CN106836273B - 一种双拱形城市地下综合体及其暗挖建造方法 - Google Patents
一种双拱形城市地下综合体及其暗挖建造方法 Download PDFInfo
- Publication number
- CN106836273B CN106836273B CN201710024042.2A CN201710024042A CN106836273B CN 106836273 B CN106836273 B CN 106836273B CN 201710024042 A CN201710024042 A CN 201710024042A CN 106836273 B CN106836273 B CN 106836273B
- Authority
- CN
- China
- Prior art keywords
- area
- tunneling
- layer
- construction
- wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 230000005641 tunneling Effects 0.000 title claims abstract description 48
- 238000010276 construction Methods 0.000 title claims abstract description 30
- 238000000034 method Methods 0.000 title claims abstract description 16
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 34
- 238000012423 maintenance Methods 0.000 claims abstract description 31
- 229910000831 Steel Inorganic materials 0.000 claims description 22
- 239000010959 steel Substances 0.000 claims description 22
- 239000004567 concrete Substances 0.000 claims description 15
- 238000002347 injection Methods 0.000 claims description 9
- 239000007924 injection Substances 0.000 claims description 9
- 239000011435 rock Substances 0.000 claims description 8
- 238000007569 slipcasting Methods 0.000 claims description 7
- 230000015572 biosynthetic process Effects 0.000 claims description 5
- 238000003786 synthesis reaction Methods 0.000 claims description 5
- 238000009412 basement excavation Methods 0.000 claims description 4
- 238000007689 inspection Methods 0.000 claims description 4
- 238000009434 installation Methods 0.000 claims description 4
- 125000004122 cyclic group Chemical group 0.000 claims description 3
- 238000013213 extrapolation Methods 0.000 claims description 3
- 238000005259 measurement Methods 0.000 claims description 3
- 239000004570 mortar (masonry) Substances 0.000 claims description 3
- 238000012545 processing Methods 0.000 claims description 3
- 230000002787 reinforcement Effects 0.000 claims description 3
- 239000011378 shotcrete Substances 0.000 claims description 3
- 238000012360 testing method Methods 0.000 claims description 3
- 210000000003 hoof Anatomy 0.000 claims description 2
- 238000010586 diagram Methods 0.000 description 15
- 238000011161 development Methods 0.000 description 6
- 230000006872 improvement Effects 0.000 description 4
- 230000008859 change Effects 0.000 description 3
- 239000007787 solid Substances 0.000 description 3
- 230000007423 decrease Effects 0.000 description 2
- 230000007812 deficiency Effects 0.000 description 2
- 201000010099 disease Diseases 0.000 description 2
- 208000037265 diseases, disorders, signs and symptoms Diseases 0.000 description 2
- 235000012779 flatbread Nutrition 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 230000008439 repair process Effects 0.000 description 2
- 230000007704 transition Effects 0.000 description 2
- 230000000007 visual effect Effects 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000011156 evaluation Methods 0.000 description 1
- 238000007726 management method Methods 0.000 description 1
- 230000007246 mechanism Effects 0.000 description 1
- 238000013439 planning Methods 0.000 description 1
- 239000000243 solution Substances 0.000 description 1
- 230000009466 transformation Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/10—Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Civil Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- Architecture (AREA)
- Environmental & Geological Engineering (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Chemical & Material Sciences (AREA)
- Oil, Petroleum & Natural Gas (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
Description
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710024042.2A CN106836273B (zh) | 2017-01-13 | 2017-01-13 | 一种双拱形城市地下综合体及其暗挖建造方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710024042.2A CN106836273B (zh) | 2017-01-13 | 2017-01-13 | 一种双拱形城市地下综合体及其暗挖建造方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106836273A CN106836273A (zh) | 2017-06-13 |
CN106836273B true CN106836273B (zh) | 2019-02-12 |
Family
ID=59124253
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710024042.2A Active CN106836273B (zh) | 2017-01-13 | 2017-01-13 | 一种双拱形城市地下综合体及其暗挖建造方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106836273B (zh) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109505609B (zh) * | 2018-11-21 | 2023-11-14 | 中交建筑集团有限公司 | 浅埋暗挖城市地下综合管廊无支架施工方法及综合管廊 |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0726406B2 (ja) * | 1989-05-12 | 1995-03-22 | 鹿島建設株式会社 | 地中構造物の構築方法 |
JP3155471B2 (ja) * | 1996-08-05 | 2001-04-09 | 山九株式会社 | トンネル工法及びトンネル支保構造 |
CN102644466B (zh) * | 2012-04-27 | 2014-10-22 | 北京城建设计发展集团股份有限公司 | 岩质地层中修建超浅埋大跨度暗挖地铁车站的托梁拱盖法 |
CN106013224B (zh) * | 2016-06-21 | 2018-11-06 | 沈阳建筑大学 | 双马蹄形城市地下综合体 |
CN105971009B (zh) * | 2016-06-21 | 2018-03-09 | 沈阳建筑大学 | 五层圆形城市地下综合体 |
-
2017
- 2017-01-13 CN CN201710024042.2A patent/CN106836273B/zh active Active
Also Published As
Publication number | Publication date |
---|---|
CN106836273A (zh) | 2017-06-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102182325B (zh) | 一种框架结构独立基础既有建筑物地下室增层方法 | |
CN101775987B (zh) | 地下立交上下主隧道交叠处零间距施工方法 | |
CN107842035B (zh) | 一种超高性能混凝土预制拼装综合管廊体系及施工方法 | |
CN107664035B (zh) | 盾构管廊先盾后井的施工方法 | |
CN106351258B (zh) | 一种全预制拼装钢混凝土组合地下综合管廊 | |
CN106013223B (zh) | 椭圆形断面城市地下综合体 | |
CN106013225A (zh) | 六层圆形交通、综合管廊和海绵城市地下综合体 | |
CN204435404U (zh) | 一种老旧住宅外加电梯基础结构 | |
CN105735354A (zh) | 一种城市地下工程盖挖全逆作施工方法 | |
CN110030016B (zh) | 一种硬岩地层暗挖单层衬砌地铁停车线大断面隧道结构 | |
CN103362513A (zh) | 暗挖区间既有洞体改造施工工法 | |
CN106013215A (zh) | 三层类矩形城市地下综合体 | |
CN106836273B (zh) | 一种双拱形城市地下综合体及其暗挖建造方法 | |
CN106013222B (zh) | 三圆形断面城市地下综合体 | |
CN206189448U (zh) | 一种椭圆形断面城市地下综合体 | |
CN112681376A (zh) | 一种井筒式地下立体车库的施工方法 | |
CN205893922U (zh) | 在带有纵坡的路基上设置的t梁预制场 | |
CN209892228U (zh) | 一种采用暗挖法施工的地下综合管廊结构 | |
CN207484508U (zh) | 一种超高性能混凝土预制拼装综合管廊体系 | |
CN106836277B (zh) | 多层城市地下综合体及其暗挖建造方法 | |
CN207619987U (zh) | 一种环保型地下车库的预制式基坑围护结构 | |
CN106013226B (zh) | 双圆形断面城市地下综合体 | |
CN113202106B (zh) | 深基坑开挖方法 | |
CN106013938B (zh) | 地上地下城市交通与管网综合体 | |
CN106640094B (zh) | 具有维修车道的合流调蓄型深层双洞隧道及其建筑方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20211216 Address after: 8D, unit 4, floor 7, building 3, a48 Zhichun Road, Haidian District, Beijing 100089 Patentee after: Desert Tianyu Co.,Ltd. Address before: 518000 No. 601, No. 5, Sixth Lane, Longtang West, Minzhi Street, Longhua District, Shenzhen City, Guangdong Province Patentee before: Shenzhen Wanzhida Technology Co.,Ltd. Effective date of registration: 20211216 Address after: 518000 No. 601, No. 5, Sixth Lane, Longtang West, Minzhi Street, Longhua District, Shenzhen City, Guangdong Province Patentee after: Shenzhen Wanzhida Technology Co.,Ltd. Address before: 110168 Liaoning province Shenyang Hunnan Hunnan Road No. 9 Patentee before: SHENYANG JIANZHU University |