CN107227688A - Pier hangs bottom technique - Google Patents
Pier hangs bottom technique Download PDFInfo
- Publication number
- CN107227688A CN107227688A CN201710457201.8A CN201710457201A CN107227688A CN 107227688 A CN107227688 A CN 107227688A CN 201710457201 A CN201710457201 A CN 201710457201A CN 107227688 A CN107227688 A CN 107227688A
- Authority
- CN
- China
- Prior art keywords
- shoulder pole
- pier
- pole girder
- steel
- pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/02—Piers; Abutments ; Protecting same against drifting ice
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
Bottom technique is hung the invention discloses a kind of pier, is comprised the following steps:Bill kept on file position is hung by a pier of two neighboring bridge steel pile tube, laying steel plate is levelling in each Steel Tubes For Bridge Application stake top face;Stand is lifted across setting pier that on the two ends of the first shoulder pole girder, the second shoulder pole girder and the 3rd shoulder pole girder is constituted on each bridge steel pile tube;Formwork erection and operation is poured on hoisting bracket;Pier lifting stand is removed, while the pier for completing two adjacent bridge steel pile tubes hangs bottom operation.In summary, present invention process, on the basis of the stability of pier lifting stand is improved, the pier that two adjacent bridge steel pile tubes can be completed simultaneously hangs bottom operation, activity level is high, and on the two ends of the first shoulder pole girder in operation process, the second shoulder pole girder, the 3rd shoulder pole girder, crossbeam, longeron and the second round steel suspension rod is recyclable recycles, effectively save construction cost.
Description
Technical field
The present invention relates to bridge construction technical field, more particularly to a kind of pier hangs bottom technique.
Background technology
As economic continues to develop, some roads receive rail friendship, highway, river course etc. and deaden what is do not connected between city
Situation has greatly improvement, and the construction progress of different types of rridges is also gradually being accelerated, still, the pier construction technology of existing bridge
Also there are problems, pier is constructed especially in water, land, pile foundation anchor ear supporting methods and steel jacket box are generally banketed into using cofferdam
The forms such as cofferdam method, wherein, banketed into double more than the 12m Larsens steel sheet piles of Lu Caiyong in cofferdam, and clay shape is filled out in double sheet pile
Into cofferdam, land construction is formed using plain earthen backfill after the shaping of cofferdam.Backfilling of earthwork and cleaning are to river course environment in work progress
Influence is larger, and cofferdam measure cost cost is high;Pile foundation anchor ear supporting methods are to use certain thickness outside the pile foundation completed using construction
Circular steel plate hoop on pier stud, using a kind of construction method of the frictional resistance by the corbels support pier support on steel plate hoop,
But drilled pile hits the regular voucher of Hold Hoop method lactation prefabricated pile or column body, frictional force is difficult to control, add install under water with
Remove the more difficult implementation of anchor ear.Steel boxed cofferdam method, the material based on steel form dresses up casing by way of split is assembled,
Submerged.Blocked water by steel jacket box with back cover Shanghai and Nanjing figure into cofferdam, anhydrous construction environment is provided for pier construction in water.Examine
Consider that steel jacket box processing, transport and installation period are long, cost input is big, is more suitable for the ultra-deep depth of water in bridge spanning the sea, Duo Geshui
Middle pier continuously has enough to meet the need construction.
The content of the invention
It is an object of the invention to solve at least the above, and provide the advantage that at least will be described later.
Bottom technique is hung it is a still further object of the present invention to provide a kind of pier, it can improve the steady of pier lifting stand
On the basis of qualitatively, the pier that two adjacent bridge steel pile tubes can be completed simultaneously hangs bottom operation, and activity level is high, and operation
On the two ends of the first shoulder pole girder in journey, the second shoulder pole girder, the 3rd shoulder pole girder, crossbeam, longeron and the second round steel suspension rod can return
Receive and recycle, effectively save construction cost, it is adaptable to which in water or land route different types of rridges pier is constructed.
Bottom technique is hung there is provided a kind of pier according to object of the present invention and further advantage in order to realize, including with
Lower step:
Step 1: bill kept on file position is hung by a pier of two neighboring bridge steel pile tube, in each Steel Tubes For Bridge Application stake top face paving
If steel plate is levelling;
Step 2: by two the first shoulder pole girders respectively across bridge to two steel-pipe piles steel plate on, any one
Corresponding skirtboard is welded on the lower surface of one shoulder pole girder so that the side wall of skirtboard is fitted with steel-pipe pile lateral wall;
Step 3: the second shoulder pole girder is set up between two the first shoulder pole girders, and the two ends of the second shoulder pole girder are welded respectively
It is connected on the middle part of the side of two the first shoulder pole girders;Two the 3rd shoulder pole girders, two are extended in the both sides of the second shoulder pole girder
One end of 3rd shoulder pole girder is welded on the middle part of the opposite side of two the first shoulder pole girders;
Step 4: uniformly drilled on the two ends of the first shoulder pole girder, the second shoulder pole girder and on the 3rd shoulder pole girder, it is flat second
The crossbeam that the first round steel suspension rod hangs direction across bridge, the brill at the first shoulder pole girder two ends are worn in the drilling of spreader beam and the 3rd shoulder pole girder
Worn in hole the second round steel suspension rod hang bridge to longeron;Wherein, longeron is located at the top of crossbeam, crossbeam and longeron contact position bundle
Prick the fixed pier that formed and lift stand;The distance between adjacent beams are no more than 1m on second shoulder pole girder or the 3rd shoulder pole girder;Its
In, the second round steel suspension rod is located in double-layer rubber fibre pipe, and before lifting, the first round steel suspension rod is used into wire-rope oil
Centralized lubrication;
Step 5: two bridge steel pile tube formworks are given respectively on pier lifting stand, in two bridge steel pile tube formworks
Between the second shoulder pole girder lower section reserve the first safe construction passage, set on other sides of two bridge steel pile tube formworks
Put the second safe construction passage and the first safe construction passage tandem array;
Step 6: correspondence longitudinal direction steel beam position lays lumps of wood cushion block on bed die, and steel is tied up in placement on lumps of wood cushion block
Muscle, meanwhile, the mouth of pipe of the double-layer rubber fibre pipe extended to below longeron outside the first round steel suspension rod is tied up into processing, double-deck rubber
Gap between glue fiber pipe and bed die uses rubber strip encapsulation process;
Step 7: pier is successively poured, when pouring to pier absolute altitude half, the second shoulder pole girder, the 3rd shoulder pole girder, are removed
Two reinforcing bar ropes and internal layer IR fiber pipe, and outer layer rubber fibre pipe is blocked using concreting;
Step 8: when pouring to skirtboard lower section at least 3cm, removing and continuing to pour after skirtboard until completing pier pours work
Industry;
Step 9: removing the first shoulder pole girder and longeron, the second round steel suspension rod is retained in pier.
Preferably, double-layer rubber fibre pipe includes internal layer IR fiber pipe and outer layer rubber fibre pipe, and internal layer rubber is fine
The difference for tieing up the internal diameter of pipe and the diameter of the first round steel suspension rod is 1-3cm;The external diameter of internal layer IR fiber pipe is fine with outer layer rubber
The difference for tieing up the internal diameter of pipe is 2-3cm.
Preferably, it is further comprising the steps of:
The step 3 be additionally included in two the first shoulder pole girders and the second shoulder pole girder and the 3rd shoulder pole girder contact position just on
Side sets up cross buttress brace.
Preferably, two the first shoulder pole girders, the second shoulder pole girder and the 3rd shoulder pole girder use 40a Two bors d's oeuveres I-steel, and
Two the first shoulder pole girders, the second shoulder pole girder and the 3rd shoulder pole girder are welded with the steel pipe and steel plate on two bridge steel pile tubes
It is fixed, and carry out solder joint detection.
Preferably, a diameter of 36mm of the first round steel suspension rod, a diameter of 48mm of the second round steel suspension rod.
Preferably, the height of the skirtboard is 15-30cm, and the thickness of the skirtboard is 20-30mm.
Preferably, the specification of lumps of wood cushion block is 300mm × 500mm × 500mm.
Preferably, the wall thickness of internal layer IR fiber pipe and/or outer layer rubber fibre pipe is 5-10mm.
Preferably, after the completion of pier pours operation in the step 9, by the exposed of the second round steel downrod lower end
Partial Resection, equating.
The present invention at least includes following beneficial effect:
Pier is illustrated by taking two neighboring bridge steel pile tube as an example and hangs bottom technique, if each Steel Tubes For Bridge Application in practice of construction
Stake sets multiple points of stakes, can respectively set the setting of first shoulder pole girder girder steel related to other in a point of stake respectively, with
The need for meeting construction safety;
Skirtboard is used to stablize the first shoulder pole girder, and to set the second shoulder pole girder and the 3rd shoulder pole girder to provide more stable branch
Support, it is to avoid be shifted in assembling process;
The crossbeam vertical with bridge direction is hung by the first round steel suspension rod, afterwards, longeron is arranged on to the top of crossbeam
And it is fixed, formed to tie up between hanging structure, and crossbeam and longeron and fixed there is provided a kind of cross stable support structure, according to
Practice of construction needs, below the formwork for placing of a pier, at least provided with two longerons and four crossbeams, and in two piers
Formwork for placing between at least provided with a crossbeam to support the first safe construction passage;Guarantee personnel's construction safety, raising is applied
Work coefficient;First safe construction passage and the second safe construction passage facilitate personnel's wiretie and concrete construction, protect
Witness person's construction safety, can directly use the parapeted steel wire of shaped steel welded bands on formwork erection lateral wall;
Lumps of wood cushion block is used to, to wiretie is supported, make it have certain distance between bed die, it is ensured that wiretie
The smooth of external protection pours operation;
The second shoulder pole girder, the 3rd shoulder pole girder, crossbeam and the second round steel suspension rod can be removed when pouring to pier absolute altitude half
It is recyclable to recycle, effectively save construction cost;Now, the latter half pier and longeron and the first round steel suspension rod poured
Overall structure be enough to ensure that pier operation smoothly pour completion;And it is retained in the second round steel suspension rod and outer layer rubber in pier
Glue fiber pipe can also improve the intensity for bearing longitudinal shear of pier.
In summary, present invention process, on the basis of the stability of pier lifting stand is improved, two can be completed simultaneously
The pier of individual adjacent bridge steel pile tube hangs bottom operation, and activity level is high, and the two ends of the first shoulder pole girder in operation process, second
On shoulder pole girder, the 3rd shoulder pole girder, crossbeam, longeron and the second round steel suspension rod are recyclable recycles, effectively save construction cost.
Further advantage, target and the feature of the present invention embodies part by following explanation, and part will also be by this
The research and practice of invention and be understood by the person skilled in the art.
Brief description of the drawings
Fig. 1 is the overlooking the structure diagram that pier of the present invention lifts stand;
Fig. 2 is the cross-sectional view of part A in Fig. 1 of the present invention.
Embodiment
The present invention is described in further detail below in conjunction with the accompanying drawings, to make those skilled in the art with reference to specification text
Word can be implemented according to this.
It should be appreciated that such as " having ", "comprising" and " comprising " term used herein do not allot one or many
The presence or addition of individual other elements or its combination.
As shown in Figure 1, 2, the present invention provides a kind of pier and hangs bottom technique, comprises the following steps:
Step 1: being that a pier hangs bill kept on file position with two neighboring bridge steel pile tube 10, in each Steel Tubes For Bridge Application stake top face
Lay steel plate 101 levelling;
Step 2: by two the first shoulder pole girders 102 respectively across bridge to two steel-pipe piles steel plate on, at any one
Corresponding skirtboard 1021 is welded on the lower surface of first shoulder pole girder so that the side wall of skirtboard is fitted with steel-pipe pile lateral wall;
Step 3: the second shoulder pole girder 103 is set up between two the first shoulder pole girders, and the two ends difference of the second shoulder pole girder
It is welded on the middle part of the side of two the first shoulder pole girders;Two the 3rd shoulder pole girders 104 are extended in the both sides of the second shoulder pole girder,
One end of two the 3rd shoulder pole girders is welded on the middle part of the opposite side of two the first shoulder pole girders;So that on each bridge steel pile tube
First shoulder pole girder, the second shoulder pole girder and the 3rd shoulder pole girder are mutually combined across, and stable support is provided subsequently to hang bottom operation;
Step 4: uniformly drilled on the two ends of the first shoulder pole girder, the second shoulder pole girder and on the 3rd shoulder pole girder, it is flat second
The crossbeam 106 that the first round steel suspension rod 105 hangs direction across bridge is worn in the drilling of spreader beam and the 3rd shoulder pole girder, in the first shoulder pole girder two
Worn in the drilling at end the second round steel suspension rod 107 hang bridge to longeron 108;Wherein, longeron be located at crossbeam top, crossbeam and
Tie up the fixed pier that formed and lift stand in longeron contact position;The distance between adjacent beams on second shoulder pole girder or the 3rd shoulder pole girder
No more than 1m;Wherein, the second round steel suspension rod is located in double-layer rubber fibre pipe, and before lifting, the first round steel suspension rod is used
Wire-rope oil centralized lubrication;
Step 5: two bridge steel pile tube formworks are given respectively on pier lifting stand, in two bridge steel pile tube formworks
Between the second shoulder pole girder lower section reserve the first safe construction passage, set on other sides of two bridge steel pile tube formworks
Put the second safe construction passage and the first safe construction passage tandem array;Step 6: corresponding to longitudinal direction steel beam position on bed die
Lumps of wood cushion block is laid, and wiretie is placed on lumps of wood cushion block, meanwhile, by extending to below longeron outside the first round steel suspension rod
The mouth of pipe of double-layer rubber fibre pipe tie up processing, the gap between double-layer rubber fibre pipe and bed die is using at rubber strip sealing
Reason;
Step 7: pier is successively poured, when pouring to pier absolute altitude half, the second shoulder pole girder, the 3rd shoulder pole girder, are removed
Two reinforcing bar ropes and internal layer IR fiber pipe, and outer layer rubber fibre pipe is blocked using concreting;
Step 8: when pouring to skirtboard lower section at least 3cm, removing and continuing to pour after skirtboard until completing pier pours work
Industry;
Step 9: removing the first shoulder pole girder and longeron, the second round steel suspension rod is retained in pier.
In this programme, by taking two neighboring bridge steel pile tube as an example being illustrated pier hangs bottom technique, if every in practice of construction
Individual bridge steel pile tube sets multiple points of stakes, can respectively set first shoulder pole girder girder steel related to other in a point of stake respectively
Setting, the need for meeting construction safety;
Skirtboard is used to stablize the first shoulder pole girder, and to set the second shoulder pole girder and the 3rd shoulder pole girder to provide more stable branch
Support, it is to avoid be shifted in assembling process;
The crossbeam vertical with bridge direction is hung by the first round steel suspension rod, afterwards, longeron is arranged on to the top of crossbeam
And it is fixed, formed to tie up between hanging structure, and crossbeam and longeron and fixed there is provided a kind of cross stable support structure, according to
Practice of construction needs, below the formwork for placing of a pier, at least provided with two longerons and four crossbeams, and in two piers
Formwork for placing between at least provided with a crossbeam to support the first safe construction passage;Guarantee personnel's construction safety, raising is applied
Work coefficient;First safe construction passage and the second safe construction passage facilitate personnel's wiretie and concrete construction, protect
Witness person's construction safety, can directly use the parapeted steel wire of shaped steel welded bands on formwork erection lateral wall;
Lumps of wood cushion block is used to, to wiretie is supported, make it have certain distance between bed die, it is ensured that wiretie
The smooth of external protection pours operation;
The second shoulder pole girder, the 3rd shoulder pole girder, crossbeam and the second round steel suspension rod can be removed when pouring to pier absolute altitude half
It is recyclable to recycle, effectively save construction cost;Now, the latter half pier and longeron and the first round steel suspension rod poured
Overall structure be enough to ensure that pier operation smoothly pour completion;And it is retained in the second round steel suspension rod and outer layer rubber in pier
Glue fiber pipe can also improve the intensity for bearing longitudinal shear of pier.
Pier is hung in bottom technique, and double-layer rubber fibre pipe includes internal layer IR fiber pipe and outer layer rubber fibre pipe, internal layer
The difference of the diameter of the internal diameter of IR fiber pipe and the first round steel suspension rod is 1-3cm;The external diameter and outer layer of internal layer IR fiber pipe
The difference of the internal diameter of IR fiber pipe is 2-3cm.Internal layer IR fiber pipe can protect the first round steel suspension rod, it is to avoid it is by corrosion
Or by Concrete contamination;Due to internal layer IR fiber pipe internal diameter and the first round steel suspension rod diameter difference and internal layer rubber
The difference of the external diameter of glue fiber pipe and the internal diameter of outer layer rubber fibre pipe is smaller, internal layer IR fiber pipe and outer layer rubber fibre pipe
Transition will not be extruded in operation is poured, therefore, outer layer rubber fibre pipe ensure that outer layer fiber pipe and the first round steel are hung
Bar is smoothly extracted, and is reused.
Pier is hung in bottom technique, further comprising the steps of:
The step 3 be additionally included in two the first shoulder pole girders and the second shoulder pole girder and the 3rd shoulder pole girder contact position just on
Side sets up cross buttress brace.Because the second shoulder pole girder and the 3rd shoulder pole girder are on the first shoulder pole girder of welding, to pass through cross
The reinforcing of buttress brace, can improve its overall mechanical stability, it is ensured that construction safety, in addition, pad is located under the first shoulder pole girder
The steel plate of side can also provide certain pad, and the stable support performance of the second shoulder pole girder and the 3rd shoulder pole girder is improved with this.
Pier is hung in bottom technique, and two the first shoulder pole girders, the second shoulder pole girder and the 3rd shoulder pole girder use 40a Two bors d's oeuveres I-shapeds
Steel, and two the first shoulder pole girders, the second shoulder pole girder and the 3rd shoulder pole girder enter with the steel pipe and steel plate on two bridge steel pile tubes
Row is welded and fixed, and carries out solder joint detection.
Pier is hung in bottom technique, a diameter of 36mm of the first round steel suspension rod, a diameter of 48mm of the second round steel suspension rod.
Pier is hung in bottom technique, and the height of the skirtboard is 15-30cm, and the thickness of the skirtboard is 20-30mm.
Pier is hung in bottom technique, and the specification of lumps of wood cushion block is 300mm × 500mm × 500mm.
Pier is hung in bottom technique, and the wall thickness of internal layer IR fiber pipe and/or outer layer rubber fibre pipe is 5-10mm.
Pier is hung in bottom technique, after the completion of pier pours operation in the step 9, by the second round steel downrod lower end
Exposed part excision, equating.
Although embodiment of the present invention is disclosed as above, it is not restricted in specification and embodiment listed
With it can be applied to various suitable the field of the invention completely, can be easily for those skilled in the art
Other modification is realized, therefore under the universal limited without departing substantially from specification and equivalency range, the present invention is not limited to
Specific details and shown here as the legend with description.
Claims (9)
1. a kind of pier hangs bottom technique, it is characterised in that comprise the following steps:
Step 1: hanging bill kept on file position by a pier of two neighboring bridge steel pile tube, steel is laid in each Steel Tubes For Bridge Application stake top face
Plate is levelling;
Step 2: by two the first shoulder pole girders respectively across bridge to two steel-pipe piles steel plate on, it is first flat at any one
Corresponding skirtboard is welded on the lower surface of spreader beam so that the side wall of skirtboard is fitted with steel-pipe pile lateral wall;
Step 3: the second shoulder pole girder is set up between two the first shoulder pole girders, and the two ends of the second shoulder pole girder are respectively welded at
The middle part of the side of two the first shoulder pole girders;Two the 3rd shoulder pole girders, two the 3rd are extended in the both sides of the second shoulder pole girder
One end of shoulder pole girder is welded on the middle part of the opposite side of two the first shoulder pole girders;
Step 4: uniformly being drilled on the two ends of the first shoulder pole girder, the second shoulder pole girder and on the 3rd shoulder pole girder, in the second shoulder pole girder
The crossbeam that the first round steel suspension rod hangs direction across bridge is worn in drilling with the 3rd shoulder pole girder, in the drilling at the first shoulder pole girder two ends
Wear the second round steel suspension rod hang bridge to longeron;Wherein, longeron is located at the top of crossbeam, and crossbeam and longeron contact position are tied up solid
It is shaped as pier lifting stand;The distance between adjacent beams are no more than 1m on second shoulder pole girder or the 3rd shoulder pole girder;Wherein,
Two round steel suspension rods are located in double-layer rubber fibre pipe, and before lifting, the first round steel suspension rod is concentrated using wire-rope oil
Lubrication;
Step 5: two bridge steel pile tube formworks are given respectively on pier lifting stand, between two bridge steel pile tube formworks
The lower section of the second shoulder pole girder reserve the first safe construction passage, the is set on other sides of two bridge steel pile tube formworks
Two safe construction passages and the first safe construction passage tandem array;
Step 6: correspondence longitudinal direction steel beam position lays lumps of wood cushion block on bed die, and wiretie is placed on lumps of wood cushion block, together
When, the mouth of pipe of the double-layer rubber fibre pipe extended to below longeron outside the first round steel suspension rod is tied up into processing, double-layer rubber is fine
Gap between dimension pipe and bed die uses rubber strip encapsulation process;
Step 7: pier is successively poured, when pouring to pier absolute altitude half, the second shoulder pole girder, the 3rd shoulder pole girder, the second steel are removed
Muscle rope and internal layer IR fiber pipe, and outer layer rubber fibre pipe is blocked using concreting;
Step 8: when pouring to skirtboard lower section at least 3cm, removing and continuing to pour after skirtboard until completing pier pours operation;
Step 9: removing the first shoulder pole girder and longeron, the second round steel suspension rod is retained in pier.
2. pier as claimed in claim 1 hangs bottom technique, it is characterised in that double-layer rubber fibre pipe includes internal layer IR fiber
The difference of the diameter of pipe and outer layer rubber fibre pipe, the internal diameter of internal layer IR fiber pipe and the first round steel suspension rod is 1-3cm;Internal layer
The difference of the external diameter of IR fiber pipe and the internal diameter of outer layer rubber fibre pipe is 2-3cm.
3. pier as claimed in claim 1 hangs bottom technique, it is characterised in that further comprising the steps of:
The step 3 is additionally included in two the first shoulder pole girders and the second shoulder pole girder and the surface frame of the 3rd shoulder pole girder contact position
If cross buttress brace.
4. pier as claimed in claim 1 hangs bottom technique, it is characterised in that two the first shoulder pole girders, the second shoulder pole girders and
Three shoulder pole girders use 40a Two bors d's oeuveres I-steel, and two the first shoulder pole girders, the second shoulder pole girder and the 3rd shoulder pole girder with two bridges
Steel pipe and steel plate on joist steel pile tube are welded and fixed, and carry out solder joint detection.
5. pier as claimed in claim 1 hangs bottom technique, it is characterised in that a diameter of 36mm of the first round steel suspension rod, second
A diameter of 48mm of round steel suspension rod.
6. pier as claimed in claim 1 hangs bottom technique, it is characterised in that the height of the skirtboard is 15-30cm, the skirt
The thickness of plate is 20-30mm.
7. pier as claimed in claim 1 hangs bottom technique, it is characterised in that the specification of lumps of wood cushion block be 300mm × 500mm ×
500mm。
8. pier as claimed in claim 1 hangs bottom technique, it is characterised in that internal layer IR fiber pipe and/or outer layer rubber are fine
The wall thickness for tieing up pipe is 5-10mm.
9. pier as claimed in claim 1 hangs bottom technique, it is characterised in that pier pours operation completion in the step 9
Afterwards, by exposed part excision, the equating of the second round steel downrod lower end.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710457201.8A CN107227688B (en) | 2017-06-16 | 2017-06-16 | Pier hangs bottom technique |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710457201.8A CN107227688B (en) | 2017-06-16 | 2017-06-16 | Pier hangs bottom technique |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107227688A true CN107227688A (en) | 2017-10-03 |
CN107227688B CN107227688B (en) | 2019-02-12 |
Family
ID=59936422
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710457201.8A Active CN107227688B (en) | 2017-06-16 | 2017-06-16 | Pier hangs bottom technique |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107227688B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109537431A (en) * | 2018-11-19 | 2019-03-29 | 上海建工五建集团有限公司 | Plank road structure and method waterborne |
CN109972519A (en) * | 2019-03-06 | 2019-07-05 | 安徽省公路桥梁工程有限公司 | The construction method of precast hollow pier mounting structure |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2010007365A (en) * | 2008-06-27 | 2010-01-14 | Taisei Corp | Form timbering apparatus and form apparatus |
CN102154989A (en) * | 2011-04-29 | 2011-08-17 | 中铁大桥局集团第六工程有限公司 | Steel-concrete structure hanging box and dismantling method thereof |
CN202359506U (en) * | 2011-12-15 | 2012-08-01 | 中交四航局第一工程有限公司 | Double hoop supporting system for pier column capping beam |
CN105926532A (en) * | 2016-05-25 | 2016-09-07 | 中交第航务工程局有限公司 | Technology for constructing shoulder pole beam reversely-suspended bottom on abutment |
CN106638588A (en) * | 2017-01-18 | 2017-05-10 | 中交航局第工程有限公司 | Steel pipe pile cap bottom lifting device and mounting method thereof |
-
2017
- 2017-06-16 CN CN201710457201.8A patent/CN107227688B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2010007365A (en) * | 2008-06-27 | 2010-01-14 | Taisei Corp | Form timbering apparatus and form apparatus |
CN102154989A (en) * | 2011-04-29 | 2011-08-17 | 中铁大桥局集团第六工程有限公司 | Steel-concrete structure hanging box and dismantling method thereof |
CN202359506U (en) * | 2011-12-15 | 2012-08-01 | 中交四航局第一工程有限公司 | Double hoop supporting system for pier column capping beam |
CN105926532A (en) * | 2016-05-25 | 2016-09-07 | 中交第航务工程局有限公司 | Technology for constructing shoulder pole beam reversely-suspended bottom on abutment |
CN106638588A (en) * | 2017-01-18 | 2017-05-10 | 中交航局第工程有限公司 | Steel pipe pile cap bottom lifting device and mounting method thereof |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109537431A (en) * | 2018-11-19 | 2019-03-29 | 上海建工五建集团有限公司 | Plank road structure and method waterborne |
CN109972519A (en) * | 2019-03-06 | 2019-07-05 | 安徽省公路桥梁工程有限公司 | The construction method of precast hollow pier mounting structure |
Also Published As
Publication number | Publication date |
---|---|
CN107227688B (en) | 2019-02-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106758841B (en) | A kind of whole construction process of the double rope face low-pylon cable-stayed bridges of double tower | |
CN102031784B (en) | Slope protection pile pouring and cable bolting construction method for deep foundation pit | |
CN108505433B (en) | Pier structure and construction method thereof | |
CN112982181B (en) | Construction method for steel-concrete combined section of through-type steel box continuous arch bridge | |
CN108660935A (en) | A kind of construction method of reinforced concrete arch bridge | |
CN109778721A (en) | Synchronization of jacking up bridge top and the bottom structure carries out the method that bridge increases transformation | |
CN107841953B (en) | High-altitude oblique crossing Liang Doupo side span cast-in-situ section construction support and construction method | |
CN110080525B (en) | Bidirectional synchronous construction method for high-rise building | |
CN106869012B (en) | Using the prefabricated thin-wall bent cap of prestressing with bond system | |
CN103603359A (en) | Deep foundation pit diagonal bracing support structure demolition method | |
CN108005094B (en) | Pier and pier top beam section construction method in naked rock river bed water | |
CN110863498A (en) | Deep foundation pit combined supporting construction method next to subway station | |
CN108004925A (en) | Prestress reinforced concrete circular arch tower construction method | |
CN114892552B (en) | Box girder type bridge reconstruction construction method | |
CN103184722A (en) | Large-span double-layer Bailey truss structure and construction method thereof | |
CN101469533A (en) | Pier top supportless temporary consolidation technique | |
CN107227688B (en) | Pier hangs bottom technique | |
CN205242278U (en) | A triangle string basket method is hanged and is watered device for deck bridge construction | |
CN106988333A (en) | The prefabricated cushion cap and its construction technology of core are filled with joint bar | |
CN106320192A (en) | Beam section replacement reinforcement method for large-span concrete continuous beam bridge | |
CN107130521B (en) | Method for constructing large-section beam bailey bracket hoisting mold of pit cliff wall section | |
CN106381810B (en) | With the cast-in-place outstanding method for filling beam of beam-column type bracket | |
CN107724252B (en) | A kind of continuous box girder hanging basket cantilever method construction | |
CN216515083U (en) | High bridge cushion cap structure of filling | |
CN102493363A (en) | Quick construction method for segment No.0 of continuous beam |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |