CN107143171B - Garbage incinerating power plant main building arrangement structure - Google Patents

Garbage incinerating power plant main building arrangement structure Download PDF

Info

Publication number
CN107143171B
CN107143171B CN201710364644.2A CN201710364644A CN107143171B CN 107143171 B CN107143171 B CN 107143171B CN 201710364644 A CN201710364644 A CN 201710364644A CN 107143171 B CN107143171 B CN 107143171B
Authority
CN
China
Prior art keywords
main building
workshop
power plant
burning
steam turbine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710364644.2A
Other languages
Chinese (zh)
Other versions
CN107143171A (en
Inventor
胡琨
张鹏
徐斌
马雪松
吕小兰
李伟科
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Energy Engineering Group Guangdong Electric Power Design Institute Co Ltd
Original Assignee
China Energy Engineering Group Guangdong Electric Power Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Energy Engineering Group Guangdong Electric Power Design Institute Co Ltd filed Critical China Energy Engineering Group Guangdong Electric Power Design Institute Co Ltd
Priority to CN201710364644.2A priority Critical patent/CN107143171B/en
Publication of CN107143171A publication Critical patent/CN107143171A/en
Application granted granted Critical
Publication of CN107143171B publication Critical patent/CN107143171B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H5/00Buildings or groups of buildings for industrial or agricultural purposes
    • E04H5/02Buildings or groups of buildings for industrial purposes, e.g. for power-plants or factories

Abstract

The invention discloses a kind of garbage incinerating power plant main building arrangement structure, including main building ontology, the main building is set inside the body between burning, and the lower section between the burning is provided with the vacant area of workshop;Turbo-generator Set, the Turbo-generator Set are set in the vacant area of the workshop;And steam turbine subsidiary engine equipment, the steam turbine subsidiary engine equipment are set in the vacant area of the workshop and are located at side of the Turbo-generator Set between the burning.So can avoid the vacant area of workshop that lower section is formed between making to burn causes vacant waste or utilization rate not high, by optimizing arrangement to each equipment, it is greatly improved the utilization rate of workshop inner space, avoids the usage economy for improving main building there are excessive space waste.

Description

Garbage incinerating power plant main building arrangement structure
Technical field
The present invention relates to garbage incinerating power plant technical fields, more particularly to a kind of garbage incinerating power plant main building cloth Set structure.
Background technique
The incinerator in country's garbage incinerating power plant generally uses stoker fired grate, and main power house of power plant arrangement knot at present Structure is generally pressed between burning (containing incinerator, waste heat boiler, pit etc.), between steam turbine and the several modules of deaerator bay are arranged;Wherein Usually individually be arranged in a workshop between burning, and between steam turbine and deaerator bay be then individually arranged in it is another between in workshop, two Workshop is disposed adjacent.In view of the work characteristics of stoker fired grate formula incinerator, rubbish heap on slag tap height and stoker fired grate The space requirement put is larger, thus needs the waste heat boiler for absorbing the heat that incineration firing generates being arranged in higher position.It presses At present the case where country's garbage incinerating power plant, waste heat boiler generallys use horizontal arrangement natural recirculating type water-tube boiler, such Type waste heat boiler is normally supported on 15 meters of platforms, vacant larger space out below platform, and the space usually only arranges Remove the gred the less equipment such as workshop and pipe sandwich, still has most of space to be underutilized, there are biggish space waste, Influence the utilization rate and economy of main building.
Summary of the invention
Based on this, it is necessary to provide a kind of garbage incinerating power plant main building arrangement structures by the present invention, by each equipment Arrangement is optimized, the utilization rate of workshop inner space is greatly improved, avoids improving main building there are excessive space waste Usage economy.
Its technical solution is as follows:
A kind of garbage incinerating power plant main building arrangement structure, comprising:
Main building ontology, the main building are set inside the body between burning, and the lower section between the burning is provided with workshop Vacant area;
Turbo-generator Set, the Turbo-generator Set are set in the vacant area of the workshop;And
Steam turbine subsidiary engine equipment, the steam turbine subsidiary engine equipment are set in the vacant area of the workshop and are located at the steamer and sends out Motor group deviates from the side between the burning.
When above-mentioned garbage incinerating power plant main building arrangement structure building, between in the inside of main building ontology, setting is burned, Lower section between burning reserves the vacant area of workshop, and Turbo-generator Set is arranged in the vacant area of workshop later, while by steam turbine Subsidiary engine equipment is arranged in the vacant area of workshop and is located at side of the Turbo-generator Set between burning.So it can avoid making to burn Between lower section formed the vacant area of workshop cause it is vacant waste or utilization rate it is not high, can be big by optimizing arrangement to each equipment The big utilization rate for improving workshop inner space, avoids the usage economy that main building is improved there are excessive space waste.
Technical solution is further described below:
The main building ontology is additionally provided between gas cleaning in one of the embodiments, is provided in the burning Waste heat boiler, between the steam turbine subsidiary engine equipment is arranged between the waste heat boiler and the gas cleaning.
The vacant area of the workshop includes the first mounting layer in one of the embodiments, and the steam turbine subsidiary engine equipment includes Oxygen-eliminating device and boiler blow down flash device, the oxygen-eliminating device and the boiler blow down flash device are arranged in first mounting layer. It can so make full use of the vacant area of workshop to be located at the space of the first installation layer region, avoid space waste, can also reduce Connecting pipe length between oxygen-eliminating device and continuous sewage-discharge volum expander for boiler.
The steam turbine subsidiary engine equipment further includes water supply pump group in one of the embodiments, and the water supply pump group includes giving Water pump, industrial water pump and hydrophobic development unit, the vacant area of workshop further include the second peace below first mounting layer Layer is filled, the feed pump, the industrial water pump and the hydrophobic development unit are arranged in second mounting layer and are located at described At zero meter of the lower section of oxygen-eliminating device.So ensuring sufficiently using the vacant area of workshop positioned at the same of the space of the second installation layer region When, the connecting pipe length between oxygen-eliminating device and feed pump can also be reduced, the resistance of ducting is reduced, reduces feed pump energy consumption, drop Low cost expenditure, improves the economy in power plant.
The vacant area of the workshop further includes pipe sandwich in one of the embodiments, and the steam turbine subsidiary engine equipment is also wrapped Heater is included, the heater is set to the pipe sandwich and between the oxygen-eliminating device and the water supply pump group.Thus By guaranteeing that heater condensate is smooth, energy can at pipe sandwich that heater is arranged between oxygen-eliminating device and water pump group While by recycling, the space utilization rate in the vacant area of workshop can also be further promoted, reduces main building because of space waste Economic attrition caused by and.
Be additionally provided at least one incinerator in the burning in one of the embodiments, the incinerator it is upper Portion's flue gas horizontally enters into the waste heat boiler.Inner space between burning can not only further made full use of, is improved The space efficiency utilization of main building ontology, while the garbage disposal efficiency in power plant can also be greatly promoted.
The steam turbine subsidiary engine equipment further includes low-pressure heater in one of the embodiments, the low-pressure heater with The Turbo-generator Set is in same layer absolute altitude.So can by the steam turbines subsidiary engine equipment such as low-pressure heater and Turbo-generator Set into One-step optimization configuration, it is ensured that enable power plant to stablize while improving space utilization rate, efficient operation, promote each unit operation Economy.
Slag treatment equipment, the slag treatment equipment are additionally provided in the burning in one of the embodiments, Positioned at the lower section of the incinerator.The region being located at below incinerator between burning can be so made full use of, the rubbish after burning is made Waste residue is able to reliable treatments, it is ensured that power plant has preferable slag treatment performance, it is ensured that surrounding sanitation.
Detailed description of the invention
Fig. 1 is the overlooking structure diagram of garbage incinerating power plant main building arrangement structure described in the embodiment of the present invention;
Fig. 2 is the side structure schematic view of garbage incinerating power plant main building arrangement structure described in the embodiment of the present invention.
Description of symbols:
100, main building ontology, between 110, burning, 120, the vacant area of workshop, the 121, first mounting layer, the 122, second installation Layer, 123, pipe sandwich, 200, Turbo-generator Set, 300, steam turbine subsidiary engine equipment, 310, oxygen-eliminating device, 330, water supply pump group, 340, heater, 400, waste heat boiler, 500, incinerator, 600, slag treatment equipment.
Specific embodiment
To make the objectives, technical solutions, and advantages of the present invention more comprehensible, below in conjunction with attached drawing and specific embodiment party Formula, the present invention is further described in detail.It should be understood that the specific embodiments described herein are only to solve The present invention is released, and the scope of protection of the present invention is not limited.
It should be noted that when element is referred to as " being fixedly arranged on ", " being set to " or " install in " another element, it can be with Directly on the other element or there may also be elements placed in the middle.When an element is considered as " connection " another yuan Part, it can be directly to another element or may be simultaneously present centering elements;One element and another element The concrete mode being fixedly connected can be achieved by the prior art, and details are not described herein, it is preferred to use the fixation side of threaded connection Formula.
Unless otherwise defined, all technical and scientific terms used herein and belong to technical field of the invention The normally understood meaning of technical staff is identical.Term as used herein in the specification of the present invention is intended merely to description tool The purpose of the embodiment of body, it is not intended that in the limitation present invention.Term " and or " used herein includes one or more Any and all combinations of relevant listed item.
Heretofore described " first ", " second " do not represent specific quantity and sequence, are only used for the differentiation of title.
As shown in Fig.1 and Fig.2, a kind of garbage incinerating power plant main building arrangement structure shown for the embodiment of the present invention, packet Include: main building ontology 100, the inside of the main building ontology 100 are equipped with 110 between burning, 110 lower section setting between the burning There is the vacant area 120 of workshop;Turbo-generator Set 200, the Turbo-generator Set 200 are set in the vacant area 120 of the workshop; And steam turbine subsidiary engine equipment 300, the steam turbine subsidiary engine equipment 300 are set in the vacant area 120 of the workshop and are located at the steamer Generating set 200 deviates between the burning 110 side.
When above-mentioned garbage incinerating power plant main building arrangement structure building, it is arranged in the inside of main building ontology 100 and burns Between 110,110 lower section reserves the vacant area 120 of workshop between burning, and it is vacant that Turbo-generator Set 200 is arranged in workshop later In area 120, while steam turbine subsidiary engine equipment 300 being arranged in the vacant area 120 of workshop and is deviated from positioned at Turbo-generator Set 200 and is burnt 110 side between burning.It so can avoid the vacant area 120 of workshop that 110 lower sections are formed between making to burn and cause vacant waste or use Rate is not high, by optimizing arrangement to each equipment, is greatly improved the utilization rate of workshop inner space, avoids existing excessively Space waste improves the usage economy of main building.
Specifically, above-mentioned main building ontology 100 can be used, armored concrete casting is manufactured, metal framework and steel plate are spelled Be connected into type etc., preferably using the manufacture of metal framework and steel plate splicing, have that difficulty of construction is low, the manufacturing cycle is short and at This is low, while can repeat the advantages of recycling.
In one embodiment, the main building ontology 100 is additionally provided with (not shown) between gas cleaning, the burning Between be provided with waste heat boiler 400 in 110, the steam turbine subsidiary engine equipment 300 is arranged in the waste heat boiler 400 and the flue gas is net Between between change.So by arranging steam turbine subsidiary engine equipment 300 between waste heat boiler 400 and gas cleaning, can mention significantly Space utilization rate inside high main building ontology 100.Wherein, for removing the flue gas of the discharge of waste heat boiler 400 between gas cleaning In pernicious gas, impurity etc.;Waste heat boiler 400 is used to recycle the heat for the high-temperature flue gas that incinerator 500 is discharged by heat exchange Amount improves the ability utilization efficiency of power plant system, promotes economy.
Referring to figure 2., in addition, the vacant area 120 of the workshop includes the first mounting layer 121, the steam turbine subsidiary engine equipment 300 Including oxygen-eliminating device 310 and boiler blow down flash device (not shown), the oxygen-eliminating device 310 and the boiler blow down flash device are equal It is arranged in first mounting layer 121.The vacant area 120 of workshop can be so made full use of to be located at the sky in 121 region of the first mounting layer Between, avoid space waste.
Further, the steam turbine subsidiary engine equipment 300 further includes water supply pump group 330, and the water supply pump group 330 includes water supply Pump, industrial water pump and hydrophobic development unit, the vacant area 120 of workshop further include positioned at the of 121 lower section of the first mounting layer Two mounting layers 122, the feed pump, the industrial water pump and the hydrophobic development unit are arranged in second mounting layer 122 And it is located at zero meter of the lower section of the oxygen-eliminating device 310.So ensuring that the vacant area 120 of workshop is sufficiently used to be located at the second mounting layer While the space in 122 regions, the connecting pipe length between oxygen-eliminating device 310 and feed pump can also be reduced, reduces pipeline damage Consumption reduces cost payout, improves the economy in power plant.
Further, the vacant area 120 of the workshop further includes pipe sandwich 123, and the steam turbine subsidiary engine equipment 300 is also wrapped Heater 340 is included, the heater 340 is set to the pipe sandwich 123 and is located at the oxygen-eliminating device 310 and the feed pump Between group 330.It, can be with thus by arranging heater 340 at the pipe sandwich 123 between oxygen-eliminating device 310 and water pump group The space utilization rate for further promoting the vacant area 120 of workshop, economic attrition caused by reducing main building due to space waste.
As depicted in figs. 1 and 2, in addition, being additionally provided at least one incinerator 500, the burning in 110 between the burning The upper smoke gas of furnace 500 horizontally enters into the waste heat boiler 400.Optionally it is simutaneously arranged the incinerator of two or more quantity 500, between burning 110 inner space can not only further made full use of, the space benefit of main building ontology 100 is improved With efficiency, while the garbage disposal efficiency in power plant can also be greatly promoted.
On the basis of the above embodiments, the steam turbine subsidiary engine equipment 300 further includes low-pressure heater, the low-pressure heating Device and the Turbo-generator Set 200 are in same layer absolute altitude.It so can be by the steam turbines subsidiary engine such as low-pressure heater equipment 300 and steamer Generating set 200 advanced optimizes configuration, it is ensured that and so that power plant is stablized while improving space utilization rate, efficient operation, Promote each unit performance driving economy.
Further, 110 between the burning in be additionally provided with slag treatment equipment 600, the slag treatment equipment 600 In the lower section of the incinerator 500.110 region below incinerator 500 between burning can be so made full use of, after making burning Rubbish waste residue be able to reliable treatments, it is ensured that power plant have preferable slag treatment performance, it is ensured that surrounding sanitation.
Each technical characteristic of embodiment described above can be combined arbitrarily, for simplicity of description, not to above-mentioned reality It applies all possible combination of each technical characteristic in example to be all described, as long as however, the combination of these technical characteristics is not deposited In contradiction, all should be considered as described in this specification.
The embodiments described above only express several embodiments of the present invention, and the description thereof is more specific and detailed, but simultaneously It cannot therefore be construed as limiting the scope of the patent.It should be pointed out that coming for those of ordinary skill in the art It says, without departing from the inventive concept of the premise, various modifications and improvements can be made, these belong to protection of the invention Range.Therefore, the scope of protection of the patent of the invention shall be subject to the appended claims.

Claims (8)

1. a kind of garbage incinerating power plant main building arrangement structure characterized by comprising
Main building ontology, the main building are set inside the body between burning, and it is vacant that the lower section between the burning is provided with workshop Area, the vacant area of workshop include the first mounting layer and the second mounting layer below first mounting layer;
Turbo-generator Set, the Turbo-generator Set are set in the vacant area of the workshop;And
Steam turbine subsidiary engine equipment, the steam turbine subsidiary engine equipment are set in the vacant area of the workshop and are located at the steam turbine generator Side of the group between the burning;The steam turbine subsidiary engine equipment includes oxygen-eliminating device and water supply pump group, and the water supply pump group includes Feed pump, the feed pump are arranged in second mounting layer and are located at zero meter of the lower section of the oxygen-eliminating device.
2. garbage incinerating power plant main building arrangement structure according to claim 1, which is characterized in that the main building sheet Body is additionally provided between gas cleaning, is provided with waste heat boiler in the burning, the steam turbine subsidiary engine equipment is arranged in the waste heat Between between boiler and the gas cleaning.
3. garbage incinerating power plant main building arrangement structure according to claim 1, which is characterized in that the steam turbine subsidiary engine Equipment further includes boiler blow down flash device, and the oxygen-eliminating device and the boiler blow down flash device are arranged in first installation Layer.
4. garbage incinerating power plant main building arrangement structure according to claim 1, which is characterized in that the water supply pump group It further include industrial water pump and hydrophobic development unit, the industrial water pump and the hydrophobic development unit are arranged in second mounting layer And it is located at zero meter of the lower section of the oxygen-eliminating device.
5. garbage incinerating power plant main building arrangement structure according to claim 1 or 4, which is characterized in that the workshop Vacant area further includes pipe sandwich, and the steam turbine subsidiary engine equipment further includes heater, and the heater is set to the pipeline folder Layer and between the oxygen-eliminating device and the water supply pump group.
6. garbage incinerating power plant main building arrangement structure according to claim 2, which is characterized in that in the burning It is additionally provided at least one incinerator, the upper smoke gas of the incinerator horizontally enters into the waste heat boiler.
7. garbage incinerating power plant main building arrangement structure according to claim 1, which is characterized in that the steam turbine subsidiary engine Equipment further includes low-pressure heater, and the low-pressure heater and the Turbo-generator Set are in same layer absolute altitude.
8. garbage incinerating power plant main building arrangement structure according to claim 6, which is characterized in that in the burning It is additionally provided with slag treatment equipment, the slag treatment equipment is located at the lower section of the incinerator.
CN201710364644.2A 2017-05-22 2017-05-22 Garbage incinerating power plant main building arrangement structure Active CN107143171B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710364644.2A CN107143171B (en) 2017-05-22 2017-05-22 Garbage incinerating power plant main building arrangement structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710364644.2A CN107143171B (en) 2017-05-22 2017-05-22 Garbage incinerating power plant main building arrangement structure

Publications (2)

Publication Number Publication Date
CN107143171A CN107143171A (en) 2017-09-08
CN107143171B true CN107143171B (en) 2019-06-28

Family

ID=59778529

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710364644.2A Active CN107143171B (en) 2017-05-22 2017-05-22 Garbage incinerating power plant main building arrangement structure

Country Status (1)

Country Link
CN (1) CN107143171B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108086727A (en) * 2017-12-25 2018-05-29 中国能源建设集团广东省电力设计研究院有限公司 Waste incineration and generating electricity integrates plant layout structure
CN110130685A (en) * 2019-05-09 2019-08-16 山西省工业设备安装集团有限公司 A kind of domestic garbage burning electricity generation construction techniques

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201198663Y (en) * 2008-04-17 2009-02-25 上海电气工程设计有限公司 Main power drive type arrangement of thermal power generation plant
CN102677924A (en) * 2011-03-18 2012-09-19 中国电力工程顾问集团华东电力设计院 Main workshop provided with high-position steam turbine room and low-position steam turbine room and having deaerator and high-pressure heater in improved arrangement
CN203487818U (en) * 2013-08-09 2014-03-19 华能国际电力股份有限公司 Main power house of thermal power plant
JP2016041939A (en) * 2015-10-20 2016-03-31 株式会社タクマ Waste power generation system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201198663Y (en) * 2008-04-17 2009-02-25 上海电气工程设计有限公司 Main power drive type arrangement of thermal power generation plant
CN102677924A (en) * 2011-03-18 2012-09-19 中国电力工程顾问集团华东电力设计院 Main workshop provided with high-position steam turbine room and low-position steam turbine room and having deaerator and high-pressure heater in improved arrangement
CN203487818U (en) * 2013-08-09 2014-03-19 华能国际电力股份有限公司 Main power house of thermal power plant
JP2016041939A (en) * 2015-10-20 2016-03-31 株式会社タクマ Waste power generation system

Also Published As

Publication number Publication date
CN107143171A (en) 2017-09-08

Similar Documents

Publication Publication Date Title
CN107143171B (en) Garbage incinerating power plant main building arrangement structure
CN106089341A (en) Strengthen the method that in many gas turbines combined cycle power plant, cold steamturbine starts
CN101319788A (en) High performance fuel heat accumulation type condensation energy-saving boiler
CN109339877B (en) Coal-based distributed energy supply system
CN204829985U (en) Multipurpose biomass combustion power generation facility
CN102374538A (en) Garbage-incinerating circulated power-generating system
CN203147726U (en) Pi-structural catalytic unit CO incineration waste heat boiler
CN110145754A (en) It can prevent the boiler flue gas treatment system and method for back-end surfaces low-temperature corrosion
CN109373332A (en) A kind of flue gas waste heat recovery system and method for coal-fired coupling garbage power
CN204665282U (en) Use the incinerator of biogas and oil
CN211647500U (en) Compact three-row steam turbine room structure of 660MW coal-fired generator set
CN108443854A (en) A kind of energy-saving, environmental protection boiler
CN204678302U (en) Waste gas residual heat reclaims conversion steam device and jet dynamic control
CN205860468U (en) A kind of stack boiler
CN108086727A (en) Waste incineration and generating electricity integrates plant layout structure
CN204717661U (en) A kind of industrial combustion gas steam generator system
CN205481020U (en) High -efficient small -size waste incinerator of multilayer formula
CN217635643U (en) Hearth structure of solid waste incineration boiler
CN211119383U (en) Indirect steam coupling system of incinerator
CN203687169U (en) Boiler exhaust smoke waste heat efficient recovery device
RU67241U1 (en) STEAM DISPOSAL SYSTEM
CN210485682U (en) Continuous blowdown system of gas turbine exhaust-heat boiler
CN101463995B (en) Single heat accumulation type steam-filling boiler using liquid fuel, and its combustion method
CN208282123U (en) A kind of air heater apparatus
CN210398862U (en) Efficient shale-combustion gas-water pipe steam boiler

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant