CN107090978B - A kind of construction hangs connection device with displaceable mud - Google Patents
A kind of construction hangs connection device with displaceable mud Download PDFInfo
- Publication number
- CN107090978B CN107090978B CN201611247567.4A CN201611247567A CN107090978B CN 107090978 B CN107090978 B CN 107090978B CN 201611247567 A CN201611247567 A CN 201611247567A CN 107090978 B CN107090978 B CN 107090978B
- Authority
- CN
- China
- Prior art keywords
- sleeve pipe
- described sleeve
- rope
- pillar
- extension bar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims abstract description 18
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 claims abstract description 21
- 230000007423 decrease Effects 0.000 abstract description 5
- 239000000725 suspension Substances 0.000 description 6
- 238000010586 diagram Methods 0.000 description 3
- 230000009286 beneficial effect Effects 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 238000001125 extrusion Methods 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 238000009435 building construction Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/02—Conveying or working-up concrete or similar masses able to be heaped or cast
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Underground Or Underwater Handling Of Building Materials (AREA)
- Treatment Of Sludge (AREA)
Abstract
The invention discloses a kind of construction to hang connection device with displaceable mud, including casing, interconnecting piece is provided at the bottom end die of described sleeve pipe, pillar is combined in the interconnecting piece, pedestal is provided with below the pillar, there are two slippage slots for well-balanced setting on the outside of described sleeve pipe, sliding, which is provided with, in described sleeve pipe hangs extension bar, there are two scimitar portions for well-balanced setting on the outside for hanging extension bar, intert the slippage slot and extend into the outside of described sleeve pipe in the scimitar portion, the outside of described sleeve pipe and a tensioning member is connected between two scimitar portions, the present apparatus to hang extension bar sliding up and down by tensing payout, the decline of mud tank can be realized, it is simple to operate, the adjustable height of mud tank can be adjusted according to different construction requirements and is able to achieve synchronizes fixation, the structure of the present apparatus is relatively simple, cost It is more cheap, it is suitble to promote the use of.
Description
Technical field
The present invention relates to the realm of building construction, in particular to a kind of construction hangs connection device with displaceable mud.
Background technique
Mud is commonly used in construction, and mud is elongated on the relatively complete large-scale building site of some auxiliary facilities is
It is transported on floor by Cargo Lift, however is all often logical on the relatively incomplete building site of some small-sized building sites or auxiliary facility
Manpower self carrying is crossed, process not only takes time and effort, but also working efficiency and its low, and also have much makes in the prior art
Mud is conveyed with pulley instrument, but it is not able to satisfy construction personnel and synchronizes fixation for mud tank in external wall construction
Demand, and install it is excessively cumbersome, safety guarantee is not high, and use cost is excessively high.
Summary of the invention
The technical problem to be solved in the present invention is to provide a kind of construction to hang connection device with displaceable mud.
To solve the above problems, the present invention adopts the following technical scheme:
A kind of construction hangs connection device, including casing with displaceable mud, is provided at the bottom end die of described sleeve pipe
Interconnecting piece is combined with pillar in the interconnecting piece, is provided with pedestal below the pillar, well-balanced on the outside of described sleeve pipe
There are two slippage slots for setting, and sliding, which is provided with, in described sleeve pipe hangs extension bar, well-balanced on the outside for hanging extension bar to be provided with two
A scimitar portion, the scimitar portion intert the slippage slot and extend into the outside of described sleeve pipe, the outside of described sleeve pipe and two
A tensioning member is connected between a scimitar portion, the head of the tensioning member is connected with rope, and the head of described sleeve pipe is provided with peace
Slot is put, pulley is provided in the mounting groove, axle portion is combined between the pulley and the inner sidewall of the mounting groove, it is described
Pulley is equipped with annular groove, and the rope leaves the excessively described annular groove of a side hanging of the tensioning member, close to bottom end on the pillar
It is provided with through slot, the rope interts the through slot after leaving the excessively described annular groove of a side hanging of the tensioning member, and the rope is worn
It inserts and is provided with clamping portion on that side of the through slot, the clamping portion is elastic card socket part, is arranged in the clamping portion useful
Make the interspersed inserting hole of the rope, the clamping portion is movably set on the rope, when institute is inserted into the clamping portion
When stating through slot, so that the clamping portion is squeezed and deformed, the rope is fixedly clamped by the extrusion deformation of the clamping portion, described
More than four roller mounts are provided with below pedestal, the roller mount is fixedly connected with the pedestal, in the roller mount
It is provided with idler wheel, the torsion that turns to operate the idler wheel is additionally provided in the roller mount, the setting of the idler wheel is to convenient
Drive the pedestal mobile so that present apparatus conveniently moving, can use present apparatus suspension lifting mud in different places
Bucket, described turn of torsion can operate the idler wheel in present apparatus suspension lifting mud tank and not roll, in this application the roller mount
There are four settings.
Preferably, No.1 bolt is combined between the interconnecting piece and the pillar, between the pedestal and the pillar
No. two bolts are combined with, the left and right ends of the pedestal are movable to be equipped with clump weight, the inside of the axle portion and the mounting groove
Wall is fixedly connected, and the pulley is movably disposed in the midpoint of the axle portion.
Preferably, described hang slides cooperation between extension bar and described sleeve pipe, is provided in described sleeve pipe and connects as described hang
The slid chamber that bar slides up and down, the clamping portion have shrinkage.
The beneficial effects of the present invention are: realize the suspension of mud tank by two scimitar portions, then by the pulling of rope,
The upper and lower position in two scimitar portions is changed, extension bar sliding up and down in slid chamber is hung, when needing to rise, rope is pulled to make
It hangs extension bar to slide upwards, then drives and rise, to complete the conveying for mud;It is such as needed in external wall construction to mud tank reality
The position for synchronizing fixed clamping portion mobile after the completion of height adjustment on rope is applied, through slot is inserted into clamping portion, so that clamping
Portion occurs to be squeezed and deformed and clamp rope, so that rope not stretchy, two scimitar portions are fixed on the height of needs at this time
Degree, while mud tank is also suspended in the height of needs, when needing to decline, it is only necessary to extract clamping portion, then move clamping portion
Position on rope is made to hang extension bar downslide by payout, the decline of mud tank can be realized, simple to operate,
The adjustable height of mud tank can be adjusted according to different construction requirements and is able to achieve and synchronizes fixation, and the structure of the present apparatus is more
Simply, cost is more cheap, is suitble to promote the use of.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below
There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this
Some embodiments of invention for those of ordinary skill in the art without creative efforts, can be with
It obtains other drawings based on these drawings.
Fig. 1 is the overall structure diagram that connection device is hung in construction of the present invention with displaceable mud;
Fig. 2 is the partial enlarged view in Fig. 1 at A;
Fig. 3 is the structural schematic diagram of clamping portion and rope in the present invention.
Fig. 4 is the enlarged diagram of interconnecting piece.
Specific embodiment
The preferred embodiment of the present invention is described in detail with reference to the accompanying drawing, so that advantages and features of the invention energy
It is easier to be readily appreciated by one skilled in the art, so as to make a clearer definition of the protection scope of the present invention.
A kind of construction shown in -4 hangs connection device, including casing 1 with displaceable mud refering to fig. 1, described sleeve pipe 1
It is provided with interconnecting piece 2 at the die of bottom end, pillar 3 is combined in the interconnecting piece 2, the lower section of the pillar 3 is provided with pedestal
4, there are two slippage slots 101 for well-balanced setting on the outside of described sleeve pipe 1, and sliding, which is provided with, in described sleeve pipe 1 hangs extension bar 5, institute
It states and hangs the well-balanced setting in outside of extension bar 5 there are two scimitar portions 501, the scimitar portion 501 interts the slippage slot 101 and extends into
The outside of described sleeve pipe 1, the outside of described sleeve pipe 1 and is connected with a tensioning member 502, the drawing between two scimitar portions 501
The head for stretching part 502 is connected with rope 6, and the head of described sleeve pipe 1 is provided with mounting groove 102, is arranged in the mounting groove 102
There is pulley 7, axle portion 103 is combined between the pulley 7 and the inner sidewall of the mounting groove 102, the pulley 7 is equipped with annular groove
701, the rope 6 leaves the excessively described annular groove 701 of a side hanging of the tensioning member 502, is arranged on the pillar 3 close to bottom end
There is a through slot 311, the rope 6 interts the through slot 311, institute after leaving the excessively described annular groove 701 of a side hanging of the tensioning member 502
It states rope 6 and interts and be provided with clamping portion 8 on that side of the through slot 311, the clamping portion 8 is elastic card socket part, the card
The inserting hole interted as the rope 6 is provided in socket part 8, the clamping portion 8 is movably set on the rope 6,
When the through slot 311 is inserted into the clamping portion 8, so that the clamping portion 8 is squeezed and deformed, the rope 6 is by the clamping portion 8
Extrusion deformation and be fixedly clamped, the setting of the inserting hole increases the clamping between the rope 6 and the clamping portion 8
Power so that the clamping rope 6 that the clamping portion 8 can be more preferably more steady, the lower section setting of the pedestal 4 there are four with
On roller mount 81, the roller mount 81 is fixedly connected with the pedestal 4, and idler wheel 82, institute are provided in the roller mount 81
Turn torsion 83 being additionally provided in roller mount 81 to operate the idler wheel 82 is stated, the setting of the idler wheel 82 drives to facilitate
The movement of pedestal 4 can use present apparatus suspension lifting mud tank in different places so that present apparatus conveniently moving,
Described turn of torsion 83 can operate the idler wheel 82 in present apparatus suspension lifting mud tank and not roll, in this application the roller mount
There are four 81 settings.
A preferred embodiment in the present invention is combined with No.1 bolt 201 between the interconnecting piece 2 and the pillar 3,
No. two bolts 401 are combined between the pedestal 4 and the pillar 3, the left and right ends of the pedestal 4 are movable to be equipped with clump weight
402, it is by No.1 bolt 201 that the interconnecting piece 2 is fixed with the pillar 3, by No. two bolts 401 by the pedestal 4 with
The pillar 3 is fixed, can be matched according to practical operation situation by the clump weight 402 of the activity setting on pedestal 4
Weight, to keep the pedestal more firm, the axle portion 103 is fixedly connected with the inner sidewall of the mounting groove 102, the pulley
7 are movably disposed in the midpoint of the axle portion 103, to facilitate the rope 6 that the tensioning member 502 is pulled to go up and down.
A preferred embodiment in the present invention, described hang slide cooperation, described sleeve pipe 1 between extension bar 5 and described sleeve pipe 1
Inside be provided with and be used as the slid chamber 503 hanging about 5 extension bar and sliding, in order to it is described hang extension bar 5 in described sleeve pipe 1 on
To drive two scimitar portions 501 to move up and down, the clamping portion 8 has shrinkage for lower sliding, can preferably be squeezed change
Shape is also convenient for being replaced so that the rope 6 is fixed after the damage of the clamping portion 8.
The beneficial effects of the present invention are: realize the suspension of mud tank by two scimitar portions, then by the pulling of rope,
The upper and lower position in two scimitar portions is changed, extension bar sliding up and down in slid chamber is hung, when needing to rise, rope is pulled to make
It hangs extension bar to slide upwards, then drives and rise, to complete the conveying for mud;It is such as needed in external wall construction to mud tank reality
The position for synchronizing fixed clamping portion mobile after the completion of height adjustment on rope is applied, through slot is inserted into clamping portion, so that clamping
Portion occurs to be squeezed and deformed and clamp rope, so that rope not stretchy, two scimitar portions are fixed on the height of needs at this time
Degree, while mud tank is also suspended in the height of needs, when needing to decline, it is only necessary to extract clamping portion, then move clamping portion
Position on rope is made to hang extension bar downslide by payout, the decline of mud tank can be realized, simple to operate,
The adjustable height of mud tank can be adjusted according to different construction requirements and is able to achieve and synchronizes fixation, and the structure of the present apparatus is more
Simply, cost is more cheap, is suitble to promote the use of.
The basic principles, main features and advantages of the present invention have been shown and described above.The technology of the industry
Personnel are it should be appreciated that the present invention is not limited to the above embodiments, and the above embodiments and description only describe this
The principle of invention, various changes and improvements may be made to the invention without departing from the spirit and scope of the present invention, these changes
Change and improvement all fall within the protetion scope of the claimed invention.The claimed scope of the invention by appended claims and its
Equivalent defines.
Claims (2)
1. a kind of construction hangs connection device with displaceable mud, it is characterised in that: including casing, the bottom end die of described sleeve pipe
Place is provided with interconnecting piece, and pillar is combined in the interconnecting piece, is provided with pedestal below the pillar, described sleeve pipe it is outer
There are two slippage slots for well-balanced setting on face, and sliding, which is provided with, in described sleeve pipe hangs extension bar, well-balanced on the outside for hanging extension bar
There are two scimitar portion, the scimitar portion interts the slippage slot and extends into the outside of described sleeve pipe for setting, described sleeve pipe it is outer
Face and a tensioning member is connected between two scimitar portions, the head of the tensioning member is connected with rope, the head of described sleeve pipe
It is provided with mounting groove, pulley is provided in the mounting groove, is combined between the pulley and the inner sidewall of the mounting groove
Axle portion, the pulley are equipped with annular groove, and the rope leaves the excessively described annular groove of a side hanging of the tensioning member, pastes on the pillar
Positon of near bottom is provided with through slot, and the rope interts the through slot, institute after leaving the excessively described annular groove of a side hanging of the tensioning member
It states rope and interts and be provided with clamping portion on that side of the through slot, be provided in the clamping portion and intert as the rope
Inserting hole is provided with more than four roller mounts below the pedestal, and the roller mount is fixedly connected with the pedestal, institute
It states and is provided with idler wheel in roller mount, turn torsion to operate the idler wheel is additionally provided in the roller mount;It is described hang extension bar with
Cooperation is slid between described sleeve pipe, is provided in described sleeve pipe and is used as the slid chamber hanging extension bar and sliding up and down, the clamping
Portion has shrinkage.
2. construction according to claim 1 hangs connection device with displaceable mud, it is characterised in that: the interconnecting piece with
It is combined with No.1 bolt between the pillar, No. two bolts, a left side for the pedestal are combined between the pedestal and the pillar
Right both ends are movable to be equipped with clump weight, and the axle portion is fixedly connected with the inner sidewall of the mounting groove, and the pulley is movably
The midpoint of the axle portion is set.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611247567.4A CN107090978B (en) | 2016-12-29 | 2016-12-29 | A kind of construction hangs connection device with displaceable mud |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611247567.4A CN107090978B (en) | 2016-12-29 | 2016-12-29 | A kind of construction hangs connection device with displaceable mud |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107090978A CN107090978A (en) | 2017-08-25 |
CN107090978B true CN107090978B (en) | 2019-04-02 |
Family
ID=59646553
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611247567.4A Expired - Fee Related CN107090978B (en) | 2016-12-29 | 2016-12-29 | A kind of construction hangs connection device with displaceable mud |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107090978B (en) |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000064613A (en) * | 1998-08-25 | 2000-02-29 | Asuku Techno Koji Kk | Spray-coating refractory cement feeder |
CN201062777Y (en) * | 2007-07-17 | 2008-05-21 | 中国二十冶建设有限公司 | Height-adjustable lighting lamp stand for building site |
CN101866595A (en) * | 2010-02-05 | 2010-10-20 | 成都市宇中梅科技有限责任公司 | Liftable slogan bracket |
CN204702430U (en) * | 2015-01-12 | 2015-10-14 | 北京汽车研究总院有限公司 | A kind of hoisting fixture |
CN105257018A (en) * | 2015-10-19 | 2016-01-20 | 陆霞芸 | Support frame capable of being conveniently moved and placed for construction site |
CN105251076A (en) * | 2015-11-17 | 2016-01-20 | 任巧凤 | Infusion hanging device for hospital |
CN205502590U (en) * | 2016-04-20 | 2016-08-24 | 周建南 | Low -noise building material lifting device |
-
2016
- 2016-12-29 CN CN201611247567.4A patent/CN107090978B/en not_active Expired - Fee Related
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000064613A (en) * | 1998-08-25 | 2000-02-29 | Asuku Techno Koji Kk | Spray-coating refractory cement feeder |
CN201062777Y (en) * | 2007-07-17 | 2008-05-21 | 中国二十冶建设有限公司 | Height-adjustable lighting lamp stand for building site |
CN101866595A (en) * | 2010-02-05 | 2010-10-20 | 成都市宇中梅科技有限责任公司 | Liftable slogan bracket |
CN204702430U (en) * | 2015-01-12 | 2015-10-14 | 北京汽车研究总院有限公司 | A kind of hoisting fixture |
CN105257018A (en) * | 2015-10-19 | 2016-01-20 | 陆霞芸 | Support frame capable of being conveniently moved and placed for construction site |
CN105251076A (en) * | 2015-11-17 | 2016-01-20 | 任巧凤 | Infusion hanging device for hospital |
CN205502590U (en) * | 2016-04-20 | 2016-08-24 | 周建南 | Low -noise building material lifting device |
Also Published As
Publication number | Publication date |
---|---|
CN107090978A (en) | 2017-08-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107458973A (en) | A kind of hanging lifting device of surface structures steel pipe | |
CN107235412B (en) | A kind of crane pipe fitting suspender and its application method | |
CN201441244U (en) | Telescopic clothes hanger | |
CN114835062B (en) | Hydraulic climbing type lifting system | |
CN107090978B (en) | A kind of construction hangs connection device with displaceable mud | |
CN202017337U (en) | Efficient elevator mechanism adhered to electric lifting scaffold | |
CN107090980B (en) | A kind of construction slurry hangs connection device | |
CN106836813B (en) | A kind of construction hangs connection device with mud | |
CN104609336A (en) | Inverse hydraulic movable lifter and use method thereof | |
CN205322043U (en) | Lift retractable curtain | |
CN107089583B (en) | A kind of construction slurry hangs connection device | |
CN107090979B (en) | A kind of durable building construction slurry hangs connection device | |
CN203781732U (en) | Air conditioner external unit installation tool | |
CN104456025A (en) | Sling wall-hanging support | |
CN201991563U (en) | Novel telescopic sliding pull ring | |
CN209195003U (en) | Telescopic hanging landing beam | |
CN206188206U (en) | A hoist that is used for self -locking function that takes of work piece application | |
CN106049970B (en) | The installation method of the towering contactless sling system of noble metal tower mast | |
CN204454193U (en) | A kind of lift car glass side plate structure easy to assemble | |
CN104210941B (en) | Novel dragon gantry crane | |
CN210461961U (en) | Pipeline connection construction supporting device | |
CN107087949B (en) | A kind of removable bracketplant bar | |
CN210236961U (en) | Suspended ceiling lifting device | |
CN211495600U (en) | Assembly line convenient to adjust | |
CN215249005U (en) | Well point pipe hanging auxiliary device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20190308 Address after: 443201 Xinzheng Street, Laozhou Market Town, Xiannu Town, Zhijiang City, Yichang City, Hubei Province Applicant after: HUBEI HENGCHENG CONSTRUCTION Co.,Ltd. Address before: 510000 B5 building, No. 6, No. 6, Ying Long Road, Tianhe District, Guangzhou, Guangdong (Part 6, floor) Applicant before: GUANGZHOU TUOXUN SECURITY TECHNOLOGY CO.,LTD. |
|
TA01 | Transfer of patent application right | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190402 |
|
CF01 | Termination of patent right due to non-payment of annual fee |