CN106948608A - Super High curtain wall faces the security protection system and its construction method of empty construction - Google Patents

Super High curtain wall faces the security protection system and its construction method of empty construction Download PDF

Info

Publication number
CN106948608A
CN106948608A CN201710325714.3A CN201710325714A CN106948608A CN 106948608 A CN106948608 A CN 106948608A CN 201710325714 A CN201710325714 A CN 201710325714A CN 106948608 A CN106948608 A CN 106948608A
Authority
CN
China
Prior art keywords
steel wire
construction
wire rope
clasp
suspension member
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710325714.3A
Other languages
Chinese (zh)
Inventor
周予启
黄勇
任耀辉
贺茂军
刘芳
党毅章
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction First Group Corp Ltd
China Construction First Group Construction and Development Co Ltd
Original Assignee
China Construction First Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction First Group Corp Ltd filed Critical China Construction First Group Corp Ltd
Priority to CN201710325714.3A priority Critical patent/CN106948608A/en
Publication of CN106948608A publication Critical patent/CN106948608A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/32Safety or protective measures for persons during the construction of buildings
    • E04G21/3261Safety-nets; Safety mattresses; Arrangements on buildings for connecting safety-lines
    • E04G21/3276Arrangements on buildings for connecting safety-lines

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The present invention relates to the technical field of safety protection that curtain wall faces empty construction, security protection system and its construction method that a kind of Super High curtain wall faces empty construction are disclosed.The steel plate suspension member of the invention for including being fixed on structural column, level are located in the steel wire rope on steel plate suspension member and the safety rope with steel wire rope slidable connection;Steel plate suspension member includes the base for being fixed on structural column surface, the jump ring component being vertically arranged on base, jump ring component includes the big clasp of shape identical and small clasp, include U-loop and the fixing muscle being connected respectively with the two ends of U-loop, two fixing muscles are set along same rectilinear direction, and big clasp is arranged with small clasp horizontal alignment, is vertically arranged;Steel wire rope sequentially passes through the clasp on adjacent structure post, and safety rope is connected by buckle with steel cable sliding, and the sealing section outer sheath of buckle is provided with a sealing sleeve pipe, and the other end of safety rope and the safety belt of workmen are connected.Simple in construction, low cost of the invention, safety coefficient are high.

Description

Super High curtain wall faces the security protection system and its construction method of empty construction
Technical field
The present invention relates to the technical field of safety protection that curtain wall faces empty construction, more particularly to a kind of Super High curtain wall faces sky The security protection system and its construction method of construction.
Background technology
The installation of Super High curtain wall needs to lift by crane curtain wall plate, rotate and face can not in empty installation, whole work progress Peripheral hardware protective stent and construction platform are set, it is necessary to which workmen's whole process carries out facing empty construction, therefore must applied before construction Sufficient security protection work is carried out in work plane.The safety protection facility used is that construction site is hair in prevention construction Raw personnel casualty accidentses and set all kinds of facilities, equipment, utensil.The safety device of existing high-rise curtain wall is generally suspension peace Quan Sheng, protection method is more single, does not form perfect protection system, and safety coefficient is still weak.
The content of the invention
The safety that the high Super High curtain wall of a kind of simple in construction, low cost of present invention offer, safety coefficient faces empty construction is prevented Watch box system and its construction method.
The technical problem of solution is:Existing superaltitude faces air defence protection unit safety coefficient deficiency, constitutes complex, cost It is higher.
In order to solve the above technical problems, the present invention is adopted the following technical scheme that:
Super High curtain wall of the present invention faces the security protection system of empty construction, including be fixed on structural column steel plate suspension member, level The steel wire rope being located on steel plate suspension member and the safety rope with steel wire rope slidable connection;The steel plate suspension member includes being fixed on knot The base on structure post surface, the jump ring component being vertically arranged on base, the jump ring component include the big clasp of shape identical and Small clasp, the fixing muscle being connected including U-loop and respectively with the two ends of U-loop, two fixing muscles are set along same rectilinear direction Put, big clasp is arranged with small clasp horizontal alignment, is vertically arranged;The steel wire rope sequentially passes through the clasp on adjacent structure post, The safety rope is connected by buckle with steel cable sliding, and the sealing section outer sheath of the buckle is provided with a sealing sleeve pipe, safety The other end of rope and the safety belt of workmen are connected.
Super High curtain wall of the present invention faces the security protection system of empty construction, further, and the base is square plate, led to Cross and be bolted to structure outer surface of column, the thickness of the base is 3-6mm, and bolt is not less than M8, and the bolt is expanding screw Bolt or high-strength bolt.
Super High curtain wall of the present invention faces the security protection system of empty construction, further, and the U-loop is used with fixing muscle D16 plain bars are made into integration.
Super High curtain wall of the present invention faces the security protection system of empty construction, further, the big clasp and small clasp Level interval is no more than 50mm.
Super High curtain wall of the present invention faces the security protection system of empty construction, and further, the jump ring component both sides are fixed Muscle is weldingly fixed on base, and using single-sided welding, weld seam meets 10d.
Super High curtain wall of the present invention faces the security protection system of empty construction, further, the steel plate suspension member be arranged on away from At the 900-1000mm of construction layer ground.
Super High curtain wall of the present invention faces the security protection system of empty construction, further, the steel wire rope two ends difference Back bending after through clasp, fixed using wire clamp and steel wire rope;The quantity of the wire clamp is no less than 3, close to steel wire The wire clamp of rope fag end and the distance of cable wire end are not less than 0.14m.
Super High curtain wall of the present invention faces the security protection system of empty construction, further, and the quantity of the safety rope is 2 Root.
Super High curtain wall of the present invention faces the security protection system of empty construction, further, and the length of the sealing sleeve pipe is not Less than 30mm, it is made of PVC steel wire tubes.
Super High curtain wall of the present invention faces the construction method of the security protection system of empty construction, comprises the following steps:
Step 1: steel plate suspension member is processed:According to design requirement, the preprocessing of base and jump ring component, welding button are carried out in factory Ring assemblies and base, using single-sided welding, weld seam meets 10d, and the prepared screw-bolt hole on base;
Step 2: steel plate suspension member is installed:Unwrapping wire and positioning are carried out, the structural column table at distance construction layer ground 900-1000mm Face fixation steel plate suspension member, when structural column is concrete column or steel core concrete column, steel plate suspension member is consolidated using expansion bolt It is fixed;When structural column is steel column, steel plate suspension member is anchored using high-strength bolt;Ensure the steel plate suspension member on adjacent structural column Absolute altitude it is consistent;
Step 3: steel wire rope is installed:Steel wire rope is sequentially passed through into the jump ring component on adjacent structure post, the termination of steel wire rope is passed through Back bending after clasp, fixed using wire clamp and steel wire rope;Close to cable wire end wire clamp and cable wire end away from From not less than 0.14m;
Step 4: safety rope is hung:Safety rope one end is connected by buckle with steel cable sliding, and safety rope length is not more than structure Length of the post apart from floor edge;After buckle is latched on steel wire rope, casing pipe sleeve will be sealed on the outside of the sealing section of buckle;Then The safety rope other end and the safety belt of workmen are connected;
Step 5: the movement of safety rope:After the construction of certain span is completed, moving sealing sleeve pipe is removed buckle, moved To next construction span scope, be fixed, until steel wire rope coverage in construction complete, successively dismantle safety rope, Steel wire rope and steel plate suspension member.
Super High curtain wall of the present invention faces the security protection system of empty construction compared with prior art, with following beneficial effect Really:
The security protection system that Super High curtain wall of the present invention faces empty construction is simple in construction, and raw material is easy to get, and is easily installed dismounting, uses It is convenient, it is adaptable to which that different structural-system, the high-rise building curtain walls of different scales face sky security protection.
The present invention uses elongated steel wire rope, horizontal through the steel plate suspension member on adjacent structure post, by safety rope slidably On a steel cord, the stress system for form interaction, mutually restricting, the stability of overall mechanical model reaches optimization for connection, Safety and stability gets a promotion, once mounting formation steel wire rope it is in extensive range, workmen can construction area it is larger, The construction volume of safety devices is reduced, construction period is shortened, efficiency of construction is improved.
The present invention is set using dual safety rope and dual jump ring component, and has been arranged sealing on the outside of the sealing section of buckle Sleeve pipe, realizes the self-regulation of internal system, from buffering, improves the safety coefficient of protection system, it is effective reduce it is single The danger of safe fracture of rope.
The security protection system and its construction method work of empty construction are faced to the Super High curtain wall of the present invention below in conjunction with the accompanying drawings Further illustrate.
Brief description of the drawings
Fig. 1 is the structural representation for the security protection system that Super High curtain wall of the present invention faces empty construction;
Fig. 2 is the top view for the security protection system that Super High curtain wall of the present invention faces empty construction;
Fig. 3 is the side view of steel plate suspension member;
Fig. 4 is the front view of steel plate suspension member;
Fig. 5 is the attachment structure schematic diagram at steel wire rope end head;
Fig. 6 is the structural representation of buckle.
Reference:
1- structural columns;2- steel plate suspension members;21- bases;The big clasps of 22-;The small clasps of 23-;3- steel wire ropes;31- wire clamps;4- pacifies Quan Sheng;51-U shape rings;52- fixing muscles;6- buckles;61- seals sleeve pipe.
Embodiment
As shown in figs 1 to 6, Super High curtain wall of the present invention faces the security protection system of empty construction including being fixed on structural column 1 On steel plate suspension member 2, level be located in the steel wire rope 3 on steel plate suspension member 2 and the safety rope 4 with the slidable connection of steel wire rope 3;Such as Shown in Fig. 3, steel plate suspension member 2 includes the base 21 for being fixed on the surface of structural column 1, the jump ring component being vertically arranged on base 21, Base 21 is square plate, is bolted on the outer surface of structural column 1, and the thickness of base 21 is 3-6mm, and bolt is not less than M8, bolt is expansion bolt or high-strength bolt;As shown in figure 4, jump ring component includes the big clasp 22 of shape identical and small clasp 23, the fixing muscle 52 being connected including U-loop 51 and respectively with the two ends of U-loop 51, two fixing muscles 52 are along same straight line side To setting, U-loop 51 is made into integration with fixing muscle 52 using D16 plain bars, and big clasp 22 is arranged with the small horizontal alignment of clasp 23 Cloth, it is vertically arranged, the level interval of big clasp 22 and small clasp 23 is no more than 50mm, and both sides fixing muscle 52 is weldingly fixed on base On 21, using single-sided welding, weld seam meets 10d;Steel plate suspension member 2 is arranged at distance construction layer ground 900-1000mm;Such as Fig. 5 Shown, steel wire rope 3 sequentially passes through the clasp on adjacent structure post 1, and two ends are each passed through back bending after clasp, using wire clamp 31 fix with steel wire rope 3;The quantity of wire clamp 31 is no less than 3, close to the wire clamp 31 and steel wire rope of the fag end of steel wire rope 3 The distance of 3 fag ends is not less than 0.14m;The quantity of safety rope 4 is 2, is slidably connected respectively by buckle 6 with steel wire rope 3, is such as schemed Shown in 6, the sealing section outer sheath of buckle 6 is provided with a sealing sleeve pipe 61, and the length of sealing sleeve pipe 61 is not less than 30mm, using PVC Steel wire tube is made;The other end of safety rope 4 and the safety belt of workmen are connected;The length of safety rope 4 is not more than the distance of structural column 1 The length at floor edge.
Super High curtain wall of the present invention faces the construction method of the security protection system of empty construction, comprises the following steps:
Step 1: steel plate suspension member is processed:According to design requirement, the preprocessing of base 21 and jump ring component, welding are carried out in factory Jump ring component and base 21, using single-sided welding, weld seam meets 10d, and the prepared screw-bolt hole on base 21;
Step 2: steel plate suspension member is installed:Unwrapping wire and positioning are carried out, the structural column 1 at distance construction layer ground 900-1000mm Surface fixation steel plate suspension member 2, when structural column 1 is concrete column or steel core concrete column, steel plate suspension member 2 is entered using expansion bolt Row is fixed;When structural column 1 is steel column, steel plate suspension member 2 is anchored using high-strength bolt;Ensure on adjacent structural column 1 The absolute altitude of steel plate suspension member 2 is consistent;
Step 3: steel wire rope is installed:Steel wire rope 3 is sequentially passed through into the jump ring component on adjacent structure post 1, the termination of steel wire rope 3 Back bending after through clasp, fixed with steel wire rope 3 using wire clamp 31;Close to the wire clamp 31 and steel wire of the fag end of steel wire rope 3 Restrict 3 fag ends distance be not less than 0.14m;
Step 4: safety rope is hung:The one end of safety rope 4 is slidably connected by buckle 6 with steel wire rope 3, and the length of safety rope 4 is not more than Length of the structural column 1 apart from floor edge;After buckle 6 is latched on steel wire rope 3, sealing sleeve pipe 61 is enclosed within to the sealing of buckle 6 Section outside;Then the other end of safety rope 4 and the safety belt of workmen are connected;
Step 5: the movement of safety rope:After the construction of certain span is completed, moving sealing sleeve pipe 61 removes buckle 6, by it Next construction span scope is moved to, is fixed, until the construction in the coverage of steel wire rope 3 is completed, dismounting successively is pacified Full rope 4, steel wire rope 3 and steel plate suspension member 2.
Embodiment described above is only that the preferred embodiment of the present invention is described, not to the model of the present invention Enclose and be defined, on the premise of design spirit of the present invention is not departed from, technical side of the those of ordinary skill in the art to the present invention In various modifications and improvement that case is made, the protection domain that claims of the present invention determination all should be fallen into.

Claims (10)

1. Super High curtain wall faces the security protection system of empty construction, it is characterised in that:Including being fixed on structural column(1)On steel plate Suspension member(2), level be located in steel plate suspension member(2)On steel wire rope(3)With with steel wire rope(3)The safety rope of slidable connection(4); The steel plate suspension member(2)Including being fixed on structural column(1)The base on surface(21), be vertically arranged in base(21)On clasp group Part, the jump ring component includes the big clasp of shape identical(22)With small clasp(23), including U-loop(51)Respectively with U Shape ring(51)Two ends connection fixing muscle(52), two fixing muscles(52)Set along same rectilinear direction, big clasp(22)With Small clasp(23)Horizontal alignment is arranged, is vertically arranged;The steel wire rope(3)Sequentially pass through adjacent structure post(1)On clasp, institute State safety rope(4)Pass through buckle(6)With steel wire rope(3)It is slidably connected, the buckle(6)Sealing section outer sheath provided with one sealing Sleeve pipe(61), safety rope(4)The other end and workmen safety belt connect.
2. Super High curtain wall according to claim 1 faces the security protection system of empty construction, it is characterised in that:The base (21)For square plate, it is bolted on structural column(1)Outer surface;The base(21)Thickness be 3-6mm, bolt is not Less than M8, the bolt is expansion bolt or high-strength bolt.
3. Super High curtain wall according to claim 1 faces the security protection system of empty construction, it is characterised in that:The U-shaped Ring(51)With fixing muscle(52)It is made into integration using D16 plain bars.
4. Super High curtain wall according to claim 1 faces the security protection system of empty construction, it is characterised in that:The big button Ring(22)With small clasp(23)Level interval be no more than 50mm.
5. Super High curtain wall according to claim 1 faces the security protection system of empty construction, it is characterised in that:The clasp Component both sides fixing muscle(52)It is weldingly fixed on base(21)On, using single-sided welding, weld seam meets 10d.
6. Super High curtain wall according to claim 1 faces the security protection system of empty construction, it is characterised in that:The steel plate Suspension member(2)It is arranged at distance construction layer ground 900-1000mm.
7. Super High curtain wall according to claim 1 faces the security protection system of empty construction, it is characterised in that:The steel wire Rope(3)Two ends are each passed through back bending after clasp, using wire clamp(31)With steel wire rope(3)It is fixed;The wire clamp (31)Quantity be no less than 3, close to steel wire rope(3)The wire clamp of fag end(31)With steel wire rope(3)The distance of fag end is not small In 0.14m.
8. Super High curtain wall according to claim 1 faces the security protection system of empty construction, it is characterised in that:The safety Rope(4)Quantity be 2.
9. Super High curtain wall according to claim 1 faces the security protection system of empty construction, it is characterised in that:The sealing Sleeve pipe(61)Length be not less than 30mm, be made of PVC steel wire tubes.
10. the Super High curtain wall described in claim 1-9 any one faces the construction method of the security protection system of empty construction, its It is characterised by:Comprise the following steps:
Step 1: steel plate suspension member is processed:According to design requirement, base is carried out in factory(21)With the preprocessing of jump ring component, weldering Connect jump ring component and base(21), using single-sided welding, weld seam meets 10d, and in base(21)Upper prepared screw-bolt hole;
Step 2: steel plate suspension member is installed:Unwrapping wire and positioning are carried out, the structural column at distance construction layer ground 900-1000mm (1)Surface fixation steel plate suspension member(2), work as structural column(1)During for concrete column or steel core concrete column, steel plate suspension member(2)Use Expansion bolt is fixed;Work as structural column(1)During for steel column, steel plate suspension member(2)Anchored using high-strength bolt;Ensure adjacent Structural column(1)On steel plate suspension member(2)Absolute altitude it is consistent;
Step 3: steel wire rope is installed:By steel wire rope(3)Sequentially pass through adjacent structure post(1)On jump ring component, steel wire rope(3) Termination pass through clasp after back bending, using wire clamp(31)With steel wire rope(3)It is fixed;Close to steel wire rope(3)The steel wire of fag end Fixture(31)With steel wire rope(3)The distance of fag end is not less than 0.14m;
Step 4: safety rope is hung:Safety rope(4)One end passes through buckle(6)With steel wire rope(3)It is slidably connected, safety rope(4)It is long Degree is not more than structural column(1)Length apart from floor edge;Buckle(6)Latch in steel wire rope(3)After upper, sleeve pipe will be sealed(61) It is enclosed within buckle(6)Sealing section outside;Then by safety rope(4)The other end and the safety belt of workmen are connected;
Step 5: the movement of safety rope:After the construction of certain span is completed, moving sealing sleeve pipe(61), remove buckle(6), Next construction span scope is moved into, is fixed, until steel wire rope(3)Construction in coverage is completed, successively Dismantle safety rope(4), steel wire rope(3)With steel plate suspension member(2).
CN201710325714.3A 2017-05-10 2017-05-10 Super High curtain wall faces the security protection system and its construction method of empty construction Pending CN106948608A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710325714.3A CN106948608A (en) 2017-05-10 2017-05-10 Super High curtain wall faces the security protection system and its construction method of empty construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710325714.3A CN106948608A (en) 2017-05-10 2017-05-10 Super High curtain wall faces the security protection system and its construction method of empty construction

Publications (1)

Publication Number Publication Date
CN106948608A true CN106948608A (en) 2017-07-14

Family

ID=59479296

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710325714.3A Pending CN106948608A (en) 2017-05-10 2017-05-10 Super High curtain wall faces the security protection system and its construction method of empty construction

Country Status (1)

Country Link
CN (1) CN106948608A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108442719A (en) * 2018-03-23 2018-08-24 中铁上海工程局集团有限公司 A kind of Metro Deep Excavation construction safety belt hanging buckle system

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08257151A (en) * 1995-03-24 1996-10-08 Kanae Kogyo Kk Safety rope holder for working at high place
GB0524517D0 (en) * 2004-12-01 2006-01-11 Crawford Harry Improved attachment device
CN201073520Y (en) * 2007-07-05 2008-06-18 攀枝花新钢钒股份有限公司 Rack working safety belts
JP2009293185A (en) * 2008-06-02 2009-12-17 Kasetsu:Kk Attachment implement
FR2963244A1 (en) * 2010-07-29 2012-02-03 Yvan Buron Continuous cables anchoring device for continuous life-line, has mooring plates permitting to anchor continuous cables, where device permits to adapt cables to any angle and is supported on tress, metallic structure and building
CN204663022U (en) * 2015-04-22 2015-09-23 中国建筑第六工程局有限公司 A kind of constructor's safety guard when building outer protective frame body construction
CN205743039U (en) * 2016-05-26 2016-11-30 河南仕腾建筑有限公司 Novel environment friendly wallboard erecting device
CN205857775U (en) * 2016-07-19 2017-01-04 北京博大经开建设有限公司 Interim security lock arrangement
CN106390323A (en) * 2016-10-11 2017-02-15 岳胜利 Safety device for mounting air conditioner
CN205964742U (en) * 2016-07-08 2017-02-22 中建城市建设发展有限公司 Aerial -working safety takes fixing device
CN206888553U (en) * 2017-05-10 2018-01-16 中建一局集团建设发展有限公司 Super High curtain wall faces the security protection system of empty construction

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08257151A (en) * 1995-03-24 1996-10-08 Kanae Kogyo Kk Safety rope holder for working at high place
GB0524517D0 (en) * 2004-12-01 2006-01-11 Crawford Harry Improved attachment device
CN201073520Y (en) * 2007-07-05 2008-06-18 攀枝花新钢钒股份有限公司 Rack working safety belts
JP2009293185A (en) * 2008-06-02 2009-12-17 Kasetsu:Kk Attachment implement
FR2963244A1 (en) * 2010-07-29 2012-02-03 Yvan Buron Continuous cables anchoring device for continuous life-line, has mooring plates permitting to anchor continuous cables, where device permits to adapt cables to any angle and is supported on tress, metallic structure and building
CN204663022U (en) * 2015-04-22 2015-09-23 中国建筑第六工程局有限公司 A kind of constructor's safety guard when building outer protective frame body construction
CN205743039U (en) * 2016-05-26 2016-11-30 河南仕腾建筑有限公司 Novel environment friendly wallboard erecting device
CN205964742U (en) * 2016-07-08 2017-02-22 中建城市建设发展有限公司 Aerial -working safety takes fixing device
CN205857775U (en) * 2016-07-19 2017-01-04 北京博大经开建设有限公司 Interim security lock arrangement
CN106390323A (en) * 2016-10-11 2017-02-15 岳胜利 Safety device for mounting air conditioner
CN206888553U (en) * 2017-05-10 2018-01-16 中建一局集团建设发展有限公司 Super High curtain wall faces the security protection system of empty construction

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108442719A (en) * 2018-03-23 2018-08-24 中铁上海工程局集团有限公司 A kind of Metro Deep Excavation construction safety belt hanging buckle system

Similar Documents

Publication Publication Date Title
CN105443871B (en) A kind of new suspension and support and construction technology for the connection of horizontal multi-pipeline counterpart
CN206987412U (en) A kind of building curtain wall construction anti-fall device
CN109372243A (en) A kind of hanging basket system for the installation of steel construction metal Roof bottom plate
CN103669815A (en) Method for constructing hanging rope and pipe combined all-round scaffold construction platform and protective system
CN207079828U (en) A kind of oblique outer reverse erecting device of eaves panel of large cantilever
CN101775896A (en) Method for installing pipeline scaffold of steel roof equipment and rigid suspended scaffold
CN204899185U (en) Adhere to formula lift high altitude construction device
CN106948608A (en) Super High curtain wall faces the security protection system and its construction method of empty construction
CN206888553U (en) Super High curtain wall faces the security protection system of empty construction
CN204752026U (en) Tower crane escape way
RU2735137C1 (en) Device for preventing a person falling during ascent and descent (embodiments)
CN203684625U (en) Suspending cord pipe combined full scaffolding construction platform and protection system
CN105040965A (en) Attached type raising and falling overhead working device and construction method
CN108487621A (en) Assembled movement shield cage and its construction method
CN111851982A (en) Scaffold frame liftable prevents weighing down safety device
CN204024097U (en) Skin safety net bracing frame
CN207330285U (en) A kind of removable spider-man's lifting-point device
CN110778094A (en) High-altitude large-span dragline net operating platform and construction method
CN209670389U (en) A kind of safety device for Rock Crane Rail Support
CN210087221U (en) Lifting and translation construction hanging ladder outside floor window
CN112160582A (en) Assembling platform suitable for construction of spoke type cable membrane system
CN207063567U (en) A kind of seat-belt anchorage for standing-seam metal Roof
WO2020181615A1 (en) Connecting structure of attaching lifting scaffold safety protection net and connecting method
CN209397944U (en) A kind of safety belt suspension device of falling from high altitude when preventing construction
KR20110084609A (en) Connecting apparatus of vertical protection net for forconstruction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170714

RJ01 Rejection of invention patent application after publication