CN107016510A - One kind research and development intermediate item life cycle management system - Google Patents
One kind research and development intermediate item life cycle management system Download PDFInfo
- Publication number
- CN107016510A CN107016510A CN201710243871.XA CN201710243871A CN107016510A CN 107016510 A CN107016510 A CN 107016510A CN 201710243871 A CN201710243871 A CN 201710243871A CN 107016510 A CN107016510 A CN 107016510A
- Authority
- CN
- China
- Prior art keywords
- project
- life cycle
- unit
- generation unit
- thing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0633—Workflow analysis
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0637—Strategic management or analysis, e.g. setting a goal or target of an organisation; Planning actions based on goals; Analysis or evaluation of effectiveness of goals
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Strategic Management (AREA)
- Economics (AREA)
- Entrepreneurship & Innovation (AREA)
- Educational Administration (AREA)
- Operations Research (AREA)
- Development Economics (AREA)
- Marketing (AREA)
- Game Theory and Decision Science (AREA)
- Quality & Reliability (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- General Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- Stored Programmes (AREA)
Abstract
The present invention discloses a kind of research and development intermediate item life cycle management system, including:Time quantum, project generation unit, life cycle generation unit, project circulation unit delivers thing generation unit, delivers thing examination & approval unit, profiling unit and prewarning unit.The traditional project management system of contrast, not only creatively proposes the management mode of life cycle, while also project processing circulates, thing examination & approval management is delivered in defect management early warning, and project life cycle early warning intactly combines, and forms a unified entirety.In the life cycle of whole project, pass through the circulation between disparity items state, the task of current project is submitted in corresponding processing human hand, after processing people is disposed, then the stream of items can be gone to another processing people, for processing people, the progress of current project is commented on, task to delivery is handled, and delivers thing document by profiling unit storage, until project processing life cycle latter stage is closed.
Description
Technical field
The present invention relates to a kind of project management system, more particularly to it is a kind of be used to researching and developing class based on the project life cycle
Project management system.
Background technology
The project for researching and developing class includes huge number, from major class point, can be divided into software project, and item of hardware supports project
Deng from the start to finish of project, being discussed according to the project management method of canonical system, each different life cycle rank should be undergone
Section, from the initiation of project to each project of extinction, should all be tracked the management of formula.Life cycle structure is with tree-like for knot
Structure, is showed as follows:
A--XXX projects
The B-- project stages
C-- project status
D-- project tasks
E-- project delivery things
Project can include multiple project stages, and each stage can include multiple project status, and each project status can be included
Multiple project tasks and delivery thing.In the past traditional project management system is main to be processed as master with affairs circulation, can not be from item
Mesh life cycle is tracked to project.
The content of the invention
In order to solve the above-mentioned technical problem, present invention aims at provide a kind of research and development intermediate item life cycle management system
System.
A kind of research and development intermediate item life cycle management system of the present invention, it is characterised in that including:
Time quantum, national legal festivals and holidays, perpetual calendar and time adjustment are obtained for networking;
Project generation unit, for generating project framework;
Life cycle generation unit, according to project framework and time calendar generating item purpose life cycle;
Project circulation unit, judges whether to need to circulate to next task or stage one by one according to project framework;
Thing generation unit is delivered, the corresponding delivery thing of the task is generated when each task is completed;
Thing examination & approval unit is delivered, is judged to deliver whether thing passes through according to project standard, and will determine that result is sent to project circulation
Unit circulate operation;
Profiling unit, automatic archiving storage is carried out to each delivery thing/task/state/stage of project;
Prewarning unit, date-time early warning is all carried out according to life cycle task/state/stage each to project flow.
Described life cycle generation unit is according to the life cycle of each project of CMMI3 standard productions.
Described life cycle generation unit updates this after project generation unit is modified/adjusted to project framework
Purpose life cycle.
A kind of research and development intermediate item life cycle management system of the present invention, the advantage is that, contrast traditional project
Management system, not only creatively proposes the management mode of life cycle, while also project processing circulates, defect management is pre-
It is alert, thing examination & approval management is delivered, project life cycle early warning intactly combines, and forms a unified entirety.In whole item
In purpose life cycle, by the circulation between disparity items state, the task of current project is submitted to corresponding processing people
In hand, after processing people is disposed, then the stream of items can be gone to another processing people, be to working as processing people
Preceding paragraph purpose progress is commented on, and the task to delivery is handled, and delivers thing document by profiling unit storage, until item
Mesh processing life cycle latter stage is closed, and the height of the management of development project improved into a step.
Brief description of the drawings
Fig. 1 is a kind of structural representation for researching and developing intermediate item life cycle management system of the present invention.
Fig. 2 is a kind of schematic flow sheet for researching and developing intermediate item life cycle management system of the present invention.
Embodiment
According to Fig. 1, a kind of research and development intermediate item life cycle management system of the present invention includes:Time quantum,
National legal festivals and holidays, perpetual calendar and time adjustment are obtained for networking;Project generation unit, for generating project framework;
Life cycle generation unit, according to project framework and time calendar generating item purpose life cycle;Project circulation unit, according to item
Mesh framework judges whether to need to circulate to next task or stage one by one;Thing generation unit is delivered, is given birth to when each task is completed
Into the corresponding delivery thing of the task;Thing examination & approval unit is delivered, is judged to deliver whether thing passes through according to project standard, and will determine that knot
Fruit is sent to project circulation unit circulate operation;Profiling unit, enters to each delivery thing/task/state/stage of project
Row automatic archiving is stored;Prewarning unit, when all carrying out the date according to life cycle task/state/stage each to project flow
Between early warning.Described life cycle generation unit is according to the life cycle of each project of CMMI3 standard productions;In project generation
Unit updates the life cycle of the project after project framework is modified/adjusted.
The operation principle and flow of system of the present invention are as shown in Figure 2:
1st, automatically generate and matching entries life cycle
When research staff starts project and after project generation unit establishment project, life cycle generation unit is soft according to project
Part project or item of hardware, and required according to CMMI3 project management, the corresponding Life Cycle of the project is automatically generated to project
Phase, comprising each project stage, state and task, delivery thing.
If during grassroot project, being to be carried out in conventional project newly-built, inputting different version numbers, then system automatic identification
The project is upgrading project, and life cycle generation unit will update corresponding life according to CMMI3 project management code requirement
Cycle.
If grassroot project is brand-new project, the project management code requirement of life cycle generation unit then according to CMMI3
Produce corresponding life cycle.
2nd, according to work calendar, the project plan is calculated automatically
System default provide work calendar it is instant between unit, the automatic legal festivals and holidays for obtaining country are used as the inoperative of system
Day, also can artificially it be operated, after work calendar is set, all project plans are then by system automatically according to work calendar
It is automatic to calculate.The setting of the project plan can be divided into two kinds:Period, working day.
Period:After the ps in the project that sets each stage and plan Close Date are the period, if
In the range of the period of setting, nonworkdays is had all through the ages according to working day, then the working day number of days in the period are then the project
The planned time in stage.
Working day:When setting project stage planned time for working day, such as demand stage is 8 working days, then is
System is skipped nonworkdays and calculated automatically according to from date and working day number of days, and date current generation calculates will be automatic
Next stage is calculated automatically.As second stage setting at the beginning of between for November 14 to November 18, when to first
Stage sets November 7 time started, and working day is 7, then system is automatically according to the nonworkdays on work calendar(November 12
Day, November 13), the automatic Close Date for calculating the first stage is November 15, then the Start Date of second stage is then automatic
Calculate as November 16 to November 22.
3rd, project task/stage closed loop circulation
Project circulation unit after the completion of each subtask/stage, all judge whether to need to circulate to next task or stage after
Continuous work, closed loop circulation ensures the smooth of work and will not omitted any task/stage.
4th, project document is automated
Project is flowed through in journey, according to CMMI3 project management specification, can produce the process management document of many, the friendship of system
Pay thing generation unit according to different life cycles automatically generate delivery thing document, deliver thing most contents all by system from
Dynamic generation, and submit delivery thing examination & approval unit to be examined, filing storage is then completed by profiling unit.
5th, the active early warning of project
For the project plan, the prewarning unit of system is developed, mainly project manager's project plan is supplied on one's own initiative
Warning information, include project plan early warning, document delivery thing examination & approval early warning, defect processing early warning.
Project plan early warning:According to the overall planning time of project, the planned time in each stage, when system automatic decision is each
Between point, before it will expire, pass through short message and the form of wechat message, notify project relevant administrative staff.
For those skilled in the art, technical scheme that can be as described above and design, make other each
Corresponding change and deformation are planted, and all these change and deformation should all belong to the protection model of the claims in the present invention
Within enclosing.
Claims (3)
1. one kind research and development intermediate item life cycle management system, it is characterised in that including:
Time quantum, national legal festivals and holidays, perpetual calendar and time adjustment are obtained for networking;
Project generation unit, for generating project framework;
Life cycle generation unit, according to project framework and time calendar generating item purpose life cycle;
Project circulation unit, judges whether to need to circulate to next task or stage one by one according to project framework;
Thing generation unit is delivered, the corresponding delivery thing of the task is generated when each task is completed;
Thing examination & approval unit is delivered, is judged to deliver whether thing passes through according to project standard, and will determine that result is sent to project circulation
Unit circulate operation;
Profiling unit, automatic archiving storage is carried out to each delivery thing/task/state/stage of project;
Prewarning unit, date-time early warning is all carried out according to life cycle task/state/stage each to project flow.
2. system according to claim 1, it is characterised in that described life cycle generation unit is according to CMMI3 standards
Produce the life cycle of each project.
3. system according to claim 1, it is characterised in that described life cycle generation unit is in project generation unit
The life cycle of the project is updated after project framework is modified/adjusted.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710243871.XA CN107016510A (en) | 2017-04-14 | 2017-04-14 | One kind research and development intermediate item life cycle management system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710243871.XA CN107016510A (en) | 2017-04-14 | 2017-04-14 | One kind research and development intermediate item life cycle management system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107016510A true CN107016510A (en) | 2017-08-04 |
Family
ID=59446320
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710243871.XA Pending CN107016510A (en) | 2017-04-14 | 2017-04-14 | One kind research and development intermediate item life cycle management system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107016510A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109960488A (en) * | 2019-01-28 | 2019-07-02 | 平安科技(深圳)有限公司 | APP complete period monitoring method, device, computer equipment and storage medium |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1629851A (en) * | 2003-12-16 | 2005-06-22 | 上海汽轮机有限公司 | Steam turbine product database management method |
CN101676932A (en) * | 2008-09-16 | 2010-03-24 | 深圳市红旗信息技术有限公司 | Electronic monitoring method and system of government-invested construction project |
CN103530099A (en) * | 2012-07-05 | 2014-01-22 | 上海汽车集团股份有限公司 | Data development and management system |
CN104463503A (en) * | 2014-12-29 | 2015-03-25 | 机械科学研究总院海西(福建)分院 | Intellectual information service system of a new product research and development full life circle based on cloud manufacturing |
CN104573991A (en) * | 2015-01-28 | 2015-04-29 | 携程计算机技术(上海)有限公司 | Project process management system |
-
2017
- 2017-04-14 CN CN201710243871.XA patent/CN107016510A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1629851A (en) * | 2003-12-16 | 2005-06-22 | 上海汽轮机有限公司 | Steam turbine product database management method |
CN101676932A (en) * | 2008-09-16 | 2010-03-24 | 深圳市红旗信息技术有限公司 | Electronic monitoring method and system of government-invested construction project |
CN103530099A (en) * | 2012-07-05 | 2014-01-22 | 上海汽车集团股份有限公司 | Data development and management system |
CN104463503A (en) * | 2014-12-29 | 2015-03-25 | 机械科学研究总院海西(福建)分院 | Intellectual information service system of a new product research and development full life circle based on cloud manufacturing |
CN104573991A (en) * | 2015-01-28 | 2015-04-29 | 携程计算机技术(上海)有限公司 | Project process management system |
Non-Patent Citations (1)
Title |
---|
金小敏: "面向汽车产品研发的项目管理系统的研究与实现", 《中国优秀硕士学位论文全文数据库(工程科技II辑)》 * |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109960488A (en) * | 2019-01-28 | 2019-07-02 | 平安科技(深圳)有限公司 | APP complete period monitoring method, device, computer equipment and storage medium |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103593236B (en) | Computer equipment, method and device for scheduling service process | |
CN108985709A (en) | Workflow management method towards more satellite data centers collaboration Remote Sensing Products production | |
Wang et al. | A graph-based ant colony optimization approach for integrated process planning and scheduling | |
CN107578158A (en) | A kind of Order Scheduling optimization method suitable for manufacturing works | |
CN105956953A (en) | Case information distribution system and method | |
CN109429515A (en) | Production line constitutes altering system and production line constitutes variation | |
CN108734454A (en) | Reimbursement processing method and system | |
CN104199820A (en) | Cloud platform MapReduce workflow scheduling optimizing method | |
Kim et al. | Reinforcement learning approach to scheduling of precast concrete production | |
CN106408162A (en) | Product oil pipeline sequence conveying batch control method | |
CN110275799A (en) | Billing and accounting system does not shut down a day method for point of contact snapshot remaining sum | |
JP2019117454A (en) | Production planning support system | |
CN109242269A (en) | Job instruction generation method, device, system, electronic equipment and storage medium | |
CN107016510A (en) | One kind research and development intermediate item life cycle management system | |
CN114971407A (en) | Automatic scheduling control method and system for maintenance plan | |
JPS59214964A (en) | Conversational scheduling system | |
CN112435077A (en) | Sales forecasting method | |
CN107679635A (en) | Client's follow-up method, system and readable storage medium storing program for executing based on priority | |
CN116934009A (en) | Factory scheduling method, device, equipment and storage medium | |
CN106484792A (en) | A kind of data power supply management method for Persistence Layer Framework and device | |
CN110163518A (en) | A kind of production management method | |
Rose et al. | Improving productivity through value stream mapping (VSM): A case study at electrical & electronic company | |
Şafak et al. | A hierarchical approach for solving simultaneous lot sizing and scheduling problem with secondary resources | |
CN108171440A (en) | A kind of hydraulic tube piece management of the processing and production system and method | |
JP2011048459A (en) | System and method for supporting project planning |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170804 |
|
RJ01 | Rejection of invention patent application after publication |