CN106816848B - The dark cable duct of assembled - Google Patents

The dark cable duct of assembled Download PDF

Info

Publication number
CN106816848B
CN106816848B CN201710246643.8A CN201710246643A CN106816848B CN 106816848 B CN106816848 B CN 106816848B CN 201710246643 A CN201710246643 A CN 201710246643A CN 106816848 B CN106816848 B CN 106816848B
Authority
CN
China
Prior art keywords
cable duct
dark
bright
cable
cushion cap
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710246643.8A
Other languages
Chinese (zh)
Other versions
CN106816848A (en
Inventor
张若玮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Rizhao Ruiyi e-commerce industry Co., Ltd
Original Assignee
张若玮
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 张若玮 filed Critical 张若玮
Priority to CN201710246643.8A priority Critical patent/CN106816848B/en
Publication of CN106816848A publication Critical patent/CN106816848A/en
Application granted granted Critical
Publication of CN106816848B publication Critical patent/CN106816848B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G9/00Installations of electric cables or lines in or on the ground or water
    • H02G9/06Installations of electric cables or lines in or on the ground or water in underground tubes or conduits; Tubes or conduits therefor

Abstract

The present invention provides a kind of dark cable duct of assembled, the fixed powerful connection mode of construction, sealing structure, bucketing screw of its industry type, the corresponding underground foundation measure taken along with adaptation to local conditions, prevent from often occurring tilting using cable duct soon, settle, deform, ponding the problems such as, and water resistance is more preferably.The dark cable duct of assembled includes underground foundation facility, cable duct assembly, it is characterized in that:Cable duct assembly is located in the ground above infrastructure;The cable duct assembly, between dark cable duct and dark cable duct, between dark cable duct and bright cable duct, embedded shape of the mouth as one speaks sealing element between dark cable duct and intercommunication cable duct, be connected after the fixation of bucketing screw;Segmentation sets bright cable duct in cable duct assembly, convenient for the laying and maintenance of cable.

Description

The dark cable duct of assembled
Technical field
The present invention relates to a kind of assembly type cable slots.
Background technology
Cable duct has brick, armored concrete cable respectively according to buried depth, load, level of ground water situation at present The types such as ditch, with the continuous development of power engineering, the requirement to duration, safety construction is continuously improved, both above electricity The defects of cable ditch, is gradually notable.
1) above two cable duct Contraction in Site program is various, and long in time limit, resource cost is larger, causes live confusion Increase with security risk, management difficulty increases, and is unfavorable for the development of safety construction.
2) cost of above two cable duct is above prefabricated assembled cable trench, calculates according to 1 meter of cable duct, brick table About 700 yuan/meter of cost of face plastering ditch body, about 900 yuan/meter of armored concrete cable duct cost.
3) in comparison, brick cable duct due to the technological requirement of brick plastering it is higher, the quality of plastering is generally relatively low, hold Easily there is common quality defect;Then there are formwork difficulty, ditch body concrete surface smoothness is difficult to protect cast-in-situ steel reinforced concrete cable duct Card.
4) above two cable duct due to resource cost it is more, and situ wet operation program is more, long in time limit, security civilization is applied Work is poor, does not adapt to the needs of current power engineering development." amphitypy one is changed " is advocated according to Guo Wang companies, i.e., it is resource-effective Type, environmentally friendly, industrialized requirement, it will be following developing direction to carry out prefabricated assembled cable trench.
5) for current prefabricated assembled cable trench since floor space is less than normal and width is partially narrow, overall stability is poor, because Often there is the problems such as inclination, sedimentation, deformation in ground variation;Especially itself Anti-inclining scarce capacity near rivers, is constructed and is opened It is more serious that larger its problem of location is flowed in the locations such as digging, i.e. underground.
6)Since ground changes, using cable duct ditch bottom surface soon often out-of-flatness and ponding, this is also current Cable duct common fault.
Therefore, on the basis of existing cable ditch, research and development is also needed to be resistant to tilt, settle, local deformation, ponding cable Ditch.
Invention content
For it is above-mentioned the problem of, the present invention provides a kind of dark cable duct of assembled, the construction of its industry type, sealing structure, right The fixed powerful connection mode of screw is struck, along with the corresponding underground foundation measure that adaptation to local conditions is taken, prevents from using soon The problems such as cable duct often occurs tilting, settles, deforms, ponding, and water resistance is more preferably.
The invention is realized in this way:The dark cable duct of assembled includes underground foundation facility, cable duct assembly, feature It is:Cable duct assembly is located in the ground above infrastructure;The cable duct assembly, between dark cable duct and dark cable duct, Secretly embedded shape of the mouth as one speaks sealing element between cable duct and bright cable duct, between dark cable duct and intercommunication cable duct, is fixed through bucketing screw After be connected;Segmentation sets bright cable duct in cable duct assembly, convenient for the laying and maintenance of cable;
The dark cable duct, prefabricated dark cable duct are in industry type, set cable bearer in it, its peripheral hardware anti-settling tilts Extension edge A, anti-settling, inclined extension edge A both ends set three arms of angle and connect with the ontology of dark cable duct;
The bright cable duct, prefabricated bright cable duct are in industry type, set cable bearer, water-proof type cover board support in it, bright Set up defences above cable duct ability of swimming cover board, its peripheral hardware anti-settling, inclined extension edge B, anti-settling, inclined extension edge B both ends If three arms of angle are connect with the ontology of bright cable duct;
The underground foundation facility, it includes mountain type cushion cap, rectangle cushion cap;Stake is set below the strip cushion cap of mountain type cushion cap Head is Anti-inclining pile crown among it;The quadrangle pile crown of the rectangle frame cushion cap of rectangle cushion cap, the under-filled stone of rectangle cushion cap, Rubble, coarse sand are filled above, it is smooth after being then compacted.
Dark cable duct, bright cable duct bottom set rhone.
In the good location of geological state, cancel underground foundation facility in order to cost-effective, cable duct assembly is directly arranged in Above processed ground.
The present invention effect be:
1. prefabricated cable duct is constructed in industry type, since floor space is larger and wider, overall stability is much better, prevents Tilt capability increases substantially, and along with sealing structure, the fixed powerful connection mode of bucketing screw, makes its Anti-inclining, sinks Drop, deformability significantly improve;In the good location of geological state, cancel underground foundation facility, cable duct in order to cost-effective Assembly is laid immediately on above processed ground.
2. the underground foundation facility including mountain type cushion cap, rectangle cushion cap, can be according to geological state adaptation to local conditions pointedly Take, especially near rivers, the undergrounds such as construction and excavation flow larger location, can specific aim effectively set up defences.
3. assembly type cable slot solves existing brick plastering formula and armored concrete formula cable duct wet construction program is numerous and diverse The problem of, have the characteristics that the construction period is extremely short, saves resource, is easy for construction.
4. assembly type cable slot bottom of trench surfacing, the bottom of cable duct sets many places rhone again, is conducive to exclude product Water has well solved the common fault of bottom of trench ponding.
5. assembly type cable slot integral strength is high, durability is good.
6. segmentation sets bright cable duct in whole cable duct assembly, convenient for the laying and maintenance of cable.
Description of the drawings
The present invention is further described with reference to the accompanying drawings and examples.
Fig. 1 is one of stereoscopic schematic diagram of the dark cable duct of assembled of the present invention.
Fig. 2 is the two of the stereoscopic schematic diagram of the dark cable duct of assembled of the present invention.
In figure:1. mountain type cushion cap, 2. dark cable ducts, 3. extension edge A, 4. bright cable ducts, 5. extension edge B, 6. intercommunications Cable duct, 7. pile crowns, 8. rectangle cushion caps, 9. 4 jiaos of pile crowns.
Specific embodiment
As shown in the figure, the dark cable duct of assembled includes underground foundation facility, cable duct assembly, cable duct assembly is located in the ground Above infrastructure.Between dark cable duct 2 in cable duct assembly and dark cable duct 2, dark cable duct 2 and bright cable duct 4 it Between, embedded shape of the mouth as one speaks sealing element between dark cable duct 2 and intercommunication cable duct 6, be connected after the fixation of bucketing screw;In cable duct Segmentation sets bright cable duct 4 in assembly, convenient for the laying and maintenance of cable.
The dark cable duct 2, prefabricated dark cable duct 2 are in industry type, set cable bearer in it, for supporting cable;It Peripheral hardware anti-settling, inclined extension edge A 3, anti-settling, inclined extension edge A 3 both ends set three arms of angle and dark cable duct 2 Ontology connects.
The bright cable duct 4, prefabricated bright cable duct 4 are in industry type, set cable bearer, water-proof type cover board support in it, Bright cable duct 4 is set up defences ability of swimming cover board above, its peripheral hardware anti-settling, inclined extension edge B 5, anti-settling, inclined extension edge B 5 Both ends set three arms of angle and connect with the ontology of bright cable duct 4.
Dark cable duct 2, bright cable duct 4 bottom set rhone, and connect with sump, drainage system.
Underground foundation facility it include mountain type cushion cap 1, rectangle cushion cap 8;Pile crown 7 is set below the strip board of mountain type cushion cap 1, Centre is Anti-inclining pile crown, plays increasing surely, even if the appearance such as ground construction excavation of both sides are significantly fluctuated, it will not be very Sedimentation and inclination, just more it is over after on ground, backfill is restored;The quadrangle pile crown 9 of the rectangle frame cushion cap of rectangle cushion cap 8, rectangle is held The under-filled stone of platform 8 fills rubble, coarse sand above, smooth after being then compacted, since its good integrity, bearing surface are again big, It is highly suitable near rivers, the location for the geological stability difference that level of ground water is high.
In the good location of geological state, cancel underground foundation facility in order to cost-effective, cable duct assembly is directly arranged in Above processed ground.
The structure of the present invention is not limited to form described in embodiment, and those of ordinary skill in the art make according to the present invention Further expand each fall within protection scope of the present invention.
The dark cable duct of assembled of the present invention can implement mechanized construction, and short time limit, long lifespan, effect are good, suitable for it is long away from From laying.

Claims (3)

1. a kind of dark cable duct of assembled, it includes underground foundation facility, cable duct assembly, it is characterized in that:Cable duct assembly is set Above underground foundation facility;The cable duct assembly, dark cable duct(2)With dark cable duct(2)Between, dark cable duct (2)With bright cable duct(4)Between, dark cable duct(2)With intercommunication cable duct(6)Between embedded shape of the mouth as one speaks sealing element, through bucketing screw It is connected after fixation;Segmentation sets bright cable duct in cable duct assembly(4);
The dark cable duct(2), prefabricated dark cable duct(2)Cable bearer is set in industry type, in it, its peripheral hardware anti-settling is inclined Oblique extension edge A(3), anti-settling, inclined extension edge A(3)Both ends set three arms of angle and dark cable duct(2)Ontology connection;
The bright cable duct(4), prefabricated bright cable duct(4)Cable bearer, water-proof type cover board support are set in industry type, in it, Bright cable duct(4)It sets up defences above ability of swimming cover board, its peripheral hardware anti-settling, inclined extension edge B(5), anti-settling, inclined extension edge B(5)Both ends set three arms of angle and bright cable duct(4)Ontology connection;
The underground foundation facility, it includes mountain type cushion cap(1), rectangle cushion cap(8);Mountain type cushion cap(1)Strip cushion cap under Face sets pile crown(7), it is Anti-inclining pile crown among it;Rectangle cushion cap(8)Rectangle frame cushion cap quadrangle pile crown(9), rectangle cushion cap (8)Under-filled stone, above fill rubble, coarse sand, then be compacted after it is smooth.
2. the dark cable duct of assembled according to claim 1, it is characterized in that:Dark cable duct(2), bright cable duct(4)Bottom Portion sets rhone.
3. the dark cable duct of assembled according to claim 1, it is characterized in that:In the good location of geological state, in order to save Cost and cancel underground foundation facility, cable duct assembly is directly arranged in above processed ground.
CN201710246643.8A 2017-04-16 2017-04-16 The dark cable duct of assembled Active CN106816848B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710246643.8A CN106816848B (en) 2017-04-16 2017-04-16 The dark cable duct of assembled

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710246643.8A CN106816848B (en) 2017-04-16 2017-04-16 The dark cable duct of assembled

Publications (2)

Publication Number Publication Date
CN106816848A CN106816848A (en) 2017-06-09
CN106816848B true CN106816848B (en) 2018-06-29

Family

ID=59116006

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710246643.8A Active CN106816848B (en) 2017-04-16 2017-04-16 The dark cable duct of assembled

Country Status (1)

Country Link
CN (1) CN106816848B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111463738A (en) * 2020-06-01 2020-07-28 合肥智瑞工程科技有限公司 Cable trench structure based on assembled
CN111682456A (en) * 2020-06-29 2020-09-18 中国化学工程第十一建设有限公司 Desert environment cable laying method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2005013450A1 (en) * 2003-07-30 2005-02-10 Prysmian Cavi E Sistemi Energia S.R.L. Method for shielding the magnetic field generated by an electrical power transmission line and electrical power transmission line so shielded
CN203787920U (en) * 2014-04-10 2014-08-20 江苏神马电力股份有限公司 Composite material cable trench
CN203983929U (en) * 2014-07-23 2014-12-03 新疆拓源节能技术开发有限责任公司 Assemble type underground cable ditch based on city integrated wiring
CN205610169U (en) * 2016-05-20 2016-09-28 温州电力设计有限公司 Cable trough box
CN205863876U (en) * 2016-08-10 2017-01-04 上海国孚电力设计工程股份有限公司 Steel cable duct device
CN206004274U (en) * 2016-09-12 2017-03-08 广州电力设计院 Cable groove structure and cabling arrangements
CN106558861A (en) * 2016-11-04 2017-04-05 安徽华电工程咨询设计有限公司 A kind of multi-functional cable ditch

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2005013450A1 (en) * 2003-07-30 2005-02-10 Prysmian Cavi E Sistemi Energia S.R.L. Method for shielding the magnetic field generated by an electrical power transmission line and electrical power transmission line so shielded
CN203787920U (en) * 2014-04-10 2014-08-20 江苏神马电力股份有限公司 Composite material cable trench
CN203983929U (en) * 2014-07-23 2014-12-03 新疆拓源节能技术开发有限责任公司 Assemble type underground cable ditch based on city integrated wiring
CN205610169U (en) * 2016-05-20 2016-09-28 温州电力设计有限公司 Cable trough box
CN205863876U (en) * 2016-08-10 2017-01-04 上海国孚电力设计工程股份有限公司 Steel cable duct device
CN206004274U (en) * 2016-09-12 2017-03-08 广州电力设计院 Cable groove structure and cabling arrangements
CN106558861A (en) * 2016-11-04 2017-04-05 安徽华电工程咨询设计有限公司 A kind of multi-functional cable ditch

Also Published As

Publication number Publication date
CN106816848A (en) 2017-06-09

Similar Documents

Publication Publication Date Title
KR100970766B1 (en) Process for reinforcing base and preventing wash-out of earth under the bridges
Grantz Immersed tunnel settlements. Part 1: nature of settlements
CN103981898A (en) Integral open-excavation node top-down underground engineering construction method
CN102352590A (en) Method for splicing highfill roadbed by adopting pile-sheet retaining wall
CN105672451A (en) Method for laying percolation type rainwater drainage pipes in Sponge City Construction
CN107151950A (en) The construction method of desert area railway underground water route moat
CN103669374A (en) Combined supporting construction method of steel sheet pile used in silt soil slope
CN110397050B (en) Beam-anchor type light drainage retaining wall and construction method thereof
CN203808088U (en) Gabion gully detention structure for top of hydropower station slag yard
CN104846781A (en) Ecological interlocking block and ecological interlocking block type slope protection construction method
CN106816848B (en) The dark cable duct of assembled
CN108221528B (en) Roadbed building overlapping structure and construction method
CN110004842A (en) A kind of fabricated culvert tube coupling based on centrifugal casting integrally prepares and installation method
CN109706952A (en) Large-scale well-sinking construction method
CN106877266B (en) The bright cable duct of assembled
CN105544622A (en) Floating resisting device, and seepage insulation device and drainage path checking device thereof for underground building
CN208981282U (en) A kind of high earthquake territory concrete face rockfill dam dam crest structure
CN205134342U (en) Large -tonnage list double -walled combines steel cofferdam
CN110144834A (en) A kind of slab culvert construction technology
CN203716064U (en) Roadbed sewer convenient for dredging
CN110453687B (en) Protection structure of subway station foundation pit excavation pipeline and construction method
CN107288120A (en) A kind of stabilization by drainage structure of new and old roadbed in the firm splicing of watersplash
CN108316237B (en) Revetment retaining wall
CN103114605B (en) Anti-seepage drainage layer structure and construction method
CN104846837A (en) Construction method for ultra-deep well pit in surface drainage foundation pit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20211221

Address after: Workshop A4 and A6, electronic information industrial park, Gaoxin 7th Road, Donggang District, Rizhao City, Shandong Province

Patentee after: Rizhao Ruiyi e-commerce industry Co., Ltd

Address before: 315040, room 24, Lane 165, Lane 1001, rainbow North Road, Jiangdong District, Zhejiang, Ningbo

Patentee before: Zhang Ruowei