CN106917414A CN201710046121.3A CN201710046121A CN106917414A CN 106917414 A CN106917414 A CN 106917414A CN 201710046121 A CN201710046121 A CN 201710046121A CN 106917414 A CN106917414 A CN 106917414A
Authority
CN
China
Prior art keywords
cabin
venting
combustion gas
rainwater storage
dust explosion
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710046121.3A
Other languages
Chinese (zh)
Other versions
CN106917414B (en
Inventor
丁勇
花嘉骏
龚燚
周凯笛
张昊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Ze Chu Technology Co Ltd
Original Assignee
Nanjing Ze Chu Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Ze Chu Technology Co Ltd filed Critical Nanjing Ze Chu Technology Co Ltd
Priority to CN201710046121.3A priority Critical patent/CN106917414B/en
Publication of CN106917414A publication Critical patent/CN106917414A/en
Application granted granted Critical
Publication of CN106917414B publication Critical patent/CN106917414B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/10Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/04Gullies inlets, road sinks, floor drains with or without odour seals or sediment traps
    • E03F5/06Gully gratings
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/10Collecting-tanks; Equalising-tanks for regulating the run-off; Laying-up basins
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/22Adaptations of pumping plants for lifting sewage

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Hydrology & Water Resources (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Health & Medical Sciences (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Oil, Petroleum & Natural Gas (AREA)
  • Chemical & Material Sciences (AREA)
  • Revetment (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The present invention is provided and a kind of carries out the pipe gallery of venting of dust explosion, including combustion gas pipe trench, rainwater storage cabin, gate, venting of dust explosion plate, water proof rubber circle, integrated pipe cabin, drainage ditch cover plate, aqueduct, suction pump, gutter by subsurface stormwater cabin of regulating and storing.The combustion gas pipe trench is placed in integrated pipe cabin;The rainwater storage cabin is adjacent with integrated pipe cabin or so, and adjacent side uniformly stays some openings along longitudinal direction;The venting of dust explosion plate is combined with the water proof rubber circle and seals opening;Each opening top sets the gate that can control lifting;The ground of the combustion gas pipe trench is provided with drainage ditch cover plate;The gutter is placed in rainwater storage cabin lower section, and is connected with suction pump with aqueduct.The blast pressure of combustion gas pipe trench can because in the destruction of venting of dust explosion plate and rainwater storage cabin rainwater buffering energy-absorbing strongly reduce.After blast terminates, general who has surrendered's Gas Pipe ditch separates with rainwater storage cabin under gate, the water in combustion gas pipe trench is entered into rainwater storage cabin by suction pump, to facilitate professional to carry out maintenance process.

Description

A kind of pipe gallery that venting of dust explosion is carried out by rainwater storage cabin
Technical field
The pipe gallery of venting of dust explosion is carried out by subsurface stormwater cabin of regulating and storing the present invention relates to a kind of.
Background technology
The pipelines such as electric power, information, feedwater, heating power are included mostly in domestic common pipe gallery at present, Gas Pipe is included The pipe gallery of line only has several places.Often due to worrying the fire safety evaluating problem of burning line design in the past in, will without consideration It includes pipe gallery, but burning line is the important component of urban infrastructure, is to ensure people's lives and city The facility that function runs well, is lifeline engineering.And installation of gas pipeline can improve the fortune of pipeline in pipe gallery Row environment, improves the Daily Round Check and Maintain level of pipeline.Therefore to include pipe gallery imperative for burning line, in order to solve combustion Gas pipeline enters some safety problems of corridor, is badly in need of a kind of new piping lane that can tackle blast.
The content of the invention
In view of existing piping lane does not include burning line, the present invention proposes one kind and can receive burning line and have certain The pipe gallery of explosion-proof capabilities.
The technical solution for realizing the object of the invention is:The pipe gallery of venting of dust explosion is carried out by subsurface stormwater cabin of regulating and storing, Including combustion gas pipe trench, rainwater storage cabin, gate, venting of dust explosion plate, water proof rubber circle, integrated pipe cabin, drainage ditch cover plate, aqueduct, take out Water pump, gutter.The combustion gas pipe trench is placed in integrated pipe cabin, and by prefabricated high strength anti-explosion armoured concrete slab bolt It is assembled;The rainwater storage cabin is adjacent with the integrated pipe cabin or so, and if uniformly being left along longitudinal direction in adjacent side Dry opening;The venting of dust explosion plate is combined and can sealed up opening with the water proof rubber circle;Each in close rainwater storage cabin is opened The top of mouth sets a gate that can control lifting;The combustion gas pipe trench ground is provided with drainage ditch cover plate;The gutter Rainwater storage cabin and integrated pipe cabin lower section are arranged at, have aqueduct and suction pump between the gutter and the rainwater storage cabin; Sealing is formed between the aqueduct and the rainwater storage cabin.
When burning line is leaked in combustion gas pipe trench, its combustable gas concentration reaches explosion limit and explodes, when When blast impulse wave pressure rises rapidly and reaches the maximum of venting of dust explosion plate and bear pressure, venting of dust explosion plate is destroyed, now combustion gas pipe trench Interior pressure can occur pressure release from destroyed open-mouth, so as to reduce brisance.If in addition, being stored in rainwater storage cabin rainy Water, after venting of dust explosion plate is destroyed, rainwater enters combustion gas pipe trench by open, and it has buffering energy-absorbing effect to explosion wave.By Above-mentioned reaction, the power for producing of exploding will be greatly reduced, and effectively reduce the damage of the building on integrated pipe cabin and ground Evil.When blast terminates, scene after calamity is processed for convenience, the water in combustion gas pipe trench need to be drained, under controlling the gate first Drop, opening is closed, and then controls suction pump to start to draw water, and water enters rainwater storage cabin by aqueduct.When in combustion gas pipe trench After water is drained, professional can carry out maintenance process into the scene of the accident.
Preferably, the area of section of the combustion gas pipe trench is smaller with integrated pipe cabin compared to rainwater storage cabin.
Preferably, the combustion gas pipe trench is assembled by prefabricated high strength anti-explosion armoured concrete slab.
Preferably, design grade control alluvial problem in the rainwater storage cabin.
Preferably, the venting of dust explosion plate uses lightweight fragile material, in block and powder when being destroyed by shock Last shape, is difficult to form secondary injury in pressure release.
Preferably, the water proof rubber circle is water swelling rubber ring, and every block of venting of dust explosion plate sets twice water proof rubber circle To meet waterproof requirement of the combustion gas pipe trench in rainwater storage cabin.
Preferably, in the rainwater storage cabin of the aqueduct has back bending.
Compared with prior art, its remarkable advantage is the present invention:(1)The unusual peace in view of burning line of traditional piping lane Without burning line included into piping lane, the present invention solves burning line and enters the safety of corridor and asks full sex chromosome mosaicism to a certain extent Topic.(2)Add the theory that rainwater storage cabin meets sponge city.(3)Combustion gas pipe trench area of section is smaller, if it is quick-fried that combustion gas occurs Fried, its blast magnitude also can be accordingly smaller(4)Venting of dust explosion plate is applied on combustion gas pipe trench, explosion time occurs will effectively be let out Pressure, reduces brisance.(5)Water in Adjusting rainwater cabin has energy-absorbing effect to blast, can effectively reduce brisance.(6) Combustion gas pipe trench is spliced by prefabricated high strength reinforced concrete plate with bolt, when gas pipeline need to repair replacing, can be straight Demolition diaphragm gas pipe trench is connect to be operated.(7)The application of gutter and suction pump effectively solves the place after the blast of combustion gas pipe trench Reason site problems.
Brief description of the drawings
Fig. 1 be the present invention it is a kind of by subsurface stormwater regulate and store cabin carry out venting of dust explosion pipe gallery sectional view
Fig. 2 be the present invention it is a kind of by subsurface stormwater regulate and store cabin carry out venting of dust explosion pipe gallery venting of dust explosion seal assembly detail drawing.
Specific embodiment
With reference to Fig. 1, Fig. 2, the present invention is a kind of to carry out the pipe gallery of venting of dust explosion, including Gas Pipe by subsurface stormwater cabin of regulating and storing Ditch 1, rainwater storage cabin 2, gate 3, venting of dust explosion plate 4, water proof rubber circle 5, integrated pipe cabin 6, drainage ditch cover plate 7, aqueduct 8, draw water Pump 9, gutter 10.The combustion gas pipe trench 1 is placed in integrated pipe cabin 6, and is used by prefabricated high strength anti-explosion armoured concrete slab Bolt is assembled;The rainwater storage cabin is adjacent with the integrated pipe cabin or so, and is uniformly stayed along longitudinal direction in adjacent side There are some openings;The venting of dust explosion plate 3 is combined and can sealed up opening with the water proof rubber circle 4;Near rainwater storage cabin 2 The top of each opening sets a gate 3 that can control lifting;The ground of combustion gas pipe trench 1 is provided with drainage ditch cover plate 7;Institute State gutter 10 and be arranged at rainwater storage cabin 2 and the lower section of integrated pipe cabin 6, led between the gutter 10 and the rainwater storage cabin Water pipe 8 and suction pump 9;Sealing is formed between the aqueduct 8 and the rainwater storage cabin 2.
When burning line is leaked in combustion gas pipe trench 1, its combustable gas concentration reaches explosion limit and explodes, when When blast impulse wave pressure rises rapidly and reaches the maximum of venting of dust explosion plate 4 and bear pressure, venting of dust explosion plate 4 is destroyed, now Gas Pipe Pressure in ditch 1 can occur pressure release from destroyed open-mouth, so as to reduce brisance.If in addition, being stored in rainwater storage cabin 2 Rain, after venting of dust explosion plate is destroyed, rainwater enters combustion gas pipe trench 1 by open, and it has buffering energy-absorbing effect to explosion wave. By above-mentioned reaction, the power for producing of exploding will be greatly reduced, and effectively reduce the building on integrated pipe cabin 6 and ground Infringement.When blast terminates, scene after calamity being processed for convenience, the water in combustion gas pipe trench 1 need to being drained, the lock is controlled first Door 3 declines, and opening is closed, and then controls suction pump 9 to start to draw water, and water enters rainwater storage cabin 2 by aqueduct 8.Work as combustion After the reclaimed water of tracheae ditch 1 is drained, professional can carry out maintenance process into the scene of the accident.
Preferably, the area of section of the combustion gas pipe trench is smaller with integrated pipe cabin compared to rainwater storage cabin.
Preferably, the combustion gas pipe trench 1 is assembled by prefabricated high strength anti-explosion armoured concrete slab.
Preferably, design grade control alluvial problem in the rainwater storage cabin 2.
Preferably, the venting of dust explosion plate 4 uses lightweight fragile material, in block and powder when being destroyed by shock Last shape, is difficult to form secondary injury in pressure release.
Preferably, the water proof rubber circle 5 is water swelling rubber ring, and every block of venting of dust explosion plate sets twice water proof rubber circle To meet the waterproof requirement of combustion gas pipe trench 1 and rainwater storage cabin 2.
Preferably, in the rainwater storage cabin 2 of the aqueduct 8 has back bending.
Embodiment
As shown in Figure 1-2, the present embodiment is proposed and a kind of carries out the pipe gallery of venting of dust explosion by subsurface stormwater cabin of regulating and storing.Such as In the subregion of every 200 meters one of pipe gallery, rainwater storage cabin 2 is 270cm × 270cm with the inner section in integrated pipe cabin 6, An opening is reserved every 2 meters along longitudinal direction on the side panel in two cabin, open size is 30.3cm × 30.3cm, and each is opened Mouth is sealed against with the venting of dust explosion plate 4 of every piece of about 30cm × 30cm with reference to twice water proof rubber circle 5.Corresponding each opening also sets A gate 3 is put, its size is 33cm × 33cm, under normal operating conditions, gate 3 is all the time in open surface.It is comprehensive With prefabricated high strength anti-explosion armoured concrete slab in pipe cabin 6(80cm×100cm×10cm)It is spliced into a combustion gas pipe trench 1 (Inner section size is 70cm × 80cm), twice drainage ditch cover plate is provided with combustion gas pipe trench 1.The inner section size of gutter 10 is 310cm × 30cm, an aqueduct 8 and suction pump 9 are set in the subregion in 200 meters along longitudinal direction every 20 meters.
When burning line is leaked in combustion gas pipe trench 1, its combustable gas concentration reaches explosion limit and explodes, when When blast impulse wave pressure rises rapidly and reaches the maximum of venting of dust explosion plate 4 and bear pressure, venting of dust explosion plate 4 is destroyed, now Gas Pipe Pressure in ditch 1 can occur pressure release from destroyed open-mouth, so as to reduce brisance.If in addition, being stored in rainwater storage cabin 2 Rain, after venting of dust explosion plate is destroyed, rainwater enters combustion gas pipe trench 1 by open, and it has buffering energy-absorbing effect to explosion wave. By above-mentioned reaction, the power for producing of exploding will be greatly reduced, and effectively reduce the building on integrated pipe cabin 6 and ground Infringement.When blast terminates, scene after calamity being processed for convenience, the water in combustion gas pipe trench 1 need to being drained, the lock is controlled first Door 3 declines, and opening is closed, and then controls suction pump 9 to start to draw water, and water enters rainwater storage cabin 2 by aqueduct 8.Work as combustion After the reclaimed water of tracheae ditch 1 is drained, professional can carry out maintenance process into the scene of the accident.
Piping lane in this example is compared traditional piping lane and is had the advantage that:(1)Traditional piping lane is unusual in view of burning line Safety issue without burning line included into piping lane, the present invention solves the safety that burning line enters corridor to a certain extent Problem.(2)Add the theory that rainwater storage cabin meets sponge city.(3)Combustion gas pipe trench area of section is smaller, if there is combustion gas Blast, its blast magnitude also can be accordingly smaller(4)Venting of dust explosion plate is applied on combustion gas pipe trench, explosion time occurs will effectively be let out Pressure, reduces brisance.(5)Water in Adjusting rainwater cabin has energy-absorbing effect to blast, can effectively reduce brisance.(6) Combustion gas pipe trench is spliced by prefabricated high strength reinforced concrete plate with bolt, when gas pipeline need to repair replacing, can be straight Demolition diaphragm gas pipe trench is connect to be operated.(7)The application of gutter and suction pump effectively solves the place after the blast of combustion gas pipe trench Reason site problems.
Preferred embodiment of the invention described in detail above.It should be appreciated that one of ordinary skill in the art without Need creative work just can make many modifications and variations with design of the invention.Therefore, all technologies in the art Personnel are available by logical analysis, reasoning, or a limited experiment on the basis of existing technology under this invention's idea Technical scheme, all should be in the protection domain being defined in the patent claims.

Claims (7)

1. it is a kind of that the pipe gallery of venting of dust explosion is carried out by subsurface stormwater cabin of regulating and storing, it is characterised in that including combustion gas pipe trench 1, rainwater Regulate and store cabin 2, gate 3, venting of dust explosion plate 4, water proof rubber circle 5, integrated pipe cabin 6, drainage ditch cover plate 7, aqueduct 8, suction pump 9, draining Ditch 10;The combustion gas pipe trench 1 is placed in integrated pipe cabin 6, and assembled with bolt by prefabricated high strength anti-explosion armoured concrete slab Form;The rainwater storage cabin is adjacent with the integrated pipe cabin or so, and uniformly leaves some opening along longitudinal direction in adjacent side Mouthful;The venting of dust explosion plate 3 is combined and can sealed up opening with the water proof rubber circle 4;In each opening near rainwater storage cabin 2 Top set one can control lift gate 3;The ground of combustion gas pipe trench 1 is provided with drainage ditch cover plate 7;The gutter 10 are arranged at the lower section of rainwater storage cabin 2 and integrated pipe cabin 6, have between the gutter 10 and the rainwater storage cabin aqueduct 8 and Suction pump 9;Sealing is formed between the aqueduct 8 and the rainwater storage cabin 2;When burning line is let out in combustion gas pipe trench 1 Leakage, its combustable gas concentration reaches explosion limit and explodes, when blast impulse wave pressure rises rapidly and reaches venting of dust explosion plate 4 Maximum when bearing pressure, venting of dust explosion plate 4 is destroyed, and now the pressure in combustion gas pipe trench 1 can be let out from destroyed open-mouth Pressure, so as to reduce brisance;If in addition, storing rain in rainwater storage cabin 2, after venting of dust explosion plate is destroyed, rainwater is by open Into combustion gas pipe trench 1, it has buffering energy-absorbing effect to explosion wave;By above-mentioned reaction, exploding the power for producing will significantly Reduce, effectively reduce the infringement of the building on integrated pipe cabin 6 and ground;When blast terminates, calamity is processed for convenience Scene, need to drain the water in combustion gas pipe trench 1 afterwards, control the gate 3 to decline first, and opening is closed, and then control is drawn water Pump 9 starts to draw water, and water enters rainwater storage cabin 2 by aqueduct 8;After the reclaimed water of combustion gas pipe trench 1 is drained, professional can enter The scene of the accident carries out maintenance process.
2. it is according to claim 1 that the pipe gallery of venting of dust explosion is carried out by subsurface stormwater cabin of regulating and storing, it is characterised in that described The area of section of combustion gas pipe trench 1 is smaller with integrated pipe cabin 6 compared to rainwater storage cabin 2.
3. it is according to claim 1 that the pipe gallery of venting of dust explosion is carried out by subsurface stormwater cabin of regulating and storing, the combustion gas pipe trench 1 by Prefabricated high strength anti-explosion armoured concrete slab is assembled.
4. it is according to claim 1 that the pipe gallery of venting of dust explosion is carried out by subsurface stormwater cabin of regulating and storing, it is characterised in that described Design grade control alluvial problem in rainwater storage cabin 2.
5. it is according to claim 1 that the pipe gallery of venting of dust explosion is carried out by subsurface stormwater cabin of regulating and storing, it is characterised in that described Venting of dust explosion plate 4 uses lightweight fragile material, in block and powdered when being destroyed by shock, shape is difficult in pressure release Into secondary injury.
6. it is according to claim 1 that the pipe gallery of venting of dust explosion is carried out by subsurface stormwater cabin of regulating and storing, it is characterised in that described Water proof rubber circle 5 is water swelling rubber ring, and every block of venting of dust explosion plate 4 twice water proof rubber circle 5 is set with meet combustion gas pipe trench 1 with The waterproof requirement in rainwater storage cabin 2.
7. it is according to claim 1 that the pipe gallery of venting of dust explosion is carried out by subsurface stormwater cabin of regulating and storing, it is characterised in that described One in the rainwater storage cabin 2 of aqueduct 8 has back bending.
CN201710046121.3A 2017-01-22 2017-01-22 Utility tunnel who explodes is let out through rainwater regulation cabin Active CN106917414B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710046121.3A CN106917414B (en) 2017-01-22 2017-01-22 Utility tunnel who explodes is let out through rainwater regulation cabin

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710046121.3A CN106917414B (en) 2017-01-22 2017-01-22 Utility tunnel who explodes is let out through rainwater regulation cabin

Publications (2)

Publication Number Publication Date
CN106917414A true CN106917414A (en) 2017-07-04
CN106917414B CN106917414B (en) 2021-01-01

Family

ID=59454087

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710046121.3A Active CN106917414B (en) 2017-01-22 2017-01-22 Utility tunnel who explodes is let out through rainwater regulation cabin

Country Status (1)

Country Link
CN (1) CN106917414B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107190774A (en) * 2017-07-13 2017-09-22 南京理工大学 A kind of explosion-proof pipe gallery
CN108385724A (en) * 2018-04-26 2018-08-10 厦门精图信息技术有限公司 A kind of pipe gallery safety management system
CN111608228A (en) * 2020-04-16 2020-09-01 中国一冶集团有限公司 Sponge city and utility tunnel integration system
CN113958738A (en) * 2021-10-13 2022-01-21 浙江省长三角城市基础设施科学研究院 Comprehensive pipe rack convenient for explosion venting of gas pipe and use method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09302689A (en) * 1996-05-14 1997-11-25 Ohbayashi Corp City structure
CN202969415U (en) * 2012-09-29 2013-06-05 何江 Multifunctional assembled comprehensive pipe gallery
JP2014005597A (en) * 2012-06-21 2014-01-16 Hinode Ltd Floatation prevention pile for underground structure and floatation prevention method for underground structure
CN105113543A (en) * 2015-09-22 2015-12-02 赵洪志 Assembled and combined cabin concrete structure of shallow-buried 0815-type underground comprehensive pipe gallery
CN105241414A (en) * 2015-10-21 2016-01-13 中国石油化工股份有限公司 Pipe gallery explosion venting interval measurement device and measurement method thereof
CN105696623A (en) * 2016-02-02 2016-06-22 上海市政工程设计研究总院(集团)有限公司 Externally-hung type underground comprehensive pipe rack
CN205687087U (en) * 2016-06-20 2016-11-16 四川汉华信和环保机械设备有限公司 A kind of pressure release cabin and conveyer device

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09302689A (en) * 1996-05-14 1997-11-25 Ohbayashi Corp City structure
JP2014005597A (en) * 2012-06-21 2014-01-16 Hinode Ltd Floatation prevention pile for underground structure and floatation prevention method for underground structure
CN202969415U (en) * 2012-09-29 2013-06-05 何江 Multifunctional assembled comprehensive pipe gallery
CN105113543A (en) * 2015-09-22 2015-12-02 赵洪志 Assembled and combined cabin concrete structure of shallow-buried 0815-type underground comprehensive pipe gallery
CN105241414A (en) * 2015-10-21 2016-01-13 中国石油化工股份有限公司 Pipe gallery explosion venting interval measurement device and measurement method thereof
CN105696623A (en) * 2016-02-02 2016-06-22 上海市政工程设计研究总院(集团)有限公司 Externally-hung type underground comprehensive pipe rack
CN205687087U (en) * 2016-06-20 2016-11-16 四川汉华信和环保机械设备有限公司 A kind of pressure release cabin and conveyer device

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
陆景慧等: "地下综合管廊设置燃气管舱的风险分析与应对 ", 《煤气与热力》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107190774A (en) * 2017-07-13 2017-09-22 南京理工大学 A kind of explosion-proof pipe gallery
CN108385724A (en) * 2018-04-26 2018-08-10 厦门精图信息技术有限公司 A kind of pipe gallery safety management system
CN108385724B (en) * 2018-04-26 2023-06-09 厦门精图信息技术有限公司 Comprehensive pipe rack safety management system
CN111608228A (en) * 2020-04-16 2020-09-01 中国一冶集团有限公司 Sponge city and utility tunnel integration system
CN113958738A (en) * 2021-10-13 2022-01-21 浙江省长三角城市基础设施科学研究院 Comprehensive pipe rack convenient for explosion venting of gas pipe and use method thereof
CN113958738B (en) * 2021-10-13 2023-10-24 广东恒益数智科技有限公司 Comprehensive pipe rack convenient for explosion venting of gas pipe and use method thereof

Also Published As

Publication number Publication date
CN106917414B (en) 2021-01-01

Similar Documents

Publication Publication Date Title
CN106917414A (en) A kind of pipe gallery that venting of dust explosion is carried out by rainwater storage cabin
KR101062932B1 (en) Easy Install Valve Room
CN107190774A (en) A kind of explosion-proof pipe gallery
CN108193707A (en) A kind of comprehensive pipe gallery structure
CN204456011U (en) Self-floating turns over gate baffle device for water
CN104790435A (en) Post-subsidence pouring belt advancing waterstop impermeable concrete structure and construction technology thereof
CN101906819A (en) Integrated prebuilt house
EA012289B1 (en) Shaft waterproof bulkhead
CN211524240U (en) Civil air defense engineering car ramp structure that peacetime and war combines
CN107100670A (en) A kind of built-in pump room structure of shield tunnel
CN208564632U (en) Tunnel gas library in mine
CN205445075U (en) Air -raid basement
CN205724711U (en) A kind of cable duct bank leakage proof water jacket dress
CN214464266U (en) Maintainable tunnel intelligent water-proof and drainage system
CN115012451A (en) Underground structure induced joint
CN106522266A (en) Light high-strength anti-seepage anti-seismic pipe gallery and construction method
CN211596835U (en) Comprehensive prefabricated pipe gallery with antiknock function
CN212179152U (en) Explosion venting and ventilation combined action system for underground combustion equipment machine room
CN102808652A (en) Inherent karst tunnel drainage outburst prevention and hydrogeological environment protection method
CN206070568U (en) Precast concrete pipe gallery interface sealing structure
CN207111174U (en) A kind of built-in pump room structure of shield tunnel
CN107524247A (en) A kind of wall body structure for being provided with plastic conduit
CN206267173U (en) A kind of high-strength light antiseepage antidetonation piping lane
CN206784434U (en) A kind of basement waterproofing drainage structure
CN202181921U (en) Full-automatic disaster anti-blocking device of mine gate way

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant