CN202945622U - Composite repaired structure of reinforced concrete base plate cracks in basement - Google Patents

Composite repaired structure of reinforced concrete base plate cracks in basement Download PDF

Info

Publication number
CN202945622U
CN202945622U CN 201220634091 CN201220634091U CN202945622U CN 202945622 U CN202945622 U CN 202945622U CN 201220634091 CN201220634091 CN 201220634091 CN 201220634091 U CN201220634091 U CN 201220634091U CN 202945622 U CN202945622 U CN 202945622U
Authority
CN
China
Prior art keywords
base plate
inverted trapezoidal
trapezoidal groove
reinforced concrete
basement
Prior art date
Application number
CN 201220634091
Other languages
Chinese (zh)
Inventor
吴建中
徐建光
段谟新
徐亮
胡海武
郑策
Original Assignee
浙江信博城市建设有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 浙江信博城市建设有限公司 filed Critical 浙江信博城市建设有限公司
Priority to CN 201220634091 priority Critical patent/CN202945622U/en
Application granted granted Critical
Publication of CN202945622U publication Critical patent/CN202945622U/en

Links

Abstract

The utility model relates to a composite repaired structure of reinforced concrete base plate cracks in a basement. The composite repaired structure of the reinforced concrete base plate cracks in the basement is characterized in that an inverted trapezoidal groove which does not penetrate through the base plate is formed along the direction of base plate cracks, the base plate at the lower portion of the inverted trapezoidal groove forms a base plate reserved zone, the groove position of the base plate forms a base plate repaired zone, an injected hole which is communicated with the base plate reserved zone is formed in the bottom of the inverted trapezoidal groove, grouting is injected into the bottom the base plate through the injected hole, holes are respectively formed in the bottom and the side wall of the inverted trapezoidal groove, binding ribs are arranged in the holes, and a waterproof layer of the bottom of the repaired zone is casted on the bottom of the inverted trapezoidal groove, horizontal mesh reinforcing ribs are fixed between the binding ribs of the side wall of the inverted trapezoidal groove, and a strip-shaped grouting repaired zone, a waterproof layer on the top portion of the repaired zone and a repaired layer on the top portion of the base plate are arranged on the waterproof layer of the bottom portion of the inverted trapezoidal groove in sequence. The composite repaired structure of the reinforced concrete base plate cracks in the basement has good leakage-proof performance, reduces or prevents the cracks from occurring or further expanding, has good technical economic benefit and is suitable for repairing cracks of various base plates in the basement.

Description

The composite repair structure in a kind of basement reinforced concrete floor crack
Technical field
The utility model relates to a kind of base plate crack repairing structure, particularly a kind of basement reinforced concrete floor crack combined type preparing structure.Belong to building engineering field.
Background technology
The basement bottom board crack is Common Diseases in construction work, the main cause of its formation is reinforced concrete floor impact of being subjected to uneven settlement of foundation, difference variation, external loads and concrete self quality etc., in use due to the cracking, not only can have a strong impact on the normal use of basement, and the phenomenon such as consequent infiltration also can make the reinforcing bar of base plate interior produce corrosion, thereby cause the reduction of supporting capacity, durability and the impermeability of Reinforced Concrete Materials, therefore need in time take the crack repairing measure.
At present the repairing measures for the base plate crack mainly contains following several:
First method is grouting or joint filling patching, and way is directly will repair injecting cement paste to inject the crack it is played a role, and generally is applicable to the operating mode that remedial is repaired, and has advantages of reparation speed piece, cheap.Portland cement grouting is applicable to roomy crack, waterproof effectively, but bonding not ideal enough to the cracking part; Chemical grouting method can be used for wet environment, and can control time of setting, also can be used for very trickle crack, and shortcoming is that technological requirement is high, and intensity is low.Grouting or joint filling patching are repaired and are contacted often firmly not between injecting cement paste and original concrete floor, and further the carrying out of uncontrollable crack is therefore be unsuitable for the repairing in structural crack.
Secondly be reinforcement anchoring method, usually adopt in the time must repairing the tensile strength of main slight crack section.Way is in the boring of both sides, crack, imbeds at a certain distance reinforced steel, and fills out embedding with atresia shrinkage water mud.This method is repaired for structural crack has effect preferably, but waterproofing course for want of, water easily infiltrate repair structure inside, cause corrosion of steel bar and make concrete new crack occur because of alkali, can't guarantee the durability of structure, and the structure outward appearance is had considerable influence.
In sum, for solve the repair structure durability that existing crack recovery technique exists not enough, can't effectively resist the problem such as further carrying out of crack, be badly in need of at present a kind of continuation cracking that has certain barrier performance, also can effectively control the crack of invention, have the Novel bottom plate crack repairing structure of technical economic benefit preferably.
Summary of the invention
The purpose of this utility model is to fully utilize the advantage of grouting or grouting joint filling method and reinforcement anchoring method etc., by forming injecting cement paste at base plate bottom injection slurries, and waterproofing course, horizontal mesh reinforcement, tension rib etc. are set strengthen the durability of structures and load-carrying properties etc., invent a kind of have good barrier performance, and the Novel reinforced concrete basement bottom board crack repair structure that can control effectively that the continuation in crack ftractures.
In order to realize above-mentioned technical purpose, the utility model has adopted following technical scheme:
The composite repair structure in a kind of basement reinforced concrete floor crack is characterized in that opening along the base plate fractuer direction inverted trapezoidal groove of non-through base plate, and the base plate of inverted trapezoidal groove bottom forms the base plate leave strip, and the fluting place of base plate forms base plate reparation band; Connect the base plate leave strip in the bottom of inverted trapezoidal groove and open injected hole, and inject injecting cement paste by injected hole bottom base plate;
In bottom land and the sidewall perforate respectively of inverted trapezoidal groove, arrange tension rib in the hole; The inverted trapezoidal bottom land is built to repair and is with the bottom waterproofing course; The netted reinforcement of fixed level between the tension rib of inverted trapezoidal groove sidewall; Set gradually bar shaped slip casting reparation band on inverted trapezoidal groove inner bottom part waterproofing course, repair band top waterproofing course, base plate top repair layer.
The composite repair structure in aforesaid basement reinforced concrete floor crack is characterized in that described injecting cement paste is positioned at the part of base plate bottom, and its injecting cement paste reinforcing scope is more than or equal to inverted trapezoidal groove upper opening width.
The composite repair structure in aforesaid basement reinforced concrete floor crack, it is characterized in that repairing band bottom waterproofing course and reparation is the SBS modified bitumen with top waterproofing course waterproofing materials used; Base plate top repair layer adopts carbon fiber reinforced concrete.
The composite repair structure in aforesaid basement reinforced concrete floor crack is characterized in that the reinforced mesh that the horizontal mesh reinforcement adopts high tensile steel wire grid or welding colligation to form.
The utlity model has following characteristics and beneficial effect:
(1) the base plate leave strip has strengthened base plate and has repaired the cooperative bearing performance of being with, offer injected hole and enter injecting cement paste to the base plate rising pouring on the base plate leave strip, can strengthen the holistic resistant behavior of base plate bottom, thereby solve that traditional restorative procedure effects on surface is repaired and can't carry out to the base plate bottom drawback of consolidation process.
(2) be provided with tension rib between bar shaped slip casting reparation band and both sides base plate, base plate leave strip, can strengthen the globality of repair structure, effectively prevent further carrying out of crack, be particularly useful for the repairing in structural crack.
(3) bar shaped slip casting reparation band bottom and top are provided with waterproofing course, can stop underground water or top water accumulation leaking to enter and repair band etc., can effectively avoid the appearance of the diseases such as base plate leakage, thereby strengthen the durability of repair structure.
Description of drawings
Fig. 1 is the composite repair structure section figure in the utility model basement reinforced concrete floor crack;
In figure: 1-reinforced concrete floor, 2-base plate leave strip, 3-injected hole, 4-injecting cement paste, 5-are repaired band bottom waterproofing course, and 6, the 7-tension rib, 8-bar shaped slip casting reparation band, 9-horizontal mesh reinforcement, 10-are repaired band top waterproofing course, 11-base plate top repair layer.
Specific embodiment
Fig. 1 is the composite repair structure section figure in the utility model basement reinforced concrete floor crack, with reference to shown in Figure 1.Reinforced concrete floor 1 thickness of required reparation in the present embodiment is 200mm, opens the inverted trapezoidal groove of non-through base plate at base plate 1, inverted trapezoidal groove bottom base plate form base plate leave strip 2, the fluting place of base plate forms base plate reparation band.The degree of depth of inverted trapezoidal groove is 100mm, upper opening width 200mm, lower openings width 100mm.
Bottom land perforation base plate leave strip 2 at the inverted trapezoidal groove is opened injected hole 3, bore dia 20mm, pitch-row 200mm.By the part injection injecting cement paste 4 of injected hole 3 to the base plate bottom, injecting cement paste 4 adopts BCE-200S fiber type cement pastes, and its injecting cement paste 4 reinforcing scopes are more than or equal to inverted trapezoidal groove upper opening width.
Avoid the position of injected hole 3 and arrange respectively tension rib 6,7 at the sidewall of groove at the bottom land of inverted trapezoidal groove; Sidewall tension rib 7 vertically is arranged in inverted trapezoidal groove center line absolute altitude place, arranges 1 along crack developing direction interval 200mm; The inverted trapezoidal bottom land is built to repair and is with bottom waterproofing course 5; The netted reinforcement 9 of fixed level between the tension rib 7 of inverted trapezoidal groove sidewall; Repair in the inverted trapezoidal groove and set gradually on the waterproofing course 5 of band bottom that bar shaped slip casting reparation is with 8, is repaired band top waterproofing course 10, base plate top repair layer 11.
Bar shaped slip casting reparation is with 8 also to adopt BCE-200S fiber type cement paste; Horizontal mesh reinforcement 9 is the high tensile steel wire grid, both side ends and tension rib 7 welding, and the high tensile steel wire grid adopts diameter 4mm steel wire welded to be connected into net, and mesh size 50mm * 50mm, width are 150mm.
Tension rib 6,7 adopts the hot-rolled ribbed high tensile reinforcement of HRB400 level, bar diameter 8mm, and long 60mm inserts respectively base plate leave strip 2 and base plate reparation band sidewall 30mm; The high-strength bonded adhesives of filling between tension rib and base plate space is epoxy resin.
Repairing band bottom waterproofing course 5 and repairing is the SBS modified bitumen with top waterproofing course 10 waterproofing materials used, waterproof bed thickness 10mm.
Base plate top repair layer 11 adopts TC4101 carbon fiber reinforced concrete, thick 20mm.
The construction sequence of the composite repair structure in the utility model basement reinforced concrete floor crack is as follows:
(1) open the inverted trapezoidal groove of non-through base plate along the base plate fractuer direction, the base plate of inverted trapezoidal groove bottom forms base plate leave strip 2, and the fluting place of base plate forms base plate reparation band;
(2) open injected hole 3 at the bottom land perforation base plate leave strip 2 of inverted trapezoidal groove, and inject injecting cement paste 4, and injecting cement paste 4 is filled with injected hole 3 simultaneously;
(3) avoid the position of injected hole 3 and at the side-wall hole of groove at the bottom land of inverted trapezoidal groove, and arrange respectively tension rib 6,7 in the hole, the space filling epoxy resin between tension rib and hole;
(4) after cleaning bottom land foreign material, build one deck SBS modified bitumen at the inverted trapezoidal bottom land, form to repair and be with bottom waterproofing course 5;
(5) horizontal mesh reinforcement 9 is fixed on the tension rib 7 of inverted trapezoidal groove sidewall, then injects in the inverted trapezoidal groove and repair injecting cement paste and form bar shaped slip casting reparation and be with 8;
(6) be with 8 top side to build one deck SBS modified bitumen in bar shaped slip casting reparation, form to repair and be with top waterproofing course 10;
(7) build one deck carbon fiber reinforced concrete repairing on band top waterproofing course 10, form base plate top repair layer 11, complete the construction of the composite repair structure in basement reinforced concrete floor crack.

Claims (4)

1. the composite repair structure in a basement reinforced concrete floor crack is characterized in that opening along the base plate fractuer direction inverted trapezoidal groove of non-through base plate, and the base plate of inverted trapezoidal groove bottom forms the base plate leave strip, and the fluting place of base plate forms base plate reparation band; Connect the base plate leave strip in the bottom of inverted trapezoidal groove and open injected hole, and inject injecting cement paste by injected hole bottom base plate;
In bottom land and the sidewall perforate respectively of inverted trapezoidal groove, arrange tension rib in the hole; The inverted trapezoidal bottom land is built to repair and is with the bottom waterproofing course; The netted reinforcement of fixed level between the tension rib of inverted trapezoidal groove sidewall; Set gradually bar shaped slip casting reparation band on inverted trapezoidal groove inner bottom part waterproofing course, repair band top waterproofing course, base plate top repair layer.
2. the composite repair structure in basement reinforced concrete floor according to claim 1 crack, is characterized in that described injecting cement paste is positioned at the part of base plate bottom, and its injecting cement paste reinforcing scope is more than or equal to inverted trapezoidal groove upper opening width.
3. the composite repair structure in basement reinforced concrete floor according to claim 1 crack, it is characterized in that repairing band bottom waterproofing course and reparation is the SBS modified bitumen with top waterproofing course waterproofing materials used; Base plate top repair layer adopts carbon fiber reinforced concrete.
4. the composite repair structure in basement reinforced concrete floor according to claim 1 crack, is characterized in that the reinforced mesh that the horizontal mesh reinforcement adopts high tensile steel wire grid or welding colligation to form.
CN 201220634091 2012-11-26 2012-11-26 Composite repaired structure of reinforced concrete base plate cracks in basement CN202945622U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220634091 CN202945622U (en) 2012-11-26 2012-11-26 Composite repaired structure of reinforced concrete base plate cracks in basement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220634091 CN202945622U (en) 2012-11-26 2012-11-26 Composite repaired structure of reinforced concrete base plate cracks in basement

Publications (1)

Publication Number Publication Date
CN202945622U true CN202945622U (en) 2013-05-22

Family

ID=48421330

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220634091 CN202945622U (en) 2012-11-26 2012-11-26 Composite repaired structure of reinforced concrete base plate cracks in basement

Country Status (1)

Country Link
CN (1) CN202945622U (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106638506A (en) * 2015-07-07 2017-05-10 苏州汇诚智造工业设计有限公司 Construction method of stilling pool base slab reinforcing structure
CN106759162A (en) * 2015-07-07 2017-05-31 苏州汇诚智造工业设计有限公司 The construction method of sluice force reduction pool bottom ruggedized construction
CN106854868A (en) * 2015-12-09 2017-06-16 江苏建筑职业技术学院 Glass wool cloth mounting method mending concrete sluice plate crack
CN107022985A (en) * 2016-02-27 2017-08-08 江苏建筑职业技术学院 The embedding reinforcing method mending concrete sluice plate crack of asphalt mortar, bituminous mortar
CN107059659A (en) * 2017-04-16 2017-08-18 赵洁 A kind of road and bridge crack bracing means
CN107100218A (en) * 2017-05-22 2017-08-29 中城建设有限责任公司 One kind is used for rock foundation fracture belt and handles construction method across lid
CN108589794A (en) * 2018-04-04 2018-09-28 上海三彩塑料排水板工程有限公司 Leakage of underground engineering, moist repairerment method

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106638506A (en) * 2015-07-07 2017-05-10 苏州汇诚智造工业设计有限公司 Construction method of stilling pool base slab reinforcing structure
CN106677142A (en) * 2015-07-07 2017-05-17 苏州汇诚智造工业设计有限公司 Stilling pool bottom plate strengthening structure
CN106759162A (en) * 2015-07-07 2017-05-31 苏州汇诚智造工业设计有限公司 The construction method of sluice force reduction pool bottom ruggedized construction
CN106869092A (en) * 2015-07-07 2017-06-20 苏州汇诚智造工业设计有限公司 A kind of construction method of force reduction pool bottom ruggedized construction
CN106869092B (en) * 2015-07-07 2018-09-18 宿迁峰驰安防有限公司 A kind of construction method of force reduction pool bottom ruggedized construction
CN106854868A (en) * 2015-12-09 2017-06-16 江苏建筑职业技术学院 Glass wool cloth mounting method mending concrete sluice plate crack
CN107022985A (en) * 2016-02-27 2017-08-08 江苏建筑职业技术学院 The embedding reinforcing method mending concrete sluice plate crack of asphalt mortar, bituminous mortar
CN107059659A (en) * 2017-04-16 2017-08-18 赵洁 A kind of road and bridge crack bracing means
CN107100218A (en) * 2017-05-22 2017-08-29 中城建设有限责任公司 One kind is used for rock foundation fracture belt and handles construction method across lid
CN108589794A (en) * 2018-04-04 2018-09-28 上海三彩塑料排水板工程有限公司 Leakage of underground engineering, moist repairerment method

Similar Documents

Publication Publication Date Title
CN104594210B (en) A kind of concrete prefabricated board and its preparation method and application
CN102383418B (en) Anti-seismic prefabricated concrete solid square pile and production method thereof
CN204609900U (en) A kind of corrugated steel preliminary bracing structure being applicable to benching tunnelling method excavation
CN103912011B (en) The prefabricated assembled underground structure of open cut
CN104947709A (en) Pre-assembled single-compartment municipal tunnel and construction method thereof
CN106677787B (en) Vertical shaft repairing and reinforcement structure and repairing and reinforcement construction method
KR102055436B1 (en) Prefabricated pier column member with steel-concrete composite structure
CN108019222B (en) A kind of tunnel lining structure and construction method using haydite filling
CN103321246B (en) Underground diaphragm wall based foundation pit construction method
CN102758456B (en) Construction method of basement waterproofing projects
CN102116061A (en) Masonry construction method for filling wall core pillar, core girder and building blocks into framework structure
CN102383443B (en) Connection structures between foundation pit support piles and outer walls of basement and construction method
CN101974894B (en) Combined dam
CN101629418A (en) Post-tensioned prestressing cast pile and construction method thereof
CN108005387B (en) Synchronous construction method for cast-in-place main body of assembled wallboard and short-limb shear wall
CN101748741A (en) Construction method of concrete supporting structure
CN202788022U (en) Wall crack combined type repair structure
CN204690783U (en) A kind of prefabricated assembled single cabin municipal administration synthesis pipe gallery
CN106481090B (en) A kind of Shockproof reinforcing method of existing reinforced concrete concrete frame joint
CN203569582U (en) Connecting structure of concrete pipe pile and bearing platform
CN203080430U (en) Assembly and cast-in-place combined type reinforced concrete pipe type culvert
CN104863614A (en) Method for primary support with corrugated steel plate and concrete combined structure taking place of steel grating
CN103924711A (en) Assembled type gridding shearing wall structural system and construction technology of assembled type gridding shearing wall structural system
WO2018233149A1 (en) Argillaceous soft rock roadway partition multi-granularity grouting reinforcement method
CN101818645B (en) Construction method for newly increasing arched open cut tunnel at railway operating line tunnel portal

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130522