CN106940826A - Modularization power supply plan automatic generation method - Google Patents

Modularization power supply plan automatic generation method Download PDF

Info

Publication number
CN106940826A
CN106940826A CN201710107952.7A CN201710107952A CN106940826A CN 106940826 A CN106940826 A CN 106940826A CN 201710107952 A CN201710107952 A CN 201710107952A CN 106940826 A CN106940826 A CN 106940826A
Authority
CN
China
Prior art keywords
power supply
unit
power
type
parameter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710107952.7A
Other languages
Chinese (zh)
Other versions
CN106940826B (en
Inventor
杨勇
王卿
王谦
曹俊海
张诗尧
王坤泉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Handan Power Supply Co of State Grid Hebei Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Handan Power Supply Co of State Grid Hebei Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Handan Power Supply Co of State Grid Hebei Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201710107952.7A priority Critical patent/CN106940826B/en
Publication of CN106940826A publication Critical patent/CN106940826A/en
Application granted granted Critical
Publication of CN106940826B publication Critical patent/CN106940826B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • G06Q10/043Optimisation of two dimensional placement, e.g. cutting of clothes or wood
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Theoretical Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Marketing (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Public Health (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Water Supply & Treatment (AREA)
  • Development Economics (AREA)
  • Game Theory and Decision Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention discloses modularization power supply plan automatic generation method, belong to power distribution technical field.Step is:Integrated electrical network basic data storehouse, obtains power grid architecture figure and can open capacity, it is ensured that power supply point can use;Power supply plan is subjected to modularization subdivision and type set, parameter setting is carried out to the option in each type and is verified, formation system clicks parameter;By power grid architecture figure with the data importing program that can open capacity, coupled system clicks parameter, develops power supply plan and support drawing.Efficiency high of the present invention, makes specification, and scheme depth is strong, and interactive strong, more rapidly, easily finds that construction will problems faced, requirement of the satisfaction to the quick power transmission of client.

Description

Modularization power supply plan automatic generation method
Technical field
The present invention relates to modularization power supply plan automatic generation method, belong to power distribution technical field.
Background technology
Power supply plan refers to the supply of electric power specific implementation plan for meeting customer electricity demand, is that client is set by electrical engineering Meter, path planning and the foundation of construction, are to ensure client's power supply reliability, power supply quality and the important ring of economical operation Section, the establishment and examination & verification of power supply plan directly affect the quality and efficiency of the whole engineering of client.Conventional programming exists following Problem:
(One)Lack specification:The cannonical format that establishment power supply plan is not fixed at present, it is various due to being related to basic material content, Technical parameter 150 is multinomial, and content disunity is write every time, is lack of consistency and preciseness.
(Two)It is less efficient:Power supply plan authorized personnel needs to scene to be reconnoitred, the live basic condition of record, receipt Essential information is collected, arrange and analyzed behind position, power supply point, the technical standard of relevant parameter and management requirement etc. is examined Deng, after comprehensive various situations, then carry out programming, it is necessary to time it is longer, work out less efficient.
(Three)Scheme depth is inadequate:To the shadow such as cable and client's power receiving equipment in plant-grid connection unit in current power supply plan The key parameter for ringing power grid security is not clearly stated, and client's power receiving equipment side primary connection situation is not clearly stated.Make Obtain design link and lack data, check and accept link and lack foundation.
(Four)The requirement of the quick power transmission of client, while being also the demand of company's Stiffness agent:Accelerate client to be connect by electrical engineering Electric speed is one of important measure that company strengthens service-type firm's construction, and conventional programming pattern can not meet client increasingly The demand for services of growth, it is necessary to change original pattern, accelerates programming speed, Business Process System engineering is early designed, early construct, Early power transmission, shortens the cycle of surplus capacity, while company, which also increases, has sold electricity.
For further deployment in-depth serve the people behave, serve the people " last one kilometer " problem is solved with all strength and needs progress badly New power supply programming plan.
The content of the invention
The technical problem to be solved in the invention is to provide a kind of modularization power supply plan automatic generation method, to make confession Electric programming is unified and standard, and significantly shortens the programming time.
In order to solve the above technical problems, the technical solution adopted in the present invention is:
A kind of modularization power supply plan automatic generation method, comprises the following steps:
Step A, integrated electrical network basic data storehouse, obtain power grid architecture figure and can open capacity, it is ensured that power supply point can use;
Step B, by power supply plan carry out modularization subdivision, to after subdivision modules carry out type set, then to each Option in individual type carries out parameter setting, through verify it is qualified after, formation system clicks parameter;
Step C, by power grid architecture figure and it can open in the data importing program of capacity, coupled system clicks parameter, passes through drawing Editor module develops power supply plan and support drawing.
Technical solution of the present invention further improvement is that:Electrical network basic data storehouse in step A include power grid architecture figure, Power network can open capacity, built-in pipe road geographical map and GPS map.
Technical solution of the present invention further improvement is that:Realized in step B by input module and the type of input is selected Carry out parameter setting, input module include respectively with verification prompting module be connected plant-grid connection unit, by electrical engineering unit With metering electric charge unit, plant-grid connection unit includes several power supplys and refines unit, is included several distribution by electrical engineering unit Stand type units, metering electric charge unit includes several stoichiometric points and refines unit, each power supply refinement unit, power distribution station type Unit and stoichiometric point refinement unit correspond to a type option, verification prompting module and all power supply refinement units, distribution Stand type units and stoichiometric point refinement unit be all connected with.
Technical solution of the present invention further improvement is that:Plant-grid connection unit also includes refining unit with all power supplys The power supply drawing generation unit being all connected with, the distribution being all connected with all power distribution station type units is also included by electrical engineering unit Drawing creation unit, all power supply refinement units are connected by power supply drawing generation unit with verification prompting module, Suo Youpei Power station type units are connected by distribution drawing creation unit with verification prompting module.
Technical solution of the present invention further improvement is that:The system of plant-grid connection unit clicks type and included but is not limited to Power supply natures, wire leading method, line parameter circuit value;Type, which is clicked, by the system of electrical engineering unit includes but is not limited to distribution type, master Varying capacity, metrical information, cable trace;The system of metering electric charge unit clicks type and includes but is not limited to metering method, electricity price Classification, acquisition terminal type.
Technical solution of the present invention further improvement is that:Wire leading method is divided into cable according to metering device installation site and entered Line, overhead transmission line inlet wire, aerial cable mixing inlet wire, line parameter circuit value include voltage and wire diameter, power supply drawing generation unit For to ensure that arrester and isolated switchgear design and installation meet desired antenna pole plan;
Distribution type is divided into change on post, box change, power distribution station three types, distribution drawing creation unit according to engineering construction mode Become a system figure and built on stilts change platform plan to generate power distribution station primary system figure, case.
Technical solution of the present invention further improvement is that:Wire leading method also includes client and builds metering cabinet inlet wire, distribution Type also includes client's transformer, emitting underground transformer.
Technical solution of the present invention further improvement is that:Verification in step B refers to, to the key of influence power grid security The important parameter of equipment carries out requiring to limit to require in accordance with electrical safety codes, and key equipment includes pole line switch, become Depressor and switch cubicle, the important parameter limited is short circuit current level >=25kV;Pair can open capacity verifies, when applying to install Capacity is more than when can open capacity, and system can eject prompting;Automatic matching is carried out to relevant parameter in the selection of each parameter, is System can display parameters selection gist and parameter request.
Technical solution of the present invention further improvement is that:Step B is verified by verifying prompting module, is tested and is carried Module of waking up is included to influenceing the important parameter of the key equipment of power grid security require that the Technology of Key Equipments of restriction is limited Cover half block, Technology of Key Equipments limits module and refined with power supply drawing generation unit, distribution drawing creation unit, all stoichiometric points Unit is all connected with.
By adopting the above-described technical solution, the technological progress that the present invention is obtained is:
1st, all parameters are almost only needed to click, and system automatically generates power supply plan, coordinate Portable printer, and scene is directly answered in advance It is multiple, conservation schemes editor and time for replying.
2nd, network system figure is with software directly invokes network system figure, searches power supply point.Directly looked into by power supply point Capacity can be opened by looking for, it is ensured that power supply point can use.Accomplish once to reconnoitre, determine access system plan.
3rd, support drawing system is automatically generated, and using module drawing editing system, is selected by equipment, programming automatic generation Drawing, by taking power distribution station primary system figure as an example:Incoming line cabinet represents a module map, and PT cabinets represent module map etc., software Middle to have selected after high-voltage board, system just directly generates primary connection figure.
4th, power supply plan depth is improved, and current power supply plan basically reaches preliminary design requirement, facilitates Customer design and construction, really Power grid security is ensure that after protecting the high-quality high standard of customer engineering, access power network and strong.
5th, power supply plan establishment is unified and standard, and using power supply plan modular applications, power supply plan is worked out more Plus unified standard, while standard is also improved.Same scheme, 100 people's establishment results are the same, people's establishments 100 Individual different schemes, the form of scheme is also unified, not only ensure that the important element of scheme and requires not omit, while To design the reference provided, the speed of design is accelerated.
6th, the programming time significantly shortens, and achieves noticeable achievement, on the one hand by the parameter of Integrated Solution module, simplifies ginseng Number calculates the search procedure with related data, and on the other hand by system program direct organization, programming speed is substantially accelerated, Time for replying averagely shortens 2 days.
To relatively simple by electrical engineering, it is most fast in the case of, 500 kilovolt-amperes and following industry expand project can be from original 15 working days(30 working days of dual power supply)Organize to examine after being reduced to 2 working days, first day live drawing up a plan, receipt position Core scheme, can reply client in second day.
7th, practical application, user service perceptibility is obviously improved, and passes through the application of power supply plan modular applications, visitor Family feels that programming speed is substantially accelerated, and profound lesson has arrived the lifting that industry expands efficiency of service, has embodied convenience-for-people, profit The people, the service theory for the people.Group of China Mobile, Handan Jinyu Taihang building materials Co., Ltd and Handan are completed from the beginning of this year The power transmission in advance of the projects such as new city's water building materials Co., Ltd of Dancheng city, is praised by user, is added up power transmission 50 days in advance, is increased delivery Ten thousand kilowatt hour more than 1200.
8th, the program install convenient, simple to operate, and the requirement for expanding new model with industry mutually agrees with, and practical is strong.
9th, various situations are considered when program composition, and are provided simultaneously with upgrade function, can be good at adapting to various Management mode.
10th, the modularized program practical operation is simple, power supply plan establishment more unified standard, and supplier of electricity is formulated at scene Case, it is more convenient, meet Guo Wang companies and provincial company industry expands the requirement of new model, popularizing application prospect is very wide.
Brief description of the drawings
Fig. 1 is the structured flowchart of the present invention.
Embodiment
The present invention is described in further details with reference to embodiment:
As shown in figure 1, a kind of modularization power supply plan automatic generation method, comprises the following steps:
Step A, integrated electrical network basic data storehouse, obtain power grid architecture figure and can open capacity, it is ensured that power supply point can use;Step A In electrical network basic data storehouse include power grid architecture figure, power network and can open capacity, built-in pipe road geographical map and GPS map;
Step B, by power supply plan carry out modularization subdivision, to after subdivision modules carry out type set, then to each Option in individual type carries out parameter setting, through verify it is qualified after, formation system clicks parameter;Such as:Access system power supply makes Enter ray mode with overhead transmission line, wherein voltage is divided into:10 kilovolts, 35 kilovolts etc., wire diameter is divided into:35th, 70,120,240 etc..
Step C, by power grid architecture figure and it can open in the data importing program of capacity, coupled system clicks parameter, passes through Drawing editor module develops power supply plan and support drawing.
Realized in step B by input module and parameter setting is carried out to the type option of input, input module includes difference With verification prompting module be connected plant-grid connection unit, by electrical engineering unit and metering electric charge unit, plant-grid connection unit includes Several power supplys refine unit, are included several power distribution station type units by electrical engineering unit, and metering electric charge unit includes some Individual stoichiometric point refines unit, and each power supply refinement unit, power distribution station type units and stoichiometric point refinement unit correspond to one Type option, verification prompting module connects with all power supply refinement units, power distribution station type units and stoichiometric point refinement unit Connect.
Plant-grid connection unit also includes the power supply drawing generation unit being all connected with all power supplys refinement unit, by electrician Cheng Danyuan also includes the distribution drawing creation unit being all connected with all power distribution station type units, and all power supply refinement units are equal It is connected by power supply drawing generation unit with verification prompting module, all power distribution station type units pass through distribution drawing creation list Member is connected with verification prompting module.
The system of plant-grid connection unit clicks type and includes but is not limited to power supply natures, wire leading method, line parameter circuit value;By electricity The system of engineering unit clicks type and includes but is not limited to distribution type, main transformer capacity, metrical information, cable trace;Metering electricity The system of expense unit clicks type and includes but is not limited to metering method, electricity price classification, acquisition terminal type.
Wire leading method is divided into long cable section of ingoing line, overhead transmission line inlet wire, aerial cable according to metering device installation site and is mixed into Line, line parameter circuit value includes voltage and wire diameter, and power supply drawing generation unit is to ensure arrester and isolated switchgear Design and installation meets desired antenna pole plan;
Distribution type is divided into change on post, box change, power distribution station three types, distribution drawing creation unit according to engineering construction mode Become a system figure and built on stilts change platform plan to generate power distribution station primary system figure, case.
Wire leading method also includes client and builds metering cabinet inlet wire, and distribution type also includes client's transformer, emitting underground transformer.
Verification in step B refers to that one is that the important parameter for influenceing the key equipment of power grid security is defined, To be required in accordance with electrical safety codes, such as pole line switch, client's transformer and switch cubicle, the important parameter limited as Short circuit current level >=25kV;Two be that pair can open capacity to verify, when apply to install capacity be more than can open capacity when, system meeting Ejection is reminded;Three be to carry out automatic matching to relevant parameter, such as:Power supply point quantity and stoichiometric point quantity system automatic matching;Four It is to apply to install capacity to be contrasted with overhead transmission line line footpath, once line footpath is too small, system alert;Five be each parameter selection in, System can display parameters selection gist and parameter request.
Step B is verified by verifying prompting module, and testing prompting module is included to influence power grid security The important parameter of key equipment require that the Technology of Key Equipments of restriction limits module, and Technology of Key Equipments limits module and electricity Source drawing creation unit, distribution drawing creation unit, all stoichiometric points refinement unit are all connected with.
In practice of construction, requirement is added to specialties such as protection, scheduling, communications, is not distinctly claimed in scheme originally. It is live still to need to be recorded when copywriter reconnoitres at the scene in view of live actual, again in scheme behind receipt position Operated in organizational tool.In order to solve this problem, by the renewal of more than 30 software versions, by programming tool needle Flat-panel systems and live touch operation are optimized, one is the support that increase is touched, and two be to cancel drop-down menu, all fields All operated by clicking, three be to increase dialog box area and click frame area, has realized that scene is convenient and swift by optimization Directly go out scheme.
The input module of power supply plan is divided into plant-grid connection unit, by electrical engineering unit and metering electric charge unit three Point, related content is designed to totally two ten five modules, each module situation that may be present is counted, 105 is counted altogether Ten multiple parameters.By correlation module by program composition into field, relevant parameter is directly chosen when going out scheme, quick side Just.
By the renewal of more than 30 software versions, optimized for flat-panel systems and execute-in-place, realized and reconnoitred now Directly provide power supply plan in field.
(One)Integrated more electrical network basic datas.For example built-in pipe road geographical map and GPS map positioning, by power grid architecture, Geographical map, pipeline map and GPS unite, and further improve scheme efficiency.
(Two)Work out more multi-access systems and by electrical engineering unit.Consider more rich and changeful, such as:Considered by electrical engineering Situations such as Customer Substation, emitting underground transformer.Consider that client builds situation of metering cabinet etc. in access system.
(Three)Further strengthen linking up between power utility check, O&M and designing unit, perfect scheme relevant options and ginseng Number.
(Four)Further optimize program so that procedure operation more hommization.

Claims (9)

1. a kind of modularization power supply plan automatic generation method, it is characterised in that comprise the following steps:
Step A, integrated electrical network basic data storehouse, obtain power grid architecture figure and can open capacity, it is ensured that power supply point can use;
Step B, by power supply plan carry out modularization subdivision, to after subdivision modules carry out type set, then to each Option in individual type carries out parameter setting, through verify it is qualified after, formation system clicks parameter;
Step C, by power grid architecture figure and it can open in the data importing program of capacity, coupled system clicks parameter, passes through drawing Editor module develops power supply plan and support drawing.
2. modularization power supply plan automatic generation method according to claim 1, it is characterised in that:Power network in step A Basic database, which includes power grid architecture figure, power network, can open capacity, built-in pipe road geographical map and GPS map.
3. modularization power supply plan automatic generation method according to claim 2, it is characterised in that:By defeated in step B Enter module realization and parameter setting is carried out to the type option of input, input module includes the electricity being connected respectively with verification prompting module Source access unit, by electrical engineering unit and metering electric charge unit, plant-grid connection unit includes several power supplys and refines unit, by electricity Engineering unit includes several power distribution station type units, and metering electric charge unit includes several stoichiometric points and refines unit, each Power supply refinement unit, power distribution station type units and stoichiometric point refinement unit correspond to a type option, verification prompting module with All power supply refinement unit, power distribution station type units and stoichiometric point refinement units are all connected with.
4. modularization power supply plan automatic generation method according to claim 3, it is characterised in that:Plant-grid connection unit is also Including the power supply drawing generation unit being all connected with all power supply refinement units, also included matching somebody with somebody with all by electrical engineering unit The distribution drawing creation unit that power station type units are all connected with, all power supplys refinement units by power supply drawing generation unit with Prompting module connection is verified, all power distribution station type units are connected by distribution drawing creation unit with verification prompting module.
5. modularization power supply plan automatic generation method according to claim 4, it is characterised in that:Plant-grid connection unit System clicks type and includes but is not limited to power supply natures, wire leading method, line parameter circuit value;Type is clicked by the system of electrical engineering unit Including but not limited to distribution type, main transformer capacity, metrical information, cable trace;The system of metering electric charge unit clicks type bag Include but be not limited to metering method, electricity price classification, acquisition terminal type.
6. modularization power supply plan automatic generation method according to claim 5, it is characterised in that:Wire leading method is according to meter Amount device installation site is divided into long cable section of ingoing line, overhead transmission line inlet wire, aerial cable mixing inlet wire, and line parameter circuit value includes voltage and led Line line footpath, power supply drawing generation unit is to ensure that arrester and isolated switchgear design and installation meet desired antenna pole Plan;
Distribution type is divided into change on post, box change, power distribution station three types, distribution drawing creation unit according to engineering construction mode Become a system figure and built on stilts change platform plan to generate power distribution station primary system figure, case.
7. modularization power supply plan automatic generation method according to claim 6, it is characterised in that:Wire leading method also includes Client builds metering cabinet inlet wire, and distribution type also includes client's transformer, emitting underground transformer.
8. modularization power supply plan automatic generation method according to claim 7, it is characterised in that:Verification in step B Refer to, to influenceing the important parameter of key equipment of power grid security to carry out requiring to limit to require in accordance with electrical safety codes, close Button apparatus includes pole line switch, transformer and switch cubicle, and the important parameter limited is short circuit current level >=25kV;It is right Capacity can be opened to be verified, when applying to install capacity more than that can open capacity, system can eject prompting;Relevant parameter is carried out certainly Dynamic pairing is in the selection of each parameter, and system can display parameters selection gist and parameter request.
9. modularization power supply plan automatic generation method according to claim 8, it is characterised in that:Step B is by school Test what prompting module was verified, testing prompting module includes carrying out to the important parameter of the key equipment to influenceing power grid security It is required that the Technology of Key Equipments limited limits module, Technology of Key Equipments limits module with power supply drawing generation unit, with electrograph Paper generation unit, all stoichiometric points refinement unit are all connected with.
CN201710107952.7A 2017-02-27 2017-02-27 Automatic generation method of modular power supply scheme Active CN106940826B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710107952.7A CN106940826B (en) 2017-02-27 2017-02-27 Automatic generation method of modular power supply scheme

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710107952.7A CN106940826B (en) 2017-02-27 2017-02-27 Automatic generation method of modular power supply scheme

Publications (2)

Publication Number Publication Date
CN106940826A true CN106940826A (en) 2017-07-11
CN106940826B CN106940826B (en) 2020-10-09

Family

ID=59468979

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710107952.7A Active CN106940826B (en) 2017-02-27 2017-02-27 Automatic generation method of modular power supply scheme

Country Status (1)

Country Link
CN (1) CN106940826B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108182301A (en) * 2017-12-12 2018-06-19 中国空间技术研究院 A kind of cable system branching diagram production method based on topological diagram autoplacement
CN108629492A (en) * 2018-04-15 2018-10-09 广东电网有限责任公司 Method for replying medium-voltage business expansion power supply scheme on site
CN108665138A (en) * 2018-03-27 2018-10-16 国家电网公司 A kind of modularization power supply plan selection method
CN110532695A (en) * 2019-08-30 2019-12-03 浙江虎格电气有限公司 Electrical systematic drawing software layout method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20090021074A1 (en) * 2007-07-20 2009-01-22 Infineon Technologies Ag Power Supply Scheme for Reduced Power Compensation
CN101930563A (en) * 2010-07-23 2010-12-29 中国电力科学研究院 Block supply-based distribution network planning design method
CN102496068A (en) * 2011-12-04 2012-06-13 江苏省电力公司南京供电公司 Power supply scheme auxiliary generation method based on GIS (geographic information system)
CN104966245A (en) * 2015-06-30 2015-10-07 国网天津市电力公司 Visualized power supply scheme auxiliary compilation method based on power grid GIS (Gas Insulated Switchgear)
CN105373972A (en) * 2015-12-04 2016-03-02 福建亿榕信息技术有限公司 Low-voltage client power supply scheme generation method
CN105844418A (en) * 2016-03-28 2016-08-10 国家电网公司 Business expansion intelligent mobile terminal

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20090021074A1 (en) * 2007-07-20 2009-01-22 Infineon Technologies Ag Power Supply Scheme for Reduced Power Compensation
CN101930563A (en) * 2010-07-23 2010-12-29 中国电力科学研究院 Block supply-based distribution network planning design method
CN102496068A (en) * 2011-12-04 2012-06-13 江苏省电力公司南京供电公司 Power supply scheme auxiliary generation method based on GIS (geographic information system)
CN104966245A (en) * 2015-06-30 2015-10-07 国网天津市电力公司 Visualized power supply scheme auxiliary compilation method based on power grid GIS (Gas Insulated Switchgear)
CN105373972A (en) * 2015-12-04 2016-03-02 福建亿榕信息技术有限公司 Low-voltage client power supply scheme generation method
CN105844418A (en) * 2016-03-28 2016-08-10 国家电网公司 Business expansion intelligent mobile terminal

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
崔本祥等: "业扩报装供电方案编制业务知识(续完)", 《农村电工》 *
张毅: "电力图纸标准化管理系统的开发与应用", 《中国优秀硕士学位论文全文数据库 信息科技辑(月刊)》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108182301A (en) * 2017-12-12 2018-06-19 中国空间技术研究院 A kind of cable system branching diagram production method based on topological diagram autoplacement
CN108665138A (en) * 2018-03-27 2018-10-16 国家电网公司 A kind of modularization power supply plan selection method
CN108665138B (en) * 2018-03-27 2021-09-24 国家电网公司 Modular power supply scheme selection method
CN108629492A (en) * 2018-04-15 2018-10-09 广东电网有限责任公司 Method for replying medium-voltage business expansion power supply scheme on site
CN110532695A (en) * 2019-08-30 2019-12-03 浙江虎格电气有限公司 Electrical systematic drawing software layout method
CN110532695B (en) * 2019-08-30 2023-05-12 浙江虎格电气有限公司 Electrical system diagram software configuration method

Also Published As

Publication number Publication date
CN106940826B (en) 2020-10-09

Similar Documents

Publication Publication Date Title
Medjroubi et al. Open data in power grid modelling: new approaches towards transparent grid models
CN103744422B (en) A kind of to the protective relaying device automatic test approach based on IEC61850 standard
CN105335584B (en) Distribution network systems line chart generates optimization device and method
CN106940826A (en) Modularization power supply plan automatic generation method
CN103970887B (en) A kind of information flow display system and method based on GIS power distribution network figures
CN108256745A (en) A kind of metering design Life cycle managing and control system
US20020042696A1 (en) Utility station automated design system and method
Reed et al. Sample survey of smart grid approaches and technology gap analysis
CN105356620B (en) Electric energy quality monitoring system
CN102957205A (en) Method and system for establishing distribution network model
CN109377180A (en) A kind of electric system industry expansion procedure information managing and control system
CN106940827A (en) Modularization power supply plan automatic generation method based on AR technologies and VR technologies
CN104698374A (en) Method for improving testing efficiency and accuracy of automatic relay protecting tester
Antić et al. Modeling and open source implementation of balanced and unbalanced harmonic analysis in radial distribution networks
CN104036074B (en) Low voltage discrimination method for distribution substation regions
Kilter et al. Guidelines for Power quality monitoring-Results from CIGRE/CIRED JWG C4. 112
CN104346756A (en) Method and system for constructing power grid planning platform
CN112288171A (en) Data processing method, device and system
Hafez Time of use prices considering smart meters and their future implementation in Saudi Arabia smart grid
CN206991367U (en) Modularization power supply plan automatic creation system
CN110601240B (en) Intelligent management and control method for power grid charging pile access
CN113407172A (en) Distribution cloud master station-based automatic platform area graph display system and method
Ma et al. Extended common information model for distribution network production repair platform
Xygkis et al. Optimizing D-PMU deployment for distribution system state estimation
CN108665138B (en) Modular power supply scheme selection method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant