CN107228501A - A kind of air conditioner - Google Patents

A kind of air conditioner Download PDF

Info

Publication number
CN107228501A
CN107228501A CN201710373687.7A CN201710373687A CN107228501A CN 107228501 A CN107228501 A CN 107228501A CN 201710373687 A CN201710373687 A CN 201710373687A CN 107228501 A CN107228501 A CN 107228501A
Authority
CN
China
Prior art keywords
stop valve
compressor
air conditioner
valve
evaporator
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710373687.7A
Other languages
Chinese (zh)
Other versions
CN107228501B (en
Inventor
郑润兴
杨焕弟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Chigo Heating and Ventilation Equipment Co Ltd
Original Assignee
Guangdong Chigo Heating and Ventilation Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Chigo Heating and Ventilation Equipment Co Ltd filed Critical Guangdong Chigo Heating and Ventilation Equipment Co Ltd
Priority to CN201710373687.7A priority Critical patent/CN107228501B/en
Publication of CN107228501A publication Critical patent/CN107228501A/en
Application granted granted Critical
Publication of CN107228501B publication Critical patent/CN107228501B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F25REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
    • F25BREFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
    • F25B1/00Compression machines, plants or systems with non-reversible cycle
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F25REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
    • F25BREFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
    • F25B49/00Arrangement or mounting of control or safety devices
    • F25B49/02Arrangement or mounting of control or safety devices for compression type machines, plants or systems

Abstract

The invention discloses a kind of air conditioner, including compressor, condenser and evaporator, the gas exhaust piping of the compressor is connected with the condenser, the return line of the compressor is connected with the evaporator, it is provided with the gas exhaust piping in the first stop valve, the return line and is provided with the second stop valve;When the compressor is opened, first stop valve and second stop valve are in conducting state;When the compressor just stops operating, first stop valve can be closed immediately, and second stop valve, which can be tended to remain on to preset time, to be turned off.When above-mentioned air conditioner is shut down, the refrigerant in heat exchanger system can be recovered to inside compressor, the pressure in heat exchanger and system pipeline is less than external environment condition standard atmospheric pressure, when system has minute leakage point, it is to avoid the slow leakage of refrigerant.

