CN106875321A - A kind of real-time automatic generation method of train line spatial data - Google Patents

A kind of real-time automatic generation method of train line spatial data Download PDF

Info

Publication number
CN106875321A
CN106875321A CN201710077515.5A CN201710077515A CN106875321A CN 106875321 A CN106875321 A CN 106875321A CN 201710077515 A CN201710077515 A CN 201710077515A CN 106875321 A CN106875321 A CN 106875321A
Authority
CN
China
Prior art keywords
train
line
railway
information
database
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710077515.5A
Other languages
Chinese (zh)
Other versions
CN106875321B (en
Inventor
王永桂
许世城
刘龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Xiao Hong Rope Technology Co Ltd
Original Assignee
Wuhan Xiao Hong Rope Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Xiao Hong Rope Technology Co Ltd filed Critical Wuhan Xiao Hong Rope Technology Co Ltd
Priority to CN201710077515.5A priority Critical patent/CN106875321B/en
Publication of CN106875321A publication Critical patent/CN106875321A/en
Application granted granted Critical
Publication of CN106875321B publication Critical patent/CN106875321B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/40Business processes related to the transportation industry

Landscapes

  • Business, Economics & Management (AREA)
  • Health & Medical Sciences (AREA)
  • Economics (AREA)
  • General Health & Medical Sciences (AREA)
  • Human Resources & Organizations (AREA)
  • Marketing (AREA)
  • Primary Health Care (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Engineering & Computer Science (AREA)
  • Theoretical Computer Science (AREA)
  • Train Traffic Observation, Control, And Security (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

Automatically generate and uniquely change four steps of determination with train line the invention discloses a kind of real-time automatic generation method of train line spatial data, including structure railway grid database, structure train information database, train line;The present invention is while time-table is issued, time-table can be automatically interpreted in real time, automatically generate rail track spatial data, and based on train GPS positional information, circuit to automatically generating is selected and checked, and ultimately generates unique accurately train line spatial data, serves the application program for relying on rail track data, the accuracy and reliability of base of applications information are ensured, while the speed for greatly reducing the artificial line cost drawn, improving data renewal.

Description

A kind of real-time automatic generation method of train line spatial data
Technical field
The invention belongs to GIS-Geographic Information System, railway planning, railway construction, railway operation dispatching technique field, it is related to one Plant the real-time automatic generation method of train line spatial data, and in particular to one kind automatically generates train in real time according to time-table The method of working line.
Background technology
Train operation circuit is train operation state real-time exhibition, train arrival Time Forecast, Train delay assessment and arranges The basis of car scheduling.As continuing to develop for China's railway construction, especially spring transportation etc. were gone on a journey in the busy period, train time The adjustment of table is relatively large.Adjustment all redrawing with train line of each time-table.At present, changed the line map in train operation Afterwards, China is in addition to railroad, and remaining department and agency is difficult the very first time and grasps accurate train line data.And this is caused In the application related to train line, the renewal of train line not in time, causes the mistake of information.How in time-table hair Rapid to update train line figure in the short time of cloth, related for train line application, has great importance.
With the development of GIS-Geographic Information System, spatial database technology, Spatial Data Index Technology and spatial analysis are in railway, boat The fields such as sky, digital map navigation are widely applied.GIS-Geographic Information System, by by geographic object it is abstract be spatial entities, It is managed and combines according to unified geographical coordinate code, relies on its powerful aggregation of data, simulation and analytic function, can be real Now the quick positioning to spatial data is searched for, and carries out complicated inquiry, realizes graphics process and expression.Railway construction in China Fang Xing Do not end, rail track extends in all direction, by the end of the year 2015, china railway revenue kilometres reach 12.1 ten thousand kilometers, wherein high-speed iron 1.9 ten thousand kilometers of road, 150,000 kilometers of four vertical four horizontal Line for Passenger Transportation networks will be built up to the year two thousand twenty.Complicated road network structure and huge Railway operation and maintenance system, it is necessary to powerful spatial data and method support.At present, Geodatabase, spatial analysis, shortest path Structure, railway operation adjustment, railway operation scheduling of the methods such as footpath inquiry, optimal path algorithm in railway track spatial database In played an important role.With continuing to develop for China railways road network construction, the complexity of road network is continuously increased, website is arrived Circuit is on the increase between website.The circuit of Traditional Man is changed the line map and is checked, and difficulty is increasing, workload is more and more, Railway cannot be met fast-developing and the need for railway networks run diagram is continually changing down.At present, in the drafting of China railways line, still More dependence is manually changed the line map, is drawn and group figure, and the automation generation from railway line spatial data also has a certain distance.It is a set of Based on spatial database and Spatial Data Analysis, automatically generating in real time for rail track can be realized, and build track data storehouse, had There is important meaning and realistic price.In timeliness, it is delayed that it can solve the problems, such as that related application rail track among the people updates; On cost, can solve the artificial line transfer of dependence takes time and effort problem, can provide in real time accurately circuit number for railway applications program According to.
The content of the invention
Draw that artificial dependence is big and China's rail track spatial data among the people is delayed for current rail circuit, update not Timely problem, the invention provides a kind of real-time automatic generation method of train line database based on time-table, is somebody's turn to do Method is based on disclosed train schedule information, under the support of geographic information system technology, realizes rail track in real time, quickly With automatically generate, can ensure that ageing, economy and reliability that rail track spatial data updates.
The technical solution adopted in the present invention is:A kind of real-time automatic generation method of train line spatial data, its feature It is to comprise the following steps:
Step 1:Build railway grid database
The railway grid database includes point factor data table and line feature tables of data;Described key element is railway station website Information, point key element is divided into I grade of website and II grade of website according to whether being railway terminal;The line feature is railway track information, Line feature foundation《Code for design of railway line》It is divided into I, II, III, IV grade of rail track;
Step 2:Build train information database
The information of train is gathered from time-table, the information of each column train will be collected, according to train line data Table builds and belongs to the single information table of each train, forms train information database;The train line tables of data includes train Bus Schedules, by way of site information;
Step 3:Train line is automatically generated
According to railway grid database and train information database, automatically determine each train by way of website and website between Optional line unit, obtains the coordinate set of all composition points of each train line unit, and ultimately generate each train can Route selection road spatial data;
Step 4:Train line uniquely changes determination;
GPS position information based on train, builds M meters of buffering area of scope of train position, and M is preset value, judges buffering Whether the line unit in the range of area has a plurality of circuit, if so, the then row where the nearest coordinate points of judging distance train position Car line number, determines that the line number is the unique correct circuit of the line unit, and then generate the unique correct line of each train The coordinate point set on road, builds the train line spatial database of each train.
The beneficial effects of the invention are as follows while time-table is issued, the iron in database being automatically updated in real time Route road spatial data, serves the application program for relying on rail track data, it is ensured that the accuracy of base of applications information And reliability, while the speed for greatly reducing the artificial line cost drawn, improving data renewal.
Brief description of the drawings
Fig. 1:The method flow diagram of the embodiment of the present invention.
Fig. 2:The flow chart that the circuit point set of the embodiment of the present invention is automatically generated.
Fig. 3:The uniqueness for having the line unit of a plurality of railway line determines schematic diagram.
Specific embodiment
Understand for the ease of those of ordinary skill in the art and implement the present invention, below in conjunction with the accompanying drawings and embodiment is to this hair It is bright to be described in further detail, it will be appreciated that implementation example described herein is merely to illustrate and explain the present invention, not For limiting the present invention.
China's railway authoritative department only issues the railway networks run diagram of form word version when railway networks run diagram is adjusted, and simultaneously Do not issue corresponding coach route spatial data, because China railways net is complicated, it is site-to-site between optional rail track It is more, this give since time-table base of applications data renewal bring greatly challenge, each railroad Carry out train operation to change the line map, related application is required for substantial amounts of manpower and materials to carry out the adjustment of coach route.Based on this, this hair It is bright to propose a kind of real-time automatic generation method of train line database based on time-table.In existing china railway unit number On the basis of, based on railway networks run diagram, automatically generating in real time to coach route spatial data is realized, iron will be efficiently solved The problems such as basic coach route data update slow, inaccurate in the related application of road.
A kind of real-time automatic generation method of train line database based on time-table, by building the railway network and row Car data storehouse, the interpretation structure train information database for carrying out time-table, automatically generate train line on this basis, and Based on train GPS location information, the uniqueness for carrying out rail track determines, and then generates train operation circuit spatial data.
See a kind of real-time automatic generation method of train line spatial data that Fig. 1, the present invention are provided, including following step Suddenly:
Step 1:Build railway grid database;
Railway grid database includes point factor data table and line feature tables of data;Point key element is railway station site information, point Key element is divided into I grade of website and II grade of website according to whether being railway terminal;Line feature is railway track information, line feature foundation 《Code for design of railway line》It is divided into I, II, III, IV grade of rail track;
Its midpoint factor data table, as shown in table 1:
1 factor data table of table
Wherein line feature tables of data, as shown in table 2:
The line feature tables of data of table 2
Step 2:Build train information database;
The information of train is gathered from time-table, the information of each column train will be collected, according to train line data Table builds and belongs to the single information table of each train, forms train information database;The train line tables of data includes train Bus Schedules, by way of site information;
Wherein train line tables of data, as shown in table 3:
The train line tables of data of table 3
After train adjustment, railroad can issue newest time-table, the car comprising train in time-table The title of all websites that secondary, train the time of departure, train pass through, in information such as each residence times stood.According to these Information, with reference to the structure of train line tables of data in step 2, builds train information database.Comprise the following steps that:
Step 2.1:The essential information of train in collection time-table, including the website that the train number of train, train pass through Title;
Step 2.2:The train number that each column train will be collected builds the single information table of train, is named as TrainName_ DB, wherein, TrainName is the train number of train;
Step 2.3:The information table of each column train is built, according to train number, in train information tables of data, search is obtained Its numbering;The title of the website passed through according to train, in a factor data table, row is inserted by the corresponding Site ID of site name In the TrainSts of car information data table, the number of all TrainSts is counted, insert train information tables of data In TrainNumsts;
Step 2.4:According to a factor data table, the place railway line ID of each website is searched for, inserted successively In TrainLines;
Step 2.5:All train information tables of data are stored in database, build train information database.
Step 3:Train line is automatically generated;
According to railway grid database and train information database, automatically determine each train by way of website and circuit, The coordinate of all composition points of each train line is obtained, the track data storehouse of each train is built.
See Fig. 2, implement including following sub-step:
Step 3.1:Determine train by way of website and circuit, from initiating station to terminus, number consecutively S_1~S_N;
Step 3.2:It is determined that the line unit of the train line to be generated, is a complete computing unit, root with train number The Origin And Destination of the calculative line unit of a coastiong time and line unit is obtained according to train information tables of data;Search starting point Stand and terminus place railway line ID, its common place railway line ID, then be the place railway line ID in table;Due to two There may be a plurality of railway line between individual station, then a line unit there may be multiple optional railway line ID, and its is all possible Line unit number represents with NUMIDS, each line unit railway line, from 1 open numbering.
The line unit of the train line is:
Step 3.3:According to the inception point and terminus of line unit S_N, in the coordinate in railway line where searching it Sequence number IDX1 and IDX2, the coordinate point set of IDX1~IDX2 is picked out from railway line database, if S_N has m coordinate points, Then the coordinate point set of line unit S_N is:
S_N=[(lon1,lat1),(lon2,lat2)…(lonm,latm)]
If the coordinate points set representations that line unit S_N has the optional railway line of K bars, a plurality of circuit of S_N are:
Step 3.4:1~N-1 all of the coordinate points of line unit are combined, the point set for obtaining is then train line Coordinate point set L;
L={ S_1, S_2 ..., S_N-1 }, wherein S_1 to S_N-1 is not all uniquely.
Step 3.5:By all trains in train information database, according to the method for step 3.1~step 3.4, automatically Generate the coordinate point set of the working line of each train.
Step 4:Train line uniquely changes determination:
GPS position information based on train, builds 10 meters of buffering areas of scope of train position, judges in the range of buffering area Whether line unit has a plurality of circuit, if so, the then train line number where the nearest coordinate points of judging distance train position, really The fixed line number is the unique correct circuit of the line unit, and then generates the coordinate points of the unique correct circuit of each train Collection, builds the train line spatial database of each train.
Fig. 3 is referred to, the coordinate point set for generating the unique correct circuit of each train specifically includes following steps:
Step 4.1:The GPS location for determining the train of current time t is P (trant_t);
P (train_t)=(lont, latt)
Step 4.2:10 meters of buffering areas of scope of train position are built, judges that the line unit S_N in the range of buffering area is compiled Number, if the NUMIDS of line unit S_N is more than 1, step 4.3 is transferred to, step 4.1 is otherwise transferred to, until train is reached home Stand, be transferred to step 4.5;
Step 4.3:Search in the coordinate point set L of the train line, the coordinate p of the point nearest apart from train_t, search is obtained The line number LineID where line unit S_N and the point where obtaining the point.
Step 4.4:Determine the unique correct circuit that LineID is line unit S_N.
Step 4.5:The point set of the unique correct circuit of all line units is connected, the coordinate point set of train line is built TL;
TL={ S_1, S_2 ..., S_N-1 }, wherein S_1 to S_N-1 are unique.
It should be appreciated that the part that this specification is not elaborated belongs to prior art.
It should be appreciated that the above-mentioned description for embodiment is more detailed, therefore can not be considered to the present invention The limitation of scope of patent protection, one of ordinary skill in the art, will right of the present invention is not departed under enlightenment of the invention Ask under protected ambit, replacement can also be made or deformed, each fall within protection scope of the present invention, it is of the invention Scope is claimed should be determined by the appended claims.

Claims (7)

1. a kind of real-time automatic generation method of train line spatial data, it is characterised in that comprise the following steps:
Step 1:Build railway grid database;
The railway grid database includes point factor data table and line feature tables of data;Described key element is believed for railway station website Breath, point key element is divided into I grade of website and II grade of website according to whether being railway terminal;The line feature is railway track information, line Key element foundation《Code for design of railway line》It is divided into I, II, III, IV grade of rail track;
Step 2:Build train information database;
The information of train is gathered from time-table, the information of each column train will be collected, according to train line tables of data structure Build and belong to the single information table of each train, form train information database;The train line tables of data includes the car of train Secondary information, by way of site information;
Step 3:Train line is automatically generated;
According to railway grid database and train information database, automatically determine each train by way of website and website between it is optional Line unit, obtain the coordinate set of all composition points of each train line unit, ultimately generate each train can route selection Road spatial data;
Step 4:Train line uniquely changes determination;
GPS position information based on train, builds M meters of buffering area of scope of train position, and M is preset value, judges buffering area model Whether the line unit in enclosing has a plurality of circuit, if so, the then train-line where the nearest coordinate points of judging distance train position Lu Hao, determines that the line number is the unique correct circuit of the line unit, and then generate the unique correct circuit of each train Coordinate point set, builds the train line spatial database of each train.
2. the real-time automatic generation method of train line database according to claim 1, it is characterised in that institute in step 1 Stating a factor data table is:
3. the real-time automatic generation method of train line database according to claim 1, it is characterised in that institute in step 1 Stating line feature tables of data is:
4. the real-time automatic generation method of train line database according to claim 1, it is characterised in that institute in step 2 Stating train line tables of data is:
5. the real-time automatic generation method of train line database according to claim 4, it is characterised in that the tool of step 2 Body is realized including following sub-step:
Step 2.1:The essential information of train in collection time-table, including the name of website that the train number of train, train pass through Claim;
Step 2.2:The train number that each column train will be collected builds the single information table of train, is named as TrainName_DB, its In, TrainName is the train number of train;
Step 2.3:The information table of each column train is built, according to train number, in train information tables of data, search obtains its volume Number;The title of the website passed through according to train, in a factor data table, train letter is inserted by the corresponding Site ID of site name Cease in the TrainSts of tables of data, count the number of all TrainSts, insert the TrainNumsts of train information tables of data In;
Step 2.4:According to a factor data table, the place railway line ID of each website is searched for, in inserting TrainLines successively;
Step 2.5:All train information tables of data are stored in database, build train information database.
6. the real-time automatic generation method of train line database according to claim 1, it is characterised in that the tool of step 3 Body is realized including following sub-step:
Step 3.1:Determine train by way of website and circuit, from initiating station to terminus, number consecutively S_1~S_N;
Step 3.2:It is determined that the line unit of the train line to be generated, is a complete computing unit with train number, according to row Car information data table obtains the Origin And Destination of the calculative line unit of a coastiong time and line unit;Search starting point station and The place railway line ID of terminus, its common place railway line ID, then be the place railway line ID in table;Due to two stations Between may have a plurality of railway line, then line unit may have multiple optional railway line ID, its all possible circuit Unit number represents with NUMIDS, each line unit railway line, from 1 open numbering;
The line unit of the train line is:
Step 3.3:According to the inception point and terminus of line unit S_N, the sequence in the coordinate in railway line where searching it Number IDX1 and IDX2, picks out the coordinate point set of IDX1~IDX2, if S_N has m coordinate points, line from railway line database The coordinate point set of road cell S _ N is:
S_N=[(lon1,lat1),(lon2,lat2)…(lonm,latm)]
If the coordinate points set representations that line unit S_N has the optional railway line of K bars, a plurality of circuit of S_N are:
S_N=S_N_1, S_N_2 ..., S_N_K }
={ [(lon1_1,lat1_1),(lon1_2,lat1_2)…(lon1_m,lat1_m)],…,[(lonN_1,latN_1), (lonN_2,latN_1)...(lonN_m,latN_m)]}
Step 3.4:1~N-1 all of the coordinate points of line unit are combined, the point set for obtaining is then the seat of train line Punctuate collection L;
L={ S_1, S_2 ..., S_N-1 }, wherein S_1 to S_N-1 is not all uniquely;
Step 3.5:By all trains in train information database, according to the method for step 3.1~step 3.4, automatically generate The coordinate point set of the working line of each train.
7. the real-time automatic generation method of train line database according to claim 1, it is characterised in that the tool of step 4 Body is realized including following sub-step:
Step 4.1:The GPS location for determining the train of current time t is P (trant_t);
P (train_t)=(lont, latt)
Step 4.2:M meters of buffering area of scope of train position is built, the line unit S_N numberings in the range of buffering area are judged, if The NUMIDS of line unit S_N is more than 1, then be transferred to step 4.3, is otherwise transferred to step 4.1, until train is reached terminal, turns Enter step 4.5;
Step 4.3:Search in the coordinate point set L of the train line, the coordinate p of the point nearest apart from train_t, search is somebody's turn to do The line number LineID where line unit S_N and the point where point;
Step 4.4:Determine the unique correct circuit that LineID is line unit S_N;
Step 4.5:The point set of the unique correct circuit of all line units is connected, the coordinate point set TL of train line is built;
TL={ S_1, S_2 ..., S_N-1 }, wherein S_1 to S_N-1 are unique.
CN201710077515.5A 2017-02-14 2017-02-14 Real-time automatic generation method for spatial data of train line Expired - Fee Related CN106875321B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710077515.5A CN106875321B (en) 2017-02-14 2017-02-14 Real-time automatic generation method for spatial data of train line

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710077515.5A CN106875321B (en) 2017-02-14 2017-02-14 Real-time automatic generation method for spatial data of train line

Publications (2)

Publication Number Publication Date
CN106875321A true CN106875321A (en) 2017-06-20
CN106875321B CN106875321B (en) 2020-07-10

Family

ID=59166936

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710077515.5A Expired - Fee Related CN106875321B (en) 2017-02-14 2017-02-14 Real-time automatic generation method for spatial data of train line

Country Status (1)

Country Link
CN (1) CN106875321B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111555829A (en) * 2020-04-23 2020-08-18 深圳市北海轨道交通技术有限公司 System and method for publishing passenger train broadcast operation profile
CN112380248A (en) * 2020-11-24 2021-02-19 深圳市长龙铁路电子工程有限公司 Train number generation method and device, computer equipment and storage medium
CN115402384A (en) * 2022-10-09 2022-11-29 中国铁道科学研究院集团有限公司通信信号研究所 Train default arrival and departure line flexible distribution method based on multiple rules and application thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101847322A (en) * 2010-05-21 2010-09-29 中国科学院地理科学与资源研究所 Method for confirming bus transfer lines
CN102194162A (en) * 2011-03-25 2011-09-21 上海磁浮交通发展有限公司 Method for realizing automatic drawing of running chart of magnetic-levitation train
CN102495896A (en) * 2011-12-13 2012-06-13 南京恩瑞特实业有限公司 Method for implementing automatic generation tool of track line database
CN103309988A (en) * 2013-06-18 2013-09-18 尹盛 Method for automatically generating rail traffic line database
CN105930917A (en) * 2016-04-10 2016-09-07 厦门卫星定位应用股份有限公司 Method and system for generating bus line on electronic map

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101847322A (en) * 2010-05-21 2010-09-29 中国科学院地理科学与资源研究所 Method for confirming bus transfer lines
CN102194162A (en) * 2011-03-25 2011-09-21 上海磁浮交通发展有限公司 Method for realizing automatic drawing of running chart of magnetic-levitation train
CN102495896A (en) * 2011-12-13 2012-06-13 南京恩瑞特实业有限公司 Method for implementing automatic generation tool of track line database
CN103309988A (en) * 2013-06-18 2013-09-18 尹盛 Method for automatically generating rail traffic line database
CN105930917A (en) * 2016-04-10 2016-09-07 厦门卫星定位应用股份有限公司 Method and system for generating bus line on electronic map

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111555829A (en) * 2020-04-23 2020-08-18 深圳市北海轨道交通技术有限公司 System and method for publishing passenger train broadcast operation profile
CN111555829B (en) * 2020-04-23 2021-10-26 深圳市北海轨道交通技术有限公司 System and method for publishing passenger train broadcast operation profile
CN112380248A (en) * 2020-11-24 2021-02-19 深圳市长龙铁路电子工程有限公司 Train number generation method and device, computer equipment and storage medium
CN115402384A (en) * 2022-10-09 2022-11-29 中国铁道科学研究院集团有限公司通信信号研究所 Train default arrival and departure line flexible distribution method based on multiple rules and application thereof
CN115402384B (en) * 2022-10-09 2023-12-26 中国铁道科学研究院集团有限公司通信信号研究所 Train default to departure flexible allocation method based on multiple rules and application thereof

Also Published As

Publication number Publication date
CN106875321B (en) 2020-07-10

Similar Documents

Publication Publication Date Title
CN103177575B (en) System and method for dynamically optimizing online dispatching of urban taxies
CN103123704B (en) A kind of Logistics Distribution Method based on rich network attribute road network
CN112133090A (en) Multi-mode traffic distribution model construction method based on mobile phone signaling data
CN107133700A (en) Mobile phone signaling data road network method based on R* tree indexes
CN106197460B (en) A method of it is predicted with carrying out trip purpose using GPS trip data
CN101295326B (en) Method for generating OD matrix based on GPS data, traffic simulation method thereof
CN110796337B (en) System for evaluating service accessibility of urban bus stop
CN105117595B (en) A kind of private car trip data integrated approach based on floating car data
CN105844362A (en) Urban traffic comprehensive travel decision-making model
CN115063978B (en) Bus arrival time prediction method based on digital twins
CN106875321A (en) A kind of real-time automatic generation method of train line spatial data
CN109816271A (en) Cycle track service level evaluation method based on shared bicycle track data
CN109002923A (en) A kind of intercity multimode travel route planing method
CN106251628B (en) A kind of method and device of the traffic trip amount of determining motor vehicle
CN108171973A (en) A kind of traffic trip mode identification method based on mobile phone grid data
CN106373384A (en) Remote area passenger transport regular bus route real-time generation method
Kang et al. Potential of urban land use by autonomous vehicles: Analyzing land use potential in Seoul capital area of Korea
CN109493601B (en) Bus branch line setting method
Chen et al. Simulation study based on opentrack on carrying capacity in district of Beijing-Shanghai high-speed railway
Liu et al. Determination of routing velocity with GPS floating car data and webGIS-based instantaneous traffic information dissemination
CN112685411A (en) High-speed rail network visualization method
Zhou et al. Integrated traffic information service system for public travel based on smart phones applications: a case in China
CN100365624C (en) Method and system of public communication source guiding
Zhuge et al. An Initial Implementation of Multiagent Simulation of Travel Behavior for a Medium‐Sized City in China
CN112085315A (en) Gas station carbon emission intensity calculation method based on motor vehicle commuting trip

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 430079 room 1315, Luojia Creative Park, No.33, Luoyu Road, Hongshan District, Wuhan City, Hubei Province

Applicant after: Wuhan Qilian Ecological Technology Co.,Ltd.

Address before: 430072 Hubei Province, Wuhan city Hongshan District Luoyu Road No. 33 creative LUOJIASHAN park one room 1315 students entrepreneurial base

Applicant before: WUHAN XIAOHONGSHENG TECHNOLOGY Co.,Ltd.

CB02 Change of applicant information
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200710

Termination date: 20220214

CF01 Termination of patent right due to non-payment of annual fee