CN107100218A - One kind is used for rock foundation fracture belt and handles construction method across lid - Google Patents
One kind is used for rock foundation fracture belt and handles construction method across lid Download PDFInfo
- Publication number
- CN107100218A CN107100218A CN201710363512.8A CN201710363512A CN107100218A CN 107100218 A CN107100218 A CN 107100218A CN 201710363512 A CN201710363512 A CN 201710363512A CN 107100218 A CN107100218 A CN 107100218A
- Authority
- CN
- China
- Prior art keywords
- fracture belt
- rock
- lid
- foundation
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D37/00—Repair of damaged foundations or foundation structures
Abstract
It is used for rock foundation fracture belt across lid processing construction method the invention discloses one kind, completely decomposed and highly weathered rock are cleared up using machinery with being manually combined by way of in rock fracture band, and at least 1 meter is extended out in original be broken on the basis of bandwidth to both sides;Design below raft foundation bottom absolute altitude 2.0m concrete levelings, then reinforcing bar is laid on request at fracture belt more than levelling rear 2.0m depth, casting concrete, using being filled by the way of lid, the width that fracture belt extends to both sides can ensure the supporting surface across lid on more complete middle decayed rock.The present invention is handled fracture belt both sides solid rock using across lid, on the premise of foundation bearing capacity requirement is met, is enhanced the globality and stability of foundation, is simplified construction technology, saved cost.
Description
Technical field:
The present invention relates to technical field of buildings, particularly a kind of rock foundation fracture belt that is used for is across lid processing construction method.
Background technology:
As the development of china's economy, the particularly quickening of urbanization process, skyscraper is more and more, building ground is carried out
The processing on base basis, which is operated in, to seem in the work progress of whole engineering and is even more important.Rock foundation is good foundation,
But the rock foundation of some areas may have crack, when fracture width, which reaches, forms rock fracture band to a certain degree,
The problem of foundation deformation can not meet design requirement just occurs, with the increasing of building dead weight, triggers ground uneven
Sedimentation, is that construction quality hides some dangers for.
The content of the invention:
To solve problems, it is used for rock foundation fracture belt across lid processing construction method the invention provides one kind, is ensureing
On the premise of foundation bearing capacity, the globality and stability of foundation are enhanced, preferable economic benefit is obtained and society imitates
Benefit.
The technical solution adopted by the present invention is:
One kind is used for rock foundation fracture belt and handles construction method across lid, it is characterised in that:Comprise the following steps:
1)Unwrapping wire and technique check:Determine fracture belt position and absolute altitude, axle are carried out using measuring instrument position across lid to fracture belt
The position determination checked with raft foundation, the determination of line are accorded with across the thickness of slab of cover plate and its support width on the solid rock of both sides
Close and require;
2)Cleaning:Fracture belt is cleared up, using manually with being carried out by the way of mechanical work compound when fracture belt is cleared up, first with machinery
It will be dug under fracture belt to design raft foundation bottom absolute altitude -3.0m places, then manually to complete in the rock foundation of fracture belt both sides
Weathering and highly weathered rock are handled to design raft foundation bottom absolute altitude -4.0m places, on the basis of original fracture bandwidth
At least one meter is extended out to both sides, to ensure that supporting surface is supported on solid rock, ensured on the solid rock of fracture belt both sides
Rubble and the poor completely decomposed rock of bearing capacity are cleaned out;
3)Crack is levelling:Treat step 1)With 2)After the completion of, using concrete to the design raft foundation absolute altitude -2.0m of fracture belt with
Under h1 regions change to fill out and pour and levelling, complete concrete leveling layer;
4)Reinforcing bar colligation:Treat step 3)In fracture belt at concrete leveling layer intensity reach after construction requirement, then disconnected
Split and carry out laying reinforcing bar operation on request with h2 regions more than levelling rear -2.0m depth, flow is as follows:
Reinforcement location line → fortune reinforcing bar is played to using in position → colligation securing plate lower rebar → placement reinforced bar support → colligation
Portion's reinforcing bar → setting posting → steel corrosion quantity;
5)Concrete placings, maintenance:Treat step 4)Reinforcing steel bar laying operation after the completion of to reinforced bar engineering carry out concealment acceptance, it is qualified laggard
The concreting operation in h2 regions more than row fracture belt -2.0m depth, the mode that pours of concrete uses inclined plane delamination, one
The secondary mode to top pours and circulates propulsion, and every layer pours thickness control within 500mm, when pouring, be in next layer of coagulation
Poured before native initial set and smash last layer concrete, must not made to produce the cold seam of construction between levels, to keep well connecing raft, improve mixed
Coagulating the compactness of soil, and carrying out maintenance to the concrete in the step in time by the way of covering, insulation can complete across lid
Plate is poured.
2. a kind of rock foundation fracture belt that is used for according to claim 1 handles construction method across lid, its feature exists
In:
More than 1 meter is respectively extended out on the width of the fracture belt both sides, is dug under thickness direction(h1+100mm)+(h2+100mm),
Wherein 100mm is concrete leveling thickness, and across cover plate supported on both sides is on solid rock, support width >=1000mm.
Compared with prior art, the beneficial effects of the present invention are:
It is convenient and quick construction of the present invention, cheap, provided for fracture belt dealing with foundation and facilitate feasible method;Using across
Lid(Reinforced concrete raft plate is crossed over)Processing engineering method is handled fracture belt both sides solid rock, is meeting foundation bearing capacity requirement
Under the premise of, enhance the globality and stability of foundation;Reinforce band size and Reinforcement Design rationally, economic effect is obvious;
Manual digging pile construction is avoided, based process difficulty is reduced.
Brief description of the drawings:
Fig. 1 is constructing structure schematic diagram of the invention.
Embodiment:
Below in conjunction with the accompanying drawings, the present invention is described in further detail by embodiment:
One kind is used for rock foundation fracture belt and handles construction method across lid, comprises the following steps:
1)Unwrapping wire and technique check:Determine the position of fracture belt 1 and using measuring instrument to across the lid position of fracture belt 1 carry out absolute altitude,
Position determination, thickness of slab of the determination across cover plate 4 and its support on both sides solid rock 3 checked with raft foundation 2 of axis
Width meets the requirements;
2)Cleaning:Fracture belt 1 is cleared up, using with being carried out by the way of mechanical work compound, machine is manually used first when fracture belt 1 is cleared up
Tool will be dug to design raft foundation 2 bottom absolute altitude -3.0m under fracture belt to be located, then manually in the both sides rock foundation of fracture belt 1
Completely decomposed and highly weathered rock handled to design the bottom absolute altitude -4.0m of raft foundation 2 place, in original width of fracture belt 1
On the basis of to both sides extend out at least one meter, with ensure supporting surface supported on solid rock 3, ensure the both sides of fracture belt 1 are hard
The poor completely decomposed rock of rubble and bearing capacity on rock 3 is cleaned out;
3)Crack is levelling:Treat step 1)With 2)After the completion of, use design raft foundation 2 absolute altitude -2.0m of the concrete to fracture belt 1
Following h1 regions carry out changing to fill out pouring and levelling, complete concrete leveling layer 5;
4)Reinforcing bar colligation:Treat step 3)In fracture belt 1 at concrete leveling layer 5 intensity reach after construction requirement, Ran Hou
H2 regions after fracture belt 1 is levelling more than -2.0m depth carry out laying reinforcing bar operation on request, and flow is as follows:
Reinforcement location line → fortune reinforcing bar is played to using in position → colligation securing plate lower rebar → placement reinforced bar support → colligation
Portion's reinforcing bar → setting posting → steel corrosion quantity;
5)Concrete placings, maintenance:Treat step 4)Reinforcing steel bar laying operation after the completion of to reinforced bar engineering carry out concealment acceptance, it is qualified laggard
The concreting operation in h2 regions more than row fracture belt 1-2.0m depth, concrete pour mode using inclined plane delamination,
The mode for once arriving top pours and circulates propulsion, and every layer pours thickness control within 500mm, when pouring, mixed in next layer
Poured before solidifying soil initial set and smash last layer concrete, must not made to produce the cold seam of construction between levels, to keep well connecing raft, improve
The compactness of concrete, and using covering, insulation by the way of in time in the step concrete carry out maintenance can complete across
Cover plate 4 is poured.
More than 1 meter is respectively extended out on the both sides width of fracture belt 1, is dug under thickness direction(h1+100mm)+(h2+100mm),
Wherein 100mm is concrete leveling thickness, across the supported on both sides of cover plate 4 on solid rock 3, support width >=1000mm.
Above-described embodiment is only the preferably embodiment of the present invention, and in addition, the present invention can also have other realizations
Mode.It should be noted that on the premise of without departing from present inventive concept, any conspicuously improved and modification all should fall
Enter within protection scope of the present invention.
Claims (2)
1. one kind is used for rock foundation fracture belt handles construction method across lid, it is characterised in that:Comprise the following steps:
1)Unwrapping wire and technique check:Determine fracture belt position and absolute altitude, axle are carried out using measuring instrument position across lid to fracture belt
The position determination checked with raft foundation, the determination of line are accorded with across the thickness of slab of cover plate and its support width on the solid rock of both sides
Close and require;
2)Cleaning:Fracture belt is cleared up, using manually with being carried out by the way of mechanical work compound when fracture belt is cleared up, first with machinery
It will be dug under fracture belt to design raft foundation bottom absolute altitude -3.0m places, then manually to complete in the rock foundation of fracture belt both sides
Weathering and highly weathered rock are handled to design raft foundation bottom absolute altitude -4.0m places, on the basis of original fracture bandwidth
At least one meter is extended out to both sides, to ensure that supporting surface is supported on solid rock, ensured on the solid rock of fracture belt both sides
Rubble and the poor completely decomposed rock of bearing capacity are cleaned out;
3)Crack is levelling:Treat step 1)With 2)After the completion of, using concrete to the design raft foundation absolute altitude -2.0m of fracture belt with
Under h1 regions change to fill out and pour and levelling, complete concrete leveling layer;
4)Reinforcing bar colligation:Treat step 3)In fracture belt at concrete leveling layer intensity reach after construction requirement, then disconnected
Split and carry out laying reinforcing bar operation on request with h2 regions more than levelling rear -2.0m depth, flow is as follows:
Reinforcement location line → fortune reinforcing bar is played to using in position → colligation securing plate lower rebar → placement reinforced bar support → colligation
Portion's reinforcing bar → setting posting → steel corrosion quantity;
5)Concrete placings, maintenance:Treat step 4)Reinforcing steel bar laying operation after the completion of to reinforced bar engineering carry out concealment acceptance, it is qualified laggard
The concreting operation in h2 regions more than row fracture belt -2.0m depth, the mode that pours of concrete uses inclined plane delamination, one
The secondary mode to top pours and circulates propulsion, and every layer pours thickness control within 500mm, when pouring, be in next layer of coagulation
Poured before native initial set and smash last layer concrete, must not made to produce the cold seam of construction between levels, to keep well connecing raft, improve mixed
Coagulating the compactness of soil, and carrying out maintenance to the concrete in the step in time by the way of covering, insulation can complete across lid
Plate is poured.
2. a kind of rock foundation fracture belt that is used for according to claim 1 handles construction method across lid, it is characterised in that:
More than 1 meter is respectively extended out on the width of the fracture belt both sides, is dug under thickness direction(h1+100mm)+(h2+100mm),
Wherein 100mm is concrete leveling thickness, and across cover plate supported on both sides is on solid rock, support width >=1000mm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710363512.8A CN107100218A (en) | 2017-05-22 | 2017-05-22 | One kind is used for rock foundation fracture belt and handles construction method across lid |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710363512.8A CN107100218A (en) | 2017-05-22 | 2017-05-22 | One kind is used for rock foundation fracture belt and handles construction method across lid |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107100218A true CN107100218A (en) | 2017-08-29 |
Family
ID=59670430
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710363512.8A Pending CN107100218A (en) | 2017-05-22 | 2017-05-22 | One kind is used for rock foundation fracture belt and handles construction method across lid |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107100218A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115584753A (en) * | 2022-10-20 | 2023-01-10 | 中建二局第三建筑工程有限公司 | Foundation structure for spanning rock cracks and construction method thereof |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CA2104844C (en) * | 1992-08-31 | 1998-08-25 | Howard Wendell Mccabe | Long hole chemical grout injector system |
CN202945622U (en) * | 2012-11-26 | 2013-05-22 | 浙江信博城市建设有限公司 | Composite repaired structure of reinforced concrete base plate cracks in basement |
WO2013173876A1 (en) * | 2012-05-23 | 2013-11-28 | Relborgn Pty Ltd | Method of limiting permeability of a matrix to limit liquid and gas inflow |
CN204627017U (en) * | 2015-03-26 | 2015-09-09 | 温州金榜建筑安装工程有限公司 | Crack repair structure |
-
2017
- 2017-05-22 CN CN201710363512.8A patent/CN107100218A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CA2104844C (en) * | 1992-08-31 | 1998-08-25 | Howard Wendell Mccabe | Long hole chemical grout injector system |
WO2013173876A1 (en) * | 2012-05-23 | 2013-11-28 | Relborgn Pty Ltd | Method of limiting permeability of a matrix to limit liquid and gas inflow |
CN202945622U (en) * | 2012-11-26 | 2013-05-22 | 浙江信博城市建设有限公司 | Composite repaired structure of reinforced concrete base plate cracks in basement |
CN204627017U (en) * | 2015-03-26 | 2015-09-09 | 温州金榜建筑安装工程有限公司 | Crack repair structure |
Non-Patent Citations (2)
Title |
---|
张剑锋: "《火力发电厂建筑物地基的断层处理》", 《电力建设》 * |
胡志耘: "《重庆岩石地基裂缝的处理方法》", 《岩土工程技术》 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115584753A (en) * | 2022-10-20 | 2023-01-10 | 中建二局第三建筑工程有限公司 | Foundation structure for spanning rock cracks and construction method thereof |
CN115584753B (en) * | 2022-10-20 | 2023-03-31 | 中建二局第三建筑工程有限公司 | Foundation structure for spanning rock cracks and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103615053B (en) | Monolithic reinforced concrete structure post empiricism engineering method | |
CN106759354A (en) | A kind of stratified continuous pouring mode of ultra-long and ultra-thick volume of concrete foundation | |
CN106088127A (en) | Open caisson construction method | |
CN102031756A (en) | Support assembly and construction method of cast-in-place box girder | |
CN108330835A (en) | The construction method of setting bracket | |
CN102839601A (en) | Fixed connection structure for steel pier column and cushion cap of portal rigid frame overbridge and construction method of fixed connection structure | |
CN104929365B (en) | Refuse of refuse burning generating plant discharging platform combined type surface construction technology | |
CN108532466A (en) | A kind of bridge pier over-form construction technique | |
CN104060781A (en) | Cast-in-situ cranked slab stair without seams at stair sections and construction method | |
CN102926398A (en) | Construction method of inclined column type corrosion resistant foundation for power line in salt lake area | |
CN105133487A (en) | Combined type bridge temporary support and construction method for rapidly building continuous beams by virtue of same | |
CN103161176A (en) | Tower crane foundation construction method in main building connected garage | |
CN104594633B (en) | The construction method and its formwork structure of umbrella shape space curved surface clear-water concrete | |
CN104074141A (en) | Construction method for small-radius curve fish belly type continuous box girder | |
CN108547337A (en) | Tear down and build the foundation construction technology of house foundation | |
CN105951842B (en) | Reversed beam styrofoam fetal membrane construction method under raft plate | |
CN107366303A (en) | Construction method and retaining wall of the aluminum alloy mould plate as highway gravity retaining wall template | |
CN108330902A (en) | The cast-in-place bottom end rail construction method of long piled wharf | |
CN104846745B (en) | Urban high-pier support-free formwork turnover construction method | |
CN206844138U (en) | A kind of bar construction of domatic isolated footing | |
CN110055844A (en) | Bubble enrockment light soil assembled barricade is used for straight-arm widening of subgrade construction method | |
CN107100218A (en) | One kind is used for rock foundation fracture belt and handles construction method across lid | |
CN110273435A (en) | A kind of construction of city open trench tunnel | |
CN202899153U (en) | Oblique column type anti-corrosion foundation device for power transmission line of salt-lake region | |
CN106869387A (en) | Multi-ribbed plate Structural Floor System HZ concrete film construction methods |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170829 |
|
RJ01 | Rejection of invention patent application after publication |