CN106988533A - A kind of construction method of concrete staircase tiling dual side-edge wall not lattice side's centering - Google Patents

A kind of construction method of concrete staircase tiling dual side-edge wall not lattice side's centering Download PDF

Info

Publication number
CN106988533A
CN106988533A CN201710333787.7A CN201710333787A CN106988533A CN 106988533 A CN106988533 A CN 106988533A CN 201710333787 A CN201710333787 A CN 201710333787A CN 106988533 A CN106988533 A CN 106988533A
Authority
CN
China
Prior art keywords
wall
line
center line
cut
long
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710333787.7A
Other languages
Chinese (zh)
Other versions
CN106988533B (en
Inventor
陈明宝
冯志斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201710333787.7A priority Critical patent/CN106988533B/en
Publication of CN106988533A publication Critical patent/CN106988533A/en
Application granted granted Critical
Publication of CN106988533B publication Critical patent/CN106988533B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F11/00Stairways, ramps, or like structures; Balustrades; Handrails
    • E04F11/02Stairways; Layouts thereof
    • E04F11/104Treads
    • E04F11/16Surfaces thereof; Protecting means for edges or corners thereof
    • E04F11/17Surfaces

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Steps, Ramps, And Handrails (AREA)
  • Finishing Walls (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a kind of construction method of concrete staircase tiling dual side-edge wall not lattice side's centering, the center line of stair bench is released according to job site SURVEYING CONTROL NETWORK, again metope distance is measured according to this center line, during less than or equal to 30mm, in the less side of the long abutment wall of distance between center line, a vertical midpoint is taken in long abutment wall and short side wall corner, and take the vertical center line of long abutment wall, using the vertical midpoint of corner as starting point, along half space and mark time move towards snap the line, long abutment wall center line is intersected in, line of cut is formed;When being less than or equal to 60mm more than 30mm, a vertical midpoint is respectively taken in long abutment wall both sides and short side corner, the midpoint of top half space corner be starting point, along half space and mark time move towards snap the line, cross to form a line of cut with the midpoint of bottom half space corner.It is an advantage of the invention that being not only simple practicality, man-hour is saved, cost is reduced, and ensure construction quality in error specification.

