CN107165052A - A kind of horizontal assembling system for packaged type bridges precast pier template - Google Patents

A kind of horizontal assembling system for packaged type bridges precast pier template Download PDF

Info

Publication number
CN107165052A
CN107165052A CN201710357873.1A CN201710357873A CN107165052A CN 107165052 A CN107165052 A CN 107165052A CN 201710357873 A CN201710357873 A CN 201710357873A CN 107165052 A CN107165052 A CN 107165052A
Authority
CN
China
Prior art keywords
bridge formwork
packaged type
bridge
support frame
guide rail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710357873.1A
Other languages
Chinese (zh)
Inventor
杨根明
罗利
吴玮
倪伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC5 Group Corp Ltd
Original Assignee
China MCC5 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC5 Group Corp Ltd filed Critical China MCC5 Group Corp Ltd
Priority to CN201710357873.1A priority Critical patent/CN107165052A/en
Publication of CN107165052A publication Critical patent/CN107165052A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of horizontal assembling system for packaged type bridges precast pier template, including guide rail and assembled dolly, the guide rail is horizontally disposed with, the many assembled dollies for being used to carry bridge formwork are set on guide rail, the assembled dolly includes mobile support, lift adjustment system and bridge formwork support frame, and the bridge formwork support frame is movably arranged on mobile support to be lifted by lift adjustment system fading margin.A kind of horizontal assembling system for packaged type bridges precast pier template of the invention, by the assembled dolly of lifting that multiple carrying bridge formworks are set in horizontal rail, the bridge formwork height on correspondence dolly can be adjusted by lifting assembled dolly, so as to effectively improve each bridge formwork joint docking goodness of fit, assembled dolly can be moved forward and backward on guide rail, it is easy to bridge formwork tandem docking, effectively reduces the working strength of workmen.

Description

A kind of horizontal assembling system for packaged type bridges precast pier template
Technical field
The present invention relates to a kind of bridge construction field, and in particular to a kind of for the sleeping of packaged type bridges precast pier template Formula assembling system.
Background technology
Large-sized bridge steel tower section typically requires progress preassembling, and preassembling in kind is divided into vertical preassembling and horizontal pre-splicing Fill two kinds:It is shorter for tower section length, vertical preassembling is typically used both at home and abroad;And it is larger for length, due to by rise Heavy equipment, factory building height etc. are limited, only using horizontal preassembling.During using horizontal preassembling, the problem of being most difficult to and solve is:Gold Category contact rate must reach higher standard requirement;The deadweight of tower section can not influence king-post linear.Wherein, how to ensure between tower section Measuring Metallic Contact Rate requirement is the difficult point and key point of horizontal preassembling dress.
The content of the invention
The purpose of the present invention is to be to overcome prior art not enough, it is therefore intended that provide a kind of beam prefabricated for unit construction bridge The horizontal assembling system of bridge abutment moulding plate, solves large-sized bridge steel tower section in assembly, wastes time and energy, assembled equipment operation is not Just, so as to influence the problem of Measuring Metallic Contact Rate is required between tower section.
The present invention is achieved through the following technical solutions:
A kind of horizontal assembling system for packaged type bridges precast pier template, including guide rail and assembled dolly, it is described Guide rail is horizontally disposed with, and many assembled dollies for being used to carry bridge formwork are set on guide rail, and the assembled dolly includes movement Support, lift adjustment system and bridge formwork support frame, the bridge formwork support frame, which is movably arranged on mobile support, to be passed through Lift adjustment system fading margin is lifted.A kind of horizontal assembling system for packaged type bridges precast pier template of the invention, passes through The assembled dolly of lifting of multiple carrying bridge formworks is set in horizontal rail, can adjust corresponding small by lifting assembled dolly Bridge formwork height on car, so as to effectively improve each bridge formwork joint docking goodness of fit, assembled dolly can be Moved forward and backward on guide rail, be easy to bridge formwork tandem docking, effectively reduce the working strength of workmen.
Further, the guide rail is double bar guide rail structures.
Further, the mobile support includes the support frame that four supporting legs are constituted, and the supporting leg lower end is all provided with There is mobile pulley, the supporting leg upper end is provided with the tube-in-tube structure with bridge formwork support frame assembly connection.
Further, the bridge formwork support frame includes the lifting support frame that four lifting supporting legs are constituted, described Lifting supporting leg lower end activity is plugged in the tube-in-tube structure of supporting leg upper end.
Further, it is provided with the positioning supporting frame coordinated with bridge formwork at the top of the bridge formwork support frame.
Further, the positioning supporting frame is two pairs of location-plates along assembled dolly moving direction spread configuration, described Location-plate upper end interior angle does chamfered.
Further, the lift adjustment system includes regulation elevating screw and shearing fork telescopic frame, the shearing fork telescopic frame The joint of lower end two is arranged on regulation elevating screw by silk braid, and the regulation elevating screw is arranged on mobile support, institute State the joint of shearing fork telescopic frame upper end two to be hinged on bridge formwork support frame, by rotating regulation elevating screw so as to control to cut Pitch expansion bracket to stretch, the shearing fork telescopic frame is flexible to drive elevating movement on bridge formwork support frame again.
Further, the shearing fork telescopic frame is two sets.
The present invention compared with prior art, has the following advantages and advantages:
A kind of horizontal assembling system for packaged type bridges precast pier template of the invention, by being set in horizontal rail The assembled dolly of lifting of multiple carrying bridge formworks is put, the bridge formwork on correspondence dolly can be adjusted by lifting assembled dolly Highly, so as to effectively improve each bridge formwork joint docking goodness of fit, assembled dolly can be moved forward and backward on guide rail, It is easy to bridge formwork tandem docking, effectively reduces the working strength of workmen;
Assembled dolly uses scissors type elevating expansion bracket, and lifting structure is simple, low manufacture cost, it is not necessary to electric driving force, Do not limited by construction site environment, operative is convenient, be easy to popularization.
Bridge formwork is hung on and can withdrawn after chassis by hanging device, liberates plant equipment, improves MU efficiency.This Invention can be applied in the assembly of a variety of prefabricated components, such as the assembly of precast pier, assembled bridge pier or bridge formwork.
Brief description of the drawings
Accompanying drawing described herein is used for providing further understanding the embodiment of the present invention, constitutes one of the application Point, do not constitute the restriction to the embodiment of the present invention.In the accompanying drawings:
Fig. 1 is a kind of structural representation of horizontal assembling system for packaged type bridges precast pier template of the invention;
Fig. 2 is a kind of main structure diagram of assembled dolly of the present invention;
The structural representation that Fig. 3 is A-A in Fig. 2;
The structural representation that Fig. 4 is B-B in Fig. 3;
The structural representation that Fig. 5 is C-C in Fig. 4;
Mark and corresponding parts title in accompanying drawing:
1- guide rails, 2- assembly dollies, 3- bridge formworks, 4- movement supports, 5- lift adjustment systems, the support of 6- bridge formworks Frame, 7- supporting legs, 8- support frames, 9- mobile pulleys, 10- tube-in-tube structures, 11- lifting supporting legs, 12- lifting support frames, 13- positioning supporting frames, 14- location-plates, 15- regulation elevating screws, 16- shearing fork telescopic framves, 17- silk braids.
Embodiment
For the object, technical solutions and advantages of the present invention are more clearly understood, with reference to embodiment and accompanying drawing, to this Invention is described in further detail, and exemplary embodiment and its explanation of the invention is only used for explaining the present invention, does not make For limitation of the invention.
Embodiment 1
As shown in figure 1, a kind of horizontal assembling system for packaged type bridges precast pier template of the invention, including guide rail 1 is horizontally disposed with assembled dolly 2, guide rail 1, sets many to be used for the assembled dollies 2 for carrying bridge formwork 3 (such as figure on guide rail 1 Shown in 1), assembled dolly 2 is moved forward and backward by being arranged on the mobile pulley 9 of bottom on guide rail 1, and (as Figure 2-3) is assembled Dolly 2 includes mobile support 4, lift adjustment system 5 and bridge formwork support frame 6, and bridge formwork support frame 6 is movably arranged on shifting Adjusted and lifted by lift adjustment system 5 on dynamic support 4.Guide rail 1 is double bar guide rail structures.Mobile support 4 includes four supports It is welded and fixed again by web beam between the support frame 8 that leg 7 is constituted, four supporting legs 7, four supporting legs 7 can be used Square hollow section steel is made, and the lower end of supporting leg 7 is equipped with mobile pulley 9, and the upper end of supporting leg 7, which is provided with to assemble with bridge formwork support frame 6, to be connected The tube-in-tube structure 10 connect.Bridge formwork support frame 6 includes the lifting support frame 12 that four lifting supporting legs 11 are constituted, lifting branch It is welded and fixed again by web beam between support leg 11, four supporting legs 7 can be made of square hollow section steel, under lifting supporting leg 11 End activity is plugged in the tube-in-tube structure 10 of the upper end of supporting leg 7.
At the construction field (site), the levelness of guide rail 1 is first verified, according to the quantity of assembled bridge formwork 3, is placed on an equal basis in guide rail 1 On the assembled dolly 2 of quantity, each dolly by splicing order respectively place a bridge formwork 3, the positioning jack of bridge formwork 3 with The top of bridge formwork support frame 6 is provided with to be engaged for the corresponding installation of the positioning supporting frame 13 of positioning, Ran Houyi with bridge formwork 3 Dynamic assembly dolly 2 makes adjacent bridge formwork 3 dock two-by-two, is aligned, is specifically adopted by adjusting the assembled lifting of dolly 2 after docking It is enclosed on regulation elevating screw 15 termination and is stretched to adjust shearing fork telescopic frame 16 with spanner, by adjacent bridge formwork 3 after alignment Joint is welded or bolt connection two-by-two.
The top of bridge formwork support frame 6 is provided with the positioning supporting frame 13 being engaged with bridge formwork 3 for positioning.Positioning branch Support 13 is two pairs of location-plates 14 along the assembled moving direction spread configuration of dolly 2, and the upper end interior angle of location-plate 14 does chamfered. The bottom of bridge formwork 3 is provided with four positioning jacks (accompanying drawing is not shown) being engaged with location-plate 14, and positioning jack is arranged on bridge The bottom centre position of beam forms 3, is easy to support to balance, and positioning jack is that bottom osculum is big, is easy to positioning.
As shown in figure 4, lift adjustment system 5 includes regulation elevating screw 15 and shearing fork telescopic frame 16, shearing fork telescopic frame 16 The joint of lower end two is arranged on regulation elevating screw 15 by silk braid 17, and the screw thread two ends on regulation elevating screw 15 are symmetrical (as shown in Figure 5), the hand of spiral are on the contrary, so as to can just make two silk braids 17 being arranged on regulation elevating screw 15 opposite or anti- To motion, the regulation elevating screw 15 is arranged on mobile support 4, and shearing fork telescopic frame 16 upper end two joint is hinged on bridge On formwork-support 6, by rotating regulation elevating screw 15 so as to control shearing fork telescopic frame 16 to stretch, the shearing fork telescopic frame 16 It is flexible to drive elevating movement on bridge formwork support frame 6 again.
A kind of horizontal assembling system for packaged type bridges precast pier template of the invention, by being set in horizontal rail The assembled dolly of lifting of multiple carrying bridge formworks is put, the bridge formwork on correspondence dolly can be adjusted by lifting assembled dolly Highly, so as to effectively improve each bridge formwork joint docking goodness of fit, assembled dolly can be moved forward and backward on guide rail, It is easy to bridge formwork tandem docking, effectively reduces the working strength of workmen;
Assembled dolly uses scissors type elevating expansion bracket, and lifting structure is simple, low manufacture cost, it is not necessary to electric driving force, Do not limited by construction site environment, operative is convenient, be easy to popularization.
Embodiment 2
As Figure 1-5, a kind of horizontal assembling system for packaged type bridges precast pier template of the invention, is implementing On the basis of example 1, shearing fork telescopic frame 16 is two sets.Pass through, two sets of shearing fork telescopic frame 16 lower end four joints,;One is shared two-by-two Individual silk braid 17, so as to control two sets of shearing fork telescopic framves 16 to stretch by a regulation elevating screw 15.Pass through two sets of shearing fork telescopics Frame 16 lifts steadiness to realize that lifting support can improve assembled dolly 2, while also providing bearing capacity.
Above-described embodiment, has been carried out further to the purpose of the present invention, technical scheme and beneficial effect Describe in detail, should be understood that the embodiment that the foregoing is only the present invention, be not intended to limit the present invention Protection domain, within the spirit and principles of the invention, any modification, equivalent substitution and improvements done etc. all should be included Within protection scope of the present invention.

Claims (8)

1. a kind of horizontal assembling system for packaged type bridges precast pier template, including guide rail (1) and assembled dolly (2), It is characterized in that:The guide rail (1) is horizontally disposed with, and sets many to be used to carry the assembled small of bridge formwork (3) on guide rail (1) Car (2), the assembled dolly (2) includes mobile support (4), lift adjustment system (5) and bridge formwork support frame (6), described Bridge formwork support frame (6) is movably arranged on mobile support (4) to adjust by lift adjustment system (5) and lifted.
2. a kind of horizontal assembling system for packaged type bridges precast pier template according to claim 1, its feature It is, the guide rail (1) is double bar guide rail structures.
3. a kind of horizontal assembling system for packaged type bridges precast pier template according to claim 1, its feature It is, the mobile support (4) includes the support frame (8) that four supporting legs (7) are constituted, and supporting leg (7) lower end is all provided with There is mobile pulley (9), supporting leg (7) upper end is provided with the tube-in-tube structure (10) with bridge formwork support frame (6) assembly connection.
4. a kind of horizontal assembling system for packaged type bridges precast pier template according to claim 3, its feature It is, the bridge formwork support frame (6) includes the lifting support frame (12) that four lifting supporting legs (11) are constituted, the liter Descending branch support leg (11) lower end activity is plugged in the tube-in-tube structure (10) of supporting leg (7) upper end.
5. a kind of horizontal assembling system for packaged type bridges precast pier template according to claim 4, its feature It is, provided with the positioning supporting frame being engaged with bridge formwork (3) for positioning at the top of the bridge formwork support frame (6) (13)。
6. a kind of horizontal assembling system for packaged type bridges precast pier template according to claim 5, its feature It is, the positioning supporting frame (13) is two pairs of location-plates (14) along assembled dolly (2) moving direction spread configuration, described fixed Position plate (14) upper end interior angle does chamfered.
7. a kind of horizontal assembling system for packaged type bridges precast pier template according to claim 6, its feature It is, the lift adjustment system (5) includes regulation elevating screw (15) and shearing fork telescopic frame (16), the shearing fork telescopic frame (16) joint of lower end two is arranged on regulation elevating screw (15) by silk braid (17), and the regulation elevating screw (15) is installed On mobile support (4), shearing fork telescopic frame (16) upper end two joint is hinged on bridge formwork support frame (6), is passed through Regulation elevating screw (15) is rotated so as to control shearing fork telescopic frame (16) to stretch, the shearing fork telescopic frame (16) is flexible to drive bridge again Elevating movement on beam form support frame (6).
8. a kind of horizontal assembling system for packaged type bridges precast pier template according to claim 7, its feature It is, the shearing fork telescopic frame (16) is two sets.
CN201710357873.1A 2017-05-19 2017-05-19 A kind of horizontal assembling system for packaged type bridges precast pier template Pending CN107165052A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710357873.1A CN107165052A (en) 2017-05-19 2017-05-19 A kind of horizontal assembling system for packaged type bridges precast pier template

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710357873.1A CN107165052A (en) 2017-05-19 2017-05-19 A kind of horizontal assembling system for packaged type bridges precast pier template

Publications (1)

Publication Number Publication Date
CN107165052A true CN107165052A (en) 2017-09-15

Family

ID=59816729

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710357873.1A Pending CN107165052A (en) 2017-05-19 2017-05-19 A kind of horizontal assembling system for packaged type bridges precast pier template

Country Status (1)

Country Link
CN (1) CN107165052A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111391077A (en) * 2020-03-25 2020-07-10 重庆建筑工程职业学院 Horizontal splicing device for prefabricated bridge pier template of assembled bridge

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2175653Y (en) * 1993-12-01 1994-08-31 吕德喜 Horizontal steel ingot casting machine without refractory brick
CN202462329U (en) * 2012-02-21 2012-10-03 山西江淮重工有限责任公司 Mechanism for horizontally and accurately assembling long and thin workpieces
CN203301008U (en) * 2013-05-29 2013-11-20 国家电网公司 Wall casing assembly vehicle
DE102013113729A1 (en) * 2013-12-09 2015-06-11 Dürr Systems GmbH Transport vehicle, manufacturing plant and manufacturing process
CN204608611U (en) * 2015-04-08 2015-09-02 中交四航局第五工程有限公司 Be applicable to the movable die block table system of large-sized concrete prefabricated units
CN105484506A (en) * 2015-12-14 2016-04-13 中国一冶集团有限公司 Universal adjustable space truss splicing device and using method thereof
CN105773046A (en) * 2016-05-25 2016-07-20 大运汽车股份有限公司 Assembling fixture for frame assembly
CN106441706A (en) * 2016-09-08 2017-02-22 西安电子科技大学 Mass center measuring device integrated to multi-size slender body assembly table
CN206706591U (en) * 2017-05-19 2017-12-05 中国五冶集团有限公司 A kind of horizontal splicing apparatus for packaged type bridges precast pier template

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2175653Y (en) * 1993-12-01 1994-08-31 吕德喜 Horizontal steel ingot casting machine without refractory brick
CN202462329U (en) * 2012-02-21 2012-10-03 山西江淮重工有限责任公司 Mechanism for horizontally and accurately assembling long and thin workpieces
CN203301008U (en) * 2013-05-29 2013-11-20 国家电网公司 Wall casing assembly vehicle
DE102013113729A1 (en) * 2013-12-09 2015-06-11 Dürr Systems GmbH Transport vehicle, manufacturing plant and manufacturing process
CN204608611U (en) * 2015-04-08 2015-09-02 中交四航局第五工程有限公司 Be applicable to the movable die block table system of large-sized concrete prefabricated units
CN105484506A (en) * 2015-12-14 2016-04-13 中国一冶集团有限公司 Universal adjustable space truss splicing device and using method thereof
CN105773046A (en) * 2016-05-25 2016-07-20 大运汽车股份有限公司 Assembling fixture for frame assembly
CN106441706A (en) * 2016-09-08 2017-02-22 西安电子科技大学 Mass center measuring device integrated to multi-size slender body assembly table
CN206706591U (en) * 2017-05-19 2017-12-05 中国五冶集团有限公司 A kind of horizontal splicing apparatus for packaged type bridges precast pier template

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111391077A (en) * 2020-03-25 2020-07-10 重庆建筑工程职业学院 Horizontal splicing device for prefabricated bridge pier template of assembled bridge

Similar Documents

Publication Publication Date Title
US9032689B2 (en) Jacking tower
CN206706591U (en) A kind of horizontal splicing apparatus for packaged type bridges precast pier template
KR101240784B1 (en) Lift apparatus
JP2008156015A (en) Mobile crane
CN204417029U (en) A kind of track lifting device
CN102825410A (en) Horizontal-type fast assembling platform for H profile steel
CN215666910U (en) Counterweight type steel rope traction combined electric lifting platform device
CN106006455A (en) Hydraulic elevator capable of achieving formwork erecting without scaffold
CN103557011A (en) Side wall trolley
CN107165052A (en) A kind of horizontal assembling system for packaged type bridges precast pier template
CN212773549U (en) Sliding device for hoisting truss
JP2019210109A (en) Lifting device of heavy load and lifting and conveying method
CN117071560A (en) Positioning and supporting device for construction of prefabricated pipe piles
CN2923644Y (en) Superhigh super-large high-tonnage walking derricktype lifting machine
CN216807824U (en) Pipeline mobile device for hydraulic engineering
CN109797964A (en) A kind of lifting platform system of integrated tower crane
JP2016142097A (en) Portable hoist unit and horizontal member dismantling method
CN203701552U (en) Attached scaffold for lifted through worm, gear and screw rod
CN112377672A (en) Old factory dust removal pipeline reconstruction and installation method and special pipeline moving and hoisting device thereof
CN110745735A (en) Stretching type synchronous lifting device
CN212077655U (en) High-speed railway highway gate-type bridging machine
CN213597452U (en) Novel building scaffold
CN210594968U (en) Sliding device for hoisting truss
CN217377083U (en) High-altitude hanger position adjusting device
CN220866931U (en) Overweight special-shaped member lifting device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170915