pumping chamber and humidification chamber in fixed disk, the upper end of the fixed disk offers exhaust tube, the exhaust tube is connected with pumping chamber, the bottom of the pumping chamber offers passage, the upper end of the fixed disk is also associated with switches set and atomizer, water inlet pipe is connected with the atomizer, the end of the atomizer is run through fixed disk and extended in humidification chamber.It can be realized in the place Min layers soil of backfill, technique of raking, and pre-buried rod is uniformly embedded in backfill, auxiliary pounds the construction of densification process, is significantly improved the construction effect for pounding densification process, reduce the generation of backfill sinkage.

Description

A kind of construction backfill rammed earth auxiliary uses pre-buried rod
Technical field
The present invention relates to the realm of building construction, more specifically to a kind of construction backfill rammed earth auxiliary with advance Bury rod.
Background technology
In construction, foundation ditch(Groove)Backfill is sunk and backfill percolating water causes the common manifestation of setting of ground to be Ground part or sheet is caused hollowing, crack occur, deform, collapse and wall body slit.
It is common technological difficulties in construction that backfill, which is sunk, causes the reason for backfill is sunk more, substantially has The earth material moisture content that backfill is selected is big, and clay soil property into " spongy soil ", backfill during compacting into not making the originals such as compaction in layers Cause.In the inspection soil property technique of backfill, whether backfill particle diameter meets regulation, and whether examines backfill soil's water content In control range, such as moisture content is higher, can be using measures such as scarifying, drying or uniform incorporation dry ground;Such as containing for backfill Water is relatively low, can be using measures such as watering wettings in advance.But in practical operation, due to external environment change and construction when Between difference, examine place Min layers soil after soil property technique, backfill soil's water content changes in technique of raking, then influence It is ensuing to pound densification process and levelling acceptance checking technology.Cause final backfill sinkage.
The content of the invention
1. the technical problem to be solved
For problems of the prior art, used it is an object of the invention to provide a kind of construction backfill rammed earth auxiliary Pre-buried rod, it can be realized in the place Min layers soil of backfill, technique of raking, and pre-buried rod is uniformly embedded in backfill, auxiliary The construction for pounding densification process is helped, the construction effect for pounding densification process is significantly improved, the generation of backfill sinkage is reduced.
2. technical scheme
To solve the above problems, the present invention is adopted the following technical scheme that.
A kind of construction backfill rammed earth auxiliary uses pre-buried rod, including center to offer the fixed disk of through hole, described solid Price fixing is hollow-core construction, and dividing plate is connected with the fixed disk, and the dividing plate will be separated out pumping chamber and humidification chamber in fixed disk, The upper end of the fixed disk offers exhaust tube, and the exhaust tube is connected with pumping chamber, and the bottom of the pumping chamber offers logical Stomata, the upper end of the fixed disk is also associated with switches set and atomizer, the atomizer being connected with water inlet pipe, the atomization The end of device is through fixed disk and extends in humidification chamber, and the lower end of the fixed disk is connected with screen pack, and screen pack is surround The lower end of fixed disk is set, and vibrating spear is connected with the through hole, and the vibrating spear is located at the inner side of screen pack, the screen pack One end away from fixed disk, which is connected with connection ring, the connection ring, is connected with drill bit, is offered and vibrating spear on the drill bit The stopper slot that matches of caput, the vibrating spear caput is through screen pack and extends in stopper slot, the vibrating spear side Face has been respectively fixedly connected with calandria and hollow bar, and the atomizer and calandria are electrically connected with switches set, described hollow The upper end of rod is connected with connecting tube, and the one end of the connecting tube away from hollow bar is through fixed disk and extends into humidification chamber, institute State and humidifier tube is connected with hollow bar, after backfill place Min layers soil, technique of raking, pre-buried rod is embedded in backfill, protected Hold pre-buried rod fixed disk above section and expose backfill, before densification process construction is pounded, then soil property technique of testing, when returning Water content of banketing is raised, and is connected the calandria and vibrating spear of pre-buried rod, is heated while being vibrated to backfill, reduction backfill Native water content, vibrating makes big soil particle diameter become broken, is conducive to drying backfill, while the soil of heating, drying is in process of vibrating In be easier discharge air, make backfill more consolidation, air and water vapour taken away by exhaust tube, when backfill water content reduction When, the atomizer and vibrating spear of pre-buried rod are connected, by water inlet tube of intaking, the water smoke that atomizer is produced is by humidifier tube to backfill Soil humidification, process of vibrating enables humidifier tube to humidify more backfills, takes air away again by exhaust tube and unnecessary water smoke; Pre-buried rod auxiliary pounds the construction of densification process, and preferably control pounds the particle diameter and moisture content of backfill in closely knit construction, shows The construction effect for improving and pounding densification process is write, the generation of backfill sinkage is reduced.
Preferably, hickey is offered in the connection ring, the drill bit is connected by hickey and connection ring screw thread Connect, convenient dismounting drill bit is safeguarded.
Preferably, the screen pack is fine and close stainless steel filter screen, and the mesh aperture of screen pack is 1-8mm, and densification is not Rust steel screen pack can reduce the inner side that backfill in process of vibrating enters screen pack, while fine and close stainless steel filter screen intensity is high, Not cracky.
Preferably, the calandria uses heating rod, and the surface of calandria scribbles waterproof layer, and waterproof layer can prevent water smoke Corrode heating rod.
Preferably, the calandria heats fluorescent tube using transparent shield is connected with the outside of heating fluorescent tube, and calandria Light produce that diffraction phenomena, homogeneous heating, and heated perimeter are big in backfill, transparent shield can protect heating fluorescent tube.
Preferably, the threaded upper ends of the fixed disk are connected with seal closure, and the upper end of the seal closure is connected with anti-pressure pipe, Seal closure and anti-pressure pipe can protect part more than pre-buried rod fixed disk.
3. beneficial effect
Compared to prior art, the advantage of the invention is that:
(1)Pre-buried rod is embedded in backfill by this programme after backfill place Min layers soil, technique of raking, and keeps pre-buried rod to consolidate Price fixing above section exposes backfill, before densification process construction is pounded, then soil property technique of testing, when backfill water content Rise, connects the calandria and vibrating spear of pre-buried rod, is heated while being vibrated to backfill, reduces backfill water content, Vibrating makes big soil particle diameter become broken, is conducive to drying backfill, while the soil of heating, drying is easier in process of vibrating Air is discharged, makes backfill more consolidation, air and water vapour is taken away by exhaust tube, when backfill water content is reduced, is connected The atomizer and vibrating spear of pre-buried rod, by water inlet tube of intaking, the water smoke that atomizer is produced is humidified by humidifier tube to backfill, Process of vibrating enables humidifier tube to humidify more backfills, takes air away again by exhaust tube and unnecessary water smoke.Pre-buried rod Auxiliary pounds the construction of densification process, and preferably control pounds the particle diameter and moisture content of backfill in closely knit construction, significantly improves The construction effect of densification process is pounded, the generation of backfill sinkage is reduced;
(2)Hickey is offered in connection ring, drill bit is threadedly coupled by hickey with connection ring, convenient dismounting drill bit enters Row is safeguarded;
(3)Screen pack is fine and close stainless steel filter screen, and the mesh aperture of screen pack is 1-8mm, fine and close stainless steel filter screen energy The inner side that backfill in process of vibrating enters screen pack is reduced, while fine and close stainless steel filter screen intensity is high, not cracky;
(4)Calandria uses heating rod, and the surface of calandria scribbles waterproof layer, and waterproof layer can prevent water smoke from corroding heating rod;
(5)Calandria heats the light of fluorescent tube in backfill using transparent shield is connected with the outside of heating fluorescent tube, and calandria Diffraction phenomena, homogeneous heating, and heated perimeter are produced in soil big, transparent shield can protect heating fluorescent tube;
(6)The threaded upper ends of fixed disk are connected with seal closure, and the upper end of seal closure is connected with anti-pressure pipe, seal closure and anti-pressure pipe energy Protect part more than pre-buried rod fixed disk.
Brief description of the drawings
Fig. 1 is front view of the invention;
Fig. 2 cuts structural representation during screen pack for the present invention;
Fig. 3 is the sectional view of fixed disk of the present invention;
Fig. 4 is the top view of fixed disk of the present invention;
Fig. 5 is sectional view of the invention;
Fig. 6 is the structural representation at A in Fig. 5;
Fig. 7 is sectional view when Fig. 5 is rotated by 90 ° by axle center of vibrating spear;
Front view when Fig. 8 is present invention connection seal closure.
Label declaration in figure:
1 exhaust tube, 2 fixed disks, 3 screen packs, 4 connection rings, 5 drill bits, 6 dividing plates, 7 water inlet pipes, 8 vibrating spears, 9 hollow bars, 10 mists Change device, 11 calandrias, 12 seal closures, 13 switches sets, 14 anti-pressure pipes, 15 connecting tubes, 16 passages, 17 humidifier tubes, 18 through holes, 19 Pumping chamber, 20 humidification chambers.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention;Technical scheme in the embodiment of the present invention is carried out clear, complete Site preparation is described;Obviously;Described embodiment is only a part of embodiment of the invention;Rather than whole embodiments.It is based on Embodiment in the present invention;It is every other that those of ordinary skill in the art are obtained under the premise of creative work is not made Embodiment;Belong to the scope of protection of the invention.
Embodiment 1:
Fig. 1-8 are referred to, a kind of construction backfill rammed earth auxiliary uses pre-buried rod, including center to offer the fixation of through hole 18 Disk 2, fixed disk 2 is that dividing plate 6 is connected with hollow-core construction, fixed disk 2, and dividing plate 6 will be separated out pumping chamber 19 and add in fixed disk 2 Wet chamber 20, the upper end of fixed disk 2 offers exhaust tube 1, and exhaust tube 1 is connected with pumping chamber 19, and the bottom of pumping chamber 19 is offered Passage 16, the upper end of fixed disk 2 is also associated with being connected with water inlet pipe 7 on switches set 13 and atomizer 10, atomizer 10, atomization The end of device 10 is through fixed disk 2 and extends in humidification chamber 20, and the lower end of fixed disk 2 is connected with screen pack 3, and screen pack 3 Set around the lower end of fixed disk 2, vibrating spear 8 is connected with through hole 18, vibrating spear 8 is located at the inner side of screen pack 3, screen pack 3 For fine and close stainless steel filter screen, and the mesh aperture of screen pack 3 is 1mm, and fine and close stainless steel filter screen can be reduced in process of vibrating Backfill enters the inner side of screen pack 3, while fine and close stainless steel filter screen intensity is high, not cracky, and screen pack 3 is away from fixed disk 2 one end, which is connected with connection ring 4, connection ring 4, offers hickey, and drill bit 5 is connected by hickey and the screw thread of connection ring 4 Connect, convenient dismounting drill bit 5 is safeguarded, the stopper slot matched with the caput of vibrating spear 8 is offered on drill bit 5, vibrating spear 8 Caput is through screen pack 3 and extends in stopper slot, and the side of vibrating spear 8 has been respectively fixedly connected with calandria 11 and hollow bar 9, mist Change device 10 and calandria 11 is electrically connected with switches set 13, calandria 11 is connected using heating fluorescent tube, and the outside of calandria 11 Transparent shield is connected to, the light of heating fluorescent tube produces diffraction phenomena, homogeneous heating, and heated perimeter greatly in backfill, thoroughly Bright protective cover can protect heating fluorescent tube, and the upper end of hollow bar 9 is connected with connecting tube 15, the one end of connecting tube 15 away from hollow bar 9 Extend through fixed disk 2 and into humidification chamber 20, be connected with humidifier tube 17 in hollow bar 9, the threaded upper ends of fixed disk 2 are connected with Seal closure 12, the upper end of seal closure 12 is connected with anti-pressure pipe 14, seal closure 12 and anti-pressure pipe 14 can protect pre-buried rod fixed disk 2 with On part.
After backfill place Min layers soil, construction of raking, according to the situation of building site weather and the interval length of engineering time, Choose appropriate number of pre-buried rod to be uniformly embedded in backfill, keep the pre-buried above section of rod fixed disk 2 to expose backfill, Pound before densification process construction, then soil property technique of testing, when the rise of backfill water content, connect the calandria 11 of pre-buried rod With vibrating spear 8, heated while being vibrated to backfill, reduce backfill water content, vibrating makes big soil particle diameter become broken, Be conducive to drying backfill, while the soil of heating, drying is easier discharge air in process of vibrating, make backfill more consolidation, Air and water vapour are taken away by exhaust tube 1, when backfill water content is reduced, the atomizer 10 and vibrating spear of pre-buried rod is connected 8, intake by water inlet pipe 7, the water smoke that atomizer 10 is produced is humidified by humidifier tube 17 to backfill, process of vibrating makes humidifier tube 17 can be evenly humidification backfill, take air away again by exhaust tube 1 and unnecessary water smoke.Pre-buried rod auxiliary pounds closely knit The construction of technique, preferably control pounds the particle diameter and moisture content of backfill in closely knit construction, pounds after closely knit construction terminates and takes Go out pre-buried rod, the hole for burying pre-buried rod is carried out filling up compacting.
Traditional backfill operating procedure includes:
1st, cleared up on the terrace of foundation ditch (groove) bottom;
2nd, soil property is examined;
3rd, place Min layers are native, rake;
4th, pound closely knit;
5th, compactness is examined;
6th, levelling check and accept is repaired.
The backfill operating procedure traditional by changing, new technology is:
1st, cleared up on the terrace of foundation ditch (groove) bottom;
2nd, soil property is examined;
3rd, pre-buried rod is buried;
4th, place Min layers are native, rake;
5th, soil property, pre-buried rod auxiliary control soil property are examined again;
6th, pound closely knit;
7th, take out pre-buried rod and carry out filling up compacting;
8th, compactness is examined;
9th, levelling check and accept is repaired.
Construction backfill rammed earth auxiliary is reached with the use of pre-buried rod significantly improves the construction for pounding densification process effect Really, the generation of backfill sinkage is reduced.
It is described above;Preferably embodiment only of the invention;But protection scope of the present invention is not limited thereto; Any one skilled in the art the invention discloses technical scope in;Technique according to the invention scheme and its Improve design and be subject to equivalent substitution or change;It should all cover within the scope of the present invention.

Claims (6)

1. a kind of construction backfill rammed earth auxiliary uses pre-buried rod, it is characterised in that:Through hole is offered including center(18)'s Fixed disk(2), the fixed disk(2)For hollow-core construction, the fixed disk(2)Inside it is connected with dividing plate(6), the dividing plate(6)Will Fixed disk(2)Inside it is separated out pumping chamber(19)And humidification chamber(20), the fixed disk(2)Upper end offer exhaust tube(1), institute State exhaust tube(1)With pumping chamber(19)Connection, the pumping chamber(19)Bottom offer passage(16), the fixed disk (2)Upper end be also associated with switches set(13)And atomizer(10), the atomizer(10)On be connected with water inlet pipe(7), it is described Atomizer(10)End run through fixed disk(2)And extend to humidification chamber(20)It is interior, the fixed disk(2)Lower end be connected with Filter screen(3), and screen pack(3)Around fixed disk(2)Lower end set, the through hole(18)Inside it is connected with vibrating spear(8), it is described Vibrating spear(8)Positioned at screen pack(3)Inner side, the screen pack(3)Away from fixed disk(2)One end be connected with connection ring(4), The connection ring(4)On be connected with drill bit(5), the drill bit(5)On offer and vibrating spear(8)Caput match it is spacing Groove, the vibrating spear(8)Caput run through screen pack(3)And extend in stopper slot, the vibrating spear(8)Side is fixed respectively It is connected with calandria(11)And hollow bar(9), the atomizer(10)And calandria(11)And switches set(13)It is electrically connected with, The hollow bar(9)Upper end be connected with connecting tube(15), the connecting tube(15)Away from hollow bar(9)One end through fix Disk(2)And to humidification chamber(20)Interior extension, the hollow bar(9)On be connected with humidifier tube(17).
2. a kind of construction backfill rammed earth auxiliary according to claim 1 uses pre-buried rod, it is characterised in that:The company Connect ring(4)On offer hickey, the drill bit(5)Pass through hickey and connection ring(4)Threaded connection.
3. a kind of construction backfill rammed earth auxiliary according to claim 1 uses pre-buried rod, it is characterised in that:The mistake Filter screen(3)For fine and close stainless steel filter screen, and screen pack(3)Mesh aperture be 1-8mm.
4. a kind of construction backfill rammed earth auxiliary according to claim 1 uses pre-buried rod, it is characterised in that:It is described to add Hot body(11)Using heating rod, and calandria(11)Surface scribble waterproof layer.
5. a kind of construction backfill rammed earth auxiliary according to claim 1 uses pre-buried rod, it is characterised in that:It is described to add Hot body(11)Using heating fluorescent tube, and calandria(11)Outside be connected with transparent shield.
6. a kind of construction backfill rammed earth auxiliary according to claim 1 uses pre-buried rod, it is characterised in that:It is described solid Price fixing(2)Threaded upper ends be connected with seal closure(12), the seal closure(12)Upper end be connected with anti-pressure pipe(14).
CN201710633942.7A 2017-07-29 2017-07-29 A kind of pre-buried stick of construction backfill rammed earth auxiliary Expired - Fee Related CN107237333B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201710633942.7A CN107237333B (en) 2017-07-29 2017-07-29 A kind of pre-buried stick of construction backfill rammed earth auxiliary
CN201811419378.XA CN109680693A (en) 2017-07-29 2017-07-29 A kind of pre-buried stick of construction backfill rammed earth auxiliary

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710633942.7A CN107237333B (en) 2017-07-29 2017-07-29 A kind of pre-buried stick of construction backfill rammed earth auxiliary

Related Child Applications (1)

Application Number Title Priority Date Filing Date
CN201811419378.XA Division CN109680693A (en) 2017-07-29 2017-07-29 A kind of pre-buried stick of construction backfill rammed earth auxiliary

Publications (2)

Publication Number Publication Date
CN107237333A true CN107237333A (en) 2017-10-10
CN107237333B CN107237333B (en) 2019-01-29

Family

ID=59989418

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201710633942.7A Expired - Fee Related CN107237333B (en) 2017-07-29 2017-07-29 A kind of pre-buried stick of construction backfill rammed earth auxiliary
CN201811419378.XA Pending CN109680693A (en) 2017-07-29 2017-07-29 A kind of pre-buried stick of construction backfill rammed earth auxiliary

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN201811419378.XA Pending CN109680693A (en) 2017-07-29 2017-07-29 A kind of pre-buried stick of construction backfill rammed earth auxiliary

Country Status (1)

Country Link
CN (2) CN107237333B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110295588B (en) * 2019-06-25 2021-04-13 东莞市广渠建筑工程有限公司 Soft soil foundation treatment device and treatment method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102758444A (en) * 2011-04-27 2012-10-31 五冶集团上海有限公司 Construction method of benzene hydrogenation engineering earthwork
CN204645688U (en) * 2015-05-29 2015-09-16 重庆科技学院 The pre-buried exposed steel bar Rustproofing apparatus of vacuum-pumping type
CN105781114A (en) * 2015-12-23 2016-07-20 刘思广 Insert type concrete vibrorammer combining vacuum air exhaust and water suction and principles thereof
DE202016107232U1 (en) * 2016-12-21 2017-03-01 BUG Dienstleistungen GmbH & Co. KG Compacting plant for the compaction of compactible soils using a carrier device
JP2017071901A (en) * 2015-10-05 2017-04-13 中国電力株式会社 Underwater compaction method

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1046564A (en) * 1996-08-06 1998-02-17 Fujita Corp Ground compacting construction method by microwave
CN101831903B (en) * 2010-05-18 2012-02-08 上海港湾软地基处理工程(集团)有限公司 Method for treating soft foundation
CN103352456B (en) * 2013-07-22 2015-03-25 中国化学工程第一岩土工程有限公司 Dry-sand preconsolidation vibrating foundation reinforcing method
CN103898892A (en) * 2014-03-06 2014-07-02 中交天津港湾工程研究院有限公司 Processing method and device for reinforcing soft foundation by hydraulic vibration combined with vacuum water suction
CN104790372B (en) * 2015-04-28 2017-05-10 上海大学 Vibration-compressed air-vacuum combination foundation reinforcement system and method
CN106149673B (en) * 2015-10-28 2019-01-01 席宁中 Collapsible loess deep is soaked heavy-tamping method in advance
CN106192981B (en) * 2016-07-08 2018-04-03 河海大学 A kind of Dewatering dynamic compaction integrated device and its application method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102758444A (en) * 2011-04-27 2012-10-31 五冶集团上海有限公司 Construction method of benzene hydrogenation engineering earthwork
CN204645688U (en) * 2015-05-29 2015-09-16 重庆科技学院 The pre-buried exposed steel bar Rustproofing apparatus of vacuum-pumping type
JP2017071901A (en) * 2015-10-05 2017-04-13 中国電力株式会社 Underwater compaction method
CN105781114A (en) * 2015-12-23 2016-07-20 刘思广 Insert type concrete vibrorammer combining vacuum air exhaust and water suction and principles thereof
DE202016107232U1 (en) * 2016-12-21 2017-03-01 BUG Dienstleistungen GmbH & Co. KG Compacting plant for the compaction of compactible soils using a carrier device

Also Published As

Publication number Publication date
CN109680693A (en) 2019-04-26
CN107237333B (en) 2019-01-29

Similar Documents

Publication Publication Date Title
CN107121371A (en) A kind of simulation laboratory test system and method suitable for layer of sand osmotic grouting
CN109914385A (en) A kind of method of hydraulic structure treatment of soft foundation
CN107737788B (en) A kind of sanitary filling field landfill gas collection processing system implementing and method
CN107237333A (en) A kind of construction backfill rammed earth auxiliary uses pre-buried rod
CN105910867B (en) A kind of simple device quickly preparing different water cut ground sample
CN206101172U (en) Solar energy type roof greening water -saving irrigation system
CN112063498A (en) Garbage landfill biogas collection system and collection method
CN106146054A (en) Mud rapid fermentation fertilizer producing system
CN208258662U (en) A kind of planting in desert water saving fixtures
CN206698990U (en) Municipal afforestation device
CN207121434U (en) It is a kind of can deodorization countryside sewage treatment equipment
CN115648373A (en) Ecological slope anti-corrosion timber pile and treatment device and treatment method thereof
CN113006039B (en) Dynamic compaction reinforcing construction method for collapsible loess foundation
CN214302991U (en) Moisture removal and maintenance system for historical building brick wall based on electroosmosis principle
CN208213933U (en) A kind of soil pollutant batch-type dystopy thermal desorption system
CN104402191B (en) Energy-saving disc type drying system
CN109140921A (en) A kind of chalk drying unit based on air-heater
CN208668802U (en) Green roof system based on secondary drainage steam discharge pipe network
CN106013046A (en) Grading loading method for variable-stress path well point plastic drainage vacuum preloading seepage consolidation
CN207891864U (en) A kind of ground heating discharge structure of vertical drainage chimney filter in-built electrical hot pin
CN105926577A (en) Vacuum prepressing seepage consolidation method
CN105862719A (en) Reinforced foundation
CN207904705U (en) A kind of permeable road of ecology garden landscape
CN207047633U (en) A kind of permeable tree pond of ecological sustainability
CN105970909A (en) Well point plastic draining pipe type vacuum preloading seepage consolidation and dewatering preloading power consolidation combined method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20181123

Address after: 230031 B-1014, 10 floor, business office building, Wo Ye garden, Shushan District, Hefei, Anhui.

Applicant after: HEFEI WISDOM LONGTUTENG INTELLECTUAL PROPERTY CO., LTD.

Address before: 235099 6 506 of Changshan South Road, Xiangshan District, Huaibei, Anhui

Applicant before: Huaibei Qing Rong high building science and Technology Co Ltd

TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20181210

Address after: 362400 B 1603-1606, building 4, financial administrative service center, Anxi County, Quanzhou, Fujian.

Applicant after: Fujian Wuzhou Construction Group Co., Ltd.

Applicant after: Su Huojin

Applicant after: Lin Jianwen

Address before: 230031 B-1014, 10 floor, business office building, Wo Ye garden, Shushan District, Hefei, Anhui.

Applicant before: HEFEI WISDOM LONGTUTENG INTELLECTUAL PROPERTY CO., LTD.

GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190129