CN106939556B - A kind of arch bridge cable-hoisting construction stayed knotting method knotted rope tensioning equipment - Google Patents

A kind of arch bridge cable-hoisting construction stayed knotting method knotted rope tensioning equipment Download PDF

Info

Publication number
CN106939556B
CN106939556B CN201710311224.8A CN201710311224A CN106939556B CN 106939556 B CN106939556 B CN 106939556B CN 201710311224 A CN201710311224 A CN 201710311224A CN 106939556 B CN106939556 B CN 106939556B
Authority
CN
China
Prior art keywords
cable anchoring
anchorage
cable
cabin
anchorage cable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710311224.8A
Other languages
Chinese (zh)
Other versions
CN106939556A (en
Inventor
王涛
韦瑾
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou University
Original Assignee
Guizhou University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou University filed Critical Guizhou University
Priority to CN201710311224.8A priority Critical patent/CN106939556B/en
Publication of CN106939556A publication Critical patent/CN106939556A/en
Application granted granted Critical
Publication of CN106939556B publication Critical patent/CN106939556B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/16Suspension cables; Cable clamps for suspension cables ; Pre- or post-stressed cables

Abstract

The invention discloses a kind of arch bridge cable-hoisting construction stayed knotting method knotted rope tensioning equipments, including anchorage cable anchoring part, telescopic section, fixing cable anchoring part, external hydraulic part, the anchorage cable anchoring part is connect with screw thread with telescopic section by anchorage cable anchoring cabin, and telescopic section is connect with screw thread with fixing cable anchoring part by fixing cable anchoring cabin connecting pin;External hydraulic part is connect with screw thread with telescopic section by oil inlet pipe, it can spin during to overcome existing arch bridge cable-hoisting construction stayed-buckle cable tensioning adjustment device use, and connected out in cable wire and be easy to happen slip rope, sliding rack slides more difficult problem in larger pulling force effect.

Description

A kind of arch bridge cable-hoisting construction stayed knotting method knotted rope tensioning equipment
Technical field
The present invention relates to a kind of arch bridge cable-hoisting construction stayed-buckle cable tensioning to adjust device, belongs to equipment for bridge construction.
Background technique
The cable-hoisting construction stayed knotting method of arch bridge is one of main construction method of arch bridge, and according to statistics, China is existing Construction of Arch Bridges in, about 70% arch bridge uses cable-hoisting construction, work progress be it is first that arch ring fragment is prefabricated, using cable The lifting of rope loop wheel machine is in place, carries out interim button by stayed-buckle cable and hangs, until arch rib joins the two sections of a bridge, etc to forming a kind of Arch Bridge Construction side of arch ring Method.Arch rib is carried out during interim button hangs using stayed-buckle cable, the rope force value of a knotted rope when installing different arch sections all Difference, so needing to be adjusted the Suo Li of knotted rope, the method for traditional Stayed-buckle Cable Forcess adjustment is by knotted rope anchor cable end The adjustment that jack top pulling buckle rope realizes Suo Li is set, cumbersome is adjusted.
Application No. is 201720280148.4 and 201010172183.9 patents can spin during use, and It is connected out in cable wire and is easy to happen slip rope, sliding rack slides more difficult in larger pulling force effect.
Summary of the invention
In order to solve the problem in the prior art, the present invention provides a kind of arch bridge cable-hoisting construction oblique pull buttons Cable stretching adjusts device, to overcome existing arch bridge cable-hoisting construction stayed-buckle cable tensioning adjustment device use during can send out Life is spinned, and is easy to happen slip rope in cable wire junction, and sliding rack slides more difficult problem in larger pulling force effect.
The technical solution of the present invention is as follows: a kind of arch bridge cable-hoisting construction stayed knotting method knotted rope tensioning equipment, including anchor Rope anchorage part, telescopic section, fixing cable anchoring part, external hydraulic part, it is characterised in that: the anchorage cable anchoring part is logical It crosses anchorage cable anchoring cabin to connect with screw thread with telescopic section, telescopic section is by fixing cable anchoring cabin connecting pin with screw thread and fixing cable anchoring Part connects;External hydraulic part is connect with screw thread with telescopic section by oil inlet pipe.
The anchorage cable anchoring part includes anchor cable, anchor cable scattered rope, anchorage cable anchoring cabin, ball bearing, anchorage cable anchoring steel tank With anchorage cable anchoring steel ingot, the anchor cable scatters steel wire to form the scattered rope of anchor cable in its end, and the rear end aperture of anchorage cable anchoring cabin dissipates Rope passes through anchorage cable anchoring cabin, ball bearing, and anchorage cable anchoring steel tank reaches outsourcing anchorage cable anchoring steel ingot after anchorage cable anchoring steel ingot, and It carries out embroidering fixation in anchorage cable anchoring steel ingot rear end, ball bearing is mounted on the bottom end in anchorage cable anchoring cabin, and at anchoring bilge end Ball orbit is constructed, the fixed steel tank of anchor cable is mounted in anchorage cable anchoring cabin, extends part in its lower end and form steel ring, anchor cable Gu top inner side setting screw thread in cabin is connected with anchorage cable anchoring cabin connecting pin.
The telescopic section includes that anchorage cable anchoring cabin connecting pin, hydraulic oil cargo tank, hydraulic stem are connected with fixing cable anchoring cabin End, the anchorage cable anchoring cabin connecting pin are welded on hydraulic oil cargo tank bottom end, and hydraulic stem is mounted in hydraulic cylinder, fixing cable anchoring Cabin connecting pin is welded on hydraulic stem top, and screw thread is arranged on the outside of anchorage cable anchoring cabin connecting pin and fixing cable anchoring cabin connecting pin.
The external hydraulic part includes oil inlet pipe, mechanical valve, connects sleeve, petroleum pipeline and hydraulic device, described Oil inlet pipe is connected by the hydraulic cargo tank of screw thread and telescopic section, and mechanical valve is mounted in the middle part of oil inlet pipe, and connection sleeve is welded on Screw thread is arranged on the inside of female connector cylinder in oil inlet pipe lower end, and screw thread is arranged in petroleum pipeline apical lateral, with connect sleeve and be connected, petroleum pipeline End connects hydraulic device.
Compared with prior art, the present invention using the hydraulic cargo tank of cylinder type steel replace it is primary it is bright in fixed chute pedestal, Using hydraulic stem replace it is primary it is bright in sliding tensioning rack gear, adapt to cable wire by the way that ball bearing is arranged in cable wire anchored end Rotation during drawing solves the problems, such as that the prior art exists in the application, and it is opposite with it is primary it is bright for, whole device can Higher by property, safety is more preferable.
Instead of traditional knotted rope stretching mode, interim structure is reduced, saves construction cost, is stretched using hydraulic stem realization Contracting, adjustment process is more reliable and secure, and operating process is easy, and can reuse.Whole device structure is simple, is easy real Existing, market prospects are good, and application space is big.
Detailed description of the invention
Fig. 1 is the device of the invention structural block diagram;
In figure: 1-1, anchor cable, 1-2, anchor cable dissipate rope, 1-3, anchorage cable anchoring cabin, 1-4, ball bearing, 1-5, anchorage cable anchoring steel Slot, 1-6, anchorage cable anchoring steel ingot, 2-1, anchorage cable anchoring cabin connecting pin, 2-2, hydraulic cargo tank, 2-3, hydraulic stem, 2-4, fixing cable anchoring Cabin connecting pin, 3-1, knotted rope, 3-2, knotted rope dissipate rope, 3-3, fixing cable anchoring cabin, 3-4, fixing cable anchoring steel tank, 3-5, fixing cable anchoring steel Slot, 3-6, fixing cable anchoring steel ingot, 4-1, oil inlet pipe, 4-2, mechanical valve, 4-3, connection sleeve, 4-4, petroleum pipeline, 4-5, hydraulic dress It sets.
Specific embodiment
The preferred embodiment that the invention will now be described in detail with reference to the accompanying drawings.
Such as Fig. 1, a kind of arch bridge cable-hoisting construction stayed knotting method knotted rope tensioning equipment, structure composition and connection are as follows: 1- anchorage cable anchoring part, 2- telescopic section, 3- fixing cable anchoring part, the external hydraulic part of 4-.
Each section detail structure.
(1) anchorage cable anchoring part.Its construction includes: 1-1 anchor cable, and 1-2 anchor cable dissipates rope, 1-3 anchorage cable anchoring cabin, 1-4 ball Bearing, 1-5 anchorage cable anchoring steel tank, 1-6 anchorage cable anchoring steel ingot.
(2) telescopic section.Its construction includes: 2-1 anchorage cable anchoring cabin connecting pin.The hydraulic cargo tank of 2-2,2-3 hydraulic stem, 2-4 Fixing cable anchoring cabin connecting pin.
(3) fixing cable anchoring part.3-1 knotted rope, 3-2 knotted rope dissipate rope 3-3 fixing cable anchoring cabin, 3-4 fixing cable anchoring steel tank, 3-5 Fixing cable anchoring steel tank, 3-6 fixing cable anchoring steel ingot.
(4) external hydraulic part.4-1 oil inlet pipe, 4-2 mechanical valve, 4-3 connection sleeve, 4-4 petroleum pipeline, the hydraulic dress of 4-5 It sets.
Each section connection
Main connection: anchorage cable anchoring part 1 connects 2-1 using by way of being threadedly coupled and pars contractilis anchorage cable anchoring cabin Divide 2 connections, telescopic section 2 is fixing cable anchoring cabin connecting pin 2-4 using by way of being threadedly coupled and fixing cable anchoring part 3 company It connects, external hydraulic part 4 is connect using by way of being threadedly coupled with telescopic section 2 oil inlet pipe 4-1.
(1) thin portion connects
Anchorage cable anchoring part.Anchor cable 1-1 scatters steel wire to form the scattered rope 1-2 of anchor cable in its end, after the 1-3 of anchorage cable anchoring cabin Aperture is held, rope 1-2 is dissipated and passes through anchorage cable anchoring cabin 1-3, ball bearing 1-4, anchorage cable anchoring steel tank 1-5 reaches anchorage cable anchoring steel ingot Outsourcing anchorage cable anchoring steel ingot 1-6 after 1-6, and carry out embroidering fixation, ball bearing 1-4 installation in the rear end anchorage cable anchoring steel ingot 1-6 Ball is facilitated to roll in the bottom end of anchorage cable anchoring cabin 1-3, and in anchoring bilge end construction ball orbit, the fixed steel tank 1-5 of anchor cable Be mounted in the 1-3 of anchorage cable anchoring cabin, its lower end extend part formed steel ring, with ball bearing 1-4 butt junction location, work as anchor When rope is by pulling force, anchorage cable anchoring steel ingot 1-6 will be driven stuck in anchorage cable anchoring steel tank 1-5 downwards, band dynamic search anchors steel tank 1-5 Move at ball bearing 1-4 stop, anchorage cable anchoring cabin 1-3 top inner side be arranged screw thread, with anchorage cable anchoring cabin connecting pin 2-1 It is connected.
Telescopic section.Anchorage cable anchoring cabin connecting pin 2-1 is welded on the bottom end hydraulic oil cargo tank 2-2, and hydraulic stem 2-3 is mounted on liquid In pressure oil steel, fixing cable anchoring cabin connecting pin is welded on the top hydraulic stem 2-3, anchorage cable anchoring cabin connecting pin 2-1 and fixing cable anchoring cabin Screw thread is set on the outside of the 2-4 of connecting pin.
The connection type of fixing cable anchoring part is identical as anchorage cable anchoring part.
External hydraulic part.Oil inlet pipe 4-1 is connected by the hydraulic cargo tank 2-2 of screw thread and telescopic section 2, mechanical valve 4-2 It is mounted in the middle part of oil inlet pipe 4-1, connection sleeve 4-3 is welded on the lower end oil inlet pipe 4-1, and screw thread, oil transportation is arranged on the inside of female connector cylinder 4-3 Screw thread is arranged in pipe 4-4 apical lateral, with connect sleeve 4-3 and is connected, the end petroleum pipeline 4-4 connection hydraulic device 4-5.
Its course of work are as follows:
When installing anchor cable and knotted rope, anchor cable top is truncated and carries out dissipating rope, passed through anchorage cable anchoring cabin after dissipating rope and lead to It crosses anchorage cable anchoring steel ingot and anchorage cable anchoring steel tank carries out embroidering binding, tense anchor cable anchorage cable anchoring steel ingot is stuck in anchorage cable anchoring Anchorage cable anchoring cabin is tightened on the connecting pin of anchorage cable anchoring cabin in steel tank, same process knotted rope is anchored after by knotted rope anchor Gu cabin is tightened on the connecting pin of fixing cable anchoring cabin, before being tensioned knotted rope, hydraulic stem is stretched to maximum shape by oil-filled in hydraulic compartment Then state is tightened hydraulic stem by hydraulic device when need to adjust knotted rope length in tensioning button anchor cable, thus will contracting The relative length of short knotted rope achievees the purpose that adjust Stayed-buckle Cable Forcess, after adjusting to designated position, closes oil inlet by mechanical valve Pipe realizes the opposite fixation for wiping length, is reconnecting hydraulic device when needing to adjust again.It should be noted that again When connecting hydraulic device, oil need to be first full of to petroleum pipeline, the work safety of hydraulic cargo tank influence hydraulic stem is entered to avoid air.
Working principle are as follows: the tune of Stayed-buckle Cable Forcess is realized by the relative distance shortened between knotted rope and the arch rib hung by button It is whole.The relative length of knotted rope is adjusted by the relative displacement of hydraulic stem and hydraulic cargo tank, by hydraulic device to hydraulic oil It carries out that oil or oil return is sent to realize the flexible of hydraulic stem in cabin.

Claims (3)

1. a kind of arch bridge cable-hoisting construction stayed knotting method knotted rope tensioning equipment, including anchorage cable anchoring part, telescopic section, button Rope anchorage part, external hydraulic part, it is characterised in that: the anchorage cable anchoring part by anchorage cable anchoring cabin with screw thread with stretch Contracting part connects, and telescopic section is connect with screw thread with fixing cable anchoring part by fixing cable anchoring cabin connecting pin;External hydraulic part It is connect with screw thread with telescopic section by oil inlet pipe;The telescopic section include anchorage cable anchoring cabin connecting pin, hydraulic oil cargo tank, Hydraulic stem and fixing cable anchoring cabin connecting pin, the anchorage cable anchoring cabin connecting pin are welded on hydraulic oil cargo tank bottom end, hydraulic stem peace In hydraulic oil steel, fixing cable anchoring cabin connecting pin is welded on hydraulic stem top, anchorage cable anchoring cabin connecting pin and fixing cable anchoring cabin Screw thread is set on the outside of connecting pin.
2. a kind of arch bridge cable-hoisting construction stayed knotting method knotted rope tensioning equipment according to claim 1, feature exist In: the anchorage cable anchoring part includes anchor cable, the scattered rope of anchor cable, anchorage cable anchoring cabin, ball bearing, anchorage cable anchoring steel tank and anchor cable Steel ingot is anchored, the anchor cable scatters steel wire to form the scattered rope of anchor cable, the rear end aperture of anchorage cable anchoring cabin in its end, and scattered rope passes through Anchorage cable anchoring cabin, ball bearing, anchorage cable anchoring steel tank reach outsourcing anchorage cable anchoring steel ingot after anchorage cable anchoring steel ingot, and in anchor cable Anchoring steel ingot rear end carries out embroidering fixation, and ball bearing is mounted on the bottom end in anchorage cable anchoring cabin, and in the construction rolling of anchoring bilge end Pearl track, the fixed steel tank of anchor cable are mounted in anchorage cable anchoring cabin, are extended part in its lower end and are formed steel ring, anchorage cable anchoring cabin top Setting screw thread in end inside is connected with anchorage cable anchoring cabin connecting pin.
3. a kind of arch bridge cable-hoisting construction stayed knotting method knotted rope tensioning equipment according to claim 1, feature exist In: the external hydraulic part includes oil inlet pipe, mechanical valve, connection sleeve, petroleum pipeline and hydraulic device, the oil inlet pipe It is connected by the hydraulic cargo tank of screw thread and telescopic section, mechanical valve is mounted in the middle part of oil inlet pipe, and connection sleeve is welded on oil inlet pipe Screw thread is arranged on the inside of female connector cylinder in lower end, and screw thread is arranged in petroleum pipeline apical lateral, with connect sleeve and is connected, oil transportation pipe end company Connect hydraulic device.
CN201710311224.8A 2017-05-05 2017-05-05 A kind of arch bridge cable-hoisting construction stayed knotting method knotted rope tensioning equipment Active CN106939556B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710311224.8A CN106939556B (en) 2017-05-05 2017-05-05 A kind of arch bridge cable-hoisting construction stayed knotting method knotted rope tensioning equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710311224.8A CN106939556B (en) 2017-05-05 2017-05-05 A kind of arch bridge cable-hoisting construction stayed knotting method knotted rope tensioning equipment

Publications (2)

Publication Number Publication Date
CN106939556A CN106939556A (en) 2017-07-11
CN106939556B true CN106939556B (en) 2019-01-18

Family

ID=59463937

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710311224.8A Active CN106939556B (en) 2017-05-05 2017-05-05 A kind of arch bridge cable-hoisting construction stayed knotting method knotted rope tensioning equipment

Country Status (1)

Country Link
CN (1) CN106939556B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110042767B (en) * 2019-05-30 2021-05-25 广西路桥工程集团有限公司 Cable buckling and anchoring method of cable hoisting system

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0220709A (en) * 1988-07-08 1990-01-24 Mitsubishi Heavy Ind Ltd Oblique hanging method for building arch bridge
CN201358439Y (en) * 2009-02-18 2009-12-09 路桥集团国际建设股份有限公司 Catwalk anchorage adjusting device
CN102704405A (en) * 2012-06-21 2012-10-03 中铁大桥局集团有限公司 Method utilizing buckle cable and anchor cable for balancing extra horizontal force
CN203782567U (en) * 2014-03-27 2014-08-20 中交一公局第一工程有限公司 Bearing cable anchor group device of large cable crane
CN104452595A (en) * 2014-11-12 2015-03-25 河海大学 Tensioning device for stay cable which is provided with single-lug or double-lug sleeve and can be adjusted in one direction or two directions and construction method of device
CN105421230A (en) * 2015-12-10 2016-03-23 中铁大桥局集团有限公司 Multi-directional adjusting type buckle beam and anchor beam device
CN205276134U (en) * 2015-12-30 2016-06-01 长安大学 Arched bridge cable hoist and mount construction method is with long adjusting device of cable
CN106544957A (en) * 2016-10-14 2017-03-29 中交公局第三工程有限公司 Length adjustment device, stiffening girder of suspension bridge mounting system and method

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN207244456U (en) * 2017-05-05 2018-04-17 贵州大学 A kind of arch bridge cable-hoisting construction stayed knotting method knotted rope tensioning equipment

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0220709A (en) * 1988-07-08 1990-01-24 Mitsubishi Heavy Ind Ltd Oblique hanging method for building arch bridge
CN201358439Y (en) * 2009-02-18 2009-12-09 路桥集团国际建设股份有限公司 Catwalk anchorage adjusting device
CN102704405A (en) * 2012-06-21 2012-10-03 中铁大桥局集团有限公司 Method utilizing buckle cable and anchor cable for balancing extra horizontal force
CN203782567U (en) * 2014-03-27 2014-08-20 中交一公局第一工程有限公司 Bearing cable anchor group device of large cable crane
CN104452595A (en) * 2014-11-12 2015-03-25 河海大学 Tensioning device for stay cable which is provided with single-lug or double-lug sleeve and can be adjusted in one direction or two directions and construction method of device
CN105421230A (en) * 2015-12-10 2016-03-23 中铁大桥局集团有限公司 Multi-directional adjusting type buckle beam and anchor beam device
CN205276134U (en) * 2015-12-30 2016-06-01 长安大学 Arched bridge cable hoist and mount construction method is with long adjusting device of cable
CN106544957A (en) * 2016-10-14 2017-03-29 中交公局第三工程有限公司 Length adjustment device, stiffening girder of suspension bridge mounting system and method

Also Published As

Publication number Publication date
CN106939556A (en) 2017-07-11

Similar Documents

Publication Publication Date Title
CN106939556B (en) A kind of arch bridge cable-hoisting construction stayed knotting method knotted rope tensioning equipment
CN106087770A (en) Hood type instrument derrick rig for steel pipe truss concrete arch-type bridge suspender replacement
CN101525108B (en) Method and device for reducing over-high deflection in amplitude changing process of caterpillar-band crane arm support
CN110186648B (en) Wave load self-propelled ship model test protection device and use method thereof
CN202338348U (en) Automatically-controllable mineral anchor cable releasing machine
CN207244456U (en) A kind of arch bridge cable-hoisting construction stayed knotting method knotted rope tensioning equipment
CN209760863U (en) External prestress steel strand connector and matched tensioning device
CN107110267A (en) Autonomous type hydraulic telescopic device
CN102359360B (en) Stepless speed regulation type oil pump
CN104609336B (en) One kind is inverted hydraulic pressure and may move lifting machine and its application method
CN207537885U (en) The anchoring mechanism in inclined guy cable stretching stage
CN106044579B (en) Cable machine walking dolly auxiliary traction carrying rope crosses river structure and method
CN201033858Y (en) Tower height-adjustable double-rope freight ropeway
CN203065086U (en) Winch pressurization system and rotary drilling machine
CN203411907U (en) Puller for cable releasing of suspension bridge
CN205319614U (en) Traditional thread binding putting of card of wire swift current race prevent during tension unwrapping wire
CN106812070B (en) A kind of arch bridge cable-hoisting construction stayed knotting method knotted rope tensioning equipment
CN207506870U (en) A kind of lower tensioning apparatus of steel wire rope drop preventer
CN106436587B (en) Loop chain type prestress rope automatic synchronization tensioning system and method
CN205839755U (en) A kind of piling facility
CN105293318B (en) A kind of crane super lifting device and application method
CN209497184U (en) Enlightening Nima rope high-altitude tightening device
CN110143525A (en) A kind of deck unit erection gantry for having wide-angle and swinging shifting and climbing capacity
CN208476686U (en) Puller system step-up system
CN2903565Y (en) Dragging fixing self locking device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant