CN107194545A - Exhibitions project cost analysis method - Google Patents

Exhibitions project cost analysis method Download PDF

Info

Publication number
CN107194545A
CN107194545A CN201710296374.6A CN201710296374A CN107194545A CN 107194545 A CN107194545 A CN 107194545A CN 201710296374 A CN201710296374 A CN 201710296374A CN 107194545 A CN107194545 A CN 107194545A
Authority
CN
China
Prior art keywords
cost
exhibitions
project
bar
control
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710296374.6A
Other languages
Chinese (zh)
Inventor
周健华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing University of Arts and Sciences
Original Assignee
Chongqing University of Arts and Sciences
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing University of Arts and Sciences filed Critical Chongqing University of Arts and Sciences
Priority to CN201710296374.6A priority Critical patent/CN107194545A/en
Publication of CN107194545A publication Critical patent/CN107194545A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0637Strategic management or analysis, e.g. setting a goal or target of an organisation; Planning actions based on goals; Analysis or evaluation of effectiveness of goals

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Educational Administration (AREA)
  • Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Development Economics (AREA)
  • Game Theory and Decision Science (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses the exhibitions project cost analysis method in exhibitions area of activities, including fixed cost analysis and variable cost analysis, fixed cost and variable cost are analyzed respectively, fixed cost is analyzed by scale forecast and human cost control, by in advance, in thing, the control of management and fixed cost to variable cost afterwards, statistics carries out the analysis and Control of variable cost, finally analyzed using standard cost variance, reflect that actual cost departs from the information of predeterminated target degree objective reality, find out reason and counter-measure, cost analysis preferably can be carried out to exhibitions project, promote the development of exhibitions economic heath.

Description

Exhibitions project cost analysis method
Technical field
The present invention relates to exhibitions area of activities, and in particular to a kind of exhibitions project cost analysis method.
Background technology
Exhibitions is meeting, exhibition, the activity of section thing, the abbreviation of sports activity.At present, China's exhibition industry growth momentum phase When swift and violent, it has also become Modern Urban Development, the boost motor of Regional Economic Development.As exhibitions itself, there is also benefit most Bigization principle.How exhibitions project cost is carried out effectively analyzing and controlling, reaches exhibitions income and economic results in society doulbe-sides' victory, It is that the problem that emphasis is solved is needed in development exhibition economy.
The content of the invention
The invention is intended to provide exhibitions project cost analysis method, to carry out cost analysis to exhibitions project.
To reach above-mentioned purpose, basic technology scheme of the invention is as follows:Exhibitions project cost analysis method, including:
A, fixed cost analytical procedure;
B, variable cost analytical procedure;
The fixed cost analytical procedure includes:
A1, human cost control;
A2, scale forecast, including personnel, fund and equipment are determined after analyzing historical summary, market conditions, security context Input, in exhibitions venue arrange people's flow control device;
The step B includes:
B1, Prior Control, in exhibitions project implementation early stage, to number of participants, exhibiter's quantity and exhibition area are predicted;
B2, mid-event control, build account to the fragmentary sub-category registration of expenditure progress in exhibitions Project Process is carried out, pass through people's flow control Cost consumption during equipment pair is controlled and counted;
B3, control afterwards, what the variable cost that exhibitions project is obtained after terminating according to fixed cost with statistics was actually occurred Cost, the cost actually occurred is compared with estimated cost and carries out cost control supervision.
This programme is divided into fixed cost and variable cost by that will open up project cost, respectively to fixed cost and variable Cost is analyzed, and fixed cost is analyzed by scale forecast and human cost control, by advance, in thing, afterwards Management and fixed cost the analysis and Control of variable cost is carried out to the control of variable cost, statistics, finally using standard costs Variance analysis, reflects that actual cost departs from the information of predeterminated target degree objective reality, finds out reason and counter-measure, can be compared with Good carries out cost analysis to exhibitions project, promotes the development of exhibitions economic heath.
Preferred scheme one, as an improvement, the data of three exhibitions activities nearest to similar exhibitions project is carried out in step A2 Collect and survey, the scale of exhibitions project is predicted according to data feedack, according to scale forecast feedack pair Personnel amount, place scale and fund input are selected.Market situation can be understood by analysis of history data, this Sample estimates the personnel amount of selection, fund input etc. and has more foundation property, more rationally.
Preferred scheme two, as an improvement, in B1 steps, the market propaganda first is carried out to exhibitions project and information for intention is collected, Number of participants, exhibiter's quantity and exhibition area are predicted according to information for intention, with reference to the result in A2 steps to exhibitions The cost of project carries out budget, obtains estimated cost.It can be grasped in time by the way that information for intention is publicized and collected to market Market actual conditions, the anticipation to the scale of attending a meeting is more accurate, is easy to be controlled the fixed cost of exhibitions project.
Preferred scheme three, as an improvement, people's flow control device in A2 steps include guidance device, flow monitoring device and Carrier frequency channel break device, builds walkway in exhibitions venue by carrier frequency channel break device, refers in the overhung of walkway Leading-in device, the guidance device is LED display board.The activity of exhibitions venue one skilled in the art, control correspondence are guided by guidance device Cost of labor, flow monitoring device is monitored to flow of the people in venue, is easy to understand exhibitions activity in exhibitions venue in real time The scale of construction, the flow of the people in exhibitions venue is controlled by carrier frequency channel break device on this basis, by controlling flow of the people Realize the control to venue use cost, other cost inputs so that exhibitions project cost analysis and Control is more facilitated.
Preferred scheme four, as an improvement, route denial device includes circular base, chassis interior is fixed with motor, electricity Wireless signal switch is connected with electromechanical source line, the rotating shaft of motor is set upward, and master bevel gear, base upper end are fixed with rotating shaft Coaxial pillar is rotatably connected to, the inner hollow of pillar is set, and pillar bottom is fixedly connected with rotating shaft, along axis pair on pillar Claim to be provided with blocking bar, support bar and groove, the top of blocking bar is rotatably connected on pillar top, and support bar includes interior bar and outer Bar, outer bar inner hollow is simultaneously fixed with interior stage clip, is fixedly connected in interior bar bottom insertion outer bar and with interior stage clip;The bottom of outer bar It is connected to by integrally formed axis of rotation between the side wall of groove, the secondary umbrella tooth engaged with master bevel gear is fixed with rotating shaft Stage clip is fixedly connected between pillar and outer bar above wheel, rotating shaft, the upper end of interior bar is slidably connected on blocking bar.Base is made For support location structure, motor is as power source, and pillar is blocking bar, support bar provides support, and groove is used to accommodate blocking bar And support bar, support bar be used for blocking bar is supported and adjusted, pass through the engaged transmission pair of secondary bevel gear and master bevel gear The lifting of blocking bar is controlled, and is so realized the lifting and rotation of blocking bar by the operating of motor, is realized by blocking bar The control of walkway, is easy to control the stream of people in exhibitions venue.
Preferred scheme five, as an improvement, flow monitoring device is Radio infrared stream of people's batching counter, the Radio infrared people Flowmeter counter is fixed on the route denial device of the gateway of exhibitions venue and walkway infall.So set and be easy to Flow of the people in exhibitions venue is monitored in real time, is easy to accordingly be controlled stream of people's cost.
Preferred scheme six, as an improvement, B2 steps include collecting the number of Radio infrared people stream counting device by computer According to, the walkway in venue is adjusted by analyze data, to route denial equipment and indexing plate send signal carry out The blocking of exhibitions venue one skilled in the art's passage.So by being automatically adjusted to the walkway in exhibitions venue before the guiding stream of people Enter, the service wear cost of control venue and equipment controls the human cost of guiding, cost analysis is more facilitated accurate.
Brief description of the drawings
Fig. 1 is the structural representation of route denial device in the embodiment of the present invention.
Embodiment
Below by embodiment, the present invention is further detailed explanation:
Reference in Figure of description includes:Base 1, pillar 2, motor 3, output shaft 31, master bevel gear 4, outer bar 5, turn Axle 51, interior bar 6, blocking bar 7, secondary bevel gear 8, wireless signal switch 9.
Embodiment:Exhibitions project cost analysis method, including:
1st, human cost is controlled, and is needed to carry out personnel selection in enterprises according to exhibitions project, according to department and post setting Staff number is determined, personnel and hilllock is realized.
2nd, scale forecast, including determine after analyzing historical summary, market conditions, security context personnel, fund and The input of equipment, arranges people's flow control device in exhibitions venue;People's flow control device includes guidance device, flow monitoring device With carrier frequency channel break device, walkway is built in exhibitions venue by carrier frequency channel break device, in the overhung of walkway Guidance device, guidance device is LED display board.As shown in figure 1, route denial device is included inside circular base 1, base 1 It is fixed with motor 3, the power line of motor 3 and is connected with wireless signal switch 9, the output shaft 31 of motor 3 is set upward, output shaft 31 On be fixed with master bevel gear 4, the upper end of base 1 is rotatably connected to coaxial pillar 2, and the inner hollow of pillar 2 is set, the bottom of pillar 2 End is fixedly connected with output shaft 31, and blocking bar 7, support bar and groove, the top of blocking bar 7 are provided with along axisymmetrical on pillar 2 The top of pillar 2 is rotatably connected on, support bar includes interior bar 6 and outer bar 5, and the inner hollow of outer bar 5 is simultaneously fixed with interior stage clip, interior bar 6 It is fixedly connected in bottom insertion outer bar 5 and with interior stage clip;The bottom of outer bar 5 is rotatably connected on recessed by integrally formed rotating shaft 51 Between the side wall of groove, the secondary bevel gear 8 engaged with master bevel gear 4, the pillar 2 and outer bar of the top of rotating shaft 51 are fixed with rotating shaft 51 Stage clip is fixedly connected between 5, the upper end of interior bar 6 is slidably connected on blocking bar 7.Flow monitoring device is the Radio infrared stream of people Batching counter, Radio infrared stream of people's batching counter is fixed on the gateway of exhibitions venue and the route denial of walkway infall On device.
3rd, Prior Control, in exhibitions project implementation early stage, first carries out the market propaganda to exhibitions project and collects information for intention, According to information for intention to number of participants, exhibiter's quantity and exhibition area be predicted, with reference in step 2 to personnel, fund and The input result of equipment carries out budget to the cost of exhibitions project, obtains estimated cost.
4th, mid-event control, account is built in exhibitions Project Process is carried out to the fragmentary sub-category registration of expenditure progress;By calculating Machine collects the data of Radio infrared people stream counting device, and the flow of the people in venue is counted by analyze data and judges to cause Venue use cost and personnel's input cost, judge whether to accordingly flow of the people control with cost of implementation control.Pass through meter The wireless signal switch 9 that calculation machine is sent to route denial equipment and indexing plate on signal, route denial device receives signal control Motor 3 processed is operated, and motor 3 drives pillar 2 to rotate the swing for carrying out blocking bar 7, and pillar 2, which is rotated, causes master bevel gear 4 to drive pair Bevel gear 8 is rotated, and secondary bevel gear 8, which is rotated, causes outer bar 5 to be rotated to groove, and outer bar 5, which is rotated, drives interior bar 6 to enter inside outer bar 5 And one groove in the same direction swing, drive blocking bar 7 to be drawn in pillar 2 in the swing process of interior bar 6, such blocking bar 7 commutates swinging While be in rounding state, for realizing that the blocking of passage more facilitates in the more exhibitions environment of personnel, enter row of channels resistance Pedestrian around will not be impacted when disconnected, so carry out the blocking of exhibitions venue one skilled in the art's passage, the personnel to during live The cost consumption of movable property life is controlled.
5th, control afterwards, the variable cost that exhibitions project is obtained after terminating according to fixed cost with statistics is actually occurred Cost, by the cost actually occurred compared with estimated cost progress cost control supervision.
This programme is divided into fixed cost and variable cost by that will open up project cost, respectively to fixed cost and variable Cost is analyzed, and fixed cost is analyzed by scale forecast and human cost control, by advance, in thing, afterwards Management and fixed cost the analysis and Control of variable cost is carried out to the control of variable cost, statistics, finally using expected cost Variance analysis, reflects that actual cost departs from the information of predeterminated target degree objective reality, finds out reason and counter-measure, can be compared with Good carries out cost analysis to exhibitions project, promotes the development of exhibitions economic heath.
Above-described is only that the known general knowledge such as concrete structure and/or characteristic is herein in embodiments of the invention, scheme Excessive description is not made.It should be pointed out that for those skilled in the art, without departing from the structure of the invention, also Several modifications and improvements can be made, these should also be considered as protection scope of the present invention, these are real all without the influence present invention The effect and practical applicability applied.The scope of protection required by this application should be based on the content of the claims, specification In embodiment etc. record the content that can be used for explaining claim.

Claims (7)

1. exhibitions project cost analysis method, it is characterised in that including:
A, fixed cost analytical procedure;
B, variable cost analytical procedure;
The fixed cost analytical procedure includes:
A1, human cost control;
A2, scale forecast, including personnel, fund and equipment are determined after analyzing historical summary, market conditions, security context Input, in exhibitions venue arrange people's flow control device;
The step B includes:
B1, Prior Control, in exhibitions project implementation early stage, to number of participants, exhibiter's quantity and exhibition area are predicted;
B2, mid-event control, build account to the fragmentary sub-category registration of expenditure progress in exhibitions Project Process is carried out, pass through people's flow control Cost consumption during equipment pair is controlled and counted;
B3, control afterwards, what the variable cost that exhibitions project is obtained after terminating according to fixed cost with statistics was actually occurred Cost, the cost actually occurred is compared with estimated cost and carries out cost control supervision.
2. exhibitions project cost analysis method according to claim 1, it is characterised in that:To similar meeting in the step A2 The data of the nearest three exhibitions activities of exhibition item mesh is collected analysis, and the scale of exhibitions project is entered according to data feedack Row prediction, is selected personnel amount, place scale and fund input according to scale forecast feedack.
3. exhibitions project cost analysis method according to claim 2, it is characterised in that:In the B1 steps, first to meeting Exhibition item mesh carries out the market propaganda and collects information for intention, according to information for intention to number of participants, exhibiter's quantity and exhibition area It is predicted, budget is carried out to the cost of exhibitions project with reference to the result in A2 steps, estimated cost is obtained.
4. exhibitions project cost analysis method according to claim 3, it is characterised in that:Stream of people's control in the A2 steps Control equipment include guidance device, flow monitoring device and carrier frequency channel break device, by carrier frequency channel break device in exhibitions venue structure Walkway is built, in the overhung guidance device of walkway, the guidance device is LED display board.
5. exhibitions project cost analysis method according to claim 4, it is characterised in that:The route denial device includes Circular base, chassis interior, which is fixed with motor, motor power-supply wire, is connected with wireless signal switch, and the rotating shaft of motor is set upward Put, master bevel gear is fixed with rotating shaft, base upper end is rotatably connected to coaxial pillar, and the inner hollow of pillar is set, pillar Bottom is fixedly connected with rotating shaft, and blocking bar, support bar and groove are provided with along axisymmetrical on pillar, and the top of blocking bar, which is rotated, to be connected Pillar top is connected on, support bar includes interior bar and outer bar, and outer bar inner hollow is simultaneously fixed with interior stage clip, interior bar bottom insertion outer bar It is interior and be fixedly connected with interior stage clip;The bottom of outer bar is connected between the side wall of groove by integrally formed axis of rotation, is turned Stage clip is fixedly connected between the pillar and outer bar that are fixed with axle above the secondary bevel gear engaged with master bevel gear, rotating shaft, it is interior The upper end of bar is slidably connected on blocking bar.
6. exhibitions project cost analysis method according to claim 5, it is characterised in that:The flow monitoring device is nothing The infrared stream of people's batching counter of line, the Radio infrared stream of people batching counter is fixed on the gateway of exhibitions venue and walkway is handed over On route denial device at fork.
7. exhibitions project cost analysis method according to claim 6, it is characterised in that:The B2 steps include passing through Computer collects the data of Radio infrared people stream counting device, and the walkway in venue is adjusted by analyze data, given Route denial equipment and indexing plate send the blocking that signal carries out exhibitions venue one skilled in the art's passage.
CN201710296374.6A 2017-04-28 2017-04-28 Exhibitions project cost analysis method Pending CN107194545A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710296374.6A CN107194545A (en) 2017-04-28 2017-04-28 Exhibitions project cost analysis method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710296374.6A CN107194545A (en) 2017-04-28 2017-04-28 Exhibitions project cost analysis method

Publications (1)

Publication Number Publication Date
CN107194545A true CN107194545A (en) 2017-09-22

Family

ID=59873399

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710296374.6A Pending CN107194545A (en) 2017-04-28 2017-04-28 Exhibitions project cost analysis method

Country Status (1)

Country Link
CN (1) CN107194545A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109886738A (en) * 2019-01-30 2019-06-14 杭州大橙知一科技有限公司 A kind of intelligence exhibition user in predicting method and apparatus
CN109903085A (en) * 2019-01-30 2019-06-18 杭州大橙知一科技有限公司 A kind of intelligence exhibition advertisement dispensing and equipment
CN117829648A (en) * 2023-12-25 2024-04-05 广州市高艺创展展览工程有限公司 Exhibition engineering intelligent monitoring method, system and medium based on big data

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109886738A (en) * 2019-01-30 2019-06-14 杭州大橙知一科技有限公司 A kind of intelligence exhibition user in predicting method and apparatus
CN109903085A (en) * 2019-01-30 2019-06-18 杭州大橙知一科技有限公司 A kind of intelligence exhibition advertisement dispensing and equipment
CN109903085B (en) * 2019-01-30 2021-10-12 杭州灿八科技有限公司 Intelligent exhibition advertisement delivery and equipment
CN109886738B (en) * 2019-01-30 2021-11-02 杭州灿八科技有限公司 Intelligent exhibition user prediction method and equipment
CN117829648A (en) * 2023-12-25 2024-04-05 广州市高艺创展展览工程有限公司 Exhibition engineering intelligent monitoring method, system and medium based on big data

Similar Documents

Publication Publication Date Title
CN107194545A (en) Exhibitions project cost analysis method
CN204706061U (en) Intelligent parking lot management system
CN111682639A (en) Power distribution room full-perception monitoring operation and maintenance system and method based on wireless multi-hop network
CN107369335B (en) A kind of reverse vehicle searching system and method based on ultrasonic listening technology
CN104318787B (en) A kind of method that improves lapping phases crossing space resources utilization ratio
CN201918030U (en) Parking management system for parking lot
CN103150924A (en) Underground parking place parking-guidance system
CN105513362B (en) A kind of bus platform adjacent area bus running state evaluation verification method
CN107610511A (en) A kind of reverse vehicle searching system and method for merging ultrasonic listening and IMAQ
CN107417091A (en) Mechanism for sorting for glass fibre wire drawing machine
CN107015566A (en) A kind of multirobot detecting system based on LabVIEW
CN112233003A (en) Green intelligent passenger station system and integration method
CN205486855U (en) Parking stall guide and reverse car system of seeking
CN112183771A (en) Intelligent operation and maintenance ecosystem for rail transit and operation method thereof
CN109544925B (en) Coordination trunk line rationality analysis and coordination mode configuration method
CN101787980A (en) Energy saving system for jet fan
WO2015162652A1 (en) Traffic system optimization device
CN104408919A (en) Manual road traffic parameter investigation system based on mobile intelligent terminal
CN108639062A (en) A kind of Vehicular intelligent control system
CN105787203A (en) Method for predicting whether longitude and latitude information of community is abnormal
CN116703087A (en) Prefabrication and assembly construction integrated management system
CN115423367A (en) Intelligent environmental sanitation management system and method based on AIOT platform
CN107767568A (en) A kind of gas meter data interactive method and device
CN206097196U (en) Parking information collection system
CN110942255B (en) Highway engineering management system and method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170922