CN106836166A - 大型海上人工岛模块现场安装场地规划方法 - Google Patents
大型海上人工岛模块现场安装场地规划方法 Download PDFInfo
- Publication number
- CN106836166A CN106836166A CN201710010797.7A CN201710010797A CN106836166A CN 106836166 A CN106836166 A CN 106836166A CN 201710010797 A CN201710010797 A CN 201710010797A CN 106836166 A CN106836166 A CN 106836166A
- Authority
- CN
- China
- Prior art keywords
- module
- contact
- contact classes
- classes
- degree
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B17/00—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
本发明公开了大型海上人工岛模块现场安装场地规划方法,包括以下步骤:(1)根据海上人工岛上设置的各模块在生产工艺流程中的联系紧密程度划分各模块彼此之间的生产联系等级;(2)记录两两模块之间的生产联系等级;(3)根据各模块之间的距离划分各模块间的距离联系等级;(4)记录两两模块之间的距离联系等级;(5)根据两两模块之间的生产联系等级和距离联系等级计算各模块的总关系分值;(6)将得分最高的场地规划方法作为最终的场地规划图。采用本方法,可以较大提高人工岛上场地的利用率。
Description
技术领域
本发明涉及场地规划方法,尤其涉及大型海上人工岛模块现场安装场地规划方法。
背景技术
在大型海上人工岛模块现场安装过程中,其主要模块有外输泵模块、闭排罐模块、三相分离器模块、换热器、计量装置模块、变电所模块、蒸汽锅炉模块、生活楼模块、应急发电间模块,由于人工岛模块较多,且现阶段对各模块的安装没有明确地规划,因此导致人工岛上空间的利用率不高,且各模块之间不能有效地联系,导致石油、天然气开采工艺效率的降低和管线等材料消耗量的增加,从而增加生产成本。
发明内容
本发明的目的在于克服已有的技术缺陷,提供一种不但可以提高人工岛上场地的利用率,而且可以通过合理的布局使得油气开采效率提高并且生产成本降低的大型海上人工岛模块现场安装场地规划方法。
为了达到上述目的,本发明采用的技术方案为:
大型海上人工岛模块现场安装场地规划方法,包括以下步骤:
(1)根据海上人工岛上设置的各模块在生产工艺流程中的联系紧密程度划分各模块彼此之间的生产联系等级;
(2)记录两两模块之间的生产联系等级;
(3)根据各模块之间的距离划分各模块间的距离联系等级;
(4)记录两两模块之间的距离联系等级;
(5)根据两两模块之间的生产联系等级和距离联系等级计算各模块的总关系分值,具体方法如下:
(a)采用专家打分法确定生产联系等级和距离联系等级相互关系的权重;
(b)量化生产联系等级和距离联系等级,然后根据两两模块之间的生产联系等级和距离联系等级以及分配的权重通过公式计算其综合相互关系程度,并规定模块自身间的综合相互关系程度值为0;最后根据各模块间的综合相互关系程度,计算每个模块的总关系分值;
所述的公式为:V=xi+yj,式中:V为两两模块间综合相互关系程度值;x为该两模块之间生产联系等级程度量化值;y为该两模块之间距离联系等级程度量化值;i、j为该两模块之间生产联系等级和距离联系等级分配的权重,且i+j=1;
(6)根据每个模块的总关系分值,按总分值的大小顺序对各模块进行排序,将总分值差值最小的两个模块靠近布置;若存在分值相同的情况,则采用模糊综合评价法通过计算得到获得相同分值情况下每种人工岛模块场地规划图的评价分数,将得分最高的场地规划方法作为最终的场地规划图。
采用本场地规划方法,可以对人工岛上各个模块的位置进行规划,从而可以较大提高人工岛上场地的利用率,以及通过合理的布局带来油气开采效率的提高和生产成本的降低。
附图说明
图1是本发明大型海上人工岛模块现场安装场地规划方法中人工岛模块物流相关表;
图2是本发明大型海上人工岛模块现场安装场地规划方法中人工岛模块非物流相关表;
图3是本发明大型海上人工岛模块现场安装场地规划方法中人工岛模块间综合相互关系表;
图4是本发明大型海上人工岛模块现场安装场地规划方法中人工岛模块场地规划评价模型。
具体实施方式
下面结合具体实施方式对本发明作进一步说明。
如附图所示的大型海上人工岛模块现场安装场地规划方法,包括以下步骤:
(1)根据海上人工岛上设置的各模块在生产工艺流程中的联系紧密程度划分各模块彼此之间的生产联系等级,具体可以根据在石油、天然气开采工艺流程中各模块在生产中联系的紧密程度,对模块生产联系等级进行划分。可以采用A、B、C、D、E五个字母来代表生产联系强度的五个等级,其强度依次为模块联系程度超高、模块联系程度较高、模块联系程度一般、模块联系程度较弱、模块联系程度可忽略;
(2)记录两两模块之间的生产联系等级,可以形成模块物流相关表,如图1所示,可以在相应的格内填入两两模块之间相互联系的等级;
(3)根据各模块之间的距离划分各模块间的距离联系等级,划分方法可以同生产联系等级划分,将距离联系等级划分为A、B、C、D、E五个级别,等级强度由强越来越弱,不同的强度等级对应两模块之间不同的距离,该五个等级代表的含义依次为:两模块绝对要求靠近;两模块关系比较密切,需要靠近;两模块关系一般密切,一般靠近;两模块关系不密切,可以靠近;两模块关系排斥,不需要靠近;而在海上人工岛上设置的各模块安装中影响其距离联系等级划分的因素主要有:1)联系频繁程度;2)工艺流程;3)模块间相互影响程度;4)方便监管;5)环境干扰程度;
(4)记录两两模块之间的距离联系等级,可以形成模块非物流相关表,如图2所示,可以在相应的格内填入两两模块之间相互联系的等级,其中在每个小格中虚线上部分填写密切程度等级,而虚线下部分填写确定该等级原因的序号,(步骤三中的影响距离联系等级划分的因素);
(5)根据两两模块之间的生产联系等级和距离联系等级计算各模块的总关系分值,具体方法如下:
(a)采用专家打分法确定生产联系等级和距离联系等级相互关系的权重,以确定生产联系等级和距离联系等级的相对重要性;专家在打分时可以根据两模块间的生产联系程度等级进行确定,生产联系程度高的,其生产联系等级与距离联系等级之间的权重比就赋予的相对大一些,反之,权重比就相对小一些;
(b)量化生产联系等级和距离联系等级,然后根据两两模块之间的生产联系等级和距离联系等级以及分配的权重通过公式计算其综合相互关系程度,并规定模块自身间的综合相互关系程度值为0;最后根据各模块间的综合相互关系程度,计算每个模块的总关系分值,在此过程中可以形成如图3所示的模块间综合相互关系表。
所述的公式为:V=xi+yj,式中:V为两两模块间综合相互关系程度值;x为该两模块之间生产联系等级程度量化值;y为该两模块之间距离联系等级程度量化值;i、j为该两模块之间生产联系等级和距离联系等级分配的权重,且i+j=1。
下面举一个例子加以说明:为了方便计算,将生产联系等级和距离联系等级进行量化,如A=a、B=b、C=c、D=d、E=e,其中a>b>c>d>e,然后根据两两模块之间的生产联系等级和距离联系等级程度以及分配的权重计算其综合相互关系程度,并规定模块自身间的综合相互关系程度值为0。具体方法为:
图中假设海上人工岛上设置有9个模块,以应急发电模块和人工岛模块之间生产联系等级为E,距离联系等级为E,且为两者分配的权重为m:n,因此,应急发电模块和人工岛模块之间的综合相互关系程度为V=e×m+e×n。
(6)根据每个模块的总关系分值,按总分值的大小顺序对各模块进行排序,将总分值差值最小的两个模块靠近布置;若存在分值相同的情况,会产生多种人工岛模块场地规划图,则采用模糊综合评价法对各种情形进行评价决策,通过计算得到获得相同分值情况下每种人工岛模块场地规划图的评价分数,将得分最高的场地规划方法作为最终的场地规划图。
模糊综合评价法的具体方法为:
(a)确定评价指标:
由于整个人工岛模块的规划还与场地利用率、模块间间距、场内运输能力、建设成本、作业环境、安全生产有关,因此可以将这些因素作为评价指标,形成如图4所示的评价模型;
(b)计算评价模型:
由于模糊综合评价法的计算理论已经很成熟,因此其具体计算过程详见2010年5月华南理工大学硕士论文“基于AHP的模糊综合评价方法研究及应用”,通过计算可以得到获得相同分值情况下每种人工岛模块场地规划图的评价分数,将得分最高的场地规划方法作为最终的场地规划图。
Claims (2)
1.大型海上人工岛模块现场安装场地规划方法,其特征在于包括以下步骤:
(1)根据海上人工岛上设置的各模块在生产工艺流程中的联系紧密程度划分各模块彼此之间的生产联系等级;
(2)记录两两模块之间的生产联系等级;
(3)根据各模块之间的距离划分各模块间的距离联系等级;
(4)记录两两模块之间的距离联系等级;
(5)根据两两模块之间的生产联系等级和距离联系等级计算各模块的总关系分值,具体方法如下:
(a)采用专家打分法确定生产联系等级和距离联系等级相互关系的权重;
(b)量化生产联系等级和距离联系等级,然后根据两两模块之间的生产联系等级和距离联系等级以及分配的权重通过公式计算其综合相互关系程度,并规定模块自身间的综合相互关系程度值为0;最后根据各模块间的综合相互关系程度,计算每个模块的总关系分值;
所述的公式为:V=xi+yj,式中:V为两两模块间综合相互关系程度值;x为该两模块之间生产联系等级程度量化值;y为该两模块之间距离联系等级程度量化值;i、j为该两模块之间生产联系等级和距离联系等级分配的权重,且i+j=1;
(6)根据每个模块的总关系分值,按总分值的大小顺序对各模块进行排序,将总分值差值最小的两个模块靠近布置;若存在分值相同的情况,则采用模糊综合评价法通过计算得到获得相同分值情况下每种人工岛模块场地规划图的评价分数,将得分最高的场地规划方法作为最终的场地规划图。
2.根据权利要求1所述的大型海上人工岛模块现场安装场地规划方法,其特征在于:在海上人工岛上设置的各模块安装中影响其距离联系等级划分的因素主要有联系频繁程度、工艺流程、模块间相互影响程度、方便监管以及环境干扰程度。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710010797.7A CN106836166B (zh) | 2017-01-06 | 2017-01-06 | 大型海上人工岛模块现场安装场地规划方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710010797.7A CN106836166B (zh) | 2017-01-06 | 2017-01-06 | 大型海上人工岛模块现场安装场地规划方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106836166A true CN106836166A (zh) | 2017-06-13 |
CN106836166B CN106836166B (zh) | 2018-11-20 |
Family
ID=59118287
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710010797.7A Active CN106836166B (zh) | 2017-01-06 | 2017-01-06 | 大型海上人工岛模块现场安装场地规划方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106836166B (zh) |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2195531C1 (ru) * | 2001-06-27 | 2002-12-27 | Российское открытое акционерное общество энергетики и электрификации | Способ возведения крупноблочного сооружения в прибрежной зоне водоема и плавкомплекс для осуществления способа |
CN202210356U (zh) * | 2011-09-08 | 2012-05-02 | 浙江海洋学院 | 跨海大桥防撞预警系统 |
CN103074878A (zh) * | 2013-02-05 | 2013-05-01 | 宏华海洋油气装备(江苏)有限公司 | 一种人工岛平台的构筑方法 |
CN104866704A (zh) * | 2015-03-21 | 2015-08-26 | 北京化工大学 | 一种基于模糊综合评判的离心泵状态评估方法 |
CN104988881A (zh) * | 2015-05-25 | 2015-10-21 | 南通中远船务工程有限公司 | 一种海洋工程装备模块建造工艺 |
CN105654232A (zh) * | 2015-12-24 | 2016-06-08 | 大连陆海科技股份有限公司 | 基于多维度空间融合的海岸监控与防御决策系统及方法 |
CN106012973A (zh) * | 2016-07-15 | 2016-10-12 | 海南海博海洋产业发展有限公司 | 一种玄武岩纤维制固沙消浪型吹填岛礁护坡 |
-
2017
- 2017-01-06 CN CN201710010797.7A patent/CN106836166B/zh active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2195531C1 (ru) * | 2001-06-27 | 2002-12-27 | Российское открытое акционерное общество энергетики и электрификации | Способ возведения крупноблочного сооружения в прибрежной зоне водоема и плавкомплекс для осуществления способа |
CN202210356U (zh) * | 2011-09-08 | 2012-05-02 | 浙江海洋学院 | 跨海大桥防撞预警系统 |
CN103074878A (zh) * | 2013-02-05 | 2013-05-01 | 宏华海洋油气装备(江苏)有限公司 | 一种人工岛平台的构筑方法 |
CN104866704A (zh) * | 2015-03-21 | 2015-08-26 | 北京化工大学 | 一种基于模糊综合评判的离心泵状态评估方法 |
CN104988881A (zh) * | 2015-05-25 | 2015-10-21 | 南通中远船务工程有限公司 | 一种海洋工程装备模块建造工艺 |
CN105654232A (zh) * | 2015-12-24 | 2016-06-08 | 大连陆海科技股份有限公司 | 基于多维度空间融合的海岸监控与防御决策系统及方法 |
CN106012973A (zh) * | 2016-07-15 | 2016-10-12 | 海南海博海洋产业发展有限公司 | 一种玄武岩纤维制固沙消浪型吹填岛礁护坡 |
Non-Patent Citations (1)
Title |
---|
闻鑫: ""月东B人工岛上部生产设施模块化的应用"", 《城市建设理论研究(电子版)》 * |
Also Published As
Publication number | Publication date |
---|---|
CN106836166B (zh) | 2018-11-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Pereira et al. | A decomposition approach to automated generation/transmission expansion planning | |
CN103903073B (zh) | 一种含分布式电源及储能的微电网优化规划方法及系统 | |
CN102025153B (zh) | 一种中压配电网最大供电能力精确计算方法 | |
CN105205611A (zh) | 一种配电网网格化规划的网格划分方法 | |
CN103955777A (zh) | 光伏发电接入配电网方案设计与分析评估辅助系统 | |
Grube et al. | An option for stranded renewables: electrolytic-hydrogen in future energy systems | |
CN104281737A (zh) | 一种海上风电场集电系统拓扑结构选型方法 | |
CN101976842A (zh) | 基于电气分区的关键断面自动获取方法 | |
CN103577901A (zh) | 潮间带风电接入电网的方法 | |
CN104504607A (zh) | 一种基于模糊聚类算法的光伏电站故障诊断方法 | |
CN104732349A (zh) | 一种电网规划方法 | |
CN102709909A (zh) | 风力发电接入时的主动配电网可靠性评估方法 | |
CN105096207A (zh) | 一种基于层次分析法的重要电力用户供电可靠性评估方法 | |
CN106469421A (zh) | 一种风电/光伏发电功率汇集拓扑的评估方法及系统 | |
CN106026079B (zh) | 海上风电场集电系统拓扑结构综合评估方法 | |
CN103887792B (zh) | 一种含分布式电源的低压配电网建模方法 | |
CN106159998A (zh) | 可再生能源微电网优化调度系统 | |
CN105488584A (zh) | 一种孤岛混合可再生能源系统的多目标组合优化配置方法 | |
CN105305488A (zh) | 一种考虑新能源并网对输电网利用率影响的评价方法 | |
CN117277307A (zh) | 基于数据驱动的电力系统有功频率控制方法及系统 | |
CN115660343A (zh) | 面向碳中和的城市综合能源发展规划方法 | |
CN104915889A (zh) | 一种基于日负荷曲线在线获取综合负荷模型参数的方法 | |
CN104063757B (zh) | 一种适应电网不同发展阶段的变电站电气主接线评估方法 | |
CN105844359A (zh) | 一种基于可靠性成本效益分析的城市电网结构优化方法 | |
CN103296678B (zh) | 一种在线大电网恢复辅助决策方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |