CN106812126B - A kind of high-precision offshore platform spud leg assemble method and its spud leg being assembled into - Google Patents

A kind of high-precision offshore platform spud leg assemble method and its spud leg being assembled into Download PDF

Info

Publication number
CN106812126B
CN106812126B CN201710024317.2A CN201710024317A CN106812126B CN 106812126 B CN106812126 B CN 106812126B CN 201710024317 A CN201710024317 A CN 201710024317A CN 106812126 B CN106812126 B CN 106812126B
Authority
CN
China
Prior art keywords
spud leg
guide plate
leg section
plate
coaming
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710024317.2A
Other languages
Chinese (zh)
Other versions
CN106812126A (en
Inventor
吴平平
李光远
陆军
张静波
马振军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Jing Yin Ocean Engineering Co Ltd
Original Assignee
Guangdong Jing Yin Ocean Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Jing Yin Ocean Engineering Co Ltd filed Critical Guangdong Jing Yin Ocean Engineering Co Ltd
Priority to CN201710024317.2A priority Critical patent/CN106812126B/en
Publication of CN106812126A publication Critical patent/CN106812126A/en
Application granted granted Critical
Publication of CN106812126B publication Critical patent/CN106812126B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0039Methods for placing the offshore structure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0056Platforms with supporting legs
    • E02B2017/0065Monopile structures

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Wind Motors (AREA)

Abstract

The invention discloses a kind of high-precision offshore platform spud leg assemble method and its spud leg being assembled into, main body is the columnar bolt-type spud leg of octagon, and spud leg is divided into multistage spud leg section and is assembled, included the following steps from bottom to top:Step A manufactures spud leg section part, and coaming plate is welded on the coaming plate position level edge of platform partition board by step B, to be assembled into the first spud leg section component;Step C manufactures moulding bed, is placed on the central axes of moulding bed and fix one piece of guide plate.The columnar bolt-type spud leg of octagon is divided into multistage from bottom to top, carries out being assembled into spud leg section independently of each other, finally multiple spud leg sections is closed up, construction environment is improved, shortens construction period, improve producing efficiency.It need to only realize the accurate positionin to the guide plate on moulding bed, you can realize that the accurate positionin to entire spud leg section assembles, not only kept high assembly precision, but also reduce positioning and assembling difficulty, greatly improve packaging efficiency, reduce assembling input cost.

Description

A kind of high-precision offshore platform spud leg assemble method and its spud leg being assembled into
Technical field
The present invention relates to ocean engineering field more particularly to a kind of high-precision offshore platform spud leg assemble method and its groups The spud leg dressed up.
Background technology
Spud leg is the important component of offshore work platform, be used to support the weight of upper hull and bear wind, wave, Environmental loads, the structure types such as stream are mainly cylindrical leg and truss framed leg, and the lifting system of spud leg mainly has hydraulic pressure Bolt-type and pinion and-rack.Currently, being mostly to make cylindrical leg, the assemble method of cylindrical leg is complex, needs The a large amount of template of pre-production is to be positioned and be spliced to cylindrical leg component, to assembling essence in complicated assembling process The control of degree is more difficult, and then seriously affects the assembling quality and packaging efficiency of spud leg.
Invention content
A kind of without making spud leg locating template it is an object of the invention to propose, assembly precision controllability height, assembling is more For convenience of efficiently high-precision offshore platform spud leg assemble method.
A kind of without making spud leg locating template it is an object of the invention to propose, assembly precision controllability height, assembling is more For convenience of efficiently high-precision spud leg.
For this purpose, the present invention uses following technical scheme:
A kind of high-precision offshore platform spud leg assemble method, main body be the columnar bolt-type spud leg of octagon, spud leg by It is divided into multistage spud leg section upwards down to be assembled, includes the following steps:
Step A manufactures spud leg section part, and the spud leg section part includes platform partition board, coaming plate and guide plate, the platform The side of partition board is octagon;The platform partition board includes that four coaming plate position level edges and four guide plates position bevelled edge Edge, coaming plate position level edge and guide plate positioning bevelled edge edge are spaced apart in the side of the platform partition board;Manufacture Guide plate include multiple pin holes, the pin hole is longitudinally disposed at evenly and at intervals on the guide plate;
Coaming plate is welded on the coaming plate position level edge of platform partition board by step B, to be assembled into the first spud leg section group Part;
Step C manufactures moulding bed, is placed on the central axes of moulding bed and fix one piece of guide plate;Then, by step B First spud leg section component of assembling overturns to the wherein one guide plate positioning bevelled edge edge of platform partition board and is horizontal Until;Then, the first spud leg section component after overturning is sling to the top of moulding bed;Wherein one guiding of last platform partition board The guide plate that plate positions on bevelled edge edge and moulding bed is aligned and welds, to be assembled into the second spud leg section component;
Step D, to the second spud leg section components welding guide plate of step C, the i.e. guide plate to the remaining item of platform partition board Bevelled edge is positioned along welding guide plate, to be assembled into spud leg section, in the spud leg section up and down two pieces of guide plates same It is mutually parallel on plumb line and with ground, and the two pieces of guide plates in left and right are mutually perpendicular in the same horizontal line and with ground;
Multiple spud leg sections are hung and on moulding bed close up being assembled into spud leg by step E.
Preferably, further include coaming plate fixing rib, the coaming plate fixing rib is longitudinally welded in the inside of coaming plate;
Accordingly, the platform partition board further includes coaming plate installation groove, and the coaming plate installation groove is set to coaming plate positioning Horizontal edge.
Preferably, the step B include it is following step by step:
Step B1, one block of coaming plate is horizontally-arranged;
Several pieces of platform partition boards are erected on coaming plate by step B2, and the wherein one coaming plate positioning of platform partition board Horizontal edge and coaming plate alignment, while the coaming plate fixing rib on coaming plate is inserted into coaming plate installation groove;Then, by coaming plate fixing rib It is welded in coaming plate installation groove, is fixed on the coaming plate with making the platform divider upright;
Step B3 welds coaming plate, and the coaming plate toward the coaming plate position level edge of remaining of the platform partition board Coaming plate fixing rib be welded in corresponding coaming plate installation groove, to be assembled into the first spud leg section component.
Preferably, the moulding bed of the step C manufactures includes moulding bed pedestal, a plurality of support post and two retention bars, institute The left and right sides that support post is symmetrically welded in moulding bed pedestal is stated, two retention bars are symmetrically welded in moulding bed pedestal Middle part;
The support post must take root;The support post has stretching structure, and the height of the support post is adjustable Section.
Preferably, further include that ground line-transect is drawn on assembling place between the step B and step C, i.e., on assembling place Horizontally-guided plate position line is drawn in advance, and the horizontally-guided plate position line is two pieces of guide plates up and down of the spud leg section All pin holes central projection and central projection between line;
Then the first vertically-guided plate position line is drawn, the first vertically-guided plate position line is a left side for the spud leg section Line between the central projection and central projection of all pin holes of the guide plate of side;
The second vertically-guided plate position line is finally drawn, the second vertically-guided plate position line is the right side of the spud leg section Line between the central projection and central projection of all pin holes of the guide plate of side.
Preferably, in the step C further include positioning to the moulding bed:
First, it is fixed on the first vertically-guided plate position line and second at left and right sides of the moulding bed pedestal of the moulding bed Between vertically-guided plate position line, and the central axes of the moulding bed pedestal and the horizontally-guided plate position line overlap;
Then, it is placed between two retention bars on the moulding bed and fixes one piece of guide plate, it is desirable that The pin hole and horizontally-guided plate position line of the guide plate are aligned.
Preferably, the step D includes the following steps:
The first Karma is installed at the top of step D1, the second spud leg section component in step C, that is, is equipped with multiple described First Karma is symmetrically installed on the outside of two blocks of coaming plates at the top of the second spud leg section component, and first Karma is close The guide plate positioning bevelled edge at the top of platform partition board is along setting;
Step D2, first Karma inside setting assembly locating groove, it is described assembly locating groove bottom surface and For the guide plate positioning bevelled edge at the top of the platform partition board along in same level, the assembly of opposite two the first Karmas is fixed Position card inter-alveolar distance and the guide plate it is of same size;
One piece of guide plate is inserted into the assembly locating groove at the top of the second spud leg section component by step D3, and And it is aligned with the guide plate of the bottom of the second spud leg section component, it is desirable that two pieces of guide plates up and down of the second spud leg section component Pin hole corresponds;Then the guide plate positioning bevelled edge at the top of the guide plate and platform partition board is along welding.
Preferably, the step D is further comprising the steps of:
Step D4 installs the second Karma to completing the left and right sides of the second spud leg section component of the step D3, that is, is equipped with Multiple second Karmas are symmetrically installed on the outside of two blocks of coaming plates of the bottom of the second spud leg section component, and second Karma Guide plate positioning bevelled edge close to the left and right sides of platform partition board is along setting;
L-type plummer is arranged in the inside of second Karma, then by the L-type plummer second in step D5 The left and right sides of spud leg section component place the guide plate, it is desirable that the L-type plummer can make the guide plate of placement and right The guide plate positioning bevelled edge answered is along the central axes for the guide plate be close to, and placed and the corresponding guide plate The midpoint for positioning bevelled edge edge overlaps;
Step D6 installs multiple third Karmas to completing the inside of the second spud leg section component of the step D5, and described the One end of three Karmas is equipped with limit scarf, and the third Karma is installed on two blocks of coaming plates of the bottom of the second spud leg section component Inside, and the guide plate of the left and right sides of the limit scarf of third Karma and the second spud leg section component is close to;
Step D7 is tightly attached to the guiding of the left and right sides of the guide plate and platform partition board at left and right sides of the second spud leg section component Plate positioning bevelled edge edge is welded, and the pin hole of the guide plate at left and right sides of the second spud leg section component is required to correspond, To be assembled into the spud leg section.
Preferably, the step E includes the following steps:
Step E1, the spud leg section assembled to step D weld enclosure support cross, the enclosure support cross Four end feets are respectively welded at the inside of corresponding coaming plate;
Step E2 supports cross, the guide plate support ten to the spud leg section welding guide plate for completing step E1 Four end feets of cabinet frame are respectively welded at the inside of corresponding guide plate;
Step E3, to welding lifting lug on four coaming plates of the spud leg section for completing the step E2;
Step E4, by lifting lug to the spud leg section of step E3 carry out overturning until the spud leg section it is one of Until coaming plate is horizontal;
Multiple spud leg sections for completing the step E4 are hung by lifting lug and on moulding bed close up being assembled by step E5 Spud leg.
Preferably, a kind of spud leg using the high-precision offshore platform spud leg assemble method assembling.
The columnar bolt-type spud leg of octagon is divided by the high-precision offshore platform spud leg assemble method from bottom to top Multistage carries out being assembled into the spud leg section independently of each other, finally closes up multiple spud leg sections, improves construction environment, contracting Short construction period, improves producing efficiency.Moreover, it is different from existing cylindrical leg assemble method, it is described high-precision Offshore platform spud leg assemble method is suitable for the assembling of the columnar bolt-type spud leg of octagon, without making spud leg locating template, Assembly cost is lower, and assembling is more convenient.The high-precision offshore platform spud leg assemble method need to only be realized in tire The accurate positionin of guide plate on frame, you can it realizes that the accurate positionin to entire spud leg section assembles, had not only kept high assembly precision, but also Positioning and assembling difficulty are reduced, packaging efficiency is greatly improved, reduces assembling input cost.
Description of the drawings
The present invention will be further described for attached drawing, but the content in attached drawing does not constitute any limitation of the invention.
Fig. 1 is the spud leg section structure schematic diagram of the one of embodiment of the present invention;
Fig. 2 is the spud leg assembling flow path schematic diagram of the one of embodiment of the present invention;
Fig. 3 is the platform diaphragm structure schematic diagram of the one of embodiment of the present invention;
Fig. 4 is the coaming plate structural schematic diagram of the one of embodiment of the present invention;
Fig. 5 is the first spud leg section component assembling process schematic diagram of the one of embodiment of the present invention;
Fig. 6 is the second spud leg section component assembling process schematic diagram of the one of embodiment of the present invention;
Fig. 7 is the moulding bed overlooking structure diagram of the one of embodiment of the present invention;
Fig. 8 is the ground line-transect structural schematic diagram of the one of embodiment of the present invention;
Fig. 9 is the spud leg section assembling process schematic diagram of the one of embodiment of the present invention;
Figure 10 is the Karma structural schematic diagram of the one of embodiment of the present invention;
Figure 11 is the support cross structure schematic diagram of the one of embodiment of the present invention.
Wherein:Spud leg section 93;Platform partition board 1;Coaming plate 2;Guide plate 3;Coaming plate position level edge 11;Guide plate locating latch Trimming is along 12;Pin hole 31;First spud leg section component 91;Moulding bed 4;Second spud leg section component 92;Coaming plate fixing rib 21;Coaming plate is installed Groove 13;Moulding bed pedestal 42;Support post 41;Retention bar 43;Ground line-transect 8;Horizontally-guided plate position line 81;First vertically leads To plate position line 82;Second vertically-guided plate position line 83;First Karma 51;Assemble locating groove 511;Second Karma 52;L-type Plummer 521;Third Karma 53;Limit scarf 531;Enclosure support cross 6;Guide plate supports cross 7.
Specific implementation mode
Technical solution to further illustrate the present invention below with reference to the accompanying drawings and specific embodiments.
The high-precision offshore platform spud leg assemble method of the present embodiment is inserted as shown in Figure 1, main body is that octagon is columnar Pin type spud leg, spud leg is divided into multistage spud leg section 93 and is assembled from bottom to top, as shown in Fig. 2, including the following steps:
Step A manufactures spud leg section part, as shown in Figure 1, the spud leg section part includes platform partition board 1, coaming plate 2 and leads To plate 3, the side of the platform partition board 1 is octagon;The platform partition board 1 includes four coaming plate position level edges 11 and four A guide plate positioning bevelled edge is along 12, as shown in figure 3, coaming plate position level edge 11 and guide plate position bevelled edge along 12 It is spaced apart in the side of the platform partition board 1;The guide plate 3 of manufacture includes multiple pin holes 31, and the pin hole 31 is spaced uniformly Ground is longitudinally disposed on the guide plate 3;
Step B, as shown in figure 5, coaming plate 2 is welded on the coaming plate position level edge 11 of platform partition board 1, to assemble At the first spud leg section component 91;
Step C, as shown in fig. 6, manufacture moulding bed 4, places on the central axes of moulding bed 4 and fix one piece of guide plate 3; Then, wherein one guide plate of the overturning of the first spud leg section component 91 to the platform partition board 1 that step B are assembled positions bevelled edge Until 12 are horizontal;Then, the first spud leg section component 91 after overturning is sling to the top of moulding bed 4;Last platform Guide plate 3 of the wherein one guide plate positioning bevelled edge of partition board 1 on 12 and moulding bed 4 is aligned and welds, to be assembled into Second spud leg section component 92;
Step D welds guide plate 3, i.e. leading to the remaining item of platform partition board 1 to the second spud leg section component 92 of step C It is led described in two pieces up and down in the spud leg section 93 along 12 welding guide plates 3 to be assembled into spud leg section 93 to plate positioning bevelled edge Be mutually parallel to plate 3 on same plumb line and with ground, and left and right two pieces of guide plates 3 in the same horizontal line and with ground Face is mutually perpendicular to;
Multiple spud leg sections 93 are hung and on moulding bed 4 close up being assembled into spud leg by step E.
The columnar bolt-type spud leg of octagon is divided by the high-precision offshore platform spud leg assemble method from bottom to top Multistage carries out being assembled into the spud leg section 93 independently of each other, finally closes up multiple spud leg sections 93, spud leg section assembling process By the way of sleeping make, spud leg folding process is improved construction environment, is shortened construction period by the way of vertical make, and is improved Producing efficiency.Moreover, the high-precision offshore platform spud leg assembling side different from existing cylindrical leg assemble method Method is suitable for the assembling of the columnar bolt-type spud leg of octagon, and without making spud leg locating template, assembly cost is lower, and assembling is more For convenience of quick.
The spud leg section 93 of the columnar bolt-type spud leg of octagon includes platform partition board 1, coaming plate 2 and guide plate 3, described The side of platform partition board 1 be octagon, the side of platform partition board 1 set there are four coaming plate position level edge 11 and four guiding A guide plate is arranged between 12, two coaming plate position level edges 11 and positions bevelled edge along 12, i.e., four for plate positioning bevelled edge A coaming plate position level edge 11 is opposite two-by-two, and four guide plate positioning bevelled edges are opposite two-by-two along 12.Multiple platforms can be equipped with The coaming plate position level edge 11 of partition board 1, the inside of the coaming plate 2 and multiple platform partition boards 1 connects, the guide plate 3 it is interior The guide plate of side and multiple platform partition boards 1 positions bevelled edge along 12 connections, and the platform partition board 1 plays a support and is coupled work With in order to assemble spud leg section 93.It can be seen that the high-precision offshore platform spud leg assemble method is that controlling four encloses The welding precision of plate 2 and four guide plates 3 controls emphatically the assembling position precision of four guide plates 3.
Four coaming plates 2 are first welded in the corresponding of platform partition board 1 by the high-precision offshore platform spud leg assemble method On coaming plate position level edge 11, to be assembled into the first spud leg section component 91.The first spud leg section component 91 is one four A angle of chamfer is the octagon cylindrical shell of hollow out, and the step C and step D are four to the first spud leg section component 91 Angle of chamfer installs guide plate 3 additional, to form the spud leg section 93.
To improve the assembling position precision of four guide plates 3, the step C manufactures the moulding bed 4, and by one piece of guide plate 3 are fixed on the central axes of moulding bed 4;Then the first spud leg section component 91 is overturn to a pair of of the angle of chamfer of its own and is in Until horizontal position, preferably flip angle is 45 °, to which the first spud leg section component 91 after overturning is upper and lower two angles of chamfer (i.e. the guide plate of about 1 two, platform partition board positions bevelled edge along 12) is horizontal, two angle of chamfer (the i.e. platforms in left and right Guide plate that partition board is 1 or so two positioning bevelled edge is oblique in order to which the guide plate 3 to be mounted on along 12) in vertical position In corner cut;Then the first spud leg section component 91 after overturning is hung to moulding bed 4 again, and the bottom of the first spud leg section component 91 Guide plate 3 in the angle of chamfer and moulding bed 4 in portion is aligned and welds, to be assembled into the second spud leg section component 92.Finally, then toward institute It states 92 remaining three angles of chamfer of the second spud leg section component and welds the guide plate 3 using technique is symmetrically welded, to be assembled into Spud leg section 93.
Therefore, the high-precision offshore platform spud leg assemble method need to only realize the standard to the guide plate 3 on moulding bed 4 Determine position, you can realize that the accurate positionin to entire spud leg section 93 assembles, not only kept high assembly precision, but also reduce positioning and group Difficulty is filled, packaging efficiency is greatly improved, reduces assembling input cost.
Preferably, as shown in figure 4, further including coaming plate fixing rib 21, the coaming plate fixing rib 21 is longitudinally welded in coaming plate 2 Inside;Accordingly, as shown in figure 3, the platform partition board 1 further includes coaming plate installation groove 13, the coaming plate installation groove 13 It is set to coaming plate position level edge 11.Multiple coaming plate fixing ribs 21 are set, and longitudinally interval is uniformly distributed in the coaming plate 2 Inside, the coaming plate fixing rib 21 play the role of enhance 2 intensity of coaming plate.Accordingly, multiple coaming plate installation grooves can be set 13, the coaming plate fixing rib 21 is connected in coaming plate installation groove 13, to increase the contact surface between coaming plate 2 and platform partition board 1 Product makes coaming plate 2 more be securely mounted at platform partition board 1, avoids 2 stress concentration of coaming plate at one, stress is more convenient for welding Uniformly.
Preferably, as shown in figure 5, the step B include it is following step by step:
Step B1, one block of coaming plate 2 is horizontally-arranged;
Several pieces of platform partition boards 1 are erected on coaming plate 2 by step B2, and wherein one coaming plate of platform partition board 1 is fixed Position horizontal edge 11 and coaming plate 2 are aligned, while the coaming plate fixing rib 21 on coaming plate 2 is inserted into coaming plate installation groove 13;Then, will Coaming plate fixing rib 21 is welded in coaming plate installation groove 13, and the platform partition board 1 is made to be fitted vertically on the coaming plate 2;
Step B3 welds coaming plate 2 toward the coaming plate position level edge 11 of remaining of the platform partition board 1, and described The coaming plate fixing rib 21 of coaming plate 2 is welded in corresponding coaming plate installation groove 13, to be assembled into the first spud leg section component 91.
It is that corresponding coaming plate installation groove 13 is welded in by coaming plate fixing rib 21 between the coaming plate 2 and platform partition board 1 On come complete assembling:Platform partition board 1 is welded in by coaming plate fixing rib 21 first and is erected in corresponding coaming plate installation groove 13 It is vertical to be fixed on the coaming plate 2;Then, and by coaming plate fixing rib 21 it is welded in the side of corresponding coaming plate installation groove 13 Formula welds coaming plate 2, to be assembled into the first spud leg section component toward the coaming plate position level edge 11 of remaining of platform partition board 1 91.This method can both realize being accurately positioned between coaming plate 2 and platform partition board 1 and weld, and effectively prevent sending out in welding process Raw displacement, assists assembling without the tool of any additional fixed coaming plate 2;It can make coaming plate 2 more by coaming plate fixing rib 21 again It is securely mounted at platform partition board 1, avoids 2 stress concentration of the coaming plate at one, stress is more uniformly distributed.
Preferably, as shown in Figure 6, Figure 7, the moulding bed 4 of the step C manufactures includes moulding bed pedestal 42, a plurality of support post 41 and two retention bars 43, the support post 41 be symmetrically welded in the left and right sides of moulding bed pedestal 42, two are described fixed Position cross bar 43 is symmetrically welded in the middle part of moulding bed pedestal 42;The support post 41 must take root;The support post 41 has Have a stretching structure, the support post 41 it is height-adjustable.
The moulding bed pedestal 42 is used for bearing assembly, and workbench is provided for spud leg assembling;The moulding bed pedestal 42 is net Lattice structure, in order to carry out positioning and in real time the assembling situation of observation spud leg to spud leg.The middle part of the moulding bed pedestal 42 is symmetrical Ground is equipped with two retention bars 43, for being positioned to the guide plate 3 that need to be fixed on the central axes of moulding bed 4, The distance between two described retention bars 43 are the width of the guide plate 3, and the guide plate 3 is fixed on two when assembling Between the retention bar 43, so that it is guaranteed that the central axes of the guide plate 3 and the central axes of moulding bed 4 overlap, and then institute is ensured Fitting can be aligned along 12 by stating the wherein one guide plate positioning bevelled edge of guide plate 3 and platform partition board 1, improve welding essence Degree.
The support post 41 is symmetrically welded in the left and right sides of moulding bed pedestal 42, the be used to support after fixed overturning One spud leg section component 91, the support post 41 are pressed against the coaming plate 2 of 91 left and right sides of the first spud leg section component, prevent respectively The first spud leg section component 91 after being overturn in assembling process shakes, and improves assembling operation safety.
Preferably, as shown in figure 8, further including drawing ground line-transect 8 on assembling place between the step B and step C, that is, exist Horizontally-guided plate position line 81 is drawn on assembling place in advance, the horizontally-guided plate position line 81 is the upper of the spud leg section 93 Line between the central projection and central projection of all pin holes 31 of lower two pieces of guide plates 3;Then first is drawn vertically to lead To plate position line 82, the first vertically-guided plate position line 82 is all pins of the guide plate 3 in the left side of the spud leg section 93 Line between the central projection and central projection in hole 31;The second vertically-guided plate position line 83 is finally drawn, described second is vertical Guide plate position line 83 is between the central projection and central projection of all pin holes 31 of the guide plate 3 on the right side of the spud leg section 93 Line.
Preferably, in the step C further include positioning to the moulding bed 4:
First, the first vertically-guided plate position line 82 is fixed in the left and right sides of the moulding bed pedestal 42 of the moulding bed 4 And second between vertically-guided plate position line 83, and the central axes of the moulding bed pedestal 42 and the horizontally-guided plate position line 81 overlap;
Then, one piece of guide plate 3 is placed and fixes between two retention bars 43 on the moulding bed 4, It is required that pin hole 31 and horizontally-guided plate position line 81 alignment of the guide plate 3.
Described ground line-transect 8 is in an assembling process positioning the position of each guide plate 3, to improve assembling essence Degree.Before assembling, the first vertically-guided plate position line 82 and are fixed in the left and right sides of the moulding bed pedestal 42 of the moulding bed 4 Between two vertically-guided plate position lines 83, and the central axes of the moulding bed pedestal 42 and 81 weight of horizontally-guided plate position line It closes;When assembling, since moulding bed pedestal 42 is network, the ground line-transect 8 being disposed below can be seen from moulding bed pedestal 4, from And when being placed between two retention bars 43 on the moulding bed 4 in step C and fixing one piece of guide plate 3, institute It states the pin hole 31 of guide plate 3 and the horizontally-guided plate position line 81 immediately below it is aligned, greatly increase guide plate 3 Positioning accuracy.And when on the first spud leg section component 91 to moulding bed 4 after hanging overturning, the first spud leg section component 91 The angle of chamfer in left side and the first vertically-guided plate position line 82 alignment, the angle of chamfer on the right side of the first spud leg section component 91 and Second vertically-guided plate position line 83 be aligned, to ensure the first spud leg section component 91 bottom angle of chamfer and moulding bed 4 On guide plate 3 be aligned, improve packaging efficiency and assembly precision.
Preferably, as shown in figure 9, the step D includes the following steps:
The first Karma 51 is installed at the top of step D1, the second spud leg section component 92 in step C, that is, is equipped with multiple First Karma 51 is symmetrically installed on the outside of two blocks of coaming plates 2 at the top of the second spud leg section component 92, and described Guide plate positioning bevelled edge of one Karma 51 close to the top of platform partition board 1 is arranged along 12;
Step D2, as shown in Figure 10, in the inside of first Karma 51 setting assembly locating groove 511, the assembly The guide plate at the bottom surface of locating groove 511 and the top of the platform partition board 1 positions bevelled edge along 12 in same level, relatively Two the first Karmas 51 assembly locating groove 511 between distance and the guide plate 3 it is of same size;
One piece of guide plate 3 is inserted into the assembly locating groove at the top of the second spud leg section component 92 by step D3 511, and be aligned with the guide plate 3 of the bottom of the second spud leg section component 92, it is desirable that two pieces up and down of the second spud leg section component 92 The pin hole 31 of the guide plate 3 corresponds;Then the guide plate positioning beveling at the top of the guide plate 3 and platform partition board 1 It welds at edge 12.
The high-precision offshore platform spud leg assemble method passes through in the first card of the top of two spud leg section components 92 installation The mode of horse 51 welds the guide plate 3 at the top of two spud leg section components 92, greatly improves assembly precision, effectively prevent Guide plate 3 described in assembling process is displaced.The guide plate 3 is inserted into the top of the second spud leg section component 92 when assembling Assembly locating groove 511, can be only moved forward and backward to limit the guide plate 3, constrain the activity of the guide plate 3.It is logical The guide plate 3 being moved forward and backward on assembly locating groove 511 is crossed, so that the guiding of itself and the bottom of the second spud leg section component 92 Plate 3 is aligned, and the pin hole 31 of upper and lower two pieces of guide plates 3 corresponds, and first Karma 51, which is arranged, makes the positioning of guide plate 3 It is highly efficient and accurate with welding.
Preferably, as shown in figure 9, the step D is further comprising the steps of:
Step D4 installs the second Karma 52, i.e., to completing the left and right sides of the second spud leg section component 92 of the step D3 The outside of two blocks of coaming plates 2 of the bottom of the second spud leg section component 92, and institute are symmetrically installed on equipped with multiple second Karmas 52 The second Karma 52 is stated close to the guide plate positioning bevelled edge of the left and right sides of platform partition board 1 along 12 settings;
Step D5, as shown in Figure 10, in the inside of second Karma 52, setting L-type plummer 521, then passes through described L-type plummer 521 places the guide plate 3 in the left and right sides of the second spud leg section component 92, it is desirable that the L-type plummer 521 The guide plate 3 and the corresponding guide plate positioning bevelled edge that can make placement are close to along 12, and the guiding of placement The central axes of plate 3 and the corresponding guide plate positioning bevelled edge are overlapped along 12 midpoint;
Step D6, as shown in Figure 10, to completing the inside installation of the second spud leg section component 92 of the step D5 multiple the One end of three Karmas 53, the third Karma 53 is equipped with limit scarf 531, and the third Karma 53 is installed on the second spud leg section The inside of two blocks of coaming plates 2 of the bottom of component 92, and the limit scarf 531 of third Karma 53 and the second spud leg section component 92 The guide plate 3 of the left and right sides be close to;
Step D7 is tightly attached to the left and right sides of the guide plate 3 and platform partition board 1 at left and right sides of the second spud leg section component 92 Guide plate positioning bevelled edge is welded along 12, and requires the pin hole of the guide plate 3 of 92 left and right sides of the second spud leg section component 31 correspond, to be assembled into the spud leg section 93.
The left and right sides of the second spud leg section component 92 to completing the step D3 is installed by the second Karma 52, second card Horse 52 is equipped with L-type plummer 521, and the L-type plummer 521 is for carrying guide plate 3.Before assembling, pass through second Karma The 52 guide plate positioning bevelled edge in 92 left and right sides of the second spud leg section component places the guide plate 3 along 12.Also at second Multiple third Karmas 53 are installed in the inside of leg section component 92, and one end of the third Karma 53 is equipped with limit scarf 531, in institute It states under the limit scarf 531 of third Karma 53 and 521 collective effect of L-type plummer of the second Karma 52, realizes to guide plate 3 Positioning and fixation, so that the guide plate 3 and corresponding guide plate positioning bevelled edge is close to along 12, and the guide plate 3 Central axes and the corresponding guide plate positioning bevelled edge are overlapped along 12 midpoint, effectively prevent guide plate described in assembling process 3 are displaced, and greatly improve assembly precision and packaging efficiency.
Preferably, as shown in figure 11, the step E includes the following steps:
Step E1, the spud leg section 93 welding enclosure support cross 6 assembled to step D, the enclosure support cross Four end feets of frame 6 are respectively welded at the inside of corresponding coaming plate 2;
Step E2 supports cross 7, the guide plate support to the spud leg section 93 welding guide plate for completing step E1 Four end feets of cross 7 are respectively welded at the inside of corresponding guide plate 3;
Step E3, to welding lifting lug on four coaming plates 2 of the spud leg section 93 for completing the step E2;
Step E4 carries out overturning up to wherein the one of the spud leg section 93 by lifting lug to the spud leg section 93 of step E3 Until the coaming plate 2 of block is horizontal;
Multiple spud leg sections 93 for completing the step E4 are hung by lifting lug and carry out closing up group on moulding bed 4 by step E5 Dress up spud leg.
The step E first installs 6 He of enclosure support cross additional before being overturn to the spud leg section 93 in the spud leg section 93 Guide plate supports cross 7, enhances the intensity of four coaming plates 2 and four guide plates 3 of the spud leg section 93, to prevent from overturning Occur cracking or breaking with 93 stress of the spud leg section concentration or unbalance stress in the process is closed up.In the spud leg section 93 Lifting lug is welded on four coaming plates 2, in order to complete subsequent overturning and close up process.
Preferably, a kind of spud leg being assembled into using the high-precision offshore platform spud leg assemble method.Using described The spud leg of high-precision offshore platform spud leg assemble method assembling, by platform partition board 1, coaming plate 2 and 3 assembling combination of guide plate At the platform partition board 1 plays the role of a support connection, in order to assemble spud leg;Guide plate 3 with pin hole 31 is set to In four angles of chamfer of spud leg, to avoid stress concentration in spud leg lifting process, stress is more uniformly distributed, and spud leg lifting can By accurate.The cross section of the spud leg is octagon, and compared with existing cylindrical leg, convenient for assembly, space availability ratio is more It is high.
The high-precision offshore platform spud leg assemble method of the present embodiment has the advantages that:1. by octagon column Bolt-type spud leg be divided into multistage from bottom to top, carry out being assembled into the spud leg section 93 independently of each other, finally by multiple stakes Leg section 93 closes up, and improves construction environment, shortens construction period, improves producing efficiency;2. columnar suitable for octagon The assembling of bolt-type spud leg, without making spud leg locating template, assembly cost is lower, and assembling is more convenient;3. needing reality Now to the accurate positionin of the guide plate 3 on moulding bed 4, you can realize that the accurate positionin to entire spud leg section 93 assembles, both kept High assembly precision, and positioning and assembling difficulty are reduced, packaging efficiency is greatly improved, assembling input cost is reduced.
The technical principle of the present invention is described above in association with specific embodiment.These descriptions are intended merely to explain the present invention's Principle, and it cannot be construed to limiting the scope of the invention in any way.Based on the explanation herein, the technology of this field Personnel would not require any inventive effort the other specific implementation modes that can associate the present invention, these modes are fallen within Within protection scope of the present invention.

Claims (10)

1. a kind of high-precision offshore platform spud leg assemble method, main body is the columnar bolt-type spud leg of octagon, and spud leg is under It is divided into multistage spud leg section upwards to be assembled, which is characterized in that include the following steps:
Step A manufactures spud leg section part, and the spud leg section part includes platform partition board, coaming plate and guide plate, the platform partition board Side be octagon;The platform partition board includes that four coaming plate position level edges and four guide plates position bevelled edge edges, Coaming plate position level edge and guide plate positioning bevelled edge edge are spaced apart in the side of the platform partition board;Manufacture is led Include multiple pin holes to plate, the pin hole is longitudinally disposed at evenly and at intervals on the guide plate;
Coaming plate is welded on the coaming plate position level edge of platform partition board by step B, to be assembled into the first spud leg section component;
Step C manufactures moulding bed, is placed on the central axes of moulding bed and fix one piece of guide plate;Then, step B is assembled The first spud leg section component overturn to wherein one guide plate of platform partition board positioning bevelled edge until be horizontal; Then, the first spud leg section component after overturning is sling to the top of moulding bed;Wherein one guide plate of last platform partition board is fixed Guide plate on position bevelled edge edge and moulding bed is aligned and welds, to be assembled into the second spud leg section component;
Step D is positioned to the second spud leg section components welding guide plate of step C to the guide plate of the remaining item of platform partition board Bevelled edge is along welding guide plate, to be assembled into spud leg section, in the spud leg section up and down two pieces of guide plates in same vertical It is mutually parallel on line and with ground, and the two pieces of guide plates in left and right are mutually perpendicular in the same horizontal line and with ground;
Multiple spud leg sections are hung and on moulding bed close up being assembled into spud leg by step E.
2. high-precision offshore platform spud leg assemble method according to claim 1, it is characterised in that:Further include that coaming plate is solid Determine rib, the coaming plate fixing rib is longitudinally welded in the inside of coaming plate;
Accordingly, the platform partition board further includes coaming plate installation groove, and the coaming plate installation groove is set to coaming plate position level Edge.
3. high-precision offshore platform spud leg assemble method according to claim 2, which is characterized in that the step B packets Include it is following step by step:
Step B1, one block of coaming plate is horizontally-arranged;
Several pieces of platform partition boards are erected on coaming plate by step B2, and wherein one coaming plate position level of platform partition board Edge and coaming plate alignment, while the coaming plate fixing rib on coaming plate is inserted into coaming plate installation groove;Then, coaming plate fixing rib is welded In coaming plate installation groove, it is fixed on the coaming plate with making the platform divider upright;
Step B3, the coaming plate position level edge of remaining the welding coaming plate of the past platform partition board, and the coaming plate enclose Plate fixing rib is welded in corresponding coaming plate installation groove, to be assembled into the first spud leg section component.
4. high-precision offshore platform spud leg assemble method according to claim 1, it is characterised in that:The step C systems The moulding bed made includes that moulding bed pedestal, a plurality of support post and two retention bars, the support post are symmetrically welded in moulding bed The left and right sides of pedestal, two retention bars are symmetrically welded in the middle part of moulding bed pedestal;
The support post must take root;The support post have stretching structure, the support post it is height-adjustable.
5. high-precision offshore platform spud leg assemble method according to claim 4, it is characterised in that:The step B and Further include drawing ground line-transect on assembling place between step C, i.e., draws horizontally-guided plate position line, institute in advance on assembling place State the central projection of all pin holes of two pieces of guide plates and the center up and down that horizontally-guided plate position line is the spud leg section Line between projection;
Then the first vertically-guided plate position line is drawn, the first vertically-guided plate position line is the left side of the spud leg section Line between the central projection and central projection of all pin holes of guide plate;
The second vertically-guided plate position line is finally drawn, the second vertically-guided plate position line is the right side of the spud leg section Line between the central projection and central projection of all pin holes of guide plate.
6. high-precision offshore platform spud leg assemble method according to claim 5, which is characterized in that in the step C It further include the positioning to the moulding bed:
First, the first vertically-guided plate position line and second is fixed at left and right sides of the moulding bed pedestal of the moulding bed vertically Between guide plate position line, and the central axes of the moulding bed pedestal and the horizontally-guided plate position line overlap;
Then, it is placed between two retention bars on the moulding bed and fixes one piece of guide plate, it is desirable that is described The pin hole and horizontally-guided plate position line of guide plate are aligned.
7. high-precision offshore platform spud leg assemble method according to claim 1, which is characterized in that the step D packets Include following steps:
The first Karma is installed at the top of step D1, the second spud leg section component in step C, that is, is equipped with multiple described first Karma is symmetrically installed on the outside of two blocks of coaming plates at the top of the second spud leg section component, and first Karma is close to platform The guide plate positioning bevelled edge at the top of partition board is along setting;
Step D2, in the inside of first Karma setting assembly locating groove, the assembly bottom surface of locating groove and described The guide plate positioning bevelled edge at the top of platform partition board is along in same level, the assembly positioning card of opposite two the first Karmas Inter-alveolar distance and the guide plate it is of same size;
One piece of guide plate, is inserted into the assembly locating groove at the top of the second spud leg section component by step D3, and with The guide plate of the bottom of second spud leg section component is aligned, it is desirable that the pin hole of two pieces of guide plates up and down of the second spud leg section component It corresponds;Then the guide plate positioning bevelled edge at the top of the guide plate and platform partition board is along welding.
8. high-precision offshore platform spud leg assemble method according to claim 7, which is characterized in that the step D is also Include the following steps:
Step D4 installs the second Karma to completing the left and right sides of the second spud leg section component of the step D3, that is, is equipped with multiple Second Karma is symmetrically installed on the outside of two blocks of coaming plates of the bottom of the second spud leg section component, and second Karma is close The guide plate positioning bevelled edge of the left and right sides of platform partition board is along setting;
L-type plummer is arranged in the inside of second Karma, then by the L-type plummer in the second spud leg in step D5 Place the guide plate in the left and right sides for saving component, it is desirable that the L-type plummer can make the guide plate of placement and corresponding The guide plate positioning bevelled edge is along the central axes for the guide plate be close to, and placed and the corresponding guide plate positioning The midpoint on bevelled edge edge overlaps;
Step D6 installs multiple third Karmas, the third card to completing the inside of the second spud leg section component of the step D5 One end of horse is equipped with limit scarf, and the third Karma is installed on the interior of two blocks of coaming plates of the bottom of the second spud leg section component Side, and the guide plate of the left and right sides of the limit scarf of third Karma and the second spud leg section component is close to;
Step D7, the guide plate for being tightly attached to the left and right sides of the guide plate and platform partition board at left and right sides of the second spud leg section component are fixed Position bevelled edge edge is welded, and the pin hole of the guide plate at left and right sides of the second spud leg section component is required to correspond, to It is assembled into the spud leg section.
9. high-precision offshore platform spud leg assemble method according to claim 1, which is characterized in that the step E packets Include following steps:
Step E1, the spud leg section welding enclosure support cross assembled to step D, four of the enclosure support cross End feet is respectively welded at the inside of corresponding coaming plate;
Step E2 supports cross, the guide plate to support cross to the spud leg section welding guide plate for completing step E1 Four end feets be respectively welded at the inside of corresponding guide plate;
Step E3, to welding lifting lug on four coaming plates of the spud leg section for completing the step E2;
Step E4 carries out the spud leg section of step E3 by lifting lug to overturn one of coaming plate until the spud leg section Until being horizontal;
Multiple spud leg sections for completing the step E4 are hung by lifting lug and carry out closing up assembling pile on moulding bed by step E5 Leg.
10. the spud leg that a kind of high-precision offshore platform spud leg assemble method using described in claim 2 is assembled into.
CN201710024317.2A 2017-01-13 2017-01-13 A kind of high-precision offshore platform spud leg assemble method and its spud leg being assembled into Active CN106812126B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710024317.2A CN106812126B (en) 2017-01-13 2017-01-13 A kind of high-precision offshore platform spud leg assemble method and its spud leg being assembled into

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710024317.2A CN106812126B (en) 2017-01-13 2017-01-13 A kind of high-precision offshore platform spud leg assemble method and its spud leg being assembled into

Publications (2)

Publication Number Publication Date
CN106812126A CN106812126A (en) 2017-06-09
CN106812126B true CN106812126B (en) 2018-10-30

Family

ID=59109844

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710024317.2A Active CN106812126B (en) 2017-01-13 2017-01-13 A kind of high-precision offshore platform spud leg assemble method and its spud leg being assembled into

Country Status (1)

Country Link
CN (1) CN106812126B (en)

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2383119A1 (en) * 1977-03-10 1978-10-06 Metalliques Entrepr Cie Fse Assembly for installation of offshore oil drilling rig - has screw jacks with locking nuts for positioning and securing piles relative to platform
CN102717248A (en) * 2012-07-05 2012-10-10 南通中远船务工程有限公司 Design method for section closure accuracy of octagonal pile leg
CN102728980B (en) * 2012-07-05 2014-12-10 南通中远船务工程有限公司 Method for limiting and positioning octagonal spud leg in folding process
CN103624488B (en) * 2013-11-15 2016-02-10 南通润邦重机有限公司 A kind of self-lifting offshore wind power job platform spud leg manufacturing process
CN104874931A (en) * 2015-04-21 2015-09-02 南通蓝岛海洋工程有限公司 Drilling platform pile leg manufacturing technology
CN104878733B (en) * 2015-04-21 2016-08-24 南通蓝岛海洋工程有限公司 A kind of drilling platform leg segment folding technique
CN104820761B (en) * 2015-05-22 2017-11-17 南通中远船务工程有限公司 A kind of octagon latch spud leg Anti-bending structure design method
KR101576504B1 (en) * 2015-10-26 2015-12-21 에스앤에스이앤지 주식회사 Barge having jackup device

Also Published As

Publication number Publication date
CN106812126A (en) 2017-06-09

Similar Documents

Publication Publication Date Title
CN106141476A (en) A kind of super-large diameter is without the assemble method of ribbed stiffener thin-wall semi top seal closure
CN105421792A (en) Lifting construction process of modular steel structural components
CN110424745A (en) The assembled moulding bed of spacial special-shaped steel pipe truss and its assembly, installation method
CN104878695B (en) Viaduct cover beam shaping bottom die support and application method thereof
CN106638645B (en) Basement bottom board catch pit steel mesh is layered precast construction and method of construction
CN109279480A (en) A kind of steel structure lift shaft splicing apparatus and method
CN106812126B (en) A kind of high-precision offshore platform spud leg assemble method and its spud leg being assembled into
CN104908885B (en) A kind of ship forecastle bulwark integral production method
CN204282228U (en) A kind of box steel arch beam Integral horizontal type group is to jig frame special
CN109295858B (en) Integral assembly jig frame for steel shell sections of double-wall combined bridge tower and working method thereof
CN209722744U (en) A kind of Bracing Systems for steel box girder assembling
KR101708372B1 (en) Method of manufacturing and disassembling goliath crane
CN203452416U (en) Garage steel framework
CN103774694A (en) Adjustable locating jig frame for reinforcement cage
CN203213300U (en) Multilayer and multiway convergence large-size super-thick plate node used in super high-rise space
CN209293696U (en) Gear rack drilling machine and derrick installation structure
CN207348448U (en) A kind of lattice formwork bracing system
CN108979113B (en) Simple nuclear power station equipment gate construction platform
CN203304840U (en) Assembly mould for triangular support of pumping unit
CN206737389U (en) A kind of movable lifting steel pipe frame operating platform
CN104775652A (en) Tower type structure and processing and mounting method thereof
CN107829373B (en) High-speed railway bridge deck curtain board does not have prefabricated construction equipment of gasket
CN206667705U (en) A kind of preset socket joint disk button-type frame set main frame
CN216892502U (en) Iron tower basis built-in fitting installation positioner
CN204522107U (en) The universal children of a kind of novel quick-installation expand framework

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20170609

Assignee: Guangdong Yaoda Financial Leasing Co.,Ltd.

Assignor: KEEN OFFSHORE ENGINEERING Co.,Ltd.

Contract record no.: X2020980005507

Denomination of invention: A high precision assembly method of offshore platform leg and its assembled legs

Granted publication date: 20181030

License type: Exclusive License

Record date: 20200828

PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: A high precision assembly method of offshore platform leg and its assembled legs

Effective date of registration: 20200904

Granted publication date: 20181030

Pledgee: Guangdong Yaoda Financial Leasing Co.,Ltd.

Pledgor: KEEN OFFSHORE ENGINEERING Co.,Ltd.

Registration number: Y2020980005706

PE01 Entry into force of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Granted publication date: 20181030

Pledgee: Guangdong Yaoda Financial Leasing Co.,Ltd.

Pledgor: KEEN OFFSHORE ENGINEERING Co.,Ltd.

Registration number: Y2020980005706

PC01 Cancellation of the registration of the contract for pledge of patent right
EC01 Cancellation of recordation of patent licensing contract

Assignee: Guangdong Yaoda Financial Leasing Co.,Ltd.

Assignor: KEEN OFFSHORE ENGINEERING Co.,Ltd.

Contract record no.: X2020980005507

Date of cancellation: 20240320

EC01 Cancellation of recordation of patent licensing contract