CN106988748A - High-order parallel heading construction and the construction method that capacity expansion revamping is double line tunnel - Google Patents

High-order parallel heading construction and the construction method that capacity expansion revamping is double line tunnel Download PDF

Info

Publication number
CN106988748A
CN106988748A CN201710153954.XA CN201710153954A CN106988748A CN 106988748 A CN106988748 A CN 106988748A CN 201710153954 A CN201710153954 A CN 201710153954A CN 106988748 A CN106988748 A CN 106988748A
Authority
CN
China
Prior art keywords
tunnel
parallel heading
double line
construction
later stage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710153954.XA
Other languages
Chinese (zh)
Other versions
CN106988748B (en
Inventor
范磊
王唤龙
刘黎
何万阳
李泽龙
杨昌宇
陶伟明
张海波
郦亚军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Eryuan Engineering Group Co Ltd CREEC
Original Assignee
China Railway Eryuan Engineering Group Co Ltd CREEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Eryuan Engineering Group Co Ltd CREEC filed Critical China Railway Eryuan Engineering Group Co Ltd CREEC
Priority to CN201710153954.XA priority Critical patent/CN106988748B/en
Publication of CN106988748A publication Critical patent/CN106988748A/en
Application granted granted Critical
Publication of CN106988748B publication Critical patent/CN106988748B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts

Abstract

High-order parallel heading construction and the construction method that capacity expansion revamping is double line tunnel, produce substantial amounts of abandoned project to be prevented effectively from capacity expansion revamping construction, farthest reduce construction safety risk, and construction investment is greatly reduced.High-order parallel heading construction includes being located at the parallel heading on the left of existing tunnel or at 30~50m of right side, the center line of the parallel heading coincides with later stage double line tunnel center line, Qi Keng bottom surfaces are located in later stage double line tunnel more than rail top surface, and its section Internal periphery shape is adapted with later stage double line tunnel top section.The parallel heading arch wall scope uses bolt-spary supports structure, is used as the permanent support system of later stage double line tunnel top arch wall scope.The parallel heading bottom surface sets form concrete bottom plate, and hole bottom gutter is arranged at parallel heading side.

Description

High-order parallel heading construction and the construction method that capacity expansion revamping is double line tunnel
Technical field
The present invention relates to Tunnel Engineering, more particularly to a kind of high-order parallel heading construction and capacity expansion revamping are double line tunnel Construction method.
Background technology
With the great-leap-forward development of China's communication, the traffic network such as railway, highway is when passing through landform difficulty mountain area Substantial amounts of super long tunnel can be emerged in large numbers, tunnel is longer, the geologic element that it passes through is more complicated, then difficulty of construction is also bigger.To solve The super long tunnel completion time of project, take into account in-cavity construction ventilation, draining, abandon quarrel, operation ventilation and take precautions against natural calamities evacuation etc. require, in combination Shape, geological conditions, and the need for the later stage expands and can increase and build Double line project, super long tunnel suitably set parallel heading as aiding in hole Road, parallel heading is normally on the left of I threaded lists road or at 30~50m of right side, and Qi Keng bottom surfaces are mostly less than rail top surface 1.2 in tunnel ~2.0m, in favor of water outlet in white-out tunnel.After tunnel I line completion of works, using existing parallel heading, enlarging is multiple in good time Line or II threaded lists road.
Parallel heading cross-section is arranged according to means of transportation, the appearance and size of current equipment, people's row safe distance, pipeline And the factor such as gutter arrangement determines that flexible transport bicycle road parallel heading section headroom size is generally 5.0m (width) × 6.0m (height), flexible transport two-way traffic parallel heading section headroom size is generally 7.5m (width) × 6.2m (height).Parallel heading is used Based on shotcrete lining cutting, weak surrounding rock and underground water development section can set up set lining on the inside of the hole of shotcrete lining cutting, Portal Section and pass through The bad geological section such as fault belt use moulded lining.Because parallel heading is deposited with the tunnel cross-section Internal periphery after need to extending In larger difference, conventional way is the concrete lining structure and bolt-spary supports for first removing existing parallel heading, and using both There is parallel heading to caunch upwards, abutment wall is digged and downward bottomed excavation, uses drilling and blasting method enlarging construction for the lining section in tunnel Profile, and apply preliminary bracing, waterproof layer and secondary lining.Existing enlargement method has the following disadvantages:Super long tunnel geology Complicated condition, the joint density area extremely developed in weak surrounding rock, crack, rich water karst stratum, fault belt etc. are poorly Quality section, the moulded lining or bolt-spary supports for removing existing parallel heading easily triggers the considerable safety thing such as landslide or gushing water, prominent mud Therefore, the safety of operating personnel and construction equipment is seriously endangered, there is high construction safety risk;Lining concrete after dismounting As quarrel processing is abandoned, reinforcing bar and steelframe are difficult to be utilized again in engineering, there is serious abandoned project, economy is very Difference.
The content of the invention
The technical problems to be solved by the invention are to provide a kind of high-order parallel heading construction, to be prevented effectively from capacity expansion revamping Construction produces substantial amounts of abandoned project, farthest reduces construction safety risk, and construction investment is greatly reduced.
The technical solution adopted for the present invention to solve the technical problems is as follows:
The high-order parallel heading construction of the present invention, including the parallel conductive on the left of existing tunnel or at 30~50m of right side Hole, it is characterized in that:The center line of the parallel heading coincides with later stage double line tunnel center line, and Qi Keng bottom surfaces are located at later stage multiple line tunnel In road more than rail top surface, its section Internal periphery shape is adapted with later stage double line tunnel top section;The parallel heading arch wall Scope uses bolt-spary supports structure, is used as the permanent support system of later stage double line tunnel top arch wall scope;The parallel heading Bottom surface sets form concrete bottom plate, and hole bottom gutter is arranged at parallel heading side.
Another technical problem to be solved by this invention is to provide a kind of above-mentioned high-order parallel heading construction capacity expansion revamping The construction method of double line tunnel, this method comprises the following steps:1. it is multiple by the use of the bolt-spary supports structure of parallel heading as the later stage The permanent preliminary bracing system in threaded list road, locally occurs in place of peeling off using spray before bottomed excavation to bolt-spary supports body structure surface Penetrate concrete to fill spray smooth-going, and cheated in parallel heading and row's grouting anchor pile is arranged symmetrically at bottom and arch springing carries out local grouting and reinforcing Country rock;2. later stage tunnel bottom is bottomed excavates, and is constructed, is first excavated away from the side lower part of existing tunnel one using left side, right side framing Rock mass, applies abutment wall preliminary bracing structure under the new excavation face in the side, inverted arch preliminary bracing structure and lock pin system in time;It is delayed 3~5m excavates another side lower part rock mass again, and abutment wall preliminary bracing structure under the new excavation face in the side, inverted arch branch at initial stage are applied in time Protection structure and lock pin system and device;3. short abutment wall, inverted arch and inverted arch packed layer are poured successively, lay waterproof layer, and apply in time Arch wall secondary lining.
The beneficial effects of the invention are as follows the high-order parallel heading implemented in advance is set in line with the principle for facing combination forever, after pressing Phase needs the profiled outline for the double line tunnel top preliminary bracing that capacity expansion revamping is to draft, and by later stage Tunnel Internal periphery Vault absolute altitude determine the elevation of high-order parallel heading, the bolt-spary supports of parallel heading arch wall scope is used as the permanent of later stage tunnel Supporting, capacity expansion revamping construction only the bottomed excavation of branch, branch need to apply the new excavation face in bottom on the basis of high-order parallel heading Supporting;Thoroughly evade the high security risk that the arch wall supporting for removing existing parallel heading and ripping construction are brought, and Avoid capacity expansion revamping construction from producing substantial amounts of abandoned project, can significantly save construction cost;Construction method security risk is low, can be real Shi Xingqiang, process are simple, operating efficiency is high, short time limit, and construction investment can be greatly reduced.
Brief description of the drawings
This specification includes following four width accompanying drawing:
Fig. 1 is the sectional drawing of high-order parallel heading construction of the invention;
Fig. 2 is that high-order parallel heading construction capacity expansion revamping of the invention is supporting reinforcing section before the construction of double line tunnel Schematic diagram;
Fig. 3 is that high-order parallel heading construction capacity expansion revamping of the invention excavates for base tunnel in the construction method of double line tunnel is bottomed And preliminary bracing applies process profile diagram;
Fig. 4 is that high-order parallel heading construction capacity expansion revamping of the invention is Tunnel Second Lining in the construction method of double line tunnel Apply process sectional schematic diagram;
Component and corresponding mark are shown in figure:Rail top surface A in later stage double line tunnel, parallel heading center line B, double line tunnel Center line C, later stage double line tunnel bottom excavation contour line D, parallel heading 10, bolt-spary supports liner structure 11, steelframe 11a, system Anchor pole 11b, shotcrete layer 11c, form concrete bottom plate 12, at the beginning of cheating bottom gutter 13, grouting anchor pile 14, lower-left side wall Phase supporting construction 21, inverted arch preliminary bracing structure 22, bottom right side wall preliminary bracing structure 23, lock pin system and device 25, short side Wall 31, inverted arch 32, waterproof layer 33, arch wall secondary lining 34, inverted arch packed layer 35.
Embodiment
The present invention is further described with reference to the accompanying drawings and examples.
Reference picture 1, high-order parallel heading construction of the invention, including on the left of existing tunnel or at 30~50m of right side Parallel heading 10.The present invention is broken the normal procedure, and parallel heading 10 is set by the theory for facing combination forever, in the parallel heading 10 Line B coincides with later stage double line tunnel center line C, and its polycrystalline substance is located in later stage double line tunnel on rail top surface A, in its section Contour shape is adapted with later stage double line tunnel top section.I.e. the headroom of parallel heading 10 except meet construction period haulage vehicle, Personnel are current and pipeline, the laying in gutter require outer, and parallel heading 10 presses the preliminary bracing lubrication groove of double line tunnel top section The Clearance requirement that exterior feature is set and reserved Support Deformation amount, secondary lining are applied.The absolute altitude of parallel heading 10 break by its cheat bottom with Rail top surface or road bed determine the routine of elevation relation in tunnel, and as at the beginning of the supporting construction vault of parallel heading 10 and double line tunnel Phase supporting vault is concordant etc., and a height of principle is determined, it is to avoid later stage increasing builds double line tunnel to parallel heading ripping construction.
Referring to Figures 1 and 2, the arch wall scope of parallel heading 10 uses bolt-spary supports structure 11, is used as later stage multiple line tunnel The permanent support system of road top arch wall scope.The bottom surface of parallel heading 10 sets form concrete bottom plate 12, mainly as Parallel heading construction period haulage vehicle and the passage of personnel's turnover are used, and thickness is generally 20cm.Hole bottom gutter 13 is set In the side of parallel heading 10, can combine I threaded lists road construction drainage needs corresponding deepen.The bolt-spary supports structure 11 is mixed by injection Solidifying soil layer 11c, bar-mat reinforcement, steelframe 11a and system anchor bolt 11b are constituted, and shotcrete layer 11c is attached on country rock, bar-mat reinforcement It is embedded in steelframe frame 11a in shotcrete layer 11c, system anchor bolt 11b is laid along country rock in blossom type, its outer end and steelframe 11a anchor connections.
The high-order parallel heading construction of the present invention is set in line with the principle for facing combination forever, and answering after capacity expansion revamping is needed by the later stage The profiled outline of threaded list road top preliminary bracing is drafted, and determines a high position by the vault absolute altitude of later stage Tunnel Internal periphery The elevation of parallel heading, the bolt-spary supports structure 11 of the arch wall scope of parallel heading 10 expands energy as the permanent support in later stage tunnel Rebuilding construction only need on the basis of high-order parallel heading branch it is bottomed excavate, branch applies the supporting of the new excavation face in bottom.It is thorough The high security risk that the arch wall supporting for removing existing parallel heading and the Enlargement excavation that caunches are brought is evaded at bottom, and avoids expanding Energy rebuilding construction produces substantial amounts of abandoned project, can significantly save construction cost.
Reference picture 2, Fig. 3 and Fig. 4, the high-order parallel heading capacity expansion revamping are the construction method of double line tunnel, including such as Lower step:
1. by the use of parallel heading 10 bolt-spary supports structure 11 as later stage double line tunnel permanent preliminary bracing system, Locally occur peeling off part to the surface of bolt-spary supports structure 11 before bottomed excavation and filled spray smooth-going using gunite concrete, and in parallel Row's grouting anchor pile 14 is arranged symmetrically at the hole bottom of base tunnel 10 and arch springing and carries out local grouting reinforcement rock, when being excavated to prevent falling stop bottom Existing bolt-spary supports structure 11 is caused sedimentation displacement occur.Grouting anchor pile 14 is laid by drilling, can be with reference between steelframe 11a longitudinal directions Away from setting;
2. later stage tunnel bottom is bottomed excavates, and is constructed, is first excavated away under existing tunnel side using left side, right side framing Portion's rock mass, applies abutment wall preliminary bracing structure under the new excavation face in the side, inverted arch preliminary bracing structure and lock pin system dress in time Put 25;Delayed 3~5m excavates another side lower part rock mass again, apply in time abutment wall preliminary bracing structure under the new excavation face in the side, Inverted arch preliminary bracing structure and lock pin system and device 25;
3. short abutment wall (31), inverted arch 32 and inverted arch packed layer 35 are poured successively, are laid waterproof layer 33, arch wall are applied in time secondary Lining cutting 34.
The step 2. after the completion of, lower left side abutment wall preliminary bracing structure 21 that tunnel both sides are newly implemented, right side abutment wall Preliminary bracing structure 23 is well connected with top bolt-spary supports structure 11, and is closed into time with inverted arch preliminary bracing structure 22 Ring, is collectively forming the carrying support system of later stage double line tunnel.
Construction method security risk of the invention is low, exploitativeness is strong, process is simple, operating efficiency is high, short time limit, and can Construction investment is greatly reduced.

Claims (4)

1. high-order parallel heading construction, including the parallel heading (10) on the left of existing tunnel or at 30~50m of right side, it is special Levying is:The center line (B) of the parallel heading (10) coincides with later stage double line tunnel center line (C), and it is cheated bottom structure and is located at the later stage In double line tunnel more than rail top surface (A), its section Internal periphery shape is adapted with later stage double line tunnel top section;It is described parallel Base tunnel (10) arch wall scope uses bolt-spary supports structure (11), is used as the permanent support body of later stage double line tunnel top arch wall scope System;Parallel heading (10) bottom surface sets form concrete bottom plate (12), and hole bottom gutter (13) is arranged at parallel heading (10) side.
2. high position parallel heading as claimed in claim 1, it is characterized in that:The bolt-spary supports structure (11) is by shotcrete layer (11c), bar-mat reinforcement, steelframe (11a) and system anchor bolt (11b) are constituted, and shotcrete layer (11c) is attached on country rock, reinforcing bar Net and steelframe (11a) are embedded in shotcrete layer (11c), and system anchor bolt (11b) is laid along country rock in blossom type, its outer end With steelframe steelframe (11a) anchor connection.
3. high position parallel heading capacity expansion revamping is the construction method of double line tunnel as claimed in claim 1, comprise the following steps:
1. by the use of parallel heading (10) bolt-spary supports structure (11) as later stage double line tunnel permanent preliminary bracing system, Locally occur peeling off part to bolt-spary supports structure (11) surface before bottomed excavation and filled spray smooth-going using gunite concrete, and in putting down Row base tunnel (10), which is cheated, is arranged symmetrically the local grouting reinforcement rock of row's grouting anchor pile (14) progress at bottom and arch springing;
2. later stage tunnel bottom is bottomed excavates, and is constructed, is first excavated away from the side lower part rock of existing tunnel one using left side, right side framing Body, applies abutment wall preliminary bracing structure under the new excavation face in the side, inverted arch preliminary bracing structure and lock pin system and device in time (25);Delayed 3~5m excavates another side lower part rock mass again, apply in time abutment wall preliminary bracing structure under the new excavation face in the side, Inverted arch preliminary bracing structure and lock pin system and device (25);
3. short abutment wall (31), inverted arch (32) and inverted arch packed layer (35) are poured successively, and laying waterproof layer (33) applies arch wall two in time Secondary lining cutting (34).
4. high position parallel heading capacity expansion revamping is the construction method of double line tunnel as claimed in claim 3, it is characterized in that:The step Suddenly 2. after the completion of, lower left side abutment wall preliminary bracing structure (21) that tunnel both sides are newly implemented, right side abutment wall preliminary bracing structure (23) well it is connected with top bolt-spary supports structure (11), and closing is cyclic in time with inverted arch preliminary bracing structure 22, common shape Into the carrying support system of later stage double line tunnel.
CN201710153954.XA 2017-03-15 2017-03-15 High-order parallel heading construction and capacity expansion revamping are the construction method of double line tunnel Active CN106988748B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710153954.XA CN106988748B (en) 2017-03-15 2017-03-15 High-order parallel heading construction and capacity expansion revamping are the construction method of double line tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710153954.XA CN106988748B (en) 2017-03-15 2017-03-15 High-order parallel heading construction and capacity expansion revamping are the construction method of double line tunnel

Publications (2)

Publication Number Publication Date
CN106988748A true CN106988748A (en) 2017-07-28
CN106988748B CN106988748B (en) 2019-10-29

Family

ID=59412741

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710153954.XA Active CN106988748B (en) 2017-03-15 2017-03-15 High-order parallel heading construction and capacity expansion revamping are the construction method of double line tunnel

Country Status (1)

Country Link
CN (1) CN106988748B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109403986A (en) * 2017-08-16 2019-03-01 中铁二院工程集团有限责任公司 The synchronous enlarging of the parallel heading of TBM tunneling construction is the construction method of double line tunnel
CN110566240A (en) * 2019-08-26 2019-12-13 中铁四局集团第五工程有限公司 Construction method suitable for protecting existing tunnel in close-proximity expanded excavation tunnel construction

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006077402A (en) * 2004-09-07 2006-03-23 Shimizu Corp Underground timbering structure and its construction method, and tunnel construction method
WO2006057545A1 (en) * 2004-11-29 2006-06-01 Dong-Hyun Seo Tunnelling method using pre-support concept and an adjustable apparatus thereof
JP2008308835A (en) * 2007-06-12 2008-12-25 Ohbayashi Corp Construction method for sidewall pilot tunnel type tunnel and its structure
CN101737061A (en) * 2009-12-24 2010-06-16 中国水电顾问集团华东勘测设计研究院 Method for constructing double-arch tunnel by rebuilding and expanding existing single-hole tunnel
JP4480907B2 (en) * 2001-02-15 2010-06-16 島田 巌乃 Tunnel excavation method
CN102155233A (en) * 2011-04-21 2011-08-17 上海市城市建设设计研究院 Tunnel excavation construction method
CN102400689A (en) * 2011-11-30 2012-04-04 中国建筑第五工程局有限公司 Convoluted excavation method for undermined tunnel with extra-large cross section
CN103821523A (en) * 2014-02-07 2014-05-28 福建省交通规划设计院 Excavating method for extending existing single-hole two-driveway tunnel into four-driveway tunnel
CN106050262A (en) * 2016-07-20 2016-10-26 中铁二院工程集团有限责任公司 Composite lining structure for super-large-span pile-foundation-joist-based bearing arched tunnel and construction method thereof
CN207018003U (en) * 2017-03-15 2018-02-16 中铁二院工程集团有限责任公司 High-order parallel heading construction

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4480907B2 (en) * 2001-02-15 2010-06-16 島田 巌乃 Tunnel excavation method
JP2006077402A (en) * 2004-09-07 2006-03-23 Shimizu Corp Underground timbering structure and its construction method, and tunnel construction method
WO2006057545A1 (en) * 2004-11-29 2006-06-01 Dong-Hyun Seo Tunnelling method using pre-support concept and an adjustable apparatus thereof
JP2008308835A (en) * 2007-06-12 2008-12-25 Ohbayashi Corp Construction method for sidewall pilot tunnel type tunnel and its structure
CN101737061A (en) * 2009-12-24 2010-06-16 中国水电顾问集团华东勘测设计研究院 Method for constructing double-arch tunnel by rebuilding and expanding existing single-hole tunnel
CN102155233A (en) * 2011-04-21 2011-08-17 上海市城市建设设计研究院 Tunnel excavation construction method
CN102400689A (en) * 2011-11-30 2012-04-04 中国建筑第五工程局有限公司 Convoluted excavation method for undermined tunnel with extra-large cross section
CN103821523A (en) * 2014-02-07 2014-05-28 福建省交通规划设计院 Excavating method for extending existing single-hole two-driveway tunnel into four-driveway tunnel
CN106050262A (en) * 2016-07-20 2016-10-26 中铁二院工程集团有限责任公司 Composite lining structure for super-large-span pile-foundation-joist-based bearing arched tunnel and construction method thereof
CN207018003U (en) * 2017-03-15 2018-02-16 中铁二院工程集团有限责任公司 High-order parallel heading construction

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109403986A (en) * 2017-08-16 2019-03-01 中铁二院工程集团有限责任公司 The synchronous enlarging of the parallel heading of TBM tunneling construction is the construction method of double line tunnel
CN110566240A (en) * 2019-08-26 2019-12-13 中铁四局集团第五工程有限公司 Construction method suitable for protecting existing tunnel in close-proximity expanded excavation tunnel construction

Also Published As

Publication number Publication date
CN106988748B (en) 2019-10-29

Similar Documents

Publication Publication Date Title
WO2021223573A1 (en) Construction structure for communication and connection between newly added mined channel and existing station hall layer
CN106437726B (en) Shallow-depth-excavation tunnel crosses ground fissure crushed zone construction method
CN202707075U (en) Long-span subway station main structure constructed based on column and arch method
CN105201516B (en) A kind of main structure of subway station and its tetrad arch PBA excavating construction methods
CN101769154A (en) Excavation supporting method for tunnel construction
CN104389610B (en) A kind of ultrashort step construction method of traversing operation freeway tunnel
CN105839643A (en) Tunnel in-hole construction method adopting foundation pit support
CN201433344Y (en) Composite protection structure for stabilizing road bed in mountain road
CN108194102A (en) The dismounting of limit section and safe stress check calculation construction method are invaded in Tunnel deformation
CN109736827B (en) Method for excavating urban subway hard rock stratum communication channel by high-pressure gas expansion fracturing
CN101280568A (en) Station pit construction method forming protection for neighboring operated subway interval tunnel
CN105240024B (en) A kind of method of parallel shield method enlarging construction subway station
CN201991017U (en) Subway large-span station body structure based on arch cover method construction forming
CN110905530B (en) Stability control construction method for water-rich soft rock tunnel penetrating fault fracture zone
CN110924959B (en) Construction method of water-rich weak surrounding rock tunnel penetrating fault fracture zone
CN103362513A (en) Transformation and construction method for existing cavity in underground excavation region
CN102817621B (en) Comprehensive construction method applicable to controlling arch basement sedimentation for tunnel in unfavorable geological conditions
CN205532615U (en) Super large section tunnel excavates structure
CN207892653U (en) Decompression hydrophobic structure suitable for Weathering-residual soil layer fissure zone
CN108797620A (en) A kind of OPT construction method of interlocking pile
CN110617067A (en) Low-risk construction method for full-section boundary advanced pipe shed of extremely-soft surrounding rock tunnel
CN207813651U (en) A kind of ground water drainage system for double-hole tunnel
CN109838240A (en) Cross the river tunnel ledge cover and cut construction method
CN112983467B (en) Treatment method for tunnel gate closing type large collapse
CN108374674B (en) Six pilot tunnels, 12 step Underground Space Excavation method for protecting support

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant