CN106968267A - One kind combination strength stem and construction method - Google Patents
One kind combination strength stem and construction method Download PDFInfo
- Publication number
- CN106968267A CN106968267A CN201710190381.8A CN201710190381A CN106968267A CN 106968267 A CN106968267 A CN 106968267A CN 201710190381 A CN201710190381 A CN 201710190381A CN 106968267 A CN106968267 A CN 106968267A
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- steel
- stem
- pipe column
- plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/10—Deep foundations
- E02D27/12—Pile foundations
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/10—Deep foundations
- E02D27/12—Pile foundations
- E02D27/14—Pile framings, i.e. piles assembled to form the substructure
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/42—Foundations for poles, masts or chimneys
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/38—Connections for building structures in general
- E04B1/58—Connections for building structures in general of bar-shaped building elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C3/00—Structural elongated elements designed for load-supporting
- E04C3/30—Columns; Pillars; Struts
- E04C3/36—Columns; Pillars; Struts of materials not covered by groups E04C3/32 or E04C3/34; of a combination of two or more materials
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
Abstract
Strength stem is combined the present invention relates to one kind, mainly including pile foundation, cushion cap, steel pipe column, steel pipe stem and shaped steel stem;Pre-buried build-in steel pipe in pile foundation;Build-in steel pipe is connected with steel pipe column locating support in cushion cap;Steel pipe column is installed on steel pipe column locating support top in cushion cap;Steel pipe column top joint steel pipe stem;Steel pipe stem top connecting-type steel core post.By the invention belongs to structural steelwork field, for the construction method of steel pipe column, steel pipe stem, shaped steel stem in high-rise, super-high building structure, effectively reduction engineering cost, accelerates speed of application, applied to can obtain preferable technical economic benefit in Practical Project.
Description
Technical field
The present invention relates to one kind combination strength stem and construction method, belong to structural steelwork field, it is adaptable to high-rise, superelevation
Steel pipe column, steel pipe stem, the construction of shaped steel stem in layer building structure.
Background technology
With continuing to develop for China's building trade, newly-built architectural style is increasingly diversified, and steel construction is widely used
In large public building, in order to meet Architectural Design Requirements so that structure type entered by letter it is numerous, structural section also from unicity to
Complicated sex reversal, the exposed complete bright permeable structures form of main structure body uses more and more, processing, installation so to steel construction
Propose requirements at the higher level.
Steel construction is managed with the advantages such as its short time limit, easy construction, energy-saving and environmental protection, antidetonation, industrialization production and recycling economy
Read and used by more and more building.Architecture structure form is from traditional reinforced concrete structure gradually to steel construction and reinforcing bar
The structure type transformation that concrete structure is combined.Especially in some high-rise, high-rise buildings, steel construction already takes up work
The principal status of public economy of journey structure.Many need such as use function, structural safety performance, appearance and modeling in order to realize building
Ask, when traditional H types, steel beam with box shape steel member can not meet these requirements, the form of steel construction also to diversified development,
Some compound section steel members are gradually available in some large-scale engineerings.
The content of the invention
The problem of it is an object of the invention to be constructed for combination strength stem, there is provided one kind combination strength stem and construction party
Method, meets the demand of structure construction.
In order to realize above-mentioned technical purpose, present invention employs following technical scheme:
One kind combination strength stem, it is characterised in that mainly include pile foundation 1, cushion cap 9, steel pipe column 12, steel pipe stem 29 and type
Steel core post 35;Pre-buried build-in steel pipe 6 in pile foundation 1;Build-in steel pipe 6 is connected with steel pipe column locating support 10 in cushion cap 9;In cushion cap 9
The top of steel pipe column locating support 10 is installed by steel pipe column 12;The top joint steel pipe stem 29 of steel pipe column 12;The top of steel pipe stem 29 connects
Direct type steel core post 35.
The bottom of build-in steel pipe 6 sets steel plate 3, and steel plate 3 is welded with steel reinforcement cage reinforcement 2;Set on build-in steel pipe 6
Peg 5 is welded with pile foundation cage bar 4;The top of pile foundation 1 cuts and is provided with PVC disrance sleeves 20 outside the build-in steel pipe 6 of position;Pile foundation 1
Top sets bed course 7;The jacking junction steel plate 19 that the top of build-in steel pipe 6 is set can with the setting of the bottom of steel pipe column locating support 10
Mode positioning support 18 is welded to connect;The top of steel pipe column locating support 10 sets monoblock type junction steel plate 15;Monoblock type junction steel plate
Positioning bloom 14 is set on 15;The middle part of steel pipe column locating support 10 sets support to fix ring flat-plate 16;On steel pipe column locating support 10
Sealing steel loop 8 is set.
The steel pipe column 12 is positioned by positioning bloom 14;The bottom of steel pipe column 12 sets steel pipe column to connect ring flat-plate 11;
Steel pipe column 12 connects ring flat-plate 11 and monoblock type junction steel plate 15 by the joint steel pipe post of steel pipe column connecting bolt 13;Steel pipe column is connected
Ring flat-plate 11 and monoblock type junction steel plate 15 are welded to connect.
The bottom of steel pipe column 12 opens up notch;The locator card 24 set on internal lining pipe 21 passes through notch;Steel pipe column 12 it
Between connect through internal lining pipe 21, locator card 24, arc backplate 25, bolt 23 carry out bolt-weld joint;When steel pipe column 12 is installed, use
Locating steel frame 27 and jack 26 carry out auxiliary positioning installation.
It is attached between the steel pipe column 12 and steel pipe stem 29 by connecting fin 30;Pass through between connection fin 30
Inner core tube 28 is attached;Steel pipe stem 29 and the lower frame portion of inner core tube 28 set connection ring flat-plate 31 inside core pipe.
The steel pipe stem 29 sets reinforcing bar fixing steel plate 42 with girder connection coupling part;Welded on reinforcing bar fixing steel plate 42
Straight screw sleeve 39;Beam main tendon 43 is connected by straight screw sleeve 39 with reinforcing bar fixing steel plate 42;Reinforcing bar fixing steel plate 42 passes through
Positioning screw 41 is positioned;Reinforcing bar fixing steel plate 42 is welded and fixed with steel pipe stem 29 and tooth form backplate 40;Reinforcing bar is determined
Hole 45 of vibrating is set on the steel plate 42 of position;Steel pipe stem 29 is provided with tooth form backplate 40 with girder connection junction;Tooth form backplate 40 it
Between be attached by inner core tube 28.
It is welded to connect between the steel pipe stem 29 and shaped steel stem 35;The shaped steel connection peg set on shaped steel stem 35
34 weld with steel pipe core column tie-bar 33.
The steel pipe stem 29 is provided with post cage bar 32, post spiral bar 36 and steel pipe stem dowel 37.
The shaped steel stem 35 is provided with shaped steel, post cage bar 32, post spiral bar 36 and shaped steel stem stirrup 38.
The construction method of combinations thereof strength stem, it is characterised in that comprise the following steps:
Step 1: build-in steel pipe 6, steel pipe column locating support 10, the column jecket of steel pipe column 12, steel pipe stem 29, shaped steel stem 35
And connection fin 30 is processed:Build-in steel pipe 6 uses the steel pipe manufacturings of φ 300, two ends welding steel, middle weld stud 5;Steel pipe column
Locating support 10, using the steel pipe manufacturings of φ 80, the adjustable positioning support 18 of lower weld, the adjustable positioning lower weld jacking of support 18
Junction steel plate 19, the upper weld monoblock type junction steel plate 15 of steel pipe column locating support 10, the middle part of steel pipe column locating support 10 is set
Support fixes welding sealing steel loop 8 on ring flat-plate 16, steel pipe column locating support 10;The making of the column jecket of steel pipe column 12, plate rolling tube
The method that welding uses Lincoln weld;Steel pipe stem 29 is rolled using steel plate and is welded;Shaped steel stem 35 is added using segmentation
Work, is its floor height per segment length, is welded into " right-angled intersection double H-type " section Steel Column;
Step 2: pile foundation construction:The pre-buried build-in steel pipe 6 in the steel reinforcement cage installation process of pile foundation 1, the bottom steel of build-in steel pipe 6
Plate is welded with steel reinforcement cage reinforcement 2;The peg 5 of build-in steel pipe 6 is welded with pile foundation cage bar 4;The top of pile foundation 1 cuts position
The build-in steel pipe 6 put installs PVC disrance sleeves 20;Then pile foundation filling concrete is carried out;
Step 3: steel pipe column locating support 10 is installed and cushion cap 9 is constructed:The top of pile foundation 1 carries out pile crown and cut, and then constructs
Bed course 7, the top of build-in steel pipe 6 carries out welded and installed with the bottom of steel pipe column locating support 10 by jacking junction steel plate 19, then
Carry out reinforcing bar colligation, model sheetinstallat and concreting;
Step 4: the installation of steel pipe column 12:First section steel pipe column 12 is positioned by positioning bloom 14, and steel pipe column 12 passes through
The joint steel pipe post of bolt 13 connects ring flat-plate 11 and monoblock type junction steel plate 15, and ring flat-plate 11 and monoblock type connection are connected to steel pipe column
Steel plate 15 is welded;Positioned between steel pipe column 12 by internal lining pipe 21 and locator card 24, pass through bolt 23 and arc protective
Plate 25 is attached, and steel pipe column 12 and the link position of arc backplate 25 are welded;
Step 5: steel pipe column 12 and steel pipe core connection:Steel pipe column 12 and steel pipe stem 29 are attached with connection fin 30;
Steel pipe column 12 is in termination along slot at axis cutting 4, and the top of steel pipe column 12 is located on flooring 1 meter, and connection fin 30 is inserted
In the slot of steel pipe column 12, the slot of steel pipe column 12 carries out reinforcing bar colligation, punching block to this section of post with being connected the full weld of fin 30, then and installed
And concreting;
Step 6: at levels beam-column node steel pipe stem 29 connection:Reinforcing bar fixing steel plate 42 passes through positioning screw 41
Positioned, beam main tendon 43 is attached by straight screw sleeve 39 with reinforcing bar fixing steel plate 42, reinforcing bar fixing steel plate 42 and steel
Tube core post 29 and tooth form backplate 40 are welded and fixed, and reinforcing bar colligation, punching block are then carried out to the section installs and concreting,
Vibrated in concreting process by the hole 45 of vibrating on reinforcing bar fixing steel plate 42;
Step 7: the connection of steel pipe stem 29 and shaped steel stem 35:In the junction of steel pipe stem 29 and shaped steel stem 35,
The termination of steel pipe stem 29 along axis cutting 4 at slot, during installation toward slot insert shaped steel and with shape steel web full weld, then it is right
The section carries out reinforcing bar colligation, punching block and installed and concreting.
The invention has the characteristics that and beneficial effect:
(1) steel pipe, steel pipe core, H profile steel core combination cylinder accomplish that stress can according to three's stress and the relation of steel quantity consumption
OK, economical rationality;
(2) component such as steel pipe column column jecket, steel pipe core, fin core is carried out batch production and made, it is ensured that dimension precision requirement, just
In in-site installation, duration and civilized construction are saved;
(3) connected between steel pipe column and the connection of steel pipe core stiffened column, every section of steel pipe core stiffened column using connection fin core
Connection construction technique, it is ensured that stiffened column quality of connection.
Brief description of the drawings
Fig. 1 is pile foundation and cushion cap and steel pipe column attachment structure figure;
Fig. 2 is reducing steel pipe column attachment structure figure;
Fig. 3 is isometrical steel pipe column attachment structure figure;
Fig. 4 is erection of steel pipe column positioning schematic diagram;
Fig. 5 is steel pipe column and steel pipe core attachment structure figure;
Fig. 6 is steel pipe stem lintel node connection plan;
Fig. 7 is steel pipe stem lintel node connection profile;
Fig. 8 is that steel pipe stem is connected plan with shaped steel stem;
Fig. 9 is that steel pipe stem is connected sectional view with shaped steel stem;
Figure 10 is steel pipe core column structure figure;
Figure 11 is shaped steel core column structure figure;
In figure:1- pile foundations;2- steel reinforcement cage reinforcements;3- steel plates;4- pile foundation cage bars;5- pegs;6- build-in steel pipes;7- pads
Layer;8- sealing steel loops;9- cushion caps;10- steel pipe column locating supports;11- steel pipe columns connect ring flat-plate;12- steel pipe columns;13- steel pipe columns
Connecting bolt;14- positions bloom;15- monoblock type junction steel plates;16- supports fix ring flat-plate;17- concrete;18- is adjustable fixed
Position support;19- jacking junction steel plates;20-PVC disrance sleeves;21- internal lining pipes;22- reducing steel pipe columns;23- bolts;24- is positioned
Card;25- arc backplates;26- jack;27- locating steel frames;28- inner core tubes;29- steel pipe stems;30- connection fins;31- cores
Connection ring flat-plate inside pipe;32- post cage bars;33- steel pipe core column tie-bars;34- shaped steel connects peg;35- shaped steel stems;36- post spiral shells
Revolve muscle;37- steel pipe stem dowels;38- shaped steel column tie-bars;39- straight screw sleeves;40- tooth form backplates;41- positioning screws;
42- reinforcing bar fixing steel plates;43- beam main tendons;44- beam stirrups;45- vibrates hole.
Embodiment
The construction technical requirement such as reinforcing bar colligation, the interior, concreting of template branch is repeated no more in embodiment of the present invention, weight
Point illustrates embodiments of the present invention, the present invention is described in further detail below in conjunction with the accompanying drawings and by embodiment, this is said
It is bright to be not limited to following examples.
Fig. 1 is pile foundation and cushion cap and steel pipe column attachment structure figure, and Fig. 2 is reducing steel pipe column attachment structure figure, and Fig. 3 is isometrical
Steel pipe column attachment structure figure, Fig. 4 is erection of steel pipe column positioning schematic diagram, and Fig. 5 is steel pipe column and steel pipe core attachment structure figure, Fig. 6
Steel pipe stem lintel node connection plan, Fig. 7 is steel pipe stem lintel node connection profile, Fig. 8 be steel pipe stem with
Shaped steel stem connects plan, and Fig. 9 is that steel pipe stem is connected sectional view with shaped steel stem, and Figure 10 is steel pipe core column structure figure, figure
11 be shaped steel core column structure figure.
Combination strength stem as shown in Figure 1 mainly includes pile foundation 1, cushion cap 9, steel pipe column 12, steel pipe stem 29 and shaped steel core
Post 35;Pre-buried build-in steel pipe 6 in pile foundation 1;Build-in steel pipe 6 is connected with steel pipe column locating support 10 in cushion cap 9;Steel pipe in cushion cap 9
The top of post locating support 10 is installed by steel pipe column 12;The top joint steel pipe stem 29 of steel pipe column 12;The top connecting-type of steel pipe stem 29
Steel core post 35.
Build-in steel pipe 6 is embedded with pile foundation 1, the bottom of build-in steel pipe 6 is provided with steel plate 3, steel plate 3 and steel reinforcement cage reinforcement 2
Welding.The peg 5 set on build-in steel pipe 6 is welded with pile foundation cage bar 4;The top of pile foundation 1 cuts the outer setting of build-in steel pipe 6 of position
There are PVC disrance sleeves 20;The top of pile foundation 1 sets bed course 7;Jacking junction steel plate 19 and steel pipe column that the top of build-in steel pipe 6 is set
The adjustable positioning support 18 that the bottom of locating support 10 is set is welded;The top of steel pipe column locating support 10 sets monoblock type junction steel plate
15;Positioning bloom 14 is set on monoblock type junction steel plate 15;The middle part of steel pipe column locating support 10 sets support to fix ring flat-plate 16;Steel
Sealing steel loop 8 is set on tubing string locating support 10.Steel pipe column 12 is positioned by positioning bloom 14;The bottom of steel pipe column 12 is set
Steel pipe column connects ring flat-plate 11;Steel pipe column 12 connects ring flat-plate 11 by the joint steel pipe post of steel pipe column connecting bolt 13 and monoblock type is connected
Steel plate 15;Steel pipe column connects ring flat-plate 11 and monoblock type junction steel plate 15 is welded to connect.
As shown in figs. 2 to 4, the bottom of steel pipe column 12 opens up notch;The locator card 24 set on internal lining pipe 21 passes through notch;Steel
Internal lining pipe 21, locator card 24, arc backplate 25, bolt 23 are connected through between tubing string 12 and carries out bolt-weld joint;Steel pipe column 12 is pacified
During dress, auxiliary positioning installation is carried out using locating steel frame 27 and jack 26.
As shown in figure 5, being attached between steel pipe column 12 and steel pipe stem 29 by connecting fin 30;Connect fin 30 it
Between be attached by inner core tube 28;Steel pipe stem 29 and the lower frame portion of inner core tube 28 set connection ring flat-plate inside core pipe
31。
As shown in figs. 6-7, steel pipe stem 29 sets reinforcing bar fixing steel plate 42 with girder connection coupling part;Reinforcing bar positions steel
Straight screw sleeve 39 is welded on plate 42;Beam main tendon 43 is connected by straight screw sleeve 39 with reinforcing bar fixing steel plate 42;Reinforcing bar is positioned
Steel plate 42 is positioned by positioning screw 41;Reinforcing bar fixing steel plate 42 carries out welding solid with steel pipe stem 29 and tooth form backplate 40
It is fixed;Hole 45 of vibrating is set on reinforcing bar fixing steel plate 42;Steel pipe stem 29 is provided with tooth form backplate 40 with girder connection junction;Tooth form
It is attached between backplate 40 by inner core tube 28.
Lead to as shown in Fig. 8~9, between steel pipe stem 29 and shaped steel stem 35 and be welded to connect;Set on shaped steel stem 35
Shaped steel connects peg 34 and carries out welding positioning with steel pipe core column tie-bar 33.
As shown in Figure 10, steel pipe stem 29 is provided with steel pipe stem 29, post cage bar 32, post spiral bar 36, steel pipe stem and connected
Connect muscle 37.
As shown in figure 11, steel core post is provided with shaped steel, post cage bar 32, post spiral bar 36, shaped steel stem stirrup 38.
The main construction course for combining the construction of strength stem is as follows:
Step 1: build-in steel pipe 6, steel pipe column locating support 10, the column jecket of steel pipe column 12, steel pipe stem 29, shaped steel stem 35
And connection fin 30 is processed:Build-in steel pipe 6 makes, and build-in steel pipe 6 uses the steel pipe manufacturings of φ 300, two ends welding steel, centre weldering
Connect peg 5;Steel pipe column locating support 10, using the steel pipe manufacturings of φ 80, the adjustable positioning support 18 of steel pipe lower weld is adjustable fixed
The position lower weld jacking junction steel plate 19 of support 18, the upper weld monoblock type junction steel plate 15 of steel pipe column locating support 10, steel pipe column
The middle part of locating support 10 sets support to fix welding sealing steel loop 8 on ring flat-plate 16, steel pipe column locating support 10;The column jecket of steel pipe column 12
Making, plate rolling tube welding using Lincoln weld method, electric current, voltage and speed of welding should be joined by technique during welding
Number and related guidelines, all weld seams all should meet the requirement of first-order weld, and 100% ultrasonic examination inspection is carried out in accordance with regulations
Look into;The making of steel pipe stem 29, steel pipe core is rolled using Q235B steel plates and is welded;The making of shaped steel stem 35;Shaped steel stem
35 segmental machinings, are its floor height per segment length, wherein one H type are cut into two shaped steel, and use CO2Gas shield
It is welded into " right-angled intersection double H-type " section Steel Column;The making of fin 30 is connected, fin core is radially welded in seamless steel pipe footpath
4 steel plates are connect, steel plate thickness, length press design requirement.Fin core be used for levels post steel pipe column 12 and steel pipe stem 29 it
Between connection and for the connection between steel pipe stem 29, width stretches out 10mm on the outside of the pipe of steel pipe column 12, meets welding requirements, in
The heart, which is stayed, connects mouth under the soldering and sealing core pipe of ring flat-plate 31 inside the core pipe in φ 100mm holes.
Step 2: pile foundation construction:The pre-buried build-in steel pipe 6 in the steel reinforcement cage installation process of pile foundation 1, the bottom steel of build-in steel pipe 6
Plate is welded with steel reinforcement cage reinforcement 2;The peg 5 of build-in steel pipe 6 is welded with pile foundation cage bar 4;The top of pile foundation 1 cuts position
The build-in steel pipe 6 put installs PVC disrance sleeves 20;Then pile foundation filling concrete is carried out.
Step 3: steel pipe column locating support 10 is installed and cushion cap 9 is constructed:The top of pile foundation 1 carries out pile crown and cut, and then constructs
Bed course 7, the top of build-in steel pipe 6 carries out welded and installed with the bottom of steel pipe column locating support 10 by jacking junction steel plate 19, then
Carry out reinforcing bar colligation, model sheetinstallat and concreting.
Step 4: the installation of steel pipe column 12:First section steel pipe column 12 is positioned by positioning bloom 14, and steel pipe column 12 passes through
The joint steel pipe post of bolt 13 connects ring flat-plate 11 and monoblock type junction steel plate 15, and ring flat-plate 11 and monoblock type connection are connected to steel pipe column
Steel plate 15 is welded;Positioned between steel pipe column 12 by internal lining pipe 21 and locator card 24, pass through bolt 23 and arc protective
Plate 25 is attached, and steel pipe column 12 and the link position of arc backplate 25 are welded.
Step 5: steel pipe column 12 and steel pipe core connection:Steel pipe column 12 and steel pipe stem 29 are attached with connection fin 30.
Steel pipe column 12 is in termination along slot at axis cutting 4, and a length of design length of slot, the top of steel pipe column 12 is located on flooring 1 meter,
The steel pipe stem 29 of the produced connection core of fin 30 in prior two ends is inserted in the slot of steel pipe column 12, the slot of steel pipe column 12 and company
The full weld of fin 30 is connect, and ensures the three same circularity of pipe, reinforcing bar colligation, punching block installation and concrete are then carried out to this section of post and is poured
Build.
Step 6: at levels beam-column node steel pipe stem 29 connection:Reinforcing bar fixing steel plate 42 passes through positioning screw 41
Positioned, beam main tendon 43 is attached by straight screw sleeve 39 with reinforcing bar fixing steel plate 42, reinforcing bar fixing steel plate 42 and steel
Tube core post 29 and tooth form backplate 40 are welded and fixed, and reinforcing bar colligation, punching block are then carried out to the section installs and concreting,
Vibrated in concreting process by the hole 45 of vibrating on reinforcing bar fixing steel plate 42.
Step 7: the connection of steel pipe stem 29 and shaped steel stem 35:In the junction of steel pipe stem 29 and shaped steel stem 35,
In the termination of steel pipe stem 29 slot, a height of design height of slot at 4 are cut along axis.Toward slot insertion shaped steel and and type during installation
Steel web full weld, then carries out reinforcing bar colligation, punching block to the section and installs and concreting.
Claims (10)
1. one kind combination strength stem, it is characterised in that mainly including pile foundation (1), cushion cap (9), steel pipe column (12), steel pipe stem
And shaped steel stem (35) (29);Pre-buried build-in steel pipe (6) in pile foundation (1);Build-in steel pipe (6) is positioned with steel pipe column in cushion cap (9)
Support (10) is connected;Steel pipe column (12) is installed on steel pipe column locating support (10) top in cushion cap (9);Steel pipe column (12) top is connected
Steel pipe stem (29);Steel pipe stem (29) top connecting-type steel core post (35).
2. strength stem is combined as claimed in claim 1, it is characterised in that build-in steel pipe (6) bottom sets steel plate (3), steel
Plate (3) is welded with steel reinforcement cage reinforcement (2);The peg (5) set on build-in steel pipe (6) is welded with pile foundation cage bar (4);Pile foundation
(1) top cuts and is provided with PVC disrance sleeves (20) outside the build-in steel pipe (6) of position;Pile foundation (1) top sets bed course (7);It is embedding
The adjustable positioning support that the jacking junction steel plate (19) that steel pipe Gu (6) top is set is set with steel pipe column locating support (10) bottom
(18) it is welded to connect;Steel pipe column locating support (10) top sets monoblock type junction steel plate (15);Monoblock type junction steel plate (15)
It is upper that positioning bloom (14) is set;Support is set to fix ring flat-plate (16) in the middle part of steel pipe column locating support (10);Steel pipe column locating support
(10) sealing steel loop (8) is set on.
3. strength stem is combined as claimed in claim 1, it is characterised in that the steel pipe column (12) is entered by positioning bloom (14)
Row positioning;Steel pipe column (12) bottom sets steel pipe column to connect ring flat-plate (11);Steel pipe column (12) passes through steel pipe column connecting bolt (13)
Joint steel pipe post connection ring flat-plate (11) and monoblock type junction steel plate (15);Steel pipe column connection ring flat-plate (11) and monoblock type junction steel plate
(15) it is welded to connect.
4. strength stem is combined as claimed in claim 1, it is characterised in that steel pipe column (12) bottom opens up notch;Internal lining pipe
(21) locator card (24) set on passes through notch;Internal lining pipe (21), locator card (24), arc are connected through between steel pipe column (12)
Shape backplate (25), bolt (23) carry out bolt-weld joint.
5. strength stem is combined as claimed in claim 1, it is characterised in that between the steel pipe column (12) and steel pipe stem (29)
It is attached by connecting fin (30);It is attached between connection fin (30) by inner core tube (28);Steel pipe stem (29)
Connection ring flat-plate (31) inside core pipe is set with inner core tube (28) lower frame portion.
6. strength stem is combined as claimed in claim 1, it is characterised in that steel pipe stem (29) is set with girder connection coupling part
Reinforcing bar fixing steel plate (42);Straight screw sleeve (39) is welded on reinforcing bar fixing steel plate (42);Beam main tendon (43) passes through straight thread set
Cylinder (39) is connected with reinforcing bar fixing steel plate (42);Reinforcing bar fixing steel plate (42) is positioned by positioning screw (41);Reinforcing bar is determined
Position steel plate (42) is welded and fixed with steel pipe stem (29) and tooth form backplate (40);Set and vibrate on reinforcing bar fixing steel plate (42)
Hole (45);Steel pipe stem (29) is provided with tooth form backplate (40) with girder connection junction;Tooth form backplate passes through inner core between (40)
Pipe (28) is attached.
7. combination strength stem as claimed in claim 1, it is characterised in that the steel pipe stem (29) and shaped steel stem (35) it
Between be welded to connect;The shaped steel connection peg (34) set on shaped steel stem (35) is welded with steel pipe core column tie-bar (33).
8. structure as claimed in claim 1, it is characterised in that the steel pipe stem (29) sets post cage bar (32), post spiral bar
And steel pipe stem dowel (37) (36).
9. structure as claimed in claim 1, it is characterised in that the shaped steel stem (35) be provided with shaped steel, post cage bar (32),
Post spiral bar (36) and shaped steel stem stirrup (38).
10. a kind of construction method for combining strength stem, it is characterised in that comprise the following steps:
Step 1: build-in steel pipe (6), steel pipe column locating support (10), steel pipe column (12) column jecket, steel pipe stem (29), shaped steel core
Post (35) and connection fin (30) processing:Build-in steel pipe (6) uses the steel pipe manufacturings of φ 300, two ends welding steel, middle weld stud
Follow closely (5);Steel pipe column locating support (10), using the steel pipe manufacturings of φ 80, the adjustable positioning support (18) of lower weld, adjustable positioning
Support (18) lower weld jacking junction steel plate (19), steel pipe column locating support (10) upper weld monoblock type junction steel plate (15),
Set support to fix in the middle part of steel pipe column locating support (10) and sealing steel loop is welded on ring flat-plate (16), steel pipe column locating support (10)
(8);The making of steel pipe column (12) column jecket, the method welded using Lincoln weld of plate rolling tube;Steel pipe stem (29) is used
Steel plate, which is rolled, to be welded;Shaped steel stem (35) uses segmental machining, is its floor height per segment length, is welded into " the double H of right-angled intersection
Type " section Steel Column;
Step 2: pile foundation construction:The pre-buried build-in steel pipe (6) in pile foundation (1) steel reinforcement cage installation process, build-in steel pipe (6) bottom
Steel plate is welded with steel reinforcement cage reinforcement (2);The peg (5) of build-in steel pipe (6) is welded with pile foundation cage bar (4);Pile foundation
(1) top cuts build-in steel pipe (6) the installation PVC disrance sleeves (20) of position;Then pile foundation filling concrete is carried out;
Step 3: steel pipe column locating support (10) is installed and cushion cap (9) construction:Pile foundation (1) top carries out pile crown and cut, Ran Houshi
Welded with steel pipe column locating support (10) bottom by jacking junction steel plate (19) on work bed course (7), build-in steel pipe (6) top
Install, then carry out reinforcing bar colligation, model sheetinstallat and concreting;
Step 4: the installation of steel pipe column (12):First section steel pipe column (12) is positioned by positioning bloom (14), steel pipe column (12)
Ring flat-plate (11) and monoblock type junction steel plate (15) are connected by bolt (13) joint steel pipe post, and ring flat-plate (11) is connected to steel pipe column
Welded with monoblock type junction steel plate (15);Determined between steel pipe column (12) by internal lining pipe (21) and locator card (24)
Position, is attached, and steel pipe column (12) and arc backplate (25) link position are entered by bolt (23) and arc backplate (25)
Row welding;
Step 5: steel pipe column (12) and steel pipe core connection:Steel pipe column (12) and steel pipe stem (29) are carried out with connection fin (30)
Connection;Steel pipe column (12) is in termination along slot at axis cutting 4, and the top of steel pipe column (12) is located on flooring 1 meter, will connect wing
In piece (30) insertion steel pipe column (12) slot, steel pipe column (12) slot is then carried out with being connected fin (30) full weld to this section of post
Reinforcing bar colligation, punching block are installed and concreting;
Step 6: at levels beam-column node steel pipe stem (29) connection:Reinforcing bar fixing steel plate (42) passes through positioning screw
(41) positioned, beam main tendon (43) is attached by straight screw sleeve (39) with reinforcing bar fixing steel plate (42), reinforcing bar positioning
Steel plate (42) is welded and fixed with steel pipe stem (29) and tooth form backplate (40), then carries out reinforcing bar colligation, punching block to the section
Install and concreting, vibrated in concreting process by the hole of vibrating (45) on reinforcing bar fixing steel plate (42);
Step 7: the connection of steel pipe stem (29) and shaped steel stem (35):In the company of steel pipe stem (29) and shaped steel stem (35)
Place is met, in steel pipe stem (29) termination along slot at axis cutting 4, shaped steel is inserted and full with shape steel web toward slot during installation
Weldering, then carries out reinforcing bar colligation, punching block to the section and installs and concreting.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710190381.8A CN106968267B (en) | 2017-03-28 | 2017-03-28 | Combined stiffening core column and construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710190381.8A CN106968267B (en) | 2017-03-28 | 2017-03-28 | Combined stiffening core column and construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106968267A true CN106968267A (en) | 2017-07-21 |
CN106968267B CN106968267B (en) | 2023-04-28 |
Family
ID=59336929
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710190381.8A Active CN106968267B (en) | 2017-03-28 | 2017-03-28 | Combined stiffening core column and construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106968267B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109208823A (en) * | 2018-11-12 | 2019-01-15 | 安徽工程大学 | It is a kind of can quick assembling built-in steel-case formula steel core concrete column and its production technology |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20130076072A (en) * | 2011-12-28 | 2013-07-08 | 주식회사 포스코 | Steel socket and apparatus connecting steel pile steel column using the same |
CN103276899A (en) * | 2013-06-05 | 2013-09-04 | 中国建筑第八工程局有限公司 | Construction method of steel bars surrounding steel column base |
CN103967129A (en) * | 2014-05-23 | 2014-08-06 | 东北石油大学 | Combination column and combination beam frame with internally-arranged pipe high-strength concrete core columns and construction method thereof |
CN103967128A (en) * | 2014-05-23 | 2014-08-06 | 东北石油大学 | Combination column and combination beam frame with internally-arranged high-strength concrete core columns and construction method thereof |
CN205153131U (en) * | 2015-10-14 | 2016-04-13 | 中铁五局集团路桥工程有限责任公司 | Shaped steel concrete combination column structure at overhead station of urban rail transit |
CN206768843U (en) * | 2017-03-28 | 2017-12-19 | 深圳市福田建安建设集团有限公司 | One kind combination strength stem |
-
2017
- 2017-03-28 CN CN201710190381.8A patent/CN106968267B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20130076072A (en) * | 2011-12-28 | 2013-07-08 | 주식회사 포스코 | Steel socket and apparatus connecting steel pile steel column using the same |
CN103276899A (en) * | 2013-06-05 | 2013-09-04 | 中国建筑第八工程局有限公司 | Construction method of steel bars surrounding steel column base |
CN103967129A (en) * | 2014-05-23 | 2014-08-06 | 东北石油大学 | Combination column and combination beam frame with internally-arranged pipe high-strength concrete core columns and construction method thereof |
CN103967128A (en) * | 2014-05-23 | 2014-08-06 | 东北石油大学 | Combination column and combination beam frame with internally-arranged high-strength concrete core columns and construction method thereof |
CN205153131U (en) * | 2015-10-14 | 2016-04-13 | 中铁五局集团路桥工程有限责任公司 | Shaped steel concrete combination column structure at overhead station of urban rail transit |
CN206768843U (en) * | 2017-03-28 | 2017-12-19 | 深圳市福田建安建设集团有限公司 | One kind combination strength stem |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109208823A (en) * | 2018-11-12 | 2019-01-15 | 安徽工程大学 | It is a kind of can quick assembling built-in steel-case formula steel core concrete column and its production technology |
CN109208823B (en) * | 2018-11-12 | 2024-03-08 | 安徽工程大学 | Quick-assembly built-in steel box type concrete filled steel tube column and production process thereof |
Also Published As
Publication number | Publication date |
---|---|
CN106968267B (en) | 2023-04-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105625570B (en) | A kind of prefabricated beam column attachment means and preparation method thereof | |
CN106988483A (en) | A kind of assembled steel reinforced Concrete U Vierendeel girder and its construction method | |
CN104775516B (en) | Field connecting method among prefabricated reinforced concrete columns | |
WO2018214477A1 (en) | Prefabricated dual-steel-tube concrete shear wall, and assembly method therefor | |
CN205777098U (en) | A kind of detachable assembling type concrete-filled circular steel tube column | |
CN201339250Y (en) | Stiffness structure framework beam preformed steel reinforcement framework structure | |
CN107288218A (en) | A kind of assembled steel tendon concrete frame structure bean column node and preparation method thereof | |
CN109372129A (en) | The novel full assembly concrete frame joint of one kind and its construction method | |
CN105908864A (en) | Interface crack preventing structure for filling brickwork and framework shear wall and construction method | |
CN101936170A (en) | Cavern arch mould spraying concrete construction structure and process | |
CN107938837A (en) | A kind of steel core concrete column and beam main tendon connecting node and construction method | |
CN106320704A (en) | Steel reinforced concrete structure formwork sleeve threaded rod pulling construction method | |
CN208669320U (en) | The anti-horizontal ovalizing deflection shield tunnel ruggedized construction of pre-embedded steel slab | |
CN206917087U (en) | A kind of prefabricated assembling type reinforced concrete framework open tubular column and its making mould | |
CN107355008B (en) | Prefabricated connection structure and method for newly added concrete filled steel tubular column and existing structure | |
CN107366353B (en) | A kind of assembled steel reinforced concrete frame column with variable cross-sections and its construction method | |
CN206157913U (en) | Assembled square steel tube concrete post and girder steel connected node | |
CN106760502A (en) | Shear wall end cylinder construction method | |
CN102619286B (en) | Connecting joint of steel pipe concrete column and profile steel concrete beam | |
CN207685996U (en) | A kind of steel core concrete column and beam main tendon connecting node | |
CN206768843U (en) | One kind combination strength stem | |
CN206768852U (en) | Combine strength stem suspension column supporting construction | |
CN206844316U (en) | A kind of assembled steel reinforced concrete column with well and post splicing node | |
CN206752693U (en) | A kind of assembled steel reinforced concrete column of stirrup encryption and post splicing node | |
CN107217790A (en) | A kind of prefabricated assembling type reinforced concrete framework open tubular column and its construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |