CN107091006A CN201710317461.5A CN201710317461A CN107091006A CN 107091006 A CN107091006 A CN 107091006A CN 201710317461 A CN201710317461 A CN 201710317461A CN 107091006 A CN107091006 A CN 107091006A
Authority
CN
China
Prior art keywords
lattice
mobile jib
steel pipe
rectangle
web member
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710317461.5A
Other languages
Chinese (zh)
Inventor
张玉明
雷晓标
顾群
应捷
贾鹏
王宁壁
李坤
郭婵娟
李毅
张伟
张咪
张红
常伟
刘峰
李尤
雷蕾
魏文彬
田旭鹏
朱旭明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Northwest Electric Power Design Institute of China Power Engineering Consulting Group
Original Assignee
Northwest Electric Power Design Institute of China Power Engineering Consulting Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Northwest Electric Power Design Institute of China Power Engineering Consulting Group filed Critical Northwest Electric Power Design Institute of China Power Engineering Consulting Group
Priority to CN201710317461.5A priority Critical patent/CN107091006A/en
Publication of CN107091006A publication Critical patent/CN107091006A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/02Structures made of specified materials
    • E04H12/08Structures made of specified materials of metal
    • E04H12/10Truss-like structures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H5/00Buildings or groups of buildings for industrial or agricultural purposes
    • E04H5/02Buildings or groups of buildings for industrial purposes, e.g. for power-plants or factories
    • E04H5/04Transformer houses; Substations or switchgear houses

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Chemical & Material Sciences (AREA)
  • Materials Engineering (AREA)
  • Wood Science & Technology (AREA)
  • Power Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

The present invention discloses a kind of half-phase and passes through half bolted 750kV steel pipe lattice types framework, the web member and mobile jib on the front and rear two sides of lattice truss column equal in width use the web member and mobile jib on two sides before and after gusset plate bolt connection, lattice frame girder to be connect in succession using node crab bolt using related subgroup connection, the web member of upper and lower surface and mobile jib using related subgroup connection, the web member on the left and right two sides of Trapezoidal and mobile jib;Lattice framework entirety front-back is smaller using lattice beam column main material and abdomen material section after connection is mutually passed through, the auxiliary material such as gusset plate, stiffener and connecting bolt of nearly half quantity is cancelled simultaneously, the overall steel using amount of 750kV steel pipe lattice type frameworks is greatly reduced, significantly, overall facade effect is more attractive slim and graceful for economic and energy saving environmental benefit.

Description

A kind of half-phase passes through half bolted 750kV steel pipe lattice types framework
【Technical field】
The invention belongs to power transmission and transformation field, it is related to a kind of half-phase and passes through half bolted 750kV steel pipe lattice types framework.
【Background technology】
So far, the Northwest, which has more than 30 Duo Zuo 750kV transformer stations and built up, puts into operation.In 750kV transformer stations 750kV frameworks are the emphasis of design, difficult point, are also bright spot.In addition to ensuring that structure is safe and reliable, still it is considered as cost and perception is light Skilful factor.
Existing rectangular steel pipe lattice framework is made up of steel pipe frame column, rectangular steel pipe lattice girder.Rectangular steel pipe lattice The beam column of framework is connected with 4 round steel pipe chord members with many round steel pipe web members respectively, forms space gate framework, and shared is led Line pulling force effect, has the advantages that structural bearing capacity is high, rigidity is big, save material, good appearance.Lattice framework beam column four The mobile jib and web member in face use gusset plate bolt connection, and it is processed, zinc-plated, transport and installation are more convenient, existing It is used widely in 750kV and 1000kV frameworks.
The shortcoming of this kind of framework is the use of the auxiliary materials such as connecting node plate, stiffener and the connecting bolt of beam column mobile jib and web member Steel amount is larger, accounts for the overall steel using amount 30% or so of framework.Assembling workload is larger simultaneously, fails more preferably to embody assembled change The theory in power station.
Although the node type of attachment simple structure of said structure, stress is clearly, big with transformer station and current conversion station Size expansion, gusset plate bolt connection node steel using amount accounting is big and the slow shortcoming of Assembling is also more highlighted.
【The content of the invention】
Half bolted 750kV steel pipe lattice types framework is passed through it is an object of the invention to provide a kind of half-phase, is significantly subtracted Few totality steel using amount, while reducing Assembling workload, accelerates construction and installation speed, economic and energy saving environmental benefit is notable, Overall facade effect is more attractive slim and graceful.
To reach above-mentioned purpose, this patent takes following scheme to be achieved:
A kind of half-phase passes through half bolted 750kV steel pipe lattice types framework, including rectangle lattice truss column and rectangle Lattice frame girder;Rectangle lattice truss column is made up of many web members of four mobile jibs and connection mobile jib, rectangle lattice structure The leptoprosopy of trestle opposite end two is equal in width, and two relative wide faces are Trapezoidal in addition, section are gradually tapered up bottom-up, most End form is into the terrace edge shape that a bottom surface is that rectangle, top surface are square, two leptoprosopy of rectangle lattice truss column equal in width Web member and mobile jib use gusset plate bolt connection using related subgroup connection, the two wide face web member of Trapezoidal and mobile jib;Rectangle Lattice frame girder is also made up of many web members of four mobile jibs and connection mobile jib, ultimately forms a rectangular shape, framework The web member and mobile jib in former and later two faces of beam use node crab bolt using related subgroup connection, the web member of upper and lower surfaces and mobile jib Connection.
Further, the wide face of rectangle lattice truss column Trapezoidal bottom-up, 2.0m is changed into from 6.0m contractings.
Further, the mobile jib and the equal surface of web member of rectangle lattice truss column and rectangle lattice frame girder are zinc-plated.
Further, rectangle lattice truss column and rectangle lattice frame girder use gusset plate bolt connection position, web member Rod member termination plate is T-shaped plate or groove profile plate.
Further, gusset plate used in rectangle lattice truss column and rectangle lattice frame girder is provided with stiffener.
Further, rectangle lattice truss column equal in width leptoprosopy and rectangle lattice frame girder front-back are overall in blocks It is welded.
The 750kV steel pipe lattice types framework of the present invention passes through half bolt connection using half-phase:Lattice truss column equal in width The web member and mobile jib in former and later two faces use node using related subgroup connection, the web member and mobile jib in the face of left and right two of Trapezoidal Crab bolt is connected;Former and later two overall faces of lattice framework are using mutually passing through after connection, and the overall area that keeps out the wind diminishes, institute's wind-engaging Load reduces, and trussed member section and key dimension can be turned down accordingly, while overall facade effect is more attractive slim and graceful.
Result of calculation shows that the overall front-back of lattice framework is used and mutually passes through lattice beam column main material and abdomen material after connection Section is smaller, while the auxiliary material such as gusset plate, stiffener and connecting bolt of nearly half quantity is cancelled, 750kV steel is greatly reduced The overall steel using amount of pipe lattice framework, economic and energy saving environmental benefit is notable;The gusset plate of the nearly half of lattice framework beam column The welding of intersection factory is changed to, full wafer is transported to scene and assembled, and reduces Assembling workload, significantly accelerates construction peace Fill speed.
Reduce main material and the abdomen material section of framework beam column, cancel gusset plate, stiffener and the bolt of nearly half quantity etc. auxiliary Material, is greatly decreased the overall steel using amount of 750kV steel pipe lattice type frameworks, while reducing Assembling workload, significantly accelerates to apply Work installation rate, economic and energy saving environmental benefit is notable.(this section is repeated with the last period, can be cancelled)
【Brief description of the drawings】
The wide face schematic diagram of the bolted post of Fig. 1 a lattice frameworks;
Fig. 1 b lattices frameworks mutually pass through the post leptoprosopy schematic diagram of connection;
Fig. 2 a gusset plate bolt connection schematic diagrames;
Fig. 2 b phases pass through connection diagram;
【Embodiment】
The present invention program is described in detail with reference to the accompanying drawings and examples:
As shown in Fig. 1 a, Fig. 1 b, Fig. 2 a and Fig. 2 b, 750kV steel pipe lattice types framework of the present invention passes through half bolt using half-phase Connection:The web member and mobile jib in former and later two faces of lattice truss column equal in width are using related subgroup connection, the left and right of Trapezoidal The web member and mobile jib in two faces use gusset plate bolt connection;
The web member and mobile jib in former and later two faces of lattice frame girder using related subgroup connection, the web member of upper and lower surfaces and Mobile jib uses gusset plate bolt connection;
Former and later two overall faces of lattice framework are using mutually passing through after connection, and the overall area that keeps out the wind diminishes, institute wind-engaging lotus Carry and reduce, trussed member section and key dimension can be turned down accordingly, while overall facade effect is more attractive slim and graceful.
Rectangle lattice truss column and rectangle lattice frame girder part of nodes no gusset plate, are put more energy into using mutually passing through connection The annex such as plate and bolt;Part of nodes uses gusset plate bolt connection, and web member rod member termination plate is that T-shaped plate or groove profile are inserted Stiffener is equipped with plate, gusset plate.
Node of the present invention passes through half bolted 750kV steel pipe lattice types framework using half-phase, by rectangular frame post and beam 2 faces in each 4 faces are changed to mutually pass through connection by gusset plate bolt connection, and another 2 face still uses gusset plate bolt connection, saves The steel using amount of the auxiliary materials such as point plate, stiffener and connecting bolt.
It is a kind of Type of Welding of steel pipe crossed node mutually to pass through weldering, and the place intersected between round steel pipe and round steel pipe is space Curve, mutually pass through weldering be exactly along these curves to pipe progress seamless welding.
For rectangle lattice column, the wide face of Trapezoidal bottom-up, 2.0m is changed into (with hanging wire beam width, beam from 6.0m contractings Ground terminal or lightning rod that absolute altitude is typically designed as drawing in upper prop), using mutually passing through, connection is integral not readily transportable.Therefore, Two width of post mutually pass through to connection is integral to be transported to scene for 2.0m front-back, then with the left and right face of post Trapezoidal using saving Point crab bolt connection is assembled.There are flange connecting portion and beam-to-column joint position for beam column main material, gusset plate spiral shell need to be used Tether to connect and be easy to segmental machining transport installation.
For rectangle lattice girder, if weldering is all mutually passed through in 4 faces, 2.0m × 2.0m heavy in section rectangular beam is zinc-plated and transports all It is relatively difficult.Therefore, the front and rear two sides mobile jib in 4 faces of beam is mutually passed through into connection respectively with web member, then by before and after beam two Individual integral planar is fitted together by the web member of beam top and bottom with gusset plate bolt connection.
Above content is to combine specific preferred embodiment further description made for the present invention, it is impossible to assert The embodiment of the present invention is only limitted to this, for general technical staff of the technical field of the invention, is not taking off On the premise of from present inventive concept, some simple deduction or replace can also be made, the present invention should be all considered as belonging to by institute Claims of submission determine scope of patent protection.

Claims (6)

1. a kind of half-phase passes through half bolted 750kV steel pipe lattice types framework, it is characterised in that:Including rectangle lattice framework Post and rectangle lattice frame girder;
Rectangle lattice truss column is made up of many web members of four mobile jibs and connection mobile jib, rectangle lattice truss column opposite end two Individual leptoprosopy is equal in width, and two relative wide faces are Trapezoidal in addition, and section is gradually tapered up bottom-up, one is ultimately formed The terrace edge shape that bottom surface is rectangle, top surface is square, the two leptoprosopy web members and mobile jib of rectangle lattice truss column equal in width Connected using related subgroup, the two wide face web member of Trapezoidal and mobile jib use gusset plate bolt connection;
Rectangle lattice frame girder is also made up of many web members of four mobile jibs and connection mobile jib, ultimately forms a cuboid Shape, the web member and mobile jib in former and later two faces of frame girder use section using related subgroup connection, the web member of upper and lower surfaces and mobile jib Point crab bolt connection.
2. half-phase according to claim 1 passes through half bolted 750kV steel pipe lattice types framework, it is characterised in that:Square The wide face of shape lattice truss column Trapezoidal bottom-up, 2.0m is changed into from 6.0m contractings.
3. half-phase according to claim 1 passes through half bolted 750kV steel pipe lattice types framework, it is characterised in that:Square The mobile jib and the equal surface of web member of shape lattice truss column and rectangle lattice frame girder are zinc-plated.
4. the half-phase according to claim 1,2 or 3 passes through half bolted 750kV steel pipe lattice types framework, its feature exists In:Rectangle lattice truss column and rectangle lattice frame girder use gusset plate bolt connection position, web member rod member termination plate For T-shaped plate or groove profile plate.
5. the half-phase according to claim 1,2 or 3 passes through half bolted 750kV steel pipe lattice types framework, its feature exists In:Gusset plate used in rectangle lattice truss column and rectangle lattice frame girder is provided with stiffener.
6. the half-phase according to claim 1,2 or 3 passes through half bolted 750kV steel pipe lattice types framework, its feature exists In:Rectangle lattice truss column equal in width leptoprosopy and rectangle lattice frame girder front-back are that entirety is welded in flakes.
CN201710317461.5A 2017-05-05 2017-05-05 A kind of half-phase passes through half bolted 750kV steel pipe lattice types framework Pending CN107091006A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710317461.5A CN107091006A (en) 2017-05-05 2017-05-05 A kind of half-phase passes through half bolted 750kV steel pipe lattice types framework

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710317461.5A CN107091006A (en) 2017-05-05 2017-05-05 A kind of half-phase passes through half bolted 750kV steel pipe lattice types framework

Publications (1)

Publication Number Publication Date
CN107091006A true CN107091006A (en) 2017-08-25

Family

ID=59637700

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710317461.5A Pending CN107091006A (en) 2017-05-05 2017-05-05 A kind of half-phase passes through half bolted 750kV steel pipe lattice types framework

Country Status (1)

Country Link
CN (1) CN107091006A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114045941A (en) * 2021-11-16 2022-02-15 浙江精工钢结构集团有限公司 Horn-shaped space curved surface node and manufacturing method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR374415A (en) * 1907-02-08 1907-06-12 Aime Joseph Bonna System of metal beams composed of equal strength, welded without assemblies
CN101906896A (en) * 2010-07-23 2010-12-08 中国电力工程顾问集团华北电力设计院工程有限公司 750KV power-transformation framework structure
CN202299572U (en) * 2011-09-07 2012-07-04 中国电力工程顾问集团西南电力设计院 Plus or minus 800kV extra-high voltage direct current large-crossing steel tubular tower joint
CN203583974U (en) * 2013-09-30 2014-05-07 中国电力工程顾问集团西南电力设计院 750KV outdoor A-shaped column, lattice type column and power distribution device
CN205046920U (en) * 2015-10-21 2016-02-24 中国电力工程顾问集团西北电力设计院有限公司 Steel pipe lattice formula framework lightning rod
CN206737538U (en) * 2017-05-05 2017-12-12 中国电力工程顾问集团西北电力设计院有限公司 A kind of half-phase passes through half bolted 750kV steel pipe lattice types framework

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR374415A (en) * 1907-02-08 1907-06-12 Aime Joseph Bonna System of metal beams composed of equal strength, welded without assemblies
CN101906896A (en) * 2010-07-23 2010-12-08 中国电力工程顾问集团华北电力设计院工程有限公司 750KV power-transformation framework structure
CN202299572U (en) * 2011-09-07 2012-07-04 中国电力工程顾问集团西南电力设计院 Plus or minus 800kV extra-high voltage direct current large-crossing steel tubular tower joint
CN203583974U (en) * 2013-09-30 2014-05-07 中国电力工程顾问集团西南电力设计院 750KV outdoor A-shaped column, lattice type column and power distribution device
CN205046920U (en) * 2015-10-21 2016-02-24 中国电力工程顾问集团西北电力设计院有限公司 Steel pipe lattice formula framework lightning rod
CN206737538U (en) * 2017-05-05 2017-12-12 中国电力工程顾问集团西北电力设计院有限公司 A kind of half-phase passes through half bolted 750kV steel pipe lattice types framework

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
常伟 等: "750kv格构式构架杆系结构设计优化", 《钢结构》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114045941A (en) * 2021-11-16 2022-02-15 浙江精工钢结构集团有限公司 Horn-shaped space curved surface node and manufacturing method thereof

Similar Documents

Publication Publication Date Title
CN104912190A (en) Dry type joggle frame structure
CN102644403B (en) Holding pole with detachable standard knots
CN206737538U (en) A kind of half-phase passes through half bolted 750kV steel pipe lattice types framework
CN107091006A (en) A kind of half-phase passes through half bolted 750kV steel pipe lattice types framework
CN207032943U (en) Tilt the tree-shaped post platform canopy of concrete filled steel tube
CN103532048A (en) Quickly combined large lattice type crossing frame
CN202785387U (en) Indoor cantilever crane
CN202248820U (en) Combined overhanging scaffold
CN203924483U (en) A kind of truss string structure of built-in oblique guy rope
CN208235924U (en) A kind of mobile working platform for cantilevered structure side skirt alien invasion surface construction
CN204126297U (en) A kind of temporary support of steel truss roof
CN207890943U (en) The combined attachment device of tower crane
CN203729623U (en) Assembled machining shed for building construction
CN205663282U (en) Light -duty lattice formula steel column of large capacity
CN207296110U (en) A kind of curtain wall beam column construction
CN207296000U (en) A kind of door headpin structure for curtain wall
CN208039878U (en) Canopy is prevent wind to portable steel construction
CN204558892U (en) The truss beam structure that a kind of band is encorbelmented
CN204189939U (en) The ruggedized construction of original support lever frame of communication antenna transformation
CN206408809U (en) A kind of triangle joint structure for glass sunlight house
CN206144181U (en) Consolidate steel construction
CN209585682U (en) A kind of girder steel beam bottom concentrates the ruggedized construction of stress
CN208396133U (en) A kind of combined hollow grillage structure
CN106150120A (en) A kind of building progressive collapse-resisting bracing means utilizing steel bonding glue
CN202866003U (en) Novel panel point structure of spatial steel pipe truss steel suspension platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170825