CN106979027A - Control the convergent lock pin stake supporting construction of Tunnel sedimentation - Google Patents

Control the convergent lock pin stake supporting construction of Tunnel sedimentation Download PDF

Info

Publication number
CN106979027A
CN106979027A CN201710337460.7A CN201710337460A CN106979027A CN 106979027 A CN106979027 A CN 106979027A CN 201710337460 A CN201710337460 A CN 201710337460A CN 106979027 A CN106979027 A CN 106979027A
Authority
CN
China
Prior art keywords
lock pin
convergent
pin stake
supporting construction
reinforcing bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710337460.7A
Other languages
Chinese (zh)
Inventor
王丽庆
伊兴芳
曾青
侯军红
高树峰
张弛
陈平
苏哿
王乐明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Design Corp
Original Assignee
China Railway Design Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Design Corp filed Critical China Railway Design Corp
Priority to CN201710337460.7A priority Critical patent/CN106979027A/en
Publication of CN106979027A publication Critical patent/CN106979027A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • E21D21/0026Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection characterised by constructional features of the bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting
    • E21D20/021Grouting with inorganic components, e.g. cement

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Inorganic Chemistry (AREA)
  • Civil Engineering (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention discloses the convergent lock pin stake supporting construction of one kind control Tunnel sedimentation, including the preliminary bracing in Tunnel room, inclined lock pin stake is provided with the preliminary bracing outer wall, the lock pin stake includes churning pile body, the churning pile body is connected with L-type steel muscle core, the L-type steel muscle core other end is connected with being connected reinforcing bar, and the connection reinforcing bar is connected with the I-steel steelframe of preliminary bracing.The technology of the present invention technique is simple, the interference of process transformer effect less, operation facility, work efficiency is improved, and excavation of being got out of a predicament or an embarrassing situation in overcoming causes that arch springing is hanging, tunnel-side is unstable or slips the problems such as collapsing and lock footnote slurry anchoring effect difference.Realize stable face, the deformation of control cavern and sedimentation and mechanized construction.

Description

Control the convergent lock pin stake supporting construction of Tunnel sedimentation
Technical field
Glued the invention belongs to settlement Control relatively tight, the fine sand layer of self-stable ability extreme difference, water-rich saturated ground or stream modeling shape Property the special formation construction risk such as soil great tunnels and underground engineering design, technical field of construction, and in particular to one kind control The convergent lock pin stake supporting construction of Tunnel sedimentation.
Background technology
Lock foot anchoring stock(Or lock pin anchor tube)The technology that combined bolting and shotcrete grows up is accompanied by, is the arch of supporting in the early stage A kind of steel construction sideling set at pin.Before gunite concrete after tunnel excavation, steelframe are set up, it is consolidated with steelframe It is fixed, limit surrouding rock deformation together with steelframe and pneumatically placed concrete.Be generally located on more than steelframe arch springing gusset plate junction 20~ In the range of 100 cm, direction is downward 15~30 degree of oblique cutting angle, 3~4m of length, anchor pole Φ 22mm hot-rolled reinforced bars(Anchor tube Φ 42 Seamless steel pipe).Play a part of abutment wall system anchor bolt constraint country rock and preliminary bracing steelframe in top is deformed and supported into tunnel, hold back Steelframe processed sedimentation and clearance convergence under pressure from surrounding rock effect.Because its construction is simple and easy to apply, economy, effect are obvious, efficiency height etc. Reason has obtained extensive utilization.
There is many nonstandard places in its construction, such as slip casting is not full, first branch steelframe base foundation chance water softening, The low problem of foundation bearing capacity, lock foot anchoring stock(Pipe)Effect can not embody, and result in deformation, the cracking of preliminary bracing, generally adopt Take avoid constructing because of it for measure and not in place above mentioned problem occur.But in Extra-fine sand of self-stable ability extreme difference etc. distinguishingly Under the conditions of matter, stratum slip casting effect is poor, plastic zone of surrounding rock is big, anchor force is weak, arch springing is hanging and side wall at country rock slip the reason such as collapse, The lock foot anchoring stock of setting(Pipe)Stratum and the load that transmits of support top preliminary bracing can not be constrained, cause preliminary bracing sedimentation and Deformation is excessive, and greatly hidden danger is left to construction.
The content of the invention
The present invention proposes that the purpose is to provide a kind of control Tunnel to solve the problem of prior art is present The convergent lock pin stake supporting construction of sedimentation.
The technical scheme is that:The convergent lock pin stake supporting construction of one kind control Tunnel sedimentation, including Inclined lock pin stake is provided with preliminary bracing in Tunnel room, the preliminary bracing outer wall, the lock pin stake includes churning Pile body, the churning pile body is connected with L-type steel muscle core, and the L-type steel muscle core other end is connected with being connected reinforcing bar, the connection steel Muscle is connected with the I-steel steelframe of preliminary bracing.
The lock pin stake is set for 30 ~ 45 degree obliquely along preliminary bracing side wall.
The churning pile body is by being anchored formed by rotating-spray campaign and slurries filling effect, restructuring rock mass structure Churning drilling is formed in body, rotary churning pile body, the reinforcing bar core is connected in churning drilling.
The top half of the tunnel cavern is located in layer of sand, and the latter half is located in loess formation, treats every circulation top bar After pneumatically placed concrete injection, before middle bench excavation, lock pin stake is applied at arch springing between two steel arch-shelfs of top bar.
The tunnel cavern is entirely located in layer of sand, after in every circulation, middle step pneumatically placed concrete injection after, in, leave office Before rank is excavated, lock pin stake is applied at arch springing between upper, middle two steel arch-shelfs of step.
The top half of the tunnel cavern is located at loess, and the latter half is located in layer of sand, treats in every circulation, middle step sprays After concrete ejection, in, before excavation of getting out of a predicament or an embarrassing situation, lock pin stake is applied at arch springing between upper, middle two steel arch-shelfs of step.
Its long side insertion churning drilling of the L-type steel muscle core, its short side is connected with being connected reinforcing bar, I-steel steelframe.
The L-type steel muscle core is with being connected reinforcing bar, the connected mode of I-steel steelframe is welding.
The connected mode of the connection reinforcing bar and I-steel steelframe is welding.
The technology of the present invention technique is simple, process transformer effect is disturbed less, operation facility, and work efficiency is improved, overcome In excavation of getting out of a predicament or an embarrassing situation cause that arch springing is hanging, tunnel-side is unstable or slip to collapse and lock the problems such as footnote slurry anchoring effect is poor.Realize Face is stable, control cavern is deformed and sedimentation and mechanized construction.
The lock pin stake major advantage wherein implemented:
1)Bearing capacity is high, settling amount is small, clearance convergence is small:Stake and stratum composite integrated, frictional resistance are big, and column rigidity is big, In get out of a predicament or an embarrassing situation excavation containment side wall quicksand phenomenon;Steel yield strength is high simultaneously, can provide stronger support force.
2)Joint is easily handled, easy to connect, reliable:Rotary churning pile inserts steel pipe in time after applying, the welding of steel pipe one end is fixed Steel bar, easily welds with first branch steelframe, can effectively implement stake and be combined with steelframe.
3)The long, adjustable angle of stake:Site operation adjusts that stake is long, angle according to monitoring measurement in time.
4)Construction is flexible:Work on the spot amount is reduced, the randomness of construction is eliminated, it is simple to operate, it is ensured that the implementation effect of lock pin Really.
5)Lock pin stake can provide larger axle power, constrain just branch steel frame deformation, got out of a predicament or an embarrassing situation in reduction and excavate the lateral of the soil body Deformation.
Brief description of the drawings
Fig. 1 is the structural representation of first embodiment of the invention;
Fig. 2 is the structural representation of second embodiment of the invention;
Fig. 3 is the structural representation of third embodiment of the invention;
Fig. 4 is node full-page proof schematic diagram at arch springing of the present invention;
Fig. 5 is Fig. 4 top view;
Fig. 6 is Fig. 4 side view;
Wherein:
1 preliminary bracing 2 lock pin stake
The lock foot anchoring stock of 3 L-type steel muscle core 4
5 I-steel steelframes 6 connect reinforcing bar
7 secondary linings.
Embodiment
Hereinafter, referring to the drawings and embodiment the present invention is described in detail:
As shown in Fig. 1 ~ 6, in one kind control Tunnel sedimentation convergent stake of lock pin supporting construction, including Tunnel room Inclined lock pin stake 2 is provided with preliminary bracing 1, the outer wall of preliminary bracing 1, the lock pin stake 2 includes churning pile body, described Churning pile body is connected with L-type steel muscle core 3, the other end of L-type steel muscle core 3 be connected reinforcing bar 6 be connected, it is described connection reinforcing bar 6 with The I-steel steelframe 5 of preliminary bracing 1 is connected.
The lock pin stake 2 is set for 30 ~ 45 degree obliquely along the side wall of preliminary bracing 1.
The churning pile body is by being anchored formed by rotating-spray campaign and slurries filling effect, restructuring rock mass structure Churning drilling is formed in body, rotary churning pile body, the reinforcing bar core 3 is connected in churning drilling.
As shown in figure 1, the top half of the tunnel cavern is located in layer of sand, the latter half is located in loess formation, because of sand Layer is unstable, and arch springing is hanging or quicksand etc. causes preliminary bracing sedimentation, deformation big, and stronger support and constraint need to be set at arch springing Distressed structure;Therefore, after after every circulation top bar pneumatically placed concrete injection, before middle bench excavation, skew back arrangement is set up at arch springing Churning machinery, lock pin stake 2 is applied at arch springing between two steel arch-shelfs of top bar.During skew back churning operation, high pressure is sent first Water, then cement mortar and pressure-air are sent, first it should be reached during injection after predetermined injection pressure, grouting amount, in gradually hoisting grouting pipe. The lap of splice that Grouting Pipe is segmented lifting cannot be less than 100mm, when reaching design stake top height or excessive slurry phenomenon occur, should stop The only churning work of current stake, and churning pipe is extracted and detergent line.The firm muscle core 3 of L-type is inserted before grout cures, and by steel Muscle is welded with steelframe.
As shown in Fig. 2 the tunnel cavern is entirely located in layer of sand, because layer of sand is unstable, arch springing is hanging or quicksand etc. Cause preliminary bracing sedimentation, deformation big, stronger support and constraint distressed structure need to be set at arch springing;Therefore, treat in every circulation, After the injection of middle step pneumatically placed concrete, in, before excavation of getting out of a predicament or an embarrassing situation, the churning machinery of skew back arrangement is set up at arch springing, at upper, middle Lock pin stake 2 is applied between two steel arch-shelfs of rank at arch springing.During skew back churning operation, water under high pressure is sent first, then send cement mortar and height Air is pressed, first should be reached during injection after predetermined injection pressure, grouting amount, in gradually hoisting grouting pipe.Grouting Pipe segmentation lifting The lap of splice cannot be less than 100mm, when reaching design stake top height or excessive slurry phenomenon occur, should stop the churning work of current stake Make, and churning pipe is extracted and detergent line.The firm muscle core 3 of L-type is inserted before grout cures, and reinforcing bar and steelframe are welded.
As shown in figure 3, the top half of the tunnel cavern is located at loess, the latter half is located in layer of sand, because of layer of sand not Stable, arch springing is hanging or quicksand etc. causes preliminary bracing sedimentation, deformation big, and stronger support and restrained deformation need to be set at arch springing Structure;Therefore, after in every circulation, middle step pneumatically placed concrete injection after, in, before excavation of getting out of a predicament or an embarrassing situation, at arch springing set up skew back cloth The churning machinery put, applies lock pin stake 2 between upper, middle two steel arch-shelfs of step at arch springing.During skew back churning operation, send first Water under high pressure, then cement mortar and pressure-air are sent, first it should be reached during injection after predetermined injection pressure, grouting amount, in gradually lifting note Slurry pipe.The lap of splice that Grouting Pipe segmentation is lifted cannot be less than 100mm, and phenomenon is starched when reaching design stake top height or occurring overflowing When, the churning work of current stake should be stopped, and churning pipe is extracted and detergent line.The firm muscle core of L-type is inserted before grout cures 3, and reinforcing bar and steelframe are welded.
Its long side insertion churning drilling of the L-type steel muscle core 3, its short side is connected with being connected reinforcing bar 6, I-steel steelframe 5.
The L-type steel muscle core 3 is with being connected reinforcing bar 6, the connected mode of I-steel steelframe 5 is welding.
The connected mode of the connection reinforcing bar 6 and I-steel steelframe 5 is welding.
After preliminary bracing 1 is applied, lock pin stake 2 is often applied between circulation steelframe, the reinforcing bar core of L-type is inserted before grout cures Material 3, and reinforcing bar core 3 is welded with I-steel steelframe 5, to ensure that load increases a connection steel of Φ 32 below L-type steel muscle 3 Muscle 6, and will connection reinforcing bar 6 and L-type steel muscle core 3, the firm welding of I-steel steelframe 5.
Reinforcing bar core 3 is processed into L-type using long 4.7m hot-rolled reinforced bars of Φ 32, long side 4m after processing, short side 0.4m, with The L-type steel rib component of 90 degree of 10cm radius bends.
The connection reinforcing bar that reinforcing bar 6 is two Pin steelframes is connected, in order to which preferably node is connected, is divided into the short side of reinforcing bar core 3 Connection reinforcing bar 6 is put, and by its reinforcing bar and steelframe firm welding.
The technology of the present invention technique is simple, process transformer effect is disturbed less, operation facility, and work efficiency is improved, overcome In excavation of getting out of a predicament or an embarrassing situation cause that arch springing is hanging, tunnel-side is unstable or slip to collapse and lock the problems such as footnote slurry anchoring effect is poor.Realize Face is stable, control cavern is deformed and sedimentation and mechanized construction.

Claims (9)

1. the preliminary bracing in one kind control Tunnel sedimentation convergent stake of lock pin supporting construction, including Tunnel room (1), it is characterised in that:The preliminary bracing(1)Inclined lock pin stake is provided with outer wall(2), the lock pin stake(2)Including rotation Spray pile body, the churning pile body and L-type steel muscle core(3)It is connected, L-type steel muscle core(3)The other end is with being connected reinforcing bar(6)Phase Even, the connection reinforcing bar(6)With preliminary bracing(1)I-steel steelframe(5)It is connected.
2. the convergent lock pin stake supporting construction of control Tunnel sedimentation according to claim 1, it is characterised in that: The lock pin stake(2)Along preliminary bracing(1)Side wall is set for 30 ~ 45 degree obliquely.
3. the convergent lock pin stake supporting construction of control Tunnel sedimentation according to claim 1, it is characterised in that: The churning pile body is by anchoring body, churning formed by rotating-spray campaign and slurries filling effect, restructuring rock mass structure Churning drilling, the reinforcing bar core are formed in pile body(3)It is connected in churning drilling.
4. the convergent lock pin stake supporting construction of control Tunnel sedimentation according to claim 1, it is characterised in that: The top half of the tunnel cavern is located in layer of sand, and the latter half is located in loess formation, treats every circulation top bar pneumatically placed concrete After injection, before middle bench excavation, lock pin stake is applied at arch springing between two steel arch-shelfs of top bar(2).
5. the convergent lock pin stake supporting construction of control Tunnel sedimentation according to claim 1, it is characterised in that: The tunnel cavern is entirely located in layer of sand, after in every circulation, middle step pneumatically placed concrete injection after, in, before excavation of getting out of a predicament or an embarrassing situation, Lock pin stake is applied at arch springing between upper, middle two steel arch-shelfs of step(2).
6. the convergent lock pin stake supporting construction of control Tunnel sedimentation according to claim 1, it is characterised in that: The top half of the tunnel cavern is located at loess, and the latter half is located in layer of sand, treats in every circulation, middle step pneumatically placed concrete sprays After penetrating, in, before excavation of getting out of a predicament or an embarrassing situation, lock pin stake is applied at arch springing between upper, middle two steel arch-shelfs of step(2).
7. the convergent lock pin stake supporting construction of control Tunnel sedimentation according to claim 3, it is characterised in that: The L-type steel muscle core(3)Its long side insertion churning drilling, its short side is with being connected reinforcing bar(6), I-steel steelframe(5)It is connected.
8. the convergent lock pin stake supporting construction of control Tunnel sedimentation according to claim 7, it is characterised in that: The L-type steel muscle core(3)With being connected reinforcing bar(6), I-steel steelframe(5)Connected mode for welding.
9. the convergent lock pin stake supporting construction of control Tunnel sedimentation according to claim 1, it is characterised in that: The connection reinforcing bar(6)With I-steel steelframe(5)Connected mode for welding.
CN201710337460.7A 2017-05-15 2017-05-15 Control the convergent lock pin stake supporting construction of Tunnel sedimentation Pending CN106979027A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710337460.7A CN106979027A (en) 2017-05-15 2017-05-15 Control the convergent lock pin stake supporting construction of Tunnel sedimentation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710337460.7A CN106979027A (en) 2017-05-15 2017-05-15 Control the convergent lock pin stake supporting construction of Tunnel sedimentation

Publications (1)

Publication Number Publication Date
CN106979027A true CN106979027A (en) 2017-07-25

Family

ID=59341968

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710337460.7A Pending CN106979027A (en) 2017-05-15 2017-05-15 Control the convergent lock pin stake supporting construction of Tunnel sedimentation

Country Status (1)

Country Link
CN (1) CN106979027A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107476809A (en) * 2017-09-05 2017-12-15 长安大学 A kind of large deformation control method of chlorite schist stratum longspan tunnel
CN108533296A (en) * 2018-06-11 2018-09-14 中铁二局第工程有限公司 Large deformation tunnel steelframe prearrangement of deformation amount unit docking structure and construction method
CN109322687A (en) * 2018-10-26 2019-02-12 林翠英 A kind of soft rock tunnel, which is got out of a predicament or an embarrassing situation, excavates the control method that anti-settling restrains hydraulic collateral support arrangement
CN109538246A (en) * 2018-12-26 2019-03-29 中铁科学研究院有限公司 Ledge method tunneling subway station arch springing ruggedized construction and construction method
CN109958456A (en) * 2019-04-25 2019-07-02 南昌工程学院 A kind of advance reinforcement construction method for building tunnel in the stratum of no self-stable ability
CN111706367A (en) * 2020-06-30 2020-09-25 中铁二院工程集团有限责任公司 Composite locking leg structure of preliminary bracing steel frame in tunnel and construction method
CN114960676A (en) * 2022-06-16 2022-08-30 广州市第二市政工程有限公司 Construction method of pressure injection type tubular pile enclosure supporting structure with embedded flexible anchor rod
CN116816362A (en) * 2023-08-31 2023-09-29 北京交通大学 Supporting and reinforcing method for intersection of positive tunnel and transverse channel of ultra-large buried soft rock tunnel

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102650210A (en) * 2012-05-11 2012-08-29 中铁十二局集团有限公司 Method for constructing tunnel with low-half cross section being dry powder and fine sand layers
CN203130108U (en) * 2013-03-15 2013-08-14 中铁十二局集团第二工程有限公司 Primary support structure of reinforced tunnel
CN103306687A (en) * 2012-10-31 2013-09-18 王卓 Construction method for deformation control via horizontal whirling jet grouting of long cantilever in soft-rock tunnel
CN205977233U (en) * 2016-08-11 2017-02-22 云南省建设投资控股集团有限公司 Tunnel lock foot spouts pilework soon
CN206942800U (en) * 2017-05-15 2018-01-30 中国铁路设计集团有限公司 The convergent lock pin stake supporting construction of one kind control Tunnel sedimentation

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102650210A (en) * 2012-05-11 2012-08-29 中铁十二局集团有限公司 Method for constructing tunnel with low-half cross section being dry powder and fine sand layers
CN103306687A (en) * 2012-10-31 2013-09-18 王卓 Construction method for deformation control via horizontal whirling jet grouting of long cantilever in soft-rock tunnel
CN203130108U (en) * 2013-03-15 2013-08-14 中铁十二局集团第二工程有限公司 Primary support structure of reinforced tunnel
CN205977233U (en) * 2016-08-11 2017-02-22 云南省建设投资控股集团有限公司 Tunnel lock foot spouts pilework soon
CN206942800U (en) * 2017-05-15 2018-01-30 中国铁路设计集团有限公司 The convergent lock pin stake supporting construction of one kind control Tunnel sedimentation

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107476809A (en) * 2017-09-05 2017-12-15 长安大学 A kind of large deformation control method of chlorite schist stratum longspan tunnel
CN107476809B (en) * 2017-09-05 2019-06-11 长安大学 A kind of large deformation control method of chlorite schist stratum longspan tunnel
CN108533296A (en) * 2018-06-11 2018-09-14 中铁二局第工程有限公司 Large deformation tunnel steelframe prearrangement of deformation amount unit docking structure and construction method
CN108533296B (en) * 2018-06-11 2023-09-15 中铁二局第一工程有限公司 Butt joint structure of reserved deformation units of large deformation tunnel steel frame and construction method
CN109322687A (en) * 2018-10-26 2019-02-12 林翠英 A kind of soft rock tunnel, which is got out of a predicament or an embarrassing situation, excavates the control method that anti-settling restrains hydraulic collateral support arrangement
CN109538246A (en) * 2018-12-26 2019-03-29 中铁科学研究院有限公司 Ledge method tunneling subway station arch springing ruggedized construction and construction method
CN109958456A (en) * 2019-04-25 2019-07-02 南昌工程学院 A kind of advance reinforcement construction method for building tunnel in the stratum of no self-stable ability
CN111706367A (en) * 2020-06-30 2020-09-25 中铁二院工程集团有限责任公司 Composite locking leg structure of preliminary bracing steel frame in tunnel and construction method
CN114960676A (en) * 2022-06-16 2022-08-30 广州市第二市政工程有限公司 Construction method of pressure injection type tubular pile enclosure supporting structure with embedded flexible anchor rod
CN116816362A (en) * 2023-08-31 2023-09-29 北京交通大学 Supporting and reinforcing method for intersection of positive tunnel and transverse channel of ultra-large buried soft rock tunnel
CN116816362B (en) * 2023-08-31 2023-10-31 北京交通大学 Supporting and reinforcing method for intersection of positive tunnel and transverse channel of ultra-large buried soft rock tunnel

Similar Documents

Publication Publication Date Title
CN106979027A (en) Control the convergent lock pin stake supporting construction of Tunnel sedimentation
CN208702421U (en) The tunnel support structure of existing pile foundation building is worn under a kind of
CN108412519A (en) The slight large deformation single-track tunnel suspension device of highlands soft rock and construction method
CN102605773B (en) Construction method of slip-casting expanded-base cast-in-situ bored pile and extruding-extending device thereof
CN101614125A (en) V level surrounding rock tunnel job practices
CN108612110B (en) Combined type supporting construction method for deep foundation pit of subway station
CN111648790B (en) Shallow-buried bias tunnel entry structure and construction method
CN106498950A (en) Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system and its implementation of pile body
CN104631440B (en) A kind of existing large-section in-situ concrete pile strength core increases foundation pit supporting construction and constructional method
CN110820762A (en) Construction method of stiff-core curtain pile and retaining wall pile anchor combined supporting structure
CN102864781A (en) Foundation pit supporting method utilizing inclined piles
CN103590408A (en) Novel double-row pile beam vertical anchor supporting system and construction method thereof
CN102650212A (en) Construction method for protecting partition wall in double-arch tunnel through temporary support of middle pilot tunnel
CN114215042A (en) Miniature steel pipe pile for reinforcing foundation and construction method thereof
CN206942800U (en) The convergent lock pin stake supporting construction of one kind control Tunnel sedimentation
CN108343450A (en) A kind of new pipe-roof method active well ruggedized construction and reinforcement means
CN109538236B (en) Tunnel entering structure and tunnel entering construction method
CN108978680B (en) Mucky soil elevator foundation pit supporting construction device and method
CN208236429U (en) A kind of new pipe-roof method active well ruggedized construction
CN100473787C (en) Connecting structure for use in piled anchor supporting system and construction method thereof
CN203768914U (en) Foundation pit bracing diagonal support pile structure
CN103410529B (en) A kind of support of tunnel arch springing ruggedized construction for weak surrounding rock and construction method
CN105840209B (en) Construction method for controlling deformation of anchor pile in tunnel body section
CN210106749U (en) Counter-force structure of soft soil foundation super large section push pipe jacking operation
CN205977233U (en) Tunnel lock foot spouts pilework soon

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170725