CN106884443A - The construction method for grouting reinforcement that foundation bottom is come to nothing - Google Patents

The construction method for grouting reinforcement that foundation bottom is come to nothing Download PDF

Info

Publication number
CN106884443A
CN106884443A CN201710143253.8A CN201710143253A CN106884443A CN 106884443 A CN106884443 A CN 106884443A CN 201710143253 A CN201710143253 A CN 201710143253A CN 106884443 A CN106884443 A CN 106884443A
Authority
CN
China
Prior art keywords
grouting
slip casting
basis
construction
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710143253.8A
Other languages
Chinese (zh)
Other versions
CN106884443B (en
Inventor
王代发
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 22MCC Group Corp Ltd
Original Assignee
China 22MCC Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 22MCC Group Corp Ltd filed Critical China 22MCC Group Corp Ltd
Priority to CN201710143253.8A priority Critical patent/CN106884443B/en
Publication of CN106884443A publication Critical patent/CN106884443A/en
Application granted granted Critical
Publication of CN106884443B publication Critical patent/CN106884443B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D37/00Repair of damaged foundations or foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/003Injection of material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/0023Slurry

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The present invention relates to the construction method for grouting reinforcement that a kind of foundation bottom is come to nothing, according to job specfication requirement, ground line is released in measurement, and releasing needs to pick the size that chisel removes basis;Surface of base cutting is carried out, the new equipment basis reconstructed according to operation normal construction;Grouting Pipe is made, is buried as requested, carry out slip casting protection of pipe;Earthwork compaction in layers backfill;Proceed basic Superstructure Construction, to crack under the original basis below whole closing basis, cave in, the defect area such as hollowing carries out slip casing by pressure;Cut to exposing the unnecessary Grouting Pipe of surface of base, blocked, surface reconditioning.The construction method for grouting reinforcement that foundation bottom of the present invention is come to nothing, basic grouting behind shaft or drift lining of first constructing, foundation construction can be accelerated;Confined pressure slip casting, significantly, quality is guaranteed for slip casting effect;Avoid structure construction and grouting with plunger cross-operation;Technological process is simple, and workman is easily operated;Injecting paste material ground materials, save construction cost, improve efficiency of construction.

Description

The construction method for grouting reinforcement that foundation bottom is come to nothing
Technical field
It is to be related to a kind of foundation bottom to take off specifically the present invention relates to a kind of construction method of concrete foundation treatment Empty construction method for grouting reinforcement.
Background technology
At present, the limitation with country to some production capacity surplus projects, advocates low-carbon environment-friendly, energy-saving and emission-reduction, green energetically Construct, therefore numerous items have to carry out technique adjustment or upgrading, it is necessary to some the equipment bases on production line Plinth carries out technological transformation, meets existing process requirement.During basic technological transformation, often a part is to remove original equipment basis top, Take bar planting or be attached mode with original basis bar splicing and reconstruct, and the deeper basis of many generally requires whole dismountings Drill through(Thoroughly)Original equipment sole plate, i.e., open up reserved construction hole equivalent in original basis upper plate, new basis of constructing again, It is connected to form new Equipment Foundations with original basis again.But picking when chisel removes large equipment base carried out using machinery (Hydraulic pick or pneumatic pick, electric pick etc.), the vibrations at this moment producing often cause near surrounding that ground beneath the earthwork occurs and caves in, splits The phenomenons such as seam, the bottom of foundation come to nothing, hollowing, and vibrations will also result in surrounding soil body landslide, sedimentation in elementary process is transformed Situations such as, the particularly soil property such as such as mud is in bad order, even more serious when level of ground water is higher.When new foundation construction is finished back The earthwork filled out can not cause that original basis bottom is closely knit, cannot also tamp, even if foundation ditch has gib measure, the soil body also can be right Supporting construction produces lateral pressure, causes sole plate to come to nothing, and it is safe to cause foundation bearing capacity deficiency to have influence on using for structure.
The content of the invention
For above-mentioned deficiency of the prior art, the present invention provides a kind of technological process simply, and easy construction improves construction Efficiency, reduces construction cost, it is ensured that the construction method for grouting reinforcement that the foundation bottom of construction quality is come to nothing.
The technical solution used in the present invention is:
The construction method for grouting reinforcement that a kind of foundation bottom is come to nothing, comprises the following steps:
The first step:According to design drawing and job specfication requirement, ground line is released in measurement, needs is then released in original basis and is picked Dig the size removed;
Second step:Cut according to pay-out rule little progress row surface of base with emery wheel or toothless saw, basis is entered with mechanical-hydraulic pick Row protective demolition;
3rd step:The new equipment basis reconstructed according to operation normal construction;
4th step:Equipment Foundations health, form removable cleaning;
5th step:Grouting Pipe is made, is buried as requested, carry out slip casting protection of pipe;
6th step:Earthwork compaction in layers backfill;
7th step:Proceed basic Superstructure Construction, basis is carried out into overall company with original equipment basis dismounting face on request Connect closure;
8th step:To crack under the original basis below whole closing basis, cave in, the defect area such as hollowing carries out slip casing by pressure;
9th step:Cut to exposing the unnecessary Grouting Pipe of surface of base, blocked, surface reconditioning.
The slip casing by pressure uses cement mortar.
The Grouting Pipe upper end is connected region welding steel seal ring with basis.
The slip casting comprises the following steps:
1st, pump line is connected;
Grouting pump one end is connected with Grouting Pipe, is fixed with thin wire and Grouting Pipe and is tightened, Grouting Pipe jumps during preventing slip casting Support;The other end and mixer lower section pulp storage tank are connected, and stretch into pipe port dense mesh or screen pack in pulp storage tank and encase;
2nd, cement mortar is made;
Mechanical agitation is carried out with mixer, the ratio of mud is controlled 1:1~0.65:Between 1;
First toward a certain amount of water is added in mixer, cement is subsequently poured into, finally adds water order, 3-5 bags of cement is stirred every time, stirred Time control is mixed at 5 minutes or so;
3rd, turn on pump starts slip casting;
Start grouting pump and start slip casting, grouting pump is adjusted to low grade when starting slip casting, be adjusted to for grouting pump when smooth by slurries flowing Top grade, notes observing the pressure of slip casting table and the torsional deformation of slip casting flexible pipe;
4th, voltage stabilizing, end slip casting;
Gage pressure tends towards stability and reaches design pressure, terminates slip casting.Found during slip casting around adjacent hole or injected hole Hole and crack have slurries to overflow, and to block in time, and closure stops slip casting without effect.First time grouting serous fluid will be answered during initial set Carry out second or third time mends slurry.
Present invention beneficial effect compared with the prior art:
The construction method for grouting reinforcement that foundation bottom of the present invention is come to nothing, rear bored grouting is not used and Grouting Pipe is buried in advance to original , to fill, permeate and the mode such as compacted, drive away ground by slip casing by pressure in sole plate cave in loosening, crack of phenomenon, the soil body of coming to nothing Moisture and gas in slabbing gap or between soil particle, and its position is filled, the soil body is cemented to an entirety after hardening, so that Ground is reinforced, in addition under the closing of whole sole plate(Equivalent under enclosed environment)Slip casing by pressure so that slip casting effect Greatly improve.Secondly Grouting Pipe tip is solved because working space is narrow in also can be inserted into lower section soil layer, and section is removed not in basis Neatly, the backfill earthwork cannot cal rolling it is closely knit and roll less than region so that whole the old and new basis surrounding slip casting hardening A veneer for closing is formed afterwards, serves water-stop curtain effect.
The construction method for grouting reinforcement that foundation bottom of the present invention is come to nothing, basic grouting behind shaft or drift lining of first constructing, foundation construction can add Hurry up;Confined pressure slip casting, significantly, quality is guaranteed for slip casting effect;Avoid structure construction and grouting with plunger cross-operation;Technique Flow is simple, and workman is easily operated;Injecting paste material ground materials, save construction cost, improve efficiency of construction.
Brief description of the drawings
The structural representation of the construction method for grouting reinforcement that Fig. 1 foundation bottoms of the present invention are come to nothing;
Fig. 2 is the original basis generalized section of the construction method for grouting reinforcement that foundation bottom of the present invention is come to nothing;
Fig. 3 is that the original basis of the construction method for grouting reinforcement that foundation bottom of the present invention is come to nothing remove earth excavation generalized section;
Fig. 4 is the basis embedded generalized section of reconstruction Grouting Pipe of the construction method for grouting reinforcement that foundation bottom of the present invention is come to nothing;
Fig. 5 is the grouting and reinforcing zone profile schematic diagram of the construction method for grouting reinforcement that foundation bottom of the present invention is come to nothing.
Critical piece symbol description in accompanying drawing:
In figure:
1st, newly-built basic 2, original basis 3, blinding layer 4, connection reinforcing bar 5, Grouting Pipe 6, steel plate water-stopping ring 7, Slurries perforation 8, injection slurry
9th, bottom foundation soil
10th, original basis base plate comes to nothing region, loose region, crack area, settling zone
11st, unreal region, narrow space region are backfilled.
Specific embodiment
Referring to the drawings and embodiment the present invention will be described in detail:
Knowable to accompanying drawing 1-5,
The construction method for grouting reinforcement that a kind of foundation bottom is come to nothing,
The first step:According to design drawing and job specfication requirement, ground line is released in measurement, needs is then released in original basis and is picked Dig the size removed;
Second step:Cut according to pay-out rule little progress row surface of base with emery wheel or toothless saw, use mechanical-hydraulic pick(Hydraulic hammer or Pneumatic pick)Protective demolition is carried out to basis;Whether reinforcing bar in basis is retained according to design requirement, it is such as direct with gas welding without reservation Slice off, manual cleaning removes building waste in surface of base and foundation ditch;
3rd step:The new equipment basis reconstructed according to operation normal construction;I.e.:Earth excavation → bed course → reinforcing bar colligation → template Closing → concreting;
4th step:Equipment Foundations health, form removable cleaning;
5th step:Grouting Pipe is made, is buried as requested, carry out slip casting protection of pipe;
Grouting Pipe can use common 4 steel splitting pipe:Φ22mm;According to the parameter determination slip casting length of tube such as original basis bottom depth, will Grouting Pipe toothless saw cuts into certain length, and tip sledgehammer pounds tapered, and the sophisticated certain distance of distance starts up spacing Surrounding sets Ф 5mm slip casting holes;Upper end is connected region with basis(In basis or terrace)Welding steel seal ring.Grouting Pipe With machinery(Or sledgehammer)Squeeze into need original basis bottom to be processed soil layer;
6th step:Basic surrounding cubic metre of earth compaction in layers backfill;
7th step:Proceed basic Superstructure Construction, basis is carried out into overall company with original equipment basis dismounting face on request Connect closure;
8th step:To whole closing basis(Ground)Crack under following original basis, cave in, the defect area such as hollowing carries out pressure Slip casting, improving improves foundation bearing capacity.
Slip casting step:
1st, pump line is connected;
By grouting pump one end and steel(Penetrate)Pipe is connected, tightened with thin wire and steel pipe colligation, and Grouting Pipe jumps during preventing slip casting Support;The other end and mixer lower section pulp storage tank are connected, and stretch into pipe port dense mesh or screen pack in pulp storage tank and encase;
2nd, cement mortar is made;
Mechanical agitation is carried out with mixer, the ratio of mud is controlled 1:1~0.65:Between 1;
First toward a certain amount of water is added in mixer, cement is subsequently poured into, adds water order, 3-5 bags of cement is stirred every time, during stirring Between control at 5 minutes or so;
Cement uses 32.5# Portland cements;
3rd, turn on pump starts slip casting;
Start grouting pump and start slip casting, grouting pump is adjusted to low grade when starting slip casting, be adjusted to for grouting pump when smooth by slurries flowing Top grade, notes observing the pressure of slip casting table and the torsional deformation of slip casting flexible pipe;
4th, voltage stabilizing, end slip casting
Gage pressure tends towards stability and reaches design pressure, terminates slip casting.Found during slip casting around adjacent hole or injected hole Hole and crack have slurries to overflow, and to block in time, and closure stops slip casting without effect.First time grouting serous fluid will be answered during initial set Carry out second or third time mends slurry;
9th step:Cut to exposing the unnecessary Grouting Pipe of surface of base, blocked, surface reconditioning
Technological process:Surveying setting-out(Pick chisel line in basis)→ basic cutting, dismounting, cleaning → newly-built foundation construction → health, mould Plate dismounting → Grouting Pipe is made, embedded → backfilling of earthwork → top foundation structure construction and original basis connection closing → pressure are noted Slurry → slip casting terminates, cutting is blocked.
It is basic grouting behind shaft or drift lining of first constructing, foundation construction can be accelerated;Confined pressure slip casting, slip casting effect is notable, quality It is guaranteed;Carried out after slip casting, it is to avoid structure construction and grouting with plunger cross-operation;Technological process is simple, and workman is easily operated;Note Pulp material(Steel pipe, cement)Gather materials on the spot, easily buying, cost-effective.
The construction method for grouting reinforcement that foundation bottom of the present invention is come to nothing, rear bored grouting is not used and Grouting Pipe is buried in advance Cave in loosening, crack of phenomenon, the soil body of being come to nothing to original basis base plate, to fill, permeate and the mode such as compacted, is driven by slip casing by pressure The moisture and gas in the crack of stratum or between soil particle are walked, and fills its position, the soil body is cemented to an entirety after hardening, from And ground is reinforced, in addition under the closing of whole sole plate(Equivalent under enclosed environment)Slip casing by pressure so that slip casting Effect is greatly improved.Secondly Grouting Pipe tip is solved because working space is narrow in also can be inserted into lower section soil layer, and basis is removed disconnected Face is irregular, the backfill earthwork cannot cal rolling it is closely knit and roll less than region so that the surrounding slip casting of whole the old and new basis A veneer for closing is formed after hardening, water-stop curtain effect is served.
The construction method for grouting reinforcement that foundation bottom of the present invention is come to nothing, basic grouting behind shaft or drift lining of first constructing, foundation construction can add Hurry up;Confined pressure slip casting, significantly, quality is guaranteed for slip casting effect;Avoid structure construction and grouting with plunger cross-operation;Technique Flow is simple, and workman is easily operated;Injecting paste material ground materials, save construction cost, improve efficiency of construction.
The above, is only presently preferred embodiments of the present invention, not makees any formal to structure of the invention Limitation.Every any simple modification, equivalent variations and modification made to above example according to technical spirit of the invention, Belong in the range of technical scheme.

Claims (4)

1. the construction method for grouting reinforcement that a kind of foundation bottom is come to nothing, it is characterised in that
The first step:According to design drawing and job specfication requirement, ground line is released in measurement, needs is then released in original basis and is picked Dig the size removed;
Second step:Cut according to pay-out rule little progress row surface of base with emery wheel or toothless saw, basis is entered with mechanical-hydraulic pick Row protective demolition;
3rd step:The new equipment basis reconstructed according to operation normal construction;
4th step:Equipment Foundations health, form removable cleaning;
5th step:Grouting Pipe is made, is buried as requested, carry out slip casting protection of pipe;
6th step:Earthwork compaction in layers backfill;
7th step:Proceed basic Superstructure Construction, basis is carried out into overall company with original equipment basis dismounting face on request Connect closure;
8th step:To crack under the original basis below whole closing basis, cave in, the defect area such as hollowing carries out slip casing by pressure;
9th step:Cut to exposing the unnecessary Grouting Pipe of surface of base, blocked, surface reconditioning.
2. the construction method for grouting reinforcement that foundation bottom is come to nothing according to claim 1, it is characterised in that:The slip casing by pressure Using cement mortar.
3. the construction method for grouting reinforcement that foundation bottom is come to nothing according to claim 1, it is characterised in that:In the Grouting Pipe Hold the region welding steel seal ring that is connected with basis.
4. the construction method for grouting reinforcement that foundation bottom is come to nothing according to claim 1, it is characterised in that:The slip casting includes Following steps:
1st, pump line is connected;
Grouting pump one end is connected with Grouting Pipe, is fixed with thin wire and Grouting Pipe and is tightened, Grouting Pipe jumps during preventing slip casting Support;The other end and mixer lower section pulp storage tank are connected, and stretch into pipe port dense mesh or screen pack in pulp storage tank and encase;
2nd, cement mortar is made;
Mechanical agitation is carried out with mixer, the ratio of mud is controlled 1:1~0.65:Between 1;
First toward a certain amount of water is added in mixer, cement is subsequently poured into, finally added water order again, and 3-5 bags of cement is stirred every time, Mixing time is controlled at 5 minutes or so;
3rd, turn on pump starts slip casting;
Start grouting pump and start slip casting, grouting pump is adjusted to low grade when starting slip casting, be adjusted to for grouting pump when smooth by slurries flowing Top grade, notes observing the pressure of slip casting table and the torsional deformation of slip casting flexible pipe;
4th, voltage stabilizing, end slip casting;
Gage pressure tends towards stability and reaches design pressure, terminates slip casting;
Find that hole and crack there are slurries to overflow around adjacent hole or injected hole, block in time during slip casting, block without effect Stop slip casting;
First time grouting serous fluid will should be carried out second or third time benefit slurry during initial set.
CN201710143253.8A 2017-03-11 2017-03-11 The construction method for grouting reinforcement that foundation bottom is come to nothing Active CN106884443B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710143253.8A CN106884443B (en) 2017-03-11 2017-03-11 The construction method for grouting reinforcement that foundation bottom is come to nothing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710143253.8A CN106884443B (en) 2017-03-11 2017-03-11 The construction method for grouting reinforcement that foundation bottom is come to nothing

Publications (2)

Publication Number Publication Date
CN106884443A true CN106884443A (en) 2017-06-23
CN106884443B CN106884443B (en) 2019-01-18

Family

ID=59179899

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710143253.8A Active CN106884443B (en) 2017-03-11 2017-03-11 The construction method for grouting reinforcement that foundation bottom is come to nothing

Country Status (1)

Country Link
CN (1) CN106884443B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109680722A (en) * 2019-01-24 2019-04-26 江苏南通三建集团股份有限公司 The construction method for setting external building access port is directly stayed on outer wall of basement body

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101168957A (en) * 2007-10-01 2008-04-30 于心然 Bridge brow plate emptying shallow layer grouting reinforcement technique
CN101994325A (en) * 2010-12-22 2011-03-30 建研地基基础工程有限责任公司 Reinforced foundation and method for improving bending and shearing resistance of existing building rigid foundation
CN101994324A (en) * 2010-12-22 2011-03-30 建研地基基础工程有限责任公司 Reinforced foundation and method for improving bending and shearing capacity of existing building rigid foundation
CN203487547U (en) * 2013-09-26 2014-03-19 中国化学工程第六建设有限公司 Equipment foundation reinforcing device
CN103741963A (en) * 2014-01-06 2014-04-23 北京筑福国际工程技术有限责任公司 Industrial plant foundation strengthening method
CN105604340A (en) * 2015-12-28 2016-05-25 长春工程学院 Old house floor adding modifying method capable of improving seismic capacity and prolonging safe life
KR20160107431A (en) * 2015-03-04 2016-09-19 윤종현 Underwater structure construction apparatus and construction method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101168957A (en) * 2007-10-01 2008-04-30 于心然 Bridge brow plate emptying shallow layer grouting reinforcement technique
CN101994325A (en) * 2010-12-22 2011-03-30 建研地基基础工程有限责任公司 Reinforced foundation and method for improving bending and shearing resistance of existing building rigid foundation
CN101994324A (en) * 2010-12-22 2011-03-30 建研地基基础工程有限责任公司 Reinforced foundation and method for improving bending and shearing capacity of existing building rigid foundation
CN203487547U (en) * 2013-09-26 2014-03-19 中国化学工程第六建设有限公司 Equipment foundation reinforcing device
CN103741963A (en) * 2014-01-06 2014-04-23 北京筑福国际工程技术有限责任公司 Industrial plant foundation strengthening method
KR20160107431A (en) * 2015-03-04 2016-09-19 윤종현 Underwater structure construction apparatus and construction method
CN105604340A (en) * 2015-12-28 2016-05-25 长春工程学院 Old house floor adding modifying method capable of improving seismic capacity and prolonging safe life

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
王鹏: "《某转炉基础地基处理及基坑支护施工技术》", 《施工技术》 *
赵志民: "《某厂房改造工程新增柱和设备基础与既有基础之间的地基关系处理》", 《工程质量》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109680722A (en) * 2019-01-24 2019-04-26 江苏南通三建集团股份有限公司 The construction method for setting external building access port is directly stayed on outer wall of basement body

Also Published As

Publication number Publication date
CN106884443B (en) 2019-01-18

Similar Documents

Publication Publication Date Title
CN106759473B (en) The constructing structure and its construction method of underground pipe gallery and road
WO2017185817A1 (en) Construction method for on-site mixing cement-soil pile overground
CN104499479A (en) Dig-hole pile construction method based on penetration of sand gravel backfilling layer
CN109610470A (en) A kind of base pit stand construction using three axes agitating pile machine
CN103233454A (en) Processing method of soaking, vacuum preloading and slurry injecting for sand piles of collapsible loess foundation
CN101487254A (en) Construction method of vibrating immersed tube gravel slip-casting pile
CN106907157B (en) A kind of shield machine normal pressure opens the cabin operation construction method
CN112081155B (en) Reinforcing and lifting method for bar-shaped or box-shaped foundation building
CN107513994A (en) One kind segmentation becomes supporting rotary digging stake and its construction method without leave
CN102877470B (en) Combined soil nailing construction method for supporting
CN106812149A (en) A kind of construction method of pile foundation
Brown Practical considerations in the selection and use of continuous flight auger and drilled displacement piles
CN114808990A (en) High-pressure pre-filling karst cave pile foundation construction method
CN112761166A (en) Construction method for shallow foundation pit of combined support of piles and pre-grouting steel pipes based on SMW (soil mixing wall) construction method
CN112695763A (en) Deep sludge stratum foundation pit excavation method
CN206721870U (en) A kind of long auger guncreting pile steel reinforcement cage
CN112081157B (en) Construction method for forming reinforced composite pile foundation by high-rise building retreating type grouting
CN102587385A (en) Foundation pit supporting method for sludge-exchanged and filled soft soil
CN106884427A (en) Immersed tube tunnel and immersed tube tunnel changeover portion soft soil foundation reinforcing method under water
CN207862925U (en) A kind of slip casting casing device
CN108411895A (en) Pipe row's pump mud injected foundation processing method
CN112081158B (en) Construction method for forming reinforced composite pile foundation by advanced grouting of high-rise building
CN106884443B (en) The construction method for grouting reinforcement that foundation bottom is come to nothing
CN111455976A (en) Construction method of self-setting mortar impervious wall by grooving method
CN111535298A (en) Seepage-proofing construction method for underground diaphragm wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant