CN107150886A - Conveying arrangement and transportation resources for the mirror unit in solar electricity generation field - Google Patents

Conveying arrangement and transportation resources for the mirror unit in solar electricity generation field Download PDF

Info

Publication number
CN107150886A
CN107150886A CN201710128198.5A CN201710128198A CN107150886A CN 107150886 A CN107150886 A CN 107150886A CN 201710128198 A CN201710128198 A CN 201710128198A CN 107150886 A CN107150886 A CN 107150886A
Authority
CN
China
Prior art keywords
mirror unit
end plate
interface arrangment
longitudinal direction
mirror
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710128198.5A
Other languages
Chinese (zh)
Inventor
M·默廷斯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Finel Ltd
Original Assignee
Finel Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Finel Ltd filed Critical Finel Ltd
Publication of CN107150886A publication Critical patent/CN107150886A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65DCONTAINERS FOR STORAGE OR TRANSPORT OF ARTICLES OR MATERIALS, e.g. BAGS, BARRELS, BOTTLES, BOXES, CANS, CARTONS, CRATES, DRUMS, JARS, TANKS, HOPPERS, FORWARDING CONTAINERS; ACCESSORIES, CLOSURES, OR FITTINGS THEREFOR; PACKAGING ELEMENTS; PACKAGES
    • B65D71/00Bundles of articles held together by packaging elements for convenience of storage or transport, e.g. portable segregating carrier for plural receptacles such as beer cans or pop bottles; Bales of material
    • B65D71/50Bundles of articles held together by packaging elements for convenience of storage or transport, e.g. portable segregating carrier for plural receptacles such as beer cans or pop bottles; Bales of material comprising a plurality of articles held together only partially by packaging elements formed otherwise than by folding a blank
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65GTRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
    • B65G35/00Mechanical conveyors not otherwise provided for
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65DCONTAINERS FOR STORAGE OR TRANSPORT OF ARTICLES OR MATERIALS, e.g. BAGS, BARRELS, BOTTLES, BOXES, CANS, CARTONS, CRATES, DRUMS, JARS, TANKS, HOPPERS, FORWARDING CONTAINERS; ACCESSORIES, CLOSURES, OR FITTINGS THEREFOR; PACKAGING ELEMENTS; PACKAGES
    • B65D61/00External frames or supports adapted to be assembled around, or applied to, articles
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65DCONTAINERS FOR STORAGE OR TRANSPORT OF ARTICLES OR MATERIALS, e.g. BAGS, BARRELS, BOTTLES, BOXES, CANS, CARTONS, CRATES, DRUMS, JARS, TANKS, HOPPERS, FORWARDING CONTAINERS; ACCESSORIES, CLOSURES, OR FITTINGS THEREFOR; PACKAGING ELEMENTS; PACKAGES
    • B65D85/00Containers, packaging elements or packages, specially adapted for particular articles or materials
    • B65D85/62Containers, packaging elements or packages, specially adapted for particular articles or materials for stacks of articles; for special arrangements of groups of articles

Abstract

In order to equip mirror unit to solar electricity generation field, the structure especially for power plant scale is, it is necessary to large number of mirror unit.Due to the sensitiveness on mirror unit surface, it is necessary to very carefully transport mirror unit.In addition, mirror unit has very big housing in order to ensure torsional rigidity, the housing must be transported together.The present invention should realize a kind of traffic program for mirror unit of equal importancely in terms of security, cost-effective and high efficiency.This is achieved like this, and installs end plate in the side of mirror unit first so that multiple end plates are complementary to one another into a conveying arrangement, each mirror unit can be constituted into delivery unit using this conveying arrangement.End plate analogously constitutes the support that can be anchored in basal orbit with picture mosaic, and the support makes it possible to reliable in narrow space and simply transports multiple mirror units.

Description

Conveying arrangement and transportation resources for the mirror unit in solar electricity generation field
Technical field
The present invention relates to a kind of conveying arrangement, the conveying arrangement includes the side that at least one is used to be fixed on mirror unit On end plate, wherein, the end plate have with interface arrangment first longitudinal direction side and with coordinate interface arrangment second indulge Xiang Bian, first longitudinal direction while interface arrangment Yu structure identical another end plate second longitudinal direction while cooperation interface arrangment coordinate Effect, the invention further relates to a kind of transportation resources for the mirror unit for being used to be arranged in solar electricity generation field.
Background technology
Similar conveying arrangement is disclosed via JP2004207667A, and disclosed herein is a kind of fortune for photovoltaic element Defeated device, but photovoltaic element be complete face formula constitute and with the transportation characterization different from mirror unit.
It is used for the interim arrangement for simplifying the end member of goods transportation for example as known to EP0924137A1, here End member can realize vertical connection with adjacent element.
In order to equip mirror unit to solar electricity generation field, especially for the solar power generation built with power plant scale Field is, it is necessary to the large number of mirror unit.Construction for example for solar thermal power generation factory is provided, absorber is built in Higher position and mirror unit is all set in the both sides of absorber, the mirror unit is by incident sunlight to absorber On.This absorber may occupy hundreds of meters of length, and there may be in such solar electricity generation field very big This absorber of quantity, is thus likely to occur the long absorber tube of thousands of rice, is disposed with around the absorber tube in both sides many Arrange mirror unit.
Mirror unit has housing in itself, and the housing can for example have trapezoidal cross section, and this cross section takes empty Between it is larger.In order to avoid the torsion that the sunshine of incidence can be caused inaccurately to turn to occurs for speculum, this housing is necessary 's.Due to this hull shape, in order to pack single speculum, to pay larger consuming, could pack the speculum with Just infield is transported it into.On the one hand in order to protect mounted speculum not by can influence reflect and thus directly affect The damage of the energy output in power plant, on the other hand also for utilization space as well as possible is realized during transportation, be at present Only require, individually packaged mirror unit or with less packet packaging mirror unit, and each packaging unit is stacked with, with Just transport can be realized.Then, it is necessary to which, by the transport material used for this, such as wooden case and the like is transported back from infield Or scene is directly recycled.Situations below must be also included in for resulting material cost, i.e. transportation and packing are same It must be transported and the weight of transportation and packing can equally bring very high cost of transportation.
The content of the invention
In this context, it is an object of the present invention to propose a kind of conveying arrangement for mirror unit and a kind of use In the transportation resources of transport mirror unit, the conveying arrangement and transportation resources are reduced for being installed in solar electricity generation field The cost of transportation of mirror unit, while simplifying the operation of mirror unit, and reduces the discarded object of generation related to transport.
This is by a kind of feature according to claim 1 for the conveying arrangement of mirror unit or by according to power arranged side by side Profit requires the transportation resources for mirror unit of 7 feature to realize.Other rational forms of implementation of the conveying arrangement can To be drawn by dependent claims 2-6, the rational form of implementation of the transportation resources can be obtained by dependent claims 8-12 Go out.
According to the setting of the present invention, the conveying arrangement for mirror unit, which includes at least one, can be fixed on the side of mirror unit On end plate.Here, the end plate have with interface arrangment first longitudinal direction side and with coordinate interface arrangment second Longitudinal edge so that each end plate can be stacked with, at this point it is possible to make adjacent end plate by its interface arrangment or with card The cooperation interface arrangment that binding structure comes in contact realizes that shape is sealed or force closure.This construction causes, only can be set on side A part for conveying arrangement is put, due to the stacking finally carried out to end plate, one is defined between the mirror unit of end plate connection Fixed spacing, so as to be contacted with each other between thus avoid each mirror unit.Thus position is set between the end plate being stacked with Safe distance between mirror unit.That is, incited somebody to action as long as the materials'use amount and workload in packaging mirror unit are reduced to End plate is arranged on the side of mirror unit, it is only necessary to will prepare the mirror unit phase of transport in the case where making each end plate contact with each other Mutually it is stacked up.
Here particularly set, the interface arrangment on the first longitudinal direction side of end plate includes retraction portion.The retraction portion causes mirror A part for the side of unit keeps not covered by the end plate.But the cooperation card on the second longitudinal direction side of the adjacent end plate of structure identical Binding structure is embedded in this uncovered part of the retraction portion and the side for covering mirror unit.Constructed by this, it is to avoid Lateral sliding occurs for mirror unit, because being correspondingly situated at the mirror list that following mirror unit fixes face disposed thereon with its end plate Member.That is, fixation and downward support in the whole plane of mirror unit are thus achieved, so as to can only take out upwards Mirror unit.Particularly advantageously, interface arrangment and cooperation interface arrangment are not set to that obstruction is taken out upwards.
In addition, end plate can have two vertical edges for carrying interface arrangment, these interface arrangments on vertical edge realize with Adjacent same end plate it is laterally attached.These interface arrangments can very advantageously be designed so that these interface arrangments point Not with the same interface arrangment mating reaction of the end plate of preferred 180 ° of a rotation, stagger respectively so as to be arranged side by side 180 ° of mirror unit, and be connected with each other in side.By this arrangement form staggeredly, especially for trapezoidal horizontal stroke The mirror unit in section, can overlappingly set the mirror unit, to realize another section space-efficient effect herein.With by same The orientation in direction is arranged side by side mirror unit and compared, it is possible thereby to dispose more mirror units in identical space.
In order to preferably operate mirror unit, the end plate of the mirror unit is equipped with rotary shaft or the receiving for rotary shaft Portion, by means of the rotary shaft or receiving portion, can realize the whole arrangement knot being made up of end plate and mirror unit when needed Rotation of the structure around rotary shaft.When for example being conveyed by lowering or hoisting gear, it is possible thereby to elevating movement is superimposed with rotary motion, from And each mirror unit can be installed with correct rotation position.
In order to further simplify transport, conveying arrangement can also include basal orbit, and the basal orbit is rest directly upon On ground and nethermost end plate can be directly loadable into the basal orbit.Therefore, basal orbit has longitudinal slot, end Plate is fitted into the longitudinal slot with its longitudinal edge.This allows to lift whole delivery unit using basal orbit, without Worry delivery unit is scattered, and end plate is protected in longitudinal slot, prevents the longitudinal sliding motion along mirror unit.In basal orbit In rational embodiment, it can particularly block in basal orbit in the longitudinal slot of basal orbit provided with least one Binding structure and/or coordinate interface arrangment, the interface arrangment and/or coordinate interface arrangment correspond to longitudinal edge interface arrangment and Constitute and work corresponding thereto with coordinating interface arrangment.Therefore the interface arrangment of end plate can load basal orbit Coordinate in interface arrangment, on the contrary, the cooperation interface arrangment of end plate can be fitted into the interface arrangment of basal orbit.It thus ensure that Reliably accommodate nethermost mirror unit layer inside delivery unit.Here also set, the interface arrangment of basal orbit and cooperation block Binding structure is set by alternate order, so that the mirror unit that can be also realized when for example there is trapezoidal cross-section is overlapping.
Furthermore, it is possible to arrange at least one at least one basal orbit in two basal orbits for delivery unit Roll or sliding members, so that by lifting delivery unit in one side on the basal orbit opposite with rolling or sliding members Whole delivery unit can just moved.For example delivery unit can be lifted in side using ground transport vehicle, then can be with Arbitrarily it is moved forward or rearward, so as to mobile whole unit, without it is entirely lifted.
Therefore, the delivery unit so constituted can be transported to infield and here by hoisting apparatus as overall The delivery unit is broken., can be particularly advantageously single directly from transport by each single mirror unit when breaking delivery unit Member is placed on bogey, and mirror unit should be arranged on the bogey.In the transport from delivery unit to bogey During, it is necessary to when can make while being suspended on crane corresponding mirror unit rotate about axle rotation, so as to Mirror unit is arranged on bogey upward with the mirrored sides of mirror unit.The bogey advantageously has track system here System, mirror unit can be moved along bogey on rail system.Thus, it is possible to which each single mirror unit is placed on into bogey An end, mirror unit is then moved to by its installation site by rail system.Here it can set, end plate is designed to make Obtaining end plate can move in rail system, so that corresponding end plate is just removed in installed position, in installed position, mirror list Member is fixed on the bearing for its setting.But alternatively can also place (onto bogey) after at once from mirror unit End plate is removed, and mirror unit is brought to its installation site using dynamic sliding part can be moved up in rail set.Can in one kind below In another form of implementation of energy property, the sliding part of oneself can be set to each mirror unit, the sliding part is finally fixed at In installation site.
Brief description of the drawings
The present invention is described in detail below with reference to embodiment.
Wherein:
Fig. 1 illustrates the details that mirror unit carries the end plate being mounted laterally with the solid from oblique upper,
Fig. 2 illustrates basal orbit with the solid from oblique upper,
Fig. 3 illustrates delivery unit with the side view for observing end plate used herein, wherein saving an end plate and with laterally Section view illustrates basal orbit,
Fig. 4 illustrates delivery unit with the solid from oblique upper, and
Fig. 5 is illustrated in mirror unit to be placed in the solar electricity generation field equally shown with the solid from oblique upper In the delivery unit of infield when on bogey.
Embodiment
Fig. 1 shows mirror unit 1, and the mirror unit 1 mainly by the housing with trapezoidal cross-section and is fixed on housing Speculum 2 is constituted.For housing, side 3 is can be seen only partially, the side 3 protrudes from the end plate 10 being fixed on the side 3 Edge.This protrusion is set intentionally, is reversely fixed by adjacent end plate 19 to realize, its end plates 10 Some parts protrude from mirror unit 1 in itself, so that itself can contact adjacent mirror unit.Thus, end plate 10 is first With first longitudinal direction side 11, the first longitudinal direction side 11 has retraction portion as interface arrangment 12.It is relative with first longitudinal direction side 11 Ground is provided with second longitudinal direction side 13, and the second longitudinal direction side has the corresponding cooperation interface arrangment 14 of projecting manner, the projection It is used as the counterpart of the interface arrangment 12 on first longitudinal direction side 11 according to its shape.End plate 10 is by rotating fixed part 16 and mirror list Member 1 is connected and with receiving portion 15, for alloing longitudinal axis of the rotary shaft that mirror unit 1 rotates along mirror unit 1 to be arranged on institute State in receiving portion 15.
Fig. 2 shows basal orbit 20, and the nethermost layer that mirror unit 1 is constituted can be fitted into the basal orbit.For this Two such basal orbits 20 are set with abreast mutually staggering, mirror unit is set equal between the two basal orbits 20 The spacing of 1 length.Shown basal orbit 20 has visible cooperation interface arrangment 23, and the cooperation interface arrangment 23 is embedded in In the interface arrangment 12 for the end plate 10 being placed on basal orbit 20.The part on first longitudinal direction side 11 loads basal orbit 20 In longitudinal slot 21, and coordinate in the link structure 12 of interface arrangment 23 and thus prevent mirror unit 1 and be connected with mirror unit 1 The vertically moving along longitudinal slot 21 of end plate 10.On the contrary, the border of longitudinal slot 21 prevents the cunning transverse to longitudinal slot 21 It is dynamic, so that so that nethermost mirror unit layer can only be taken out from basal orbit 20 by lifting.
But it is not shown in fig. 2, also there is the interface arrangment 22 with coordinating interface arrangment 23 to be alternately arranged, rotation 180 ° of mirror unit 1 can be inserted in the interface arrangment 22 with its end plate 10, in such a case, it is possible to by the second of end plate 10 The cooperation interface arrangment 14 of longitudinal edge 13 is fitted into (in the interface arrangment 22).Basal orbit 20 additionally has supporting member 24, the supporting member 24 can be provided with roller when needed.
Fig. 3 shows a kind of possible delivery unit 8, in the delivery unit 8, and 180 ° are abreast rotated with four alternatings The mirror unit of setting is mated formation in the shown basal orbit 21 only shown with the sectional view along longitudinal slot 21 as orlop.Often The individual mirror unit 1 for loading basal orbit 20 is all with other placed on it three mirror unit 1, the end plate being connected with mirror unit 10th, it is assembled into the wall portion being made up of end plate 10,19 19 puzzle types.In the figure 3 representation, in order to preferably show, eliminate One of end plate 10, so that in this position, it can be seen that the position of adjacent side 3 each other.Here it can hold Change places discovery, laterally adjacent mirror unit 1 may be arranged so that the housing phase mutual respect of mirror unit 1 due to its trapezoidal cross section Folded/overlap joint, is arranged in delivery unit 8 so as to realize that mirror unit 1 is closely aligned.
As described above, the basal orbit 20 being supported on supporting member 24 both has interface arrangment in its longitudinal slot 22, it may have coordinate interface arrangment 23., first will be with its mirrored sides down when loading basal orbit 20 by shown form of implementation Mirror unit 1 insert in existing each interface arrangment 22, and insert all 180 ° of rotations and with its mirrored sides down Mirror unit 1 after, to the mirror unit 1 of its mirrored sides upward load it is still remaining, with its coordinate interface arrangment 23 position Put.Thus, the interface arrangment 18 being arranged on vertical edge 17 is mutually rabbeted and each end plate 10 is laterally being connected with each other.Complete After the orlop of mirror unit 1, one layer is loaded on the orlop upper berth, wherein, stackedly adjacent, structure identical is in addition End plate 19 with the identical strike orientation of end plate 10 under it.The other end plate 19 is on its first longitudinal direction side 11 With interface arrangment 12, thus the cooperation interface arrangment 14 on the second longitudinal direction side 13 of the interface arrangment and end plate 10 is halved together and Prevent mirror unit 1 from being moved in the whole arrangement of delivery unit 8.As shown in the region for save end plate, lead to Cross corresponding mirror unit 1 overlapping on adjacent end plate 10,19 with its side 3, efficiently avoid along direction of observation and along from Open the movement in plan direction.
Fig. 4 shows complete bogey 8, and the bogey 8 includes multiple mirror units 1, and these mirror units 1 are alternately 180 ° of ground of rotation are stratified and set on two basal orbits 20 altogether.It can be seen that, the structure of end plate 10 being connected respectively with mirror unit 1 Into side wall, the mirror unit 1 between two basal orbits 20 is held in place by the side wall.Therefore, can only by from the top down according to It is secondary that remove each layer breaks this delivery unit 8 to realize with carrying out.The transport of delivery unit 8 can be for example done by, That is, ground handling trolley is moved into side with its pallet fork between the supporting member 24 of basal orbit 20, and delivery unit 8 is lifted, and By the roller that is arranged on the second basal orbit 20 so that delivery unit 8 is moved.
Fig. 5 finally shows bogey 4, and mirror unit 1 should be arranged on the bogey in infield.Therefore, such as It is upper described, transported by means of derrick car and unload mirror unit 1, and most it is individually positioned on bogey 4 at last.By means of cunning Moving part 7, its final installation site is moved to by the mirror unit 1 that end plate 10 has been removed in this position, herein, will Mirror unit unclamps from sliding part 7, and is connected at the scene in installation site using its rotary joint.Pass through in mirror list 1 Sliding part 7 is moved along rail system 6 in reached installation site, and mirror unit can be oriented so as needed so that incident Sun pipe arrive first on the speculum of mirror unit 1, then reach the absorber 5 that rise ground is arranged on above bogey 4.
Therefore, a kind of conveying arrangement and a kind of corresponding method are foregoing described, methods described makes it possible to efficiently transport Defeated mirror unit, is to need minimal amount of transportation and packing in the transport, in addition these transportation and packing can also without any problems after It is continuous to use.
Reference numerals list
1 mirror unit
2 speculums
3 sides
4 bogeys
5 absorbers
6 rail systems
7 sliding parts
8 delivery units
9 derrick cars
10 end plates
11 first longitudinal direction sides
12 interface arrangments
13 second longitudinal direction sides
14 coordinate interface arrangment
15 receiving portions
16 rotation fixed parts
17 vertical edges
18 interface arrangments
19 other end plates
20 basal orbits
21 longitudinal slots
22 interface arrangments
23 coordinate interface arrangment
24 supporting members

Claims (12)

1. for the conveying arrangement for the mirror unit being arranged in solar electricity generation field, the conveying arrangement is used for including at least one The end plate (10) on the side of mirror unit (1) (3) is fixed on, the end plate (10) has first with interface arrangment (12) to indulge To while (11) and with coordinate interface arrangment (14) second longitudinal direction while (13), the interface arrangment of the first longitudinal direction side (11) (12) with cooperation interface arrangment (14) mating reaction on the second longitudinal direction side (13) of structure identical another end plate (19), it is special Levy and be, the interface arrangment (12) on the first longitudinal direction side (11) of the end plate (10) includes retraction portion, and the retraction portion causes institute The part for stating the side (3) of mirror unit (1) keeps not covered by the end plate (10), and adjacent described of structure identical The embedded retraction portion of the cooperation interface arrangment (14) on the second longitudinal direction side (13) of end plate (19) simultaneously covers the mirror unit (1) The uncovered part of side (3), the end plate (10) has two vertical edges (17) for carrying interface arrangment (18), described perpendicular The interface arrangment (18) on side (17) be arranged as with structure identical rotate 180 ° another end plate (19) it is same Interface arrangment (18) mating reaction.
2. conveying arrangement according to claim 1, it is characterised in that the end plate (10) is equipped with rotary shaft or is used for The receiving portion (15) of rotary shaft.
3. conveying arrangement according to claim 1 or 2, the conveying arrangement also includes at least one basal orbit (20), The basal orbit (20) has the longitudinal slot for the longitudinal edge (11,13) for being used to accommodate at least one end plate (10) (21), wherein, the basal orbit (20) be arranged at least one supporting member (24) on.
4. conveying arrangement according to claim 3, it is characterised in that be provided with clamping knot in the longitudinal slot (21) Structure (22) and/or cooperation interface arrangment (23), first longitudinal direction is accommodated with force closure at (11) and/or second longitudinal direction (13).
5. conveying arrangement according to claim 4, it is characterised in that the interface arrangment (22) and the cooperation clamping knot Structure (23) is by being alternately set in sequence in the longitudinal slot (21).
6. the conveying arrangement according to any one in claim 3 to 5, it is characterised in that the supporting member (24) is matched somebody with somebody Provided with least one rolling or sliding members.
7. for the transportation resources for the mirror unit being arranged in solar electricity generation field, wherein, it is made up of first multiple mirror units (1) Delivery unit (8), breaks the delivery unit (8) in infield, and its mode is to take out each single mirror unit (1), And the mirror unit (1) is fixed in installation site, for forming the mirror unit (1) of the delivery unit (8) in the mirror End plate (10) can not be equipped with the side (3) of unit (1) with the relative rotation respectively, the end plate (10), which has, carries clamping knot The first longitudinal direction of structure (12) is at (11) and the second longitudinal direction with cooperation interface arrangment (14) (13), and the multiple mirror list First (1) is so stacked with the case where the end plate (10) of only the multiple mirror unit (1) comes in contact so that the end The first longitudinal direction of plate (10) in the second longitudinal direction of interface arrangment (12) and the adjacent end plate (10) of (11) (13) cooperation clamping Structure (14) mating reaction.
8. method according to claim 7, it is characterised in that the nethermost mirror unit (1) with the mirror unit (1) first longitudinal direction of the end plate (10) matched at (11) and second longitudinal direction (13) loads two basic rails staggered that are parallel to each other In the longitudinal slot (21) in road (20), two basal orbits (20) are separately mounted on supporting member (24).
9. method according to claim 8, it is characterised in that first with by alternately rotating 180 ° of the mirror unit (1) first layer of composition is mated formation onto the basal orbit (20), same other layer of then mating formation on the first layer, The adjacent end plate (10) is by means of the interface arrangment on the longitudinal edge (11,13) and vertical edge (17) of the end plate (10) respectively (12,18) and interface arrangment (14) is coordinated mutually to rabbet.
10. the method according to any one in claim 7 to 9, it is characterised in that pass through hoisting apparatus in infield The delivery unit (8) is broken, its mode is that the mirror unit (1) is individually lifted and is placed on for installing institute layer by layer State on the bogey (4) of mirror unit (1), wherein, the bogey (4) is equipped with rail system (6), by means of the rail The mirror unit (1) that road system (6) is most supplied on the bogey (4) at last is moved to the peace of the mirror unit (1) Holding position.
11. method according to claim 10, it is characterised in that make the end plate (10) on the rail system (6) Move and just remove the end plate (10) in installed position.
12. method according to claim 10, it is characterised in that filled the mirror unit (1) is placed into the carrying Just remove the end plate (10) after putting on (4), and by means of sliding part (7) along the bogey (4) by the mirror unit (1) it is moved to the installation site of the mirror unit (1).
CN201710128198.5A 2016-03-04 2017-03-06 Conveying arrangement and transportation resources for the mirror unit in solar electricity generation field Pending CN107150886A (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
DE102016103997.7 2016-03-04
DE102016103997.7A DE102016103997B3 (en) 2016-03-04 2016-03-04 Transport device and method for mirror units for mounting in a solar field

Publications (1)

Publication Number Publication Date
CN107150886A true CN107150886A (en) 2017-09-12

Family

ID=59010726

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710128198.5A Pending CN107150886A (en) 2016-03-04 2017-03-06 Conveying arrangement and transportation resources for the mirror unit in solar electricity generation field

Country Status (2)

Country Link
CN (1) CN107150886A (en)
DE (1) DE102016103997B3 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110506010A (en) * 2017-04-05 2019-11-26 菲涅尔有限公司 The conveying device and method of mirror unit for being mounted in solar farm

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102021122268A1 (en) 2021-08-27 2023-03-02 Frenell Gmbh DEVICE FOR TRANSPORTING PARTICULAR GOODS

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0332186A2 (en) * 1988-03-11 1989-09-13 Aktiengesellschaft Hoechst Moulded end wall for cores of rolled material
US5096063A (en) * 1991-08-21 1992-03-17 Reynolds Consumer Products, Inc. Interlocking flange assembly for spools
WO1992006017A1 (en) * 1990-10-04 1992-04-16 Cobane Joseph L Fabric roll
US5421537A (en) * 1990-10-04 1995-06-06 Modular Concepts, Inc. Enlarged end cap assembly made from smaller end caps
EP0924137A1 (en) * 1997-12-17 1999-06-23 Compagnon, Bernabe y Cia. Ltda Container with rigid plastic end walls
JP2004207667A (en) * 2002-10-30 2004-07-22 Kyocera Corp Solar-cell module and assembling structure thereof
JP2013067395A (en) * 2011-09-21 2013-04-18 Sanko Co Ltd Transportation storage member for roll-like material
US20140144570A1 (en) * 2011-07-28 2014-05-29 Grenzebach Maschinenbau Gmbh Method and device for producing mirror units for heliostats
CN203997546U (en) * 2014-07-15 2014-12-10 尤瑞豊 Spliced film guard board structure
WO2016012650A1 (en) * 2014-07-25 2016-01-28 Solatom Csp S.L. Linear fresnel solar power system that can be transported in a goods container

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000079961A (en) * 1998-09-01 2000-03-21 Misawa Homes Co Ltd Method for transporting roof panel with solar battery and device for transporting the same
EP1617485B1 (en) * 2004-07-12 2007-06-06 Häberlein-Lehr, Ulla Modular assembling system for the safe storage of horizontally stacked photovoltaic modules during transport

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0332186A2 (en) * 1988-03-11 1989-09-13 Aktiengesellschaft Hoechst Moulded end wall for cores of rolled material
WO1992006017A1 (en) * 1990-10-04 1992-04-16 Cobane Joseph L Fabric roll
US5421537A (en) * 1990-10-04 1995-06-06 Modular Concepts, Inc. Enlarged end cap assembly made from smaller end caps
US5096063A (en) * 1991-08-21 1992-03-17 Reynolds Consumer Products, Inc. Interlocking flange assembly for spools
EP0924137A1 (en) * 1997-12-17 1999-06-23 Compagnon, Bernabe y Cia. Ltda Container with rigid plastic end walls
JP2004207667A (en) * 2002-10-30 2004-07-22 Kyocera Corp Solar-cell module and assembling structure thereof
US20140144570A1 (en) * 2011-07-28 2014-05-29 Grenzebach Maschinenbau Gmbh Method and device for producing mirror units for heliostats
JP2013067395A (en) * 2011-09-21 2013-04-18 Sanko Co Ltd Transportation storage member for roll-like material
CN203997546U (en) * 2014-07-15 2014-12-10 尤瑞豊 Spliced film guard board structure
WO2016012650A1 (en) * 2014-07-25 2016-01-28 Solatom Csp S.L. Linear fresnel solar power system that can be transported in a goods container

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110506010A (en) * 2017-04-05 2019-11-26 菲涅尔有限公司 The conveying device and method of mirror unit for being mounted in solar farm

Also Published As

Publication number Publication date
DE102016103997B3 (en) 2017-06-29

Similar Documents

Publication Publication Date Title
CN110654760B (en) Automatic warehouse system, control method, storage medium and electronic equipment
EP3512748B1 (en) Buried system for goods distribution in urban areas
CN102171132B (en) Container handling system and the method for loading and unloading container
EP3247899B1 (en) Wind turbine nacelle
ES2965298T3 (en) Air transportation and route management system
CN103587543B (en) For carrying and the loading system of rail supported conveyer
CN109071111A (en) The storage extraction element and its operating method of parallel work-flow for high rack warehouse
CN107150886A (en) Conveying arrangement and transportation resources for the mirror unit in solar electricity generation field
CN109072887A (en) Crestal line cable drives electrical energy storage system
CN101730914B (en) Container for long-term storage with removable base
CN206436842U (en) Drawer formula movable charging vehicle
US20130136546A1 (en) Regional, national and international transport-web infrastructure network system
CN103443449A (en) Wind power installation with helicopter hoisting platform
KR20130132563A (en) Hatch cover for wind driven power plant
CN108301658A (en) A kind of composite type stereo garage
CN103010691B (en) Heavy-load chain roller row
CN102152893B (en) Material circle frame automatic loading and unloading device, and main body structure and movable carrier thereof
CN205693532U (en) Large Rotor mounting
CN211569066U (en) Cargo inspection device based on cloud storage
CN107393154A (en) Vending machine
CN205971994U (en) Pet urine fills up automatic module of packing
US20200115124A1 (en) Mirror unit transport device and method for assembling in a solar field
CN104370057A (en) Refrigerated container door plate storing and conveying line and storing and conveying method
WO2023094706A1 (en) Instrument for the inspection of one or more packages distributed in a gallery to be inspected, and associated inspection facility
KR102063588B1 (en) Pinion gear vertically fixed moving vehicle and pinion gear vertical fixing method using the same

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170912