CN107060807A - Gas tunnel passes through the multi-level leakage preventing structure applied behind coal seam and construction method - Google Patents

Gas tunnel passes through the multi-level leakage preventing structure applied behind coal seam and construction method Download PDF

Info

Publication number
CN107060807A
CN107060807A CN201710286594.0A CN201710286594A CN107060807A CN 107060807 A CN107060807 A CN 107060807A CN 201710286594 A CN201710286594 A CN 201710286594A CN 107060807 A CN107060807 A CN 107060807A
Authority
CN
China
Prior art keywords
gas
tunnel
coal seam
leakage preventing
preventing structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710286594.0A
Other languages
Chinese (zh)
Inventor
李庚许
杨彦岭
王景斌
谢光明
公彦良
李永刚
郑文华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 16th Bureau Group Co Ltd
Original Assignee
Fourth Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fourth Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd filed Critical Fourth Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd
Priority to CN201710286594.0A priority Critical patent/CN107060807A/en
Publication of CN107060807A publication Critical patent/CN107060807A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The multi-level leakage preventing structure applied behind coal seam is passed through the invention discloses a kind of gas tunnel, the gas shading ring as made from airtightness concrete is provided with the head and end on the outside of gas tunnel periphery, impervious barrier is provided with the inside of the periphery of the gas tunnel, the impervious barrier includes the airtightness concrete layer, gas sealant coating, foam carpet, gas isolation flaggy and secondary lining layer set gradually from outside to inside.Beneficial effects of the present invention:On the one hand multi-level gas antiseepage supporting is utilized, can effectively prevent gas from being permeated along tunnel ring, on the other hand can prevent gas from being spread along tunnel axial direction, so that gas is isolated in coal seam.

Description

Gas tunnel passes through the multi-level leakage preventing structure applied behind coal seam and construction method
Technical field
The present invention relates to technical field of tunnel construction, it particularly relates to which a kind of gas tunnel passes through what is applied behind coal seam Multi-level leakage preventing structure.
Background technology
Old house tunnel is located at Sichuan Province Yibin City Xingwen County kylin township within the border, total length 6423m, and circuit is 20 ‰ one side Go up a slope, on radius 7000m right avertence curves.This Tunnel Passing coal seam high methane and can lava location, tunnel initial risks etc. Level is assessed as " height ", and entrance working section is high methane work area.By geologic prospect, tunnel needs to pass through rich in 2 layers of coal seam, coal seam It is extremely crucial to the Anti-seeping technology of gas containing gas.
The problem of in correlation technique, effective solution is not yet proposed at present.
The content of the invention
For the above-mentioned technical problem in correlation technique, the present invention proposes that a kind of gas tunnel passes through applied behind coal seam many Level leakage preventing structure and construction method, can effectively prevent gas from permeating and axially diffusing along tunnel ring.
To realize above-mentioned technical purpose, the technical proposal of the invention is realized in this way:
A kind of gas tunnel passes through the multi-level leakage preventing structure applied behind coal seam, the head and end on the outside of gas tunnel periphery Place is provided with the inside of the gas shading ring as made from airtightness concrete, the periphery of the gas tunnel and is provided with impervious barrier, The impervious barrier include set gradually from outside to inside airtightness concrete layer, gas sealant coating, foam carpet, gas every From flaggy and secondary lining layer.
Further, the radial width of the gas shading ring is 1m, and axial depth is 2m.
The multi-level leakage preventing structure construction method applied behind coal seam is passed through the invention also discloses a kind of gas tunnel, including Following steps:
S1 excavates gas tunnel, and the original position in the gas tunnel and end position edge on the coal seam of populated with gas Its periphery outwards excavates a cavity;
S2 backfills airtightness concrete gas shading ring is made in the cavity;
S3 sprays airtightness concrete as first branch on the inside of gas tunnel, to form airtightness concrete layer;
S4 sprays gas sealant gas sealant coating is made on the inside of airtightness concrete layer;
S5 performs foam pad foam carpet is made on the inside of the gas sealant coating;
S6 performs gas division board on the inside of the foam carpet and isolates flaggy so that gas is made;
S7 performs secondary lining secondary lining layer is made on the inside of gas isolation flaggy.
Beneficial effects of the present invention:On the one hand multi-level gas antiseepage supporting is utilized, can effectively prevent gas along tunnel Road ring infiltration, on the other hand can prevent gas from being spread along tunnel axial direction, so that gas is isolated in coal seam.
Brief description of the drawings
In order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to institute in embodiment The accompanying drawing needed to use is briefly described, it should be apparent that, drawings in the following description are only some implementations of the present invention Example, for those of ordinary skill in the art, on the premise of not paying creative work, can also be obtained according to these accompanying drawings Obtain other accompanying drawings.
Fig. 1 is the sectional view of impervious barrier described according to embodiments of the present invention;
Fig. 2 is the structural representation of gas shading ring described according to embodiments of the present invention;
Fig. 3 is the sectional view of gas shading ring described according to embodiments of the present invention.
In figure:
1st, gas tunnel;2nd, gas shading ring;3rd, airtightness concrete layer;4th, gas sealant coating;5th, foam carpet;6th, watt This isolation flaggy;7th, secondary lining layer;8th, coal seam.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Site preparation is described, it is clear that described embodiment is only a part of embodiment of the invention, rather than whole embodiments.It is based on Embodiment in the present invention, the every other embodiment that those of ordinary skill in the art are obtained belongs to what the present invention was protected Scope.
As Figure 1-3, a kind of described gas tunnel passes through applied behind coal seam multi-level according to embodiments of the present invention Leakage preventing structure, the gas as made from airtightness concrete is provided with the head and end on the outside of the periphery of gas tunnel 1 and is isolated Impervious barrier is provided with the inside of ring 2, the periphery of the gas tunnel 1, the impervious barrier includes the gas set gradually from outside to inside Close property concrete layer 3, gas sealant coating 4, foam carpet 5, gas isolation flaggy 6 and secondary lining layer 7.
In one particular embodiment of the present invention, the radial width of the gas shading ring 2 is 1m, and axial depth is 2m。
The multi-level leakage preventing structure construction method applied behind coal seam is passed through the invention also discloses a kind of gas tunnel, including Following steps:
S1 excavates gas tunnel 1 on the coal seam 8 of populated with gas, and in the original position and stop bits of the gas tunnel 1 Put along its periphery and outwards excavate a cavity;
S2 backfills airtightness concrete gas shading ring 2 is made in the cavity;
S3 is propped up in the inner side of gas tunnel 1 injection airtightness concrete as first, to form airtightness concrete layer 3;
S4 is in the inner side spraying gas sealant of airtightness concrete layer 3 with obtained gas sealant coating 4;
S5 performs foam pad foam carpet 5 is made in the inner side of gas sealant coating 4;
S6 performs gas division board in the inner side of foam carpet 5 and isolates flaggy 6 so that gas is made;
S7 performs secondary lining secondary lining layer 7 is made in the inner side of gas isolation flaggy 6.
Understand for convenience the present invention above-mentioned technical proposal, below by way of in specifically used mode to the present invention it is above-mentioned Technical scheme is described in detail.
The present invention prevents gas from being permeated along tunnel ring by impervious barrier, and impervious barrier is followed successively by air-tightness and mixed from outside to inside Solidifying soil layer 3, gas sealant coating 4, foam carpet 5, gas isolation flaggy 6 and secondary lining layer 7, the first and last of gas tunnel 1 Two ends set gas shading ring 2, to prevent gas from being spread along tunnel axial direction, pass through being total to for gas shading ring 2 and impervious barrier Same-action completely cuts off gas.
The present invention carries out multi-level gas by impervious barrier when gas tunnel 1 passes through coal seam 8 to tunnel support structure Anti-seeping technology, it is to excavate the rapid injection air-tightness on the inside of gas tunnel 1 after gas tunnel 1 on coal seam 8 to mix that it, which applies order, Solidifying soil sprays the gas sealant formation gas sealant coating 4 that coal mine roadway is used, foam is applied afterwards afterwards as just branch Bed course 5 and gas division board, apply secondary lining again afterwards.In addition the beginning and end region in coal seam is passed through in gas tunnel 1, Backbreak during constructing tunnel towards ring, form the deep cavity of a 1m thickness, 2m, recycle airtightness concrete to be backfilled, formed The gas shading ring 2 of one ring, by gas isolation in coal seam, switchs to above-mentioned impervious barrier and applies afterwards.
To sum up, by means of the above-mentioned technical proposal of the present invention, multi-level gas antiseepage supporting, Ke Yiyou are on the one hand utilized Effect prevent gas along tunnel ring permeate, on the other hand can prevent gas along tunnel axial direction spread so that by gas every From in coal seam.
These are only presently preferred embodiments of the present invention, be not intended to limit the invention, it is all the present invention spirit and Within principle, any modification, equivalent substitution and improvements made etc. should be included in the scope of the protection.

Claims (3)

1. a kind of gas tunnel passes through the multi-level leakage preventing structure applied behind coal seam, it is characterised in that in gas tunnel(1)Circumference The gas shading ring as made from airtightness concrete is provided with head and end on the outside of face(2), the gas tunnel(1)Circle Impervious barrier is provided with the inside of side face, the impervious barrier includes the airtightness concrete layer set gradually from outside to inside(3), gas it is close Seal agent coating(4), foam carpet(5), gas isolation flaggy(6)With secondary lining layer(7).
2. gas tunnel according to claim 1 passes through the multi-level leakage preventing structure applied behind coal seam, it is characterised in that institute State gas shading ring(2)Radial width be 1m, axial depth is 2m.
3. a kind of gas tunnel passes through the multi-level leakage preventing structure construction method applied behind coal seam, it is characterised in that including following Step:
S1 is in the coal seam of populated with gas(8)Upper excavation gas tunnel(1), and in the gas tunnel(1)Original position and End position outwards excavates a cavity along its periphery;
S2 backfills airtightness concrete gas shading ring is made in the cavity(2);
S3 is in gas tunnel(1)Airtightness concrete is sprayed as first branch in inner side, to form airtightness concrete layer(3);
S4 is in airtightness concrete layer(3)Inner side sprays gas sealant gas sealant coating is made(4);
S5 is in the gas sealant coating(4)Inner side performs foam pad foam carpet is made(5);
S6 is in the foam carpet(5)Inner side performs gas division board and isolates flaggy so that gas is made(6);
S7 isolates flaggy in the gas(6)Inner side performs secondary lining secondary lining layer is made(7).
CN201710286594.0A 2017-04-27 2017-04-27 Gas tunnel passes through the multi-level leakage preventing structure applied behind coal seam and construction method Pending CN107060807A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710286594.0A CN107060807A (en) 2017-04-27 2017-04-27 Gas tunnel passes through the multi-level leakage preventing structure applied behind coal seam and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710286594.0A CN107060807A (en) 2017-04-27 2017-04-27 Gas tunnel passes through the multi-level leakage preventing structure applied behind coal seam and construction method

Publications (1)

Publication Number Publication Date
CN107060807A true CN107060807A (en) 2017-08-18

Family

ID=59605091

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710286594.0A Pending CN107060807A (en) 2017-04-27 2017-04-27 Gas tunnel passes through the multi-level leakage preventing structure applied behind coal seam and construction method

Country Status (1)

Country Link
CN (1) CN107060807A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108162545A (en) * 2017-11-28 2018-06-15 安徽徽风新型合成材料有限公司 Splash guard is isolated in a kind of polyethylene gas
CN109113758A (en) * 2018-09-21 2019-01-01 中铁十六局集团有限公司 A kind of the gas axial isolation band and its construction method of tunnel gas aggregation zone

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5324139A (en) * 1992-02-21 1994-06-28 Ingenieure Mayreder, Kraus & Co. Consult Gesellschaft M.B.H. Method for the construction of long tunnel with a lining
CN2372127Y (en) * 1999-06-28 2000-04-05 周海东 Tunnel sticking cloth rubber gas isolating board
CN201705364U (en) * 2010-06-28 2011-01-12 中铁二十局集团有限公司 Full-closed integral type lining structure of tunnel in coal-seam gob area
CN204572002U (en) * 2015-04-02 2015-08-19 四川省交通运输厅公路规划勘察设计研究院 For the tunnel structure of gas tunnel

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5324139A (en) * 1992-02-21 1994-06-28 Ingenieure Mayreder, Kraus & Co. Consult Gesellschaft M.B.H. Method for the construction of long tunnel with a lining
CN2372127Y (en) * 1999-06-28 2000-04-05 周海东 Tunnel sticking cloth rubber gas isolating board
CN201705364U (en) * 2010-06-28 2011-01-12 中铁二十局集团有限公司 Full-closed integral type lining structure of tunnel in coal-seam gob area
CN204572002U (en) * 2015-04-02 2015-08-19 四川省交通运输厅公路规划勘察设计研究院 For the tunnel structure of gas tunnel

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
熊鲲: "瓦斯隧道施工安全风险管理及应用研究", <<西南交通大学硕士学位论文>> *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108162545A (en) * 2017-11-28 2018-06-15 安徽徽风新型合成材料有限公司 Splash guard is isolated in a kind of polyethylene gas
CN109113758A (en) * 2018-09-21 2019-01-01 中铁十六局集团有限公司 A kind of the gas axial isolation band and its construction method of tunnel gas aggregation zone

Similar Documents

Publication Publication Date Title
CN207131424U (en) A kind of lining construction stitches waterproof construction
CN107083973B (en) The gas prevention method of region slip casting combination antiseepage supporting is carried out when Tunnel Passing coal seam
CN109488371B (en) Waterproof system of full-enclosed waterproof station and dynamic setting and quantity-limiting drainage method
KR101859612B1 (en) Reinforcement and waterproof structure of vertical shafts-utility tunnels interface
CN107060807A (en) Gas tunnel passes through the multi-level leakage preventing structure applied behind coal seam and construction method
CN109026012A (en) Vertical shaft surrounding rock supporting structure and its excavation supporting method
CN103437789B (en) Build waterproof structure, adopt the method for water proof mode constructing underground building
CN107780425A (en) A kind of large-scale yard drain french drain method to set up of banketing in Gullied Rolling Loess Region
CN105781575A (en) Water-rich stratum pipe piece combination structure and construction method thereof
CN107013225B (en) The anti-collapse tunneling shield method of whirl spraying water shutoff
CN107100206A (en) A kind of prevention and controls of basement leakage
CN107653872A (en) The rigid joint of ultra-deep ground-connecting-wall integrates water-stopping system and its construction method
KR100947627B1 (en) The grouting structure of tunnel and tunnel construction method using the same
KR101440258B1 (en) Messer construction method with grouting means
CN203835401U (en) Construction structure for arranging construction vertical shaft above underground engineering
KR101901848B1 (en) Design Method for Underground Structure Outer Side Waterproofing
CN203335089U (en) Protruding type environment-friendly tunnel portal with supports
KR102037135B1 (en) Waterproof Sheet with Protective Material for Exterior-Waterproof of Underground Structure and Exterior-Waterproofing Method Using the Same
CN112081607A (en) Tunnel primary support and waterproof and drainage combined system and construction method
CN204827469U (en) A tunnel for transmission fluid
CN208518685U (en) A kind of Underground Subway Station construction period water sealing structure
CN203584437U (en) First lining structure used for constructing underground engineering and having water-resisting function
CN207846429U (en) A kind of phreatic high, high basement rock go out the foundation pit supporting system shown up
CN207176733U (en) Control basis and the joint waterproofing construction of earthen fill zone open trench tunnel differential settlement
CN105133621B (en) The construction method and foundation pit enclosure system of foundation pit enclosure system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Ma Dong

Inventor after: Li Gengxu

Inventor after: Yang Yanling

Inventor after: Wang Jingbin

Inventor after: Xie Guangming

Inventor after: Gong Yanliang

Inventor after: Li Yonggang

Inventor after: Zheng Wenhua

Inventor before: Li Gengxu

Inventor before: Yang Yanling

Inventor before: Wang Jingbin

Inventor before: Xie Guangming

Inventor before: Gong Yanliang

Inventor before: Li Yonggang

Inventor before: Zheng Wenhua

TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20170918

Address after: 101400 No. 2 Yingbin Middle Road, Huairou District, Beijing

Applicant after: China Railway 16th Bureau Group Fourth Engineering Co., Ltd.

Applicant after: China Railway Construction Engineering Bureau No.16 Group Corp., Ltd.

Address before: 101400 No. 2 Yingbin Middle Road, Huairou District, Beijing

Applicant before: China Railway 16th Bureau Group Fourth Engineering Co., Ltd.

RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170818