Description

A kind of air conditioner
Technical field
The present invention relates to air-conditioning technical field, more particularly to a kind of air conditioner.
Background technology
With the rising of Global Temperature, air conditioner comes into huge numbers of families, is more and more used.Through market survey It was found that, occur often because air-conditioning refrigerant leaks the situation that causes machine and can not normally run, on the one hand influence consumer is to production The satisfaction that product are used, on the other hand, because refrigerant R22 has destruction to the ozone in atmosphere, should more reduce refrigeration Agent is leaked into air.
Cause the reason for refrigerant is leaked a lot, for detachable air conditioner, heat exchange manifold weld and interior The presence of microminiature leakage is easier at outer machine connecting line, current air conditioner shuts down after operation, compressor stops fortune Turn, refrigerant is dispersed in indoor external heat exchanger and corresponding pipeline, because internal pressure is higher than external ambient atmosphere pressure, hold very much Refrigerant is easily caused slowly to be lost in by microminiature leak.
In summary, the problem of refrigerant in the heat exchanger and respective line of air conditioner is leaked how is solved, it has also become Those skilled in the art's technical barrier urgently to be resolved hurrily.
The content of the invention
It is an object of the invention to provide a kind of air conditioner, the refrigerant in heat exchanger and respective line to avoid air conditioner Leakage.
To achieve these goals, the invention provides a kind of air conditioner, including compressor, condenser and evaporator, institute The gas exhaust piping for stating compressor is connected with the condenser, and the return line of the compressor is connected with the evaporator, described It is provided with gas exhaust piping in the first stop valve, the return line and is provided with the second stop valve;
When the compressor is opened, first stop valve and second stop valve are in conducting state;
When the compressor just stops operating, first stop valve can be closed immediately, second stop valve It can tend to remain on to preset time and turn off.
Preferably, the preset time is 20 seconds.
Preferably, first stop valve is magnetic valve.
Preferably, second stop valve is magnetic valve.
Preferably, second stop valve is tended to remain on to preset time by connecting time-delay relay and turned off.
Content is introduced compared to background technology, above-mentioned air conditioner, by setting the first stop valve and the second stop valve, makes sky When adjusting the device to shut down, namely when compressor just stops, gas exhaust piping instantaneously still in high pressure, return line still in low pressure, Although now the first stop valve is closed, the flowing of the fluid in pipeline continues flowing due to inertia, and then makes Refrigerant-recovery in heat exchanger system to inside compressor;After preset time is flowed to, the second stop valve is closed, from And cause the channel interior formation negative pressure between the first stop valve and the second stop valve, even if also in heat exchanger and system pipeline Pressure is less than external environment condition standard atmospheric pressure, when system has minute leakage point, it is to avoid the slow leakage of refrigerant.
Brief description of the drawings
Fig. 1 is the theory structure schematic diagram of air conditioner provided in an embodiment of the present invention.
In figure 1 above, arrow represents the flow direction of fluid:
Compressor 1, condenser 2, evaporator 3, gas exhaust piping 4, return line 5, the first stop valve 6, the second stop valve 7, Throttling arrangement 8.
Embodiment
The core of the present invention is to provide a kind of air conditioner, the refrigerant in heat exchanger and respective line to avoid air conditioner Leakage.
In order that those skilled in the art more fully understands the technical scheme that provides of the present invention, below in conjunction with accompanying drawing and The present invention is described in further detail for specific embodiment.
As shown in figure 1, air conditioner provided in an embodiment of the present invention, including compressor 1, condenser 2 and evaporator 3, compression The gas exhaust piping 4 of machine 1 is connected with condenser 2, and the return line 5 of compressor 1 is connected with evaporator 3, is provided with gas exhaust piping 4 The second stop valve 7 is provided with first stop valve 6, return line 5;When compressor 1 is opened, the first stop valve 6 and second section Only 7 valves are in conducting state;When compressor 1 just stops operating, the first stop valve 6 can be closed immediately, the second cut-off Valve 7 can be tended to remain on to preset time and turned off.Explanation is needed exist for, those skilled in the art should be able to What is understood is the heat exchanger system of air-conditioning, typically should also have throttling arrangement 8, and the throttling arrangement 8 is arranged on condensation Between device 2 and evaporator 3.
Content is introduced compared to background technology, above-mentioned air conditioner, by setting the first stop valve and the second stop valve, makes sky When adjusting the device to shut down, namely when compressor just stops, gas exhaust piping instantaneously still in high pressure, return line still in low pressure, Although now the first stop valve is closed, the flowing of the fluid in pipeline continues flowing due to inertia, and then makes Refrigerant-recovery in heat exchanger system to inside compressor;After preset time is flowed to, the second stop valve is closed, from And cause the channel interior formation negative pressure between the first stop valve and the second stop valve, even if also in heat exchanger and system pipeline Pressure is less than external environment condition standard atmospheric pressure, when system has minute leakage point, it is to avoid the slow leakage of refrigerant.
In some specific embodiments, the corresponding preset time of time-delay closing of above-mentioned second stop valve is 20 seconds. Of course, it should be understood that being only within above-mentioned 20 seconds the preferable examples of the embodiment of the present invention, it can also be according to air conditioner correspondence Heat exchanger built-in system facilities selection other times value.
In addition, one or two in the above-mentioned stop valve 7 of first stop valve 6 and second can be magnetic valve.By setting , can be with the opening and closing of the on-off control valve body of the power supply of application valve body, simpler convenience into magnetic valve.Can certainly Be above-mentioned magnetic valve be only the embodiment of the present invention preferable examples or mechanical valve body.
In addition, when the second stop valve 7 is magnetic valve, can be tended to remain on by connecting time-delay relay to default Time turns off.Of course, it should be understood that above-mentioned time-delay relay realizes that the second stop valve time-delay closing is only the present invention Other time-delay closing devices that the preferable examples of embodiment or those skilled in the art commonly use are realized, such as are directly led to Cross controller and control the second stop valve time-delay closing.
Air conditioner provided by the present invention is described in detail above.It should be noted that each in this specification Individual embodiment is described by the way of progressive, and what each embodiment was stressed is the difference with other embodiment, Between each embodiment identical similar part mutually referring to.
It should also be noted that, herein, such as first and second or the like relational terms are used merely to one Entity or operation make a distinction with another entity or operation, and not necessarily require or imply between these entities or operation There is any this actual relation or order.Moreover, term " comprising ", "comprising" or its any other variant are intended to contain Lid nonexcludability is included, so that article or equipment including a series of key elements not only include those key elements, but also Including other key elements being not expressly set out, or also include for this article or the intrinsic key element of equipment.Do not having In the case of more limitations, the key element limited by sentence "including a ...", it is not excluded that including the article of above-mentioned key element Or also there is other identical element in equipment.
Specific case used herein is set forth to the principle and embodiment of the present invention, and above example is said The bright method and its core concept for being only intended to help to understand the present invention.It should be pointed out that for the ordinary skill of the art For personnel, under the premise without departing from the principles of the invention, some improvement and modification can also be carried out to the present invention, these improvement Also fallen into modification in the protection domain of the claims in the present invention.

Claims (5)

1. a kind of air conditioner, including compressor (1), condenser (2) and evaporator (3), the gas exhaust piping of the compressor (1) (4) connected with the condenser (2), the return line (5) of the compressor (1) is connected with the evaporator (3), and its feature exists In being provided with the gas exhaust piping (4) on the first stop valve (6), the return line (5) and be provided with the second stop valve (7);
When the compressor (1) is opened, first stop valve (6) and described second cut-off (7) valve are in conducting state;
When the compressor (1) just stops operating, first stop valve (6) can close immediately, second cut-off Valve (7), which can be tended to remain on to preset time, to be turned off.
2. air conditioner as claimed in claim 1, it is characterised in that the preset time is 20 seconds.
3. air conditioner as claimed in claim 1, it is characterised in that first stop valve (6) is magnetic valve.
4. air conditioner as claimed in claim 1, it is characterised in that second stop valve (7) is magnetic valve.
5. air conditioner as claimed in claim 4, it is characterised in that second stop valve (7) is by connecting time-delay relay Tend to remain on to preset time and turn off.
CN201710373687.7A 2017-05-24 2017-05-24 Air conditioner Active CN107228501B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710373687.7A CN107228501B (en) 2017-05-24 2017-05-24 Air conditioner

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710373687.7A CN107228501B (en) 2017-05-24 2017-05-24 Air conditioner

Publications (2)

Publication Number Publication Date
CN107228501A true CN107228501A (en) 2017-10-03
CN107228501B CN107228501B (en) 2023-12-01

Family

ID=59934605

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710373687.7A Active CN107228501B (en) 2017-05-24 2017-05-24 Air conditioner

Country Status (1)

Country Link
CN (1) CN107228501B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111720950A (en) * 2020-05-19 2020-09-29 青岛海尔空调器有限总公司 Control method for reducing indoor side refrigerant leakage of air conditioner and air conditioner
CN115151769A (en) * 2020-02-25 2022-10-04 Lg电子株式会社 Heat pump and method of operating the same

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09264641A (en) * 1996-03-29 1997-10-07 Matsushita Electric Ind Co Ltd Refrigerating cycle device
JPH10281569A (en) * 1997-04-04 1998-10-23 Sanyo Electric Co Ltd Air conditioner
US20040003607A1 (en) * 2002-07-02 2004-01-08 Kadle Prasad S. HVAC system shutdown sequence
JP2004251130A (en) * 2003-02-18 2004-09-09 Matsushita Electric Ind Co Ltd Hermetic compressor and refrigeration cycle
JP2009115325A (en) * 2007-11-01 2009-05-28 Yazaki Corp Cooling device
CN103033003A (en) * 2011-10-10 2013-04-10 松下电器研究开发(苏州)有限公司 Refrigerant recovery device and recovery control method
CN104061659A (en) * 2014-07-10 2014-09-24 深圳麦克维尔空调有限公司 Air conditioning system and coolant recycling method thereof
CN104748295A (en) * 2014-01-01 2015-07-01 广东美的制冷设备有限公司 Air conditioner and recycling method for air conditioner refrigerant
CN205351869U (en) * 2015-12-10 2016-06-29 广东奥马冰箱有限公司 Refrigerator condenser pressure maintaining system
CN207123090U (en) * 2017-05-24 2018-03-20 广东志高暖通设备股份有限公司 A kind of air conditioner

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09264641A (en) * 1996-03-29 1997-10-07 Matsushita Electric Ind Co Ltd Refrigerating cycle device
JPH10281569A (en) * 1997-04-04 1998-10-23 Sanyo Electric Co Ltd Air conditioner
US20040003607A1 (en) * 2002-07-02 2004-01-08 Kadle Prasad S. HVAC system shutdown sequence
JP2004251130A (en) * 2003-02-18 2004-09-09 Matsushita Electric Ind Co Ltd Hermetic compressor and refrigeration cycle
JP2009115325A (en) * 2007-11-01 2009-05-28 Yazaki Corp Cooling device
CN103033003A (en) * 2011-10-10 2013-04-10 松下电器研究开发(苏州)有限公司 Refrigerant recovery device and recovery control method
CN104748295A (en) * 2014-01-01 2015-07-01 广东美的制冷设备有限公司 Air conditioner and recycling method for air conditioner refrigerant
CN104061659A (en) * 2014-07-10 2014-09-24 深圳麦克维尔空调有限公司 Air conditioning system and coolant recycling method thereof
CN205351869U (en) * 2015-12-10 2016-06-29 广东奥马冰箱有限公司 Refrigerator condenser pressure maintaining system
CN207123090U (en) * 2017-05-24 2018-03-20 广东志高暖通设备股份有限公司 A kind of air conditioner

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115151769A (en) * 2020-02-25 2022-10-04 Lg电子株式会社 Heat pump and method of operating the same
CN111720950A (en) * 2020-05-19 2020-09-29 青岛海尔空调器有限总公司 Control method for reducing indoor side refrigerant leakage of air conditioner and air conditioner

Also Published As

Publication number Publication date
CN107228501B (en) 2023-12-01

Similar Documents

Publication Publication Date Title
CN107560112B (en) A kind of control method of air conditioner refrigerating high temperature-proof protection
US11015828B2 (en) Refrigeration system with utilization unit leak detection
WO2020103516A1 (en) Evaporative cooling chiller unit heat-exchanging system and control method therefor
WO2016192347A1 (en) Light-load dehumidification and refrigeration method and device
CN107289599A (en) A kind of apparatus and method for detecting air conditioner coolant amount of leakage
WO2016088167A1 (en) Air-conditioning device
CN105805903A (en) Air conditioner and leakage preventing control method thereof
EP3361190B1 (en) Refrigeration cycle device and control method for determination of leaks in bypass valve of refrigeration cycle device
CN107228501A (en) A kind of air conditioner
CN107218742A (en) Heat pump and heat pump control method
WO2018225263A1 (en) Refrigeration apparatus and air-conditioning apparatus
CN207123090U (en) A kind of air conditioner
WO2018158886A1 (en) Refrigeration cycle device
CN111076279A (en) Control method for updating multi-split air conditioning system and multi-split air conditioning system updating method
CN204240632U (en) Air-conditioning system
CN105758050A (en) Wide temperature range air-conditioning system
CN109084392A (en) Air conditioner
CN205619430U (en) Air -conditioner
CN205536717U (en) Throttling arrangement and have its air conditioner
CN110529993B (en) Operation control device and method, air conditioner, and computer-readable storage medium
CN209690790U (en) The online height temperature changing test chamber of optics
CA2749341C (en) Positive shutoff device for a connection point of a refrigeration system
CN207455798U (en) A kind of multi-connected machine central air-conditioning
US10408513B2 (en) Oil line control system
GB2577445A8 (en) Air conditioning device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 510000 No.1 by helongsha villager group, Shengli village, Lishui Town, Nanhai District, Foshan City, Guangdong Province

Applicant after: Guangdong Kaili HVAC Co.,Ltd.

Address before: 510000 No.1 by helongsha villager group, Shengli village, Lishui Town, Nanhai District, Foshan City, Guangdong Province

Applicant before: GUANGDONG CHIGO HEATING AND VENTILATION EQUIPMENT Co.,Ltd.

CB02 Change of applicant information
GR01 Patent grant