Description

A kind of construction method of concrete staircase tiling dual side-edge wall not lattice side's centering
Technical field
The present invention relates to building structure construction technical field, more particularly to a kind of concrete staircase tiling dual side-edge wall is not The construction method of lattice side's centering.
Background technology
Concrete building ladder rung paving ceramic tile, due to concrete wall surface and marks time expander or other reasonses cause metope not It is vertical or lattice side and do not cause metope during plaster leveling and mark time out of plumb or not lattice side.At present frequently with construction method have Two:One is to take to cut metope;Two be amendment stairway width.Above-mentioned two kinds of construction methods not only waste of time, increases cost, and And metope easily produces secondary mass defect at amendment concrete bench.
The content of the invention
There is provided a kind of concrete staircase tiling dual side-edge for the problem of purpose of the present invention exists aiming at prior art The construction method of wall not lattice side's centering, is not only simple practicality, saves man-hour, reduces cost, and can reach regulation requirement, so that Ensure construction quality in error specification.
The object of the present invention is achieved like this:A kind of construction of concrete staircase tiling dual side-edge wall not lattice side's centering Method, it is characterised in that:
According to job site SURVEYING CONTROL NETWORK release stair bench center line, then according to this center line measure metope away from From different errors use different treating method, during less than or equal to 30mm, in the long abutment wall of distance between center line less one Side, a vertical midpoint is taken in long abutment wall and short side wall corner, and takes the vertical center line of long abutment wall, with corner it is vertical in Point is starting point, along half space and mark time move towards snap the line, be intersected in long abutment wall center line, form line of cut;It is small more than 30mm When equal to 60mm, respectively taken in long abutment wall both sides and short side corner in a vertical midpoint, top half space corner Point be starting point, along half space and mark time move towards snap the line, cross to form one with the midpoint of bottom half space corner Line of cut;With line of the hand-held cutting machine along bullet or picture and metope cutting at 45 °, the part below the line of bullet or picture is cut into Fritter is latticed, then is removed with chiso-mallet by cut portion, during less than or equal to 30mm, removes under joint absolute altitude 1/4 face wall, greatly When 30mm is less than or equal to 60mm, under joint absolute altitude 1/2 face wall is removed, floating grey, the loose concrete on metope is removed, Wall is cleaned one time with clear water again after cleaning out, it is again levelling in the part of removal, until meeting the stair of codes and standards Size.
A kind of construction method of concrete staircase tiling dual side-edge wall not lattice side's centering, it is characterised in that:By following step It is rapid to carry out:
1) surveying setting-outs, according to the coordinate of job site SURVEYING CONTROL NETWORK and center line datum mark, with total powerstation or longitude and latitude Instrument measuring instrument releases central point in staircase;
2) cross laser instruments cultellation centering, by the requirement of design drawing and job specfication, using cross laser instrument by four Point is thrown on same line, and formation center line is parallel with long abutment wall, and another laser rays of cross laser instrument will be parallel with short side wall, And it is vertical with long abutment wall;Check that distance center line, to the size of long or short side wall both sides, detects long abutment wall and short side wall with tape measure It is whether vertical;
3) measures snap the line centering, and the size for measuring center line to the long lateral extent of abutment wall two is less than or equal to 30mm, in center line The less side of distance wall, a vertical midpoint is taken in long abutment wall and short side wall corner, and take long abutment wall it is vertical in Line, using the vertical midpoint of corner as starting point, along half space and mark time move towards snap the line, be intersected in long abutment wall center line, formed Line of cut, take within line of cut 1/4 face wall;The size for measuring center line to the long lateral extent of wall two is less than or equal to more than 30mm 60mm, a vertical midpoint is respectively taken in long abutment wall both sides and short side corner, using the midpoint of top half space corner as Point, along half space and mark time move towards snap the line, cross to form a line of cut with the midpoint of bottom half space corner, Take below line of cut 1/2 face wall;
4) cuttings cut centering, using hand-held cutting machine along line of cut and metope cutting at 45 °, by bullet or setting-out with Interior part is cut into fritter grid, and cut portion will be removed with chiso-mallet, removes floating grey, the loose concrete on surface, clearly Wall is cleaned one time with clear water again after reason is clean, it is again levelling in the part of removal;
5) wall plasterings centering, during less than or equal to 30mm, plasters to the distance of center line than increasing 1/2 distance before removing Error;When being less than or equal to 60mm more than 30mm, the long larger side of abutment wall distance center line, which is plastered, moves 1/2 range error to outside wall, Plaster to moving 1/2 range error within the walls the long smaller side of abutment wall distance center line.
Compared with prior art, it is an advantage of the invention that:Practicality is not only simple, man-hour is saved, reduces cost, and can reach Required to regulation, so as to ensure construction quality in error specification.
Brief description of the drawings
Fig. 1:Floor map of the present invention.
Fig. 2:1-1 profiles of the present invention.
Fig. 3:3-3 profiles of the present invention.
Fig. 4:Error of the present invention is less than or equal to 30mm centering plan.
Fig. 5:2-2 profiles of the present invention.
Fig. 6:4-4 profiles of the present invention.
Fig. 7:5-5 profiles of the present invention.
Fig. 8:Error 30mm-60mm of the present invention centering plan.
In figure:1st, staircase central point 2, stair bench center line 3, the long vertical midpoint 4 in side short side wall turning, long abutment wall are erected 5,1/4 cut portion 6 of whole face wall, line of cut 7, whole floated coat 8, concrete or the whole metope 9 of brick, long abutment wall to the midline Both sides and midpoint 11,1/2 cutting of whole face wall under vertical midpoint 10, long abutment wall both sides and short side wall turning on short side wall turning Vertical 1/2 high by 15, the Y that part 12, cutting concrete wall surface part 13, Z are that staristep is wide by 14, X is stair turning are stair 1/2 depth.
Embodiment
To further describe the present invention, with reference to embodiment and accompanying drawing, the invention will be further described.
As illustrated, a kind of construction method of concrete staircase tiling dual side-edge wall not lattice side's centering, it is characterised in that:
The center line 2 of stair bench is released according to job site SURVEYING CONTROL NETWORK, then metope is measured according to this center line 2 Distance, different errors use different treating method, during less than or equal to 30mm, in the long abutment wall of distance between center line less one Side, a vertical midpoint is taken in long abutment wall and short side wall corner 3, and takes the vertical center line 4 of long abutment wall, vertical with corner Midpoint is starting point, along half space and mark time move towards snap the line, be intersected in long abutment wall center line, form line of cut 6;More than 30mm During less than or equal to 60mm, a vertical midpoint 9 is respectively taken in long abutment wall both sides and short side corner, top half space corner Midpoint is starting point, along half space and mark time move towards snap the line, cross to be formed with the midpoint 10 of bottom half space corner One line of cut 6;With line of the hand-held cutting machine along bullet or picture and metope cutting at 45 °, by the part below the line of bullet or picture It is cut into fritter latticed, then is removed with chiso-mallet by cut portion 5 and 11, during less than or equal to 30mm, is removed under joint absolute altitude 1/4 face wall, more than 30mm be less than or equal to 60mm when, remove joint absolute altitude under 1/2 face wall, remove metope on it is floating ash, Loose concrete, is again cleaned wall one time with clear water after cleaning out, again levelling in the part moved or cut, until symbol Close the stair size of codes and standards.
A kind of construction method of concrete staircase tiling dual side-edge wall not lattice side's centering, it is characterised in that:By following step It is rapid to carry out:
1) surveying setting-outs, according to the coordinate of the SURVEYING CONTROL NETWORK of job site and absolute altitude datum mark, use total powerstation or warp Latitude instrument and spirit level measuring instrument release stair central point 1 in stair lower platform and upper brace;
2) cross laser instruments cultellation centering, is thrown four points on same line using cross laser instrument, forms half space Center line 2 is parallel with long abutment wall, and another laser rays of cross laser instrument will be parallel with short side wall, and vertical with long abutment wall;
3) measures snap the line centering, checks that center line, to the distance of long abutment wall both sides, detects long abutment wall and short side wall with tape measure It is whether vertical;It is Z+00mm to Z+30mm to measure center line to the long lateral extent of abutment wall two difference staristep wide 13;Center line away from From the less side of long wall, a vertical midpoint 3 is taken in long abutment wall and short side wall corner, and take the i.e. stair of long abutment wall 15 The vertical center line 4 of 1/2 depth, is starting point with the vertical midpoint 3 of corner, along half space and mark time move towards snap the line, cross In long abutment wall center line 4, line of cut 6 is formed;It is respectively that staristep wide 13 is Z+00mm to measure center line to the long lateral extent of abutment wall two During to Z+40mm, midpoint 9 and length wall on a vertical midpoint, length wall turning are respectively taken in long abutment wall both sides and short side corner Midpoint 10 under turning, are starting point with midpoint 9 on length wall turning, along half space and mark time move towards snap the line, with and length Midpoint 10 crosses to form a line of cut under wall turning;
4) cuttings cut centering, using hand-held cutting machine along line of cut and metope cutting at 45 °, by long side line of cut Within to be cut into fritter latticed for part, form cut portion 5 and cut portion 11 respectively;It is interval in Z+00mm to Z+30mm When, cut 1/4 cut portion 5 of concrete or the whole face wall 8 of brick;When Z+00mm to Z+40mmm is interval, cut concrete or 1/2 cut portion 11 of the whole face wall 8 of brick;Cut portion is removed using chiso-mallet, it is to avoid larger instrument is shaken using electric hammer, hold Easily cause the stair metope 7 plastered and shatter or hollowing, remove floating grey, the loose concrete cleaning cut on metope 12 dry Only, wall is cleaned one time with clear water;
5) wall plasterings centering, during less than or equal to 30mm, plasters to the distance of center line than increasing 1/2 before moving or cutting Range error, than moving or cutting big 15mm before;When being less than or equal to 60mm more than 30mm, the long larger side of abutment wall distance center line Plaster and 1/2 range error is moved to outside wall, the long smaller side of abutment wall distance center line is plastered to 1/2 range error is moved within the walls, respectively 20mm is moved to outside wall, to moving 20mm within the walls;When plastering with guiding ruler will plaster part and the i.e. stair turning in metope top 14 it is vertical 1/2 high shifting cuts part vertically by flat.

Claims (2)

1. a kind of construction method of concrete staircase tiling dual side-edge wall not lattice side's centering, it is characterised in that:
The center line (2) of stair bench is released according to job site SURVEYING CONTROL NETWORK, then metope is measured according to this center line (2) Distance, different errors use different treating method, during less than or equal to 30mm, in the long abutment wall of distance between center line less one Side, a vertical midpoint is taken in long abutment wall and short side wall corner (3), and takes the vertical center line (4) of long abutment wall, with corner Vertical midpoint is starting point, along half space and mark time move towards snap the line, be intersected in long abutment wall center line, form line of cut (6);Greatly When 30mm is less than or equal to 60mm, a vertical midpoint (9), top half space are respectively taken in long abutment wall both sides and short side corner The midpoint of corner be starting point, along half space and mark time move towards snap the line, the midpoint with bottom half space corner (10) cross to form a line of cut (6);With hand-held cutting machine along bullet and the line drawn and metope cutting at 45 °, by bullet or picture Line below to be cut into fritter latticed for part, then removed with chiso-mallet by cut portion, during less than or equal to 30mm, removal crosses 1/4 face wall under point absolute altitude, when being less than or equal to 60mm more than 30mm, removes under joint absolute altitude 1/2 face wall, removing cuts wall Floating grey, loose concrete on face (12), cleans one time, in the part of removal again with clear water by wall again after cleaning out It is levelling, until meeting the stair size of codes and standards.
2. a kind of construction method of concrete staircase tiling dual side-edge wall according to claim 1 not lattice side's centering, its It is characterised by, carries out according to the following steps:
1) surveying setting-outs, according to the coordinate of the SURVEYING CONTROL NETWORK of job site and absolute altitude datum mark, use total powerstation or theodolite Stair central point (1) is released in stair lower platform and upper brace with spirit level measuring instrument;
2) cross laser instruments cultellation centering, is thrown four points on same line using cross laser instrument, forms half space center Line (2) is parallel with long abutment wall, and another laser rays of cross laser instrument will be parallel with short side wall, and vertical with long abutment wall;
3) measures snap the line centering, checks that center line arrives the distance of long abutment wall both sides with tape measure, detects whether are long abutment wall and short side wall Vertically;It is Z+00mm to Z+30mm to measure center line to the long lateral extent of abutment wall two difference staristep wide (13);In distance between center line The long less side of wall, takes a vertical midpoint (3), and take long abutment wall (15) i.e. stair in long abutment wall and short side wall corner 1/2 depth vertical center line (4), with corner vertical midpoint (3) be starting point, along half space and mark time move towards bullet Line, is intersected in long abutment wall center line, forms line of cut (6);Measure center line wide (13) to the long lateral extent of abutment wall two difference staristep During for Z+00mm to Z+40mm, midpoint on a vertical midpoint, length wall turning is respectively taken in long abutment wall both sides and short side corner (9) and under length wall turning midpoint (10), with midpoint (9) on length wall turning for starting point, along half space and walking for marking time To snap the line, with crossing to form a line of cut with midpoint (10) under length wall turning;
4) cuttings cut centering, using hand-held cutting machine along line of cut and metope cutting at 45 °, within long side line of cut To be cut into fritter latticed for part, form cut portion (5) and cut portion (11) respectively;It is interval in Z+00mm to Z+30mm When, cut 1/4 cut portion (5) of concrete or the whole face wall of brick (8);When Z+00mm to Z+40mmm is interval, coagulation is cut 1/2 cut portion (11) of soil or the whole face wall of brick (8);Cut portion is removed using chiso-mallet, it is to avoid shaken using electric hammer larger Instrument, easily cause the whole metope of the stair plastered (7) and shatter or hollowing, remove cut on metope (12) it is floating ash, pine Scattered concrete is cleaned out, and is cleaned wall one time with clear water;
5) wall plasterings centering, during less than or equal to 30mm, plasters to the distance of center line than increasing 1/2 distance before moving or cutting Error, than moving or cutting big 15mm before;When being less than or equal to 60mm more than 30mm, the long larger side of abutment wall distance center line is plastered 1/2 range error is moved to outside wall, the long smaller side of abutment wall distance center line is plastered to 1/2 range error is moved within the walls, respectively to wall Outer shifting 20mm, to moving 20mm within the walls;To be plastered part and metope top (14) i.e. vertical the 1/2 of stair turning when plastering with guiding ruler It is vertical by flat that height moves or cut part.
CN201710333787.7A 2017-05-12 2017-05-12 A kind of construction method of concrete staircase tiling dual side-edge wall not lattice side's centering Active CN106988533B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710333787.7A CN106988533B (en) 2017-05-12 2017-05-12 A kind of construction method of concrete staircase tiling dual side-edge wall not lattice side's centering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710333787.7A CN106988533B (en) 2017-05-12 2017-05-12 A kind of construction method of concrete staircase tiling dual side-edge wall not lattice side's centering

Publications (2)

Publication Number Publication Date
CN106988533A true CN106988533A (en) 2017-07-28
CN106988533B CN106988533B (en) 2019-04-05

Family

ID=59419264

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710333787.7A Active CN106988533B (en) 2017-05-12 2017-05-12 A kind of construction method of concrete staircase tiling dual side-edge wall not lattice side's centering

Country Status (1)

Country Link
CN (1) CN106988533B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107620455A (en) * 2017-09-21 2018-01-23 浙江博元建设股份有限公司 A kind of quick accurate setting-out construction method of stair facing
CN108537375A (en) * 2018-03-30 2018-09-14 苏州喆堃智能科技有限公司 Module number acquisition methods in modularization paving process
CN109138451A (en) * 2018-10-19 2019-01-04 中国十七冶集团有限公司 A kind of construction method of stair floor tile paving
CN109855611A (en) * 2019-03-27 2019-06-07 中南大学 A kind of PC wall rapid survey calibration method based on total station
CN111608389A (en) * 2019-06-21 2020-09-01 中建材创新科技研究院有限公司 Stair floor tile paving construction method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101565997A (en) * 2009-05-25 2009-10-28 青岛恒生源集团建设有限公司 Construction method for large-area irregular floor tile
CN102454269A (en) * 2010-10-21 2012-05-16 李世成 House decoration bricklayer construction method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101565997A (en) * 2009-05-25 2009-10-28 青岛恒生源集团建设有限公司 Construction method for large-area irregular floor tile
CN102454269A (en) * 2010-10-21 2012-05-16 李世成 House decoration bricklayer construction method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
不详: "山西博物馆工程装饰工程质量通病防治", 《工程质量》 *
张吉人: "瓷质板块地面砖施工及质量预控", 《建筑技术》 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107620455A (en) * 2017-09-21 2018-01-23 浙江博元建设股份有限公司 A kind of quick accurate setting-out construction method of stair facing
CN108537375A (en) * 2018-03-30 2018-09-14 苏州喆堃智能科技有限公司 Module number acquisition methods in modularization paving process
CN109138451A (en) * 2018-10-19 2019-01-04 中国十七冶集团有限公司 A kind of construction method of stair floor tile paving
CN109138451B (en) * 2018-10-19 2021-04-13 中国十七冶集团有限公司 Construction method for paving stair floor tiles
CN109855611A (en) * 2019-03-27 2019-06-07 中南大学 A kind of PC wall rapid survey calibration method based on total station
CN109855611B (en) * 2019-03-27 2022-03-15 中南大学 PC wall body rapid measurement and calibration method based on total station
CN111608389A (en) * 2019-06-21 2020-09-01 中建材创新科技研究院有限公司 Stair floor tile paving construction method

Also Published As

Publication number Publication date
CN106988533B (en) 2019-04-05

Similar Documents

Publication Publication Date Title
CN106988533B (en) A kind of construction method of concrete staircase tiling dual side-edge wall not lattice side's centering
Lynch Brickwork: History, Technology and Practice: v. 2
CN108824505B (en) Sinking construction method for close-range sinking well group
CN106381980A (en) Floor tile paving process
CN107675704A (en) A kind of artificial digging pile assembled retaining wall and its construction technology
CN103469828A (en) Construction method of hydrophobic structure of post-cast strip of bottom plate of basement
CN102995666A (en) Construction method for reducing effect of vibration on peripheral buildings (structures)
CN105089216A (en) Three-dimensional positioning decoration construction method for spiral staircase stone facing
CN205735590U (en) Ceramic tile cutting auxiliary device
CN103912127A (en) Building formwork or floor slab construction control method and special straightedge
CN106639247A (en) Construction technique for paving ceramic floor tiles
Lehner Some observations on the layout of the Khufu and Khafre pyramids
CN102995899A (en) Measurement control method for size of vertical member for building construction
CN115142583A (en) Construction method of thin masonry and thin plastering block wall
CN109057356A (en) A kind of fine leveling method of ground flat degree
CN108894498A (en) A kind of building filling wall integrated construction technique
JP7538073B2 (en) Floor construction method and floor inspection device
CN216893783U (en) Light partition wall with simple foundation
CN104631257A (en) Method for constructing Belgian road in testing track
CN109763667B (en) Anti-cracking construction method for light wallboard
CN211850620U (en) Device of straightness and thickness is plastered to accurate control ardealite
CN215483808U (en) Masonry plastering wall connection structure under full shear wall structure
CN206681388U (en) Piece crack stopper between a kind of masonry wall and structure
CN216209168U (en) Concrete slump observation chamber
CN101285295B (en) Re-projection construction method for bridge conical slope

Legal Events

Date Code Title Description