CN107190861A - A kind of contrary sequence method template construction technique - Google Patents

A kind of contrary sequence method template construction technique Download PDF

Info

Publication number
CN107190861A
CN107190861A CN201710598368.6A CN201710598368A CN107190861A CN 107190861 A CN107190861 A CN 107190861A CN 201710598368 A CN201710598368 A CN 201710598368A CN 107190861 A CN107190861 A CN 107190861A
Authority
CN
China
Prior art keywords
template
steel pipe
diagonal brace
column
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710598368.6A
Other languages
Chinese (zh)
Inventor
庄福臣
于金龙
包喜庆
郑秀杰
杨泽鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201710598368.6A priority Critical patent/CN107190861A/en
Publication of CN107190861A publication Critical patent/CN107190861A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • E04B1/3505Extraordinary methods of construction, e.g. lift-slab, jack-block characterised by the in situ moulding of large parts of a structure
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/02Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for rooms as a whole by which walls and floors are cast simultaneously, whole storeys, or whole buildings

Abstract

The invention discloses a kind of contrary sequence method template construction technique, comprise the following steps that:Step one, surveying setting-out;Step 2, formwork bracing system is set up;Step 3, the installation of Liangping platform and plate platform template;Step 4, the installation of column template;Step 5, the installation of wall form;Step 6, the installation of stair template.The working face crossings on different level of carpenter and bar bender in the technique, synchronous to carry out respective operation, procedure arrangement is compact, and carpenter and bar bender can work continuously the not work holdup, and speed of application is quick;The stirrup sealed afterwards at column template and wall form, bean column node is banded with enough working faces, it is ensured that the quality of bean column node position stirrup colligation;It can be poured using concrete one piece, reduce staying for horizontal construction joint and set;During timber work, the saw foam and garbage energy that beam, plate leave are cleaned out with hair-dryer in time, it is ensured that no debris is retained in template in reinforcing bar process of binding, improves concrete pouring quality.

Description

A kind of contrary sequence method template construction technique
Technical field
The present invention relates to building field, specifically a kind of contrary sequence method template construction technique.
Background technology
With China various regions Daxing building, architectural engineering turns into popular industry again, and construction material is the basis of architectural engineering, Construction material can be divided into structural material, ornament materials and some proprietary materials.Structural material includes timber, bamboo wood, stone material, water Mud, concrete, metal, brick and tile, ceramics, glass, engineering plastics, composite etc.;Ornament materials include various coating, paint, Coating, veneer, assorted ceramic tile, glass with special-effect etc.;Proprietary material refers to for waterproof, protection against the tide, anti-corrosion, fire prevention, resistance Combustion, sound insulation, heat-insulated, insulation, sealing etc..
Concrete structure needs to reach clear-water concrete effect in building, and the type selecting of template system is related to this engineering Construction speed and the key for reaching structure " high-quality main body " credit rating realization of goal, the wood of existing template system when mounted Work can not continuously be constructed with bar bender, and operating efficiency is slow, spends the time long, has debris to retain in template, to follow-up concrete Pouring quality has an impact, and this just brings inconvenience for people.
The content of the invention
It is an object of the invention to provide a kind of contrary sequence method template construction technique, to solve what is proposed in above-mentioned background technology Problem.
To achieve the above object, the present invention provides following technical scheme:
A kind of contrary sequence method template construction technique, is comprised the following steps that:
Step one, surveying setting-out:Set up axial control network between floors with " internal control method ", pilot measurement to construction floor, The axis of each axle of construction layer building is delivered out according to construction drawing, according to completed plane axis gauze, post position and beam is released Position frame line, 500mm positions release post control line and beam control line on the outside of its sideline, absolute altitude by bottom absolute altitude control point up Successively transmit, directly copy absolute altitude in the post cage bar tied up, each post cage bar there must be two reliefs;
Step 2, formwork bracing system is set up:Floor framework axis spacing is 7.8 meters, the both sides of floor framework axis Framed bent is provided with 0.6 meter, framed bent uses row's vertical rod, and row's spacing of vertical rod is 7.8 meters, and the border of floor frame column is first reduced One row's disk buckle type scaffold, then carries out installing for post template, then be fixed on disk buckle type scaffold with steel pipe and cruciform fastening for falsework On, the U-shaped jacking of steel tube head is used for the diagonal brace for reinforcing pillar on the outside of template, and the vertical spacing of diagonal brace is 200mm, diagonal brace Level interval be 400mm, then to it is U-shaped support carry out top elevation vertical rod highly adjust, on the steel pipe at the beam bottom of floor framework Lay and beam bottom plate is laid on 50*100mm flitches, flitch, the spacing at beam bottom, which is not more than at 1000mm, is provided with vertical rod, floor framework Outermost surrounding sets the elongated bridging of vertical continous way from the bottom to top, and the centre of floor framework is vertically and horizontally being set every 10M It is equipped with vertical continous way bridging from the bottom to top and horizontal cross brace is set at the bar of sweeping the floor at the top of bridging, vertically connects The bottom of continuous formula bridging is held out against with ground and in 45-60 degree angles;
Step 3, the installation of Liangping platform and plate platform template:Beam form is positioned, the fixed of adjacent forms is carried out, then carried out The installation of beam column wall mouth template, carries out the cleaning of template surface debris, then install beam forms by beam muscle and carry out bed die Arch;
Step 4, the installation of column template:Bar bender carries out the colligation of beam steel and slab muscle in upper strata working face, while wooden Work carries out the installation and reinforcing of wall form and column template in lower floor's working face, and wall form and column template are previously positioned at into wall column phase Answer position side, beam bottom and beam side primary and secondary is stupefied is attached to away from 150mm, the support system of column template uses φ on the outside of wall column formwork 48mm diagonal brace steel pipe, each face of column template sets twice diagonal brace steel pipe and diagonal brace steel pipe is withstood on away from post mould by bar of sweeping the floor On edges of boards edge 2M φ 32mm pre-buried ground dowel, the middle part of diagonal brace steel pipe sets horizontal steel pipe reverse drawing steel pipe with together with together;
Step 5, the installation of wall form:The big face wall template opsition dependent line lifting in side is in place, diagonal brace is installed and adjusted to wall Template, on 75 degree and the stable located reference plane of wall form, is fixed with ground, installs through walls on wall form temporarily Bolt and fix plastic bushing, inside cleaning wall form, using the wall form of same step opposite side in place, adjust both walls Position, plumbness and the diagonal brace angle of template, then fixed and fastening diagonal brace, fasten the nut of through-wall bolt;Using same The step of adjacent wall form and angle mould are installed, using steel pipe supporting system support and check;
Step 6, the installation of stair template:Platform template is installed, then installs stair end template, check of staircase is then installed, Eject stair base plate thickness line and the side plate position line on the inside of check of staircase, side form, kick step template and template of marking time is processed by figure It is molded and Assembling, stair template support system uses and is provided with one of cross-tie in the middle of diagonal brace steel pipe, diagonal brace steel pipe, Side form is fixed using 50*100mm wooden a tree, used in making timber for boats.
It is used as further scheme of the invention:The quantity at absolute altitude control point is not less than 3 in step one.
It is used as further scheme of the invention:Vertical rod buckles steel pipe scaffold using φ 48 × 3.5 disk, and vertical rod spacing is 900mm × 900mm, horizontal step pitch is 1200mm, and the spiral screw thread of U-shaped support is highly not more than 250mm, and top joist uses φ 48 Vertical rod support is added in the middle part of × 3.5mm double steel pipe, beam bottom, height is no more than 300mm to girt from the ground.
It is used as further scheme of the invention:Diagonal brace uses steel pipe or the lumps of wood, and bridging includes steel pipe and fastener, vertically connected The width of continuous formula bridging is 4-6M.
It is used as further scheme of the invention:A U-shaped support is set up in the bottom of disk buckle type scaffold.
Compared with prior art, the beneficial effects of the invention are as follows:The working face solid of carpenter and bar bender are handed in the technique Fork, synchronous to carry out respective operation, procedure arrangement is compact, and carpenter and bar bender can work continuously the not work holdup, and speed of application is fast Speed;The stirrup sealed afterwards at column template and wall form, bean column node is banded with enough working faces, it is ensured that bind round at bean column node position The quality of muscle colligation;It can be poured using concrete one piece, reduce staying for horizontal construction joint and set;During timber work, beam, The saw foam that plate leaves is cleaned out with hair-dryer in time with garbage energy, it is ensured that no debris is deposited in template in reinforcing bar process of binding Stay, improve concrete pouring quality.
Embodiment
The technical scheme of this patent is described in more detail with reference to embodiment.
Embodiment 1
A kind of contrary sequence method template construction technique, is comprised the following steps that:
Step one, surveying setting-out:Set up axial control network between floors with " internal control method ", pilot measurement to construction floor, The axis of each axle of construction layer building is delivered out according to construction drawing, according to completed plane axis gauze, post position and beam is released Position frame line, 500mm positions release post control line and beam control line on the outside of its sideline, as installation, check column template and beam The foundation of template, absolute altitude is up successively transmitted by bottom absolute altitude control point, and absolute altitude transmission point is no less than three, should answer from each other Core is closed, and during levelling, is directly copied absolute altitude in the post cage bar tied up, each post must have two reliefs, one is used for Transmission, one is used to check;
Step 2, formwork bracing system is set up:Floor framework axis spacing is 7.8 meters, the both sides of floor framework axis Framed bent is provided with 0.6 meter, framed bent uses row's vertical rod, and row's spacing of vertical rod is 7.8 meters, for local particularly irregular , in 7.8 meters of axis of floor framework have crossbeam, then be suitably adjusted using 1.5 meters and 0.9 meter long disk buckle type scaffolds Vertical rod spacing, it is ensured that vertical rod starts to walk since beam axis 600mm distances, vertical rod and horizon bar use 48 × 3.5mm of φ disk Steel pipe scaffold is detained, vertical rod spacing is 900mm × 900mm, and horizontal step pitch is using U-shaped support support, U at the top of 1200mm, vertical rod Type support spiral screw thread is highly not more than 250mm, and top joist uses and adds vertical rod in the middle part of 48 × 3.5mm of φ double steel pipe, beam bottom Support, spacing is not more than 1000mm, and horizon bar highly must not exceed 300mm from the ground, and the border of floor frame column first reduces one Disk buckle type scaffold is arranged, installing for post template is then carried out, then is fixed on steel pipe and cruciform fastening for falsework on disk buckle type scaffold, The U-shaped jacking of steel tube head is used for the diagonal brace for reinforcing pillar on the outside of template, and the vertical spacing of diagonal brace is 200mm, diagonal brace Level interval is 400mm, and the screw thread of U-shaped support is adjusted, it is ensured that supported to the reinforcing of frame column firmly, for top plate, by Just arrival beam bottom of highly differing surely is installed in eye-splice-type scaffold, therefore, on eye-splice-type scaffold top, is added U-shaped The vertical rod that support carries out top elevation highly adjust, and vertical rod top is U-shaped to hold in the palm that screw mandrel is exposed must not exceed 20CM, if it exceeds then carrying out Appropriate adjustment, can again be added in eye-splice-type support bottom a U-shaped support, i.e. vertical rod the top respectively set with bottom one it is U-shaped Support, it is ensured that U asks exposed screw thread to be less than 25CM, it is ensured that on support and the stability under loading of U-shaped support, the steel pipe at the beam bottom of floor framework Lay and beam bottom plate is laid on 50*100mm flitches, flitch, the spacing at beam bottom, which is not more than at 1000mm, is provided with vertical rod, floor framework Outermost surrounding sets the elongated bridging of vertical continous way from the bottom to top, and the centre of floor framework is vertically and horizontally being set every 10M It is equipped with vertical continous way bridging from the bottom to top and horizontal cross brace is set at the bar of sweeping the floor at the top of bridging, vertically connects The bottom of continuous formula bridging is held out against with ground and in 45-60 degree angles;
Step 3, the installation of Liangping platform and plate platform template:Survey 1M lines should be first copied before slab form construction, are taken according to 1M lines If socket joint type disk buckle type scaffold;Disk buckle frame vertical rod bottom is laid flat, and the beam position line is put well, by the position line by the way of messenger wire falls Lead on steel pipe frame, adjustment beam bottom steel pipe absolute altitude after leveling, lays beam bottom board, beam bottom board both sides are locked with fastener, prevent beam bottom Mould positioning, platform template is held on beam side, beam side support platform template, platform primary and secondary skeletal frame is laid, by allocation plan Template is well placed, formwork edge joint is tight, with nail that Template nail is firm.Main joist must be supported at the top of column, and With column fixing-stable, beam bottom mother plate springing height is carried out according to the 1 ‰ -3 ‰ of beam span, and beam-slab template support uses disk button Scaffold, vertical rod spacing is supported according to 900mm, and vertical levels connecting rod, spacing 1500mm is attached, and vertical rod spacing is in beam Position be adjusted, the clear height of beam adds split bolt when being more than 600mm, and puts PVC sleeve pipes, installs outer stupefied, tightens pair Bolt is drawn, adjustment beam is suitable for reading straight, inlaying template and should be put in span centre in beam and landing slab template must not be put in termination node Place, to ensure node quality;
Step 4, the installation of column template:Bar bender carries out the colligation of beam steel and slab muscle in upper strata working face, while wooden Work carries out the installation and reinforcing of wall form and column template in lower floor's working face, and wall form and column template are previously positioned at into wall column phase Answer position side, beam bottom and beam side primary and secondary is stupefied is attached to away from the outside of wall column formwork at 150mm, to seal mould, full wafer protection wall column template When, wall column formwork is directly erected into propulsion relevant position and be can be reinforced;When burst seals mould, column cap template should be in shaft template Reinforcing is installed again after in place;Wall form and column template are relatively independent, it is impossible to draw logical line carry out school and, wall form and column template it is flat Face position and perpendicularity inspection, checking work should be rechecked by flooring control line, and the support system of column template uses φ 48mm diagonal brace steel pipe, each face of column template sets twice diagonal brace steel pipe and diagonal brace steel pipe is withstood on away from post mould by bar of sweeping the floor On edges of boards edge 2M φ 32mm pre-buried ground dowel, the middle part of diagonal brace steel pipe sets horizontal steel pipe reverse drawing steel pipe with together with together, Column template sets 2 ㎜ of ф 48 × 3.5 per 300-400mm using the thick plank sheathings of 18mm, 50 × 100mm wooden a tree, used in making timber for boats, wooden a tree, used in making timber for boats outside Double steel pipe is socketed with split bolt, (when column section length and width be more than 600mm when use Φ 12mm split bolts, quantity according to Length and width determines that general spacing is 455mm, and liftoff bottom cannot be greater than 200mm together, and be drawn with periphery vertical steel pipe level Connect, bottom and top steel pipe are socketed with diagonal brace steel pipe and bar of sweeping the floor, and installing front template bottom panel should be smooth, along wall sideline to Outer 3-5mm posts sponge strip, checks wall form numbering, checks whether template is cleaned out, door-window opening mould plate and built-in fitting Whether it is installed in place;
Step 5, the installation of wall form:The big face wall template opsition dependent line lifting in side is in place, diagonal brace is installed and adjusted to wall Template, on 75 degree and the stable located reference plane of wall form, is fixed with ground, installs through walls on wall form temporarily Bolt and fix plastic bushing, inside cleaning wall form, using the wall form of same step opposite side in place, make through-wall bolt Fastener and nut are worn through template and in bolt rod end, position, plumbness and the diagonal brace angle of both sides wall form is adjusted, then Fixed and fastening diagonal brace, fastens the nut of through-wall bolt;Adjacent wall form and angle mould are installed using same step, using steel pipe Support system is supported, after model sheetinstallat is finished, and checks whether fastener, bolt, diagonal brace fasten, stably comprehensively, formwork edge joint and under Whether mouth is tight, and outer wall of basement, pond wall body opposite pulling screw rod should be welded with 80 × 80 × 5mm sealing piece steel plate in centre, only Water piece steel plate wants full weld, and interior wall Screw arbor with nut at both-ends overcoat PVC sleeve pipes split out screw rod, both without cutting off screw rod, screw rod after concrete placings are complete It can be used in turn again, inner side of outer wall template and inside wall formwork support system add quick dismounting head diagonal brace using φ 48mm steel pipes, in diagonal brace Horizontal steel pipe and reverse drawing steel pipe are set in the middle part of steel pipe together.The pre-buried φ 32mm earth anchors on floor, diagonal brace steel pipe is with earth anchor by sweeping The thin end of the scroll is connected, and exterior wall outboard template support system uses bowl buckle scaffold stull, vertically sets level and vertical steel pipe pull bar together;
Step 6, the installation of stair template:Platform template is installed, then installs stair end template, check of staircase is then installed, End template exceeds side form 2-3cm, ejects stair base plate thickness line and the side plate position line on the inside of check of staircase, side form, kicks step mould Plate and template is marked time by figure machine-shaping and Assembling, in order to ensure step plate one-shot forming, kick step template using sizing Steel plate, lower mouth back of the body a tree, used in making timber for boats falls 45° angle, to ensure the accurate of line size of marking time, the height that the height of step plate must be with stair step Degree is consistent, during setting-out, must reserve the thickness of finishing surface layer, and stair template support system is used in diagonal brace steel pipe, diagonal brace steel pipe Between be provided with one of cross-tie, side form is fixed using 50*100mm wooden a tree, used in making timber for boats, to ensure the accurate of line size of marking time, is marked time The height of plate must be highly consistent with stair step, during setting-out, must reserve the thickness of finishing surface layer.Stair template supporter System adds quick dismounting head diagonal brace using steel pipe, and centre sets cross-tie together, and side form is fixed to be fixed using 50*100mm wooden a tree, used in making timber for boats.
It is obvious to a person skilled in the art that the invention is not restricted to the details of above-mentioned one exemplary embodiment, Er Qie In the case of without departing substantially from spirit or essential attributes of the invention, the present invention can be realized in other specific forms.Therefore, no matter From the point of view of which point, embodiment all should be regarded as exemplary, and be nonrestrictive, the scope of the present invention is by appended power Profit is required rather than described above is limited, it is intended that all in the implication and scope of the equivalency of claim by falling Change is included in the present invention.
Moreover, it will be appreciated that although the present specification is described in terms of embodiments, not each embodiment is only wrapped Containing an independent technical scheme, this narrating mode of specification is only that for clarity, those skilled in the art should Using specification as an entirety, the technical solutions in the various embodiments may also be suitably combined, forms those skilled in the art It may be appreciated other embodiment.

Claims (5)

1. a kind of contrary sequence method template construction technique, it is characterised in that comprise the following steps that:
Step one, surveying setting-out:Axial control network, pilot measurement to construction floor, foundation are set up between floors with " internal control method " Construction drawing delivers out the axis of each axle of construction layer building, according to completed plane axis gauze, releases post position and Liang Weibian Wire, 500mm positions release post control line and beam control line on the outside of its sideline, absolute altitude by bottom absolute altitude control point up successively Transmission, directly copies absolute altitude in the post cage bar tied up, each post cage bar must have two reliefs;
Step 2, formwork bracing system is set up:Floor framework axis spacing is 7.8 meters, 0.6 meter of the both sides of floor framework axis Place is provided with framed bent, and framed bent uses row's vertical rod, and row's spacing of vertical rod is 7.8 meters, and a row is first reduced by the border of floor frame column Disk buckle type scaffold, then carries out installing for post template, then be fixed on steel pipe and cruciform fastening for falsework on disk buckle type scaffold, steel The U-shaped jacking of pipe end is used for the diagonal brace for reinforcing pillar on the outside of template, and the vertical spacing of diagonal brace is 200mm, the water of diagonal brace Flat spacing is 400mm, then the vertical rod for carrying out top elevation to U-shaped support is highly adjusted, and is laid on the steel pipe at the beam bottom of floor framework Beam bottom plate is laid on 50*100mm flitches, flitch, the spacing at beam bottom, which is not more than at 1000mm, is provided with vertical rod, floor framework outermost Side surrounding sets the elongated bridging of vertical continous way from the bottom to top, and the centre of floor framework is vertically and horizontally being provided with every 10M Vertical continous way bridging and setting horizontal cross brace, vertical continous way at the bar of sweeping the floor at the top of bridging from the bottom to top The bottom of bridging is held out against with ground and in 45-60 degree angles;
Step 3, the installation of Liangping platform and plate platform template:Beam form is positioned, the fixed of adjacent forms is carried out, then carries out beam column The installation of wall mouth template, carries out the cleaning of template surface debris, then install beam forms by beam muscle and carry out bed die arch camber;
Step 4, the installation of column template:Bar bender carries out the colligation of beam steel and slab muscle in upper strata working face, while carpenter exists Lower floor's working face carries out the installation and reinforcing of wall form and column template, and wall form and column template are previously positioned at into wall column corresponding positions Put side, beam bottom and beam side primary and secondary is stupefied is attached to away from 150mm, the support system of column template is using φ 48mm's on the outside of wall column formwork Diagonal brace steel pipe, each face of column template sets twice diagonal brace steel pipe and diagonal brace steel pipe is withstood on away from column template edge by bar of sweeping the floor On 2M φ 32mm pre-buried ground dowel, the middle part of diagonal brace steel pipe sets horizontal steel pipe reverse drawing steel pipe with together with together,;
Step 5, the installation of wall form:The big face wall template opsition dependent line lifting in side is in place, diagonal brace is installed and adjusted to wall form With ground on 75 degree and the stable located reference plane of wall form, fixed temporarily, through-wall bolt is installed on wall form With fix plastic bushing, inside cleaning wall form, using the wall form of same step opposite side in place, adjust both sides wall form Position, plumbness and diagonal brace angle, it is then fixed and fasten diagonal brace, fasten the nut of through-wall bolt;Using same step Adjacent wall form and angle mould are installed suddenly, supports and checks using steel pipe supporting system;
Step 6, the installation of stair template:Platform template is installed, then installs stair end template, check of staircase is then installed, in building Ejection stair base plate thickness line and the side plate position line on the inside of side of the ladder plate, side form, kick step template and template of marking time by figure machine-shaping And Assembling, stair template support system uses and is provided with one of cross-tie, side form in the middle of diagonal brace steel pipe, diagonal brace steel pipe Fixed using 50*100mm wooden a tree, used in making timber for boats.
2. contrary sequence method template construction technique according to claim 1, it is characterised in that absolute altitude control point in the step one Quantity be not less than 3.
3. contrary sequence method template construction technique according to claim 1 or 2, it is characterised in that the vertical rod using φ 48 × 3.5 disk buckles steel pipe scaffold, and vertical rod spacing is 900mm × 900mm, and horizontal step pitch is 1200mm, and the spiral screw thread of U-shaped support is high Degree is not more than 250mm, and top joist uses 48 × 3.5mm of φ double steel pipe, adds vertical rod support in the middle part of beam bottom, girt from Ground level is no more than 300mm.
4. contrary sequence method template construction technique according to claim 1, it is characterised in that the diagonal brace uses steel pipe or side Wood, bridging includes steel pipe and fastener, and the width of vertical continous way bridging is 4-6M.
5. contrary sequence method template construction technique according to claim 1, it is characterised in that the bottom of the disk buckle type scaffold Set up a U-shaped support.
CN201710598368.6A 2017-07-21 2017-07-21 A kind of contrary sequence method template construction technique Pending CN107190861A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710598368.6A CN107190861A (en) 2017-07-21 2017-07-21 A kind of contrary sequence method template construction technique

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710598368.6A CN107190861A (en) 2017-07-21 2017-07-21 A kind of contrary sequence method template construction technique

Publications (1)

Publication Number Publication Date
CN107190861A true CN107190861A (en) 2017-09-22

Family

ID=59883895

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710598368.6A Pending CN107190861A (en) 2017-07-21 2017-07-21 A kind of contrary sequence method template construction technique

Country Status (1)

Country Link
CN (1) CN107190861A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109184210A (en) * 2018-10-11 2019-01-11 鼎宸建设管理有限公司 A kind of 3D printing decorative model template construction technique
CN110629934A (en) * 2019-09-04 2019-12-31 东莞市建筑科学研究所 BIM-based formed steel bar and forming template combined application construction method
CN114108812A (en) * 2021-12-09 2022-03-01 中国化学工程第九建设有限公司 Construction method of main body frame of concrete engineering frame structure building

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104806018A (en) * 2015-05-08 2015-07-29 南通华新建工集团有限公司 Construction technology of steel frame and wood form type combined formwork
CN106437140A (en) * 2016-07-06 2017-02-22 江苏江中集团有限公司 Vault shear wall anti-explosion and drilling-resistant formwork erecting construction method
CN106639316A (en) * 2016-11-16 2017-05-10 郑洪均 Method capable of improving construction efficiency of furniture workshop project

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104806018A (en) * 2015-05-08 2015-07-29 南通华新建工集团有限公司 Construction technology of steel frame and wood form type combined formwork
CN106437140A (en) * 2016-07-06 2017-02-22 江苏江中集团有限公司 Vault shear wall anti-explosion and drilling-resistant formwork erecting construction method
CN106639316A (en) * 2016-11-16 2017-05-10 郑洪均 Method capable of improving construction efficiency of furniture workshop project

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109184210A (en) * 2018-10-11 2019-01-11 鼎宸建设管理有限公司 A kind of 3D printing decorative model template construction technique
CN110629934A (en) * 2019-09-04 2019-12-31 东莞市建筑科学研究所 BIM-based formed steel bar and forming template combined application construction method
CN114108812A (en) * 2021-12-09 2022-03-01 中国化学工程第九建设有限公司 Construction method of main body frame of concrete engineering frame structure building

Similar Documents

Publication Publication Date Title
CN108678258B (en) Large-span hemispherical reinforced concrete dome structure and construction method thereof
CN102277959B (en) Standard steel frame formwork system for concrete floor slabs and construction method thereof
CN103615110B (en) Random oblique netted nine-squares beam Hyperbolic Roof construction method
CN105040970A (en) Comprehensive gymnasium high formwork support system and construction method of comprehensive gymnasium high formwork support system
US8978331B2 (en) Building construction with lost shuttering and construction method
CN105544873B (en) A kind of construction method of the hollow roofing of waveform
US20150013255A1 (en) Hybrid cementitious buildings for a multi-level habitat
CN104405062A (en) Integrated column-equipped heat preservation wallboard, production and building techniques and matched equipment
CN111926910A (en) Installation method of fabricated building
CN104060629A (en) Covered top-down excavation subway station overlapped wall construction method and movable side wall formwork jumbo
CN107190861A (en) A kind of contrary sequence method template construction technique
CN111236604A (en) Safe construction method for cantilever platform on cylinder main body structure
CN108894488A (en) A kind of construction method of Novel section steel keel steel and wood composite template
CN107780559A (en) A kind of construction method of heat-insulation and heat-preservation gypsum partition wall
CN105672664A (en) Integral heat insulation wallboard building system
CN102644382A (en) Mounting technology of large-module wall
CN103266766B (en) Shear wall with short piers, column template construction after the first beam slab of agent structure
CN109898698B (en) Construction method of antique building wire seam wall
CN106894538A (en) Filling wall and agent structure concrete integral shaping method
CN206220240U (en) A kind of assembled steel concrete frame panel structure system
McMorrough The Architecture Reference & Specification Book: Everything Architects Need to Know Every Day
US20150204067A1 (en) Building system and method
CN111119368A (en) Construction method for externally-hung metal rock wool sandwich board of autoclaved sand aerated concrete wallboard
CN111894266B (en) Integral construction method for primary formwork support of plate-rafter integrated roof of antique building
CN205242631U (en) Building building structure can be dismantled in full assembly

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170922

RJ01 Rejection of invention patent application after publication