CN106638645B - Basement bottom board catch pit steel mesh is layered precast construction and method of construction - Google Patents
Basement bottom board catch pit steel mesh is layered precast construction and method of construction Download PDFInfo
- Publication number
- CN106638645B CN106638645B CN201611246113.5A CN201611246113A CN106638645B CN 106638645 B CN106638645 B CN 106638645B CN 201611246113 A CN201611246113 A CN 201611246113A CN 106638645 B CN106638645 B CN 106638645B
- Authority
- CN
- China
- Prior art keywords
- sump
- mesh
- steel
- pit
- reinforcement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 229
- 239000010959 steel Substances 0.000 title claims abstract description 229
- 238000010276 construction Methods 0.000 title claims abstract description 47
- 238000000034 method Methods 0.000 title claims abstract description 15
- 230000002787 reinforcement Effects 0.000 claims abstract description 187
- 238000009417 prefabrication Methods 0.000 claims abstract description 17
- 239000011449 brick Substances 0.000 claims abstract description 9
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 7
- 239000000725 suspension Substances 0.000 claims description 9
- 238000009415 formwork Methods 0.000 claims 1
- 238000010586 diagram Methods 0.000 description 6
- 238000004364 calculation method Methods 0.000 description 4
- 238000004519 manufacturing process Methods 0.000 description 4
- 238000003466 welding Methods 0.000 description 3
- 230000009286 beneficial effect Effects 0.000 description 2
- 238000005520 cutting process Methods 0.000 description 2
- 230000003014 reinforcing effect Effects 0.000 description 2
- 238000004873 anchoring Methods 0.000 description 1
- 238000005452 bending Methods 0.000 description 1
- 239000012141 concentrate Substances 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000004078 waterproofing Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D19/00—Keeping dry foundation sites or other areas in the ground
- E02D19/22—Lining sumps in trenches or other foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/02—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Hydrology & Water Resources (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
本发明公开了一种地下室底板集水坑钢筋网分层预制结构及其建造方法,通过在项目现场或加工厂提前分层预制集水坑板底及板面钢筋网,利用塔吊先将集水坑板底钢筋网吊装置于集水坑的垫层或砖胎模上,再将集水坑板面钢筋网吊装置于集水坑板底钢筋网上,在坑内拼装成整体,人工连接预制钢筋网与周边底板钢筋,最终浇筑混凝土的施工工艺。由于分开预制,可以有效减少集水坑内的大量现场钢筋绑扎工作,提高施工效率,缩短施工工期,而且提前预制有利于提升钢筋定位及连接精度,从而解决了集水坑内钢筋绑扎工作条件差,钢筋定位难、施工繁琐的问题,避免了预制集水坑板底钢筋网以及集水坑板面钢筋网整体预制在一起所造成的吊装质量过大的问题。
The invention discloses a layered prefabricated structure and a construction method of reinforcement mesh for a basement sump pit. By layering and prefabricating the bottom of the sump pit and the steel mesh on the surface of the sump in advance at the project site or in a processing plant, the water collecting pit is firstly moved by a tower crane. The steel mesh at the bottom of the pit slab is hoisted on the cushion or brick tire mold of the sump, and then the steel mesh on the slab surface of the sump is hoisted on the steel mesh at the bottom of the sump pit, assembled into a whole in the pit, and the prefabricated steel bars are manually connected Mesh and surrounding bottom plate reinforcement, and finally the construction process of pouring concrete. Due to separate prefabrication, it can effectively reduce a large number of on-site steel bar binding work in the sump, improve construction efficiency, and shorten the construction period, and prefabrication in advance is conducive to improving the positioning and connection accuracy of steel bars, thus solving the poor working conditions of steel bar binding in the sump. The problem of difficult positioning and cumbersome construction avoids the problem of excessive hoisting quality caused by the prefabricated steel mesh at the bottom of the sump slab and the overall prefabrication of the steel mesh on the slab surface of the sump pit.
Description
技术领域technical field
本发明属于建筑业施工领域,特别涉及地下室底板集水坑施工技术领域。The invention belongs to the construction field of the building industry, in particular to the technical field of basement floor sump construction technology.
背景技术Background technique
随着目前高层及超高层建筑的不断涌现,地下室的防水问题也越来越突出。地下室常见的一种防水的方法就是在底板上设置集水坑,将水集中于底板的深坑即集水坑内,而后统一用水泵将水排出。With the continuous emergence of high-rise and super high-rise buildings, the problem of waterproofing in basements has become more and more prominent. A common waterproof method for the basement is to set a sump on the base plate, concentrate the water in the deep pit of the base plate, that is, the sump, and then discharge the water with a unified water pump.
现有地下室底板集水坑构造,其钢筋包括板底及板面两大部分。传统的施工工艺为:1)先挖好坑,并做好集水坑的垫层或砖胎模;2)将加工好钢筋逐根搬入坑中,逐根定位并连接钢筋,形成集水坑钢筋网;3)浇筑混凝土。The sump structure of the existing basement floor includes two major parts of the bottom plate and the surface of the plate. The traditional construction process is: 1) dig a hole first, and make a cushion or brick tire mold for the sump; 2) move the processed steel bars into the pit one by one, position and connect the steel bars one by one to form a sump 3) Pouring concrete.
这种施工工艺存在以下缺点:1)施工工期长,对于超高层或高层而言,尽快形成基坑底板对于基坑安全及稳定尤为重要;2)逐根钢筋定位及对接,劳动量大,施工效率低;3)集水坑内钢筋绑扎工作条件差,钢筋定位难、施工繁琐。This construction technique has the following disadvantages: 1) The construction period is long. For super high-rise or high-rise buildings, it is particularly important to form the foundation pit floor as soon as possible for the safety and stability of the foundation pit; Efficiency is low; 3) working condition of reinforcing bar binding in sump pit is poor, reinforcing bar location is difficult, and construction is loaded down with trivial details.
因此,如何提供一种可以避免在坑内绑扎钢筋、施工效率高、工期短、保证钢筋连接质量的地下室底板集水坑钢筋网分层预制结构及建造方法,已成为建筑施工界需进一步完善优化的技术问题。Therefore, how to provide a layered prefabricated structure and construction method of steel mesh in the basement sump pit that can avoid binding steel bars in the pit, have high construction efficiency, short construction period, and ensure the quality of steel bar connection has become an issue that needs to be further improved and optimized by the construction industry. technical problem.
发明内容Contents of the invention
针对现有技术存在的上述缺陷,本发明的目的在于提供一种地下室底板集水坑钢筋网分层预制结构及建造方法,解决现有地下室底板集水坑钢筋逐根绑扎难、施工效率低、工期长、连接质量难以保障的技术问题。In view of the above-mentioned defects in the prior art, the object of the present invention is to provide a layered prefabricated structure and construction method of steel mesh in the sump pit of the basement floor, which solves the problem of difficulty in tying steel bars one by one in the sump pit of the basement floor, low construction efficiency, Technical problems such as long construction period and difficulty in guaranteeing connection quality.
为解决上述技术问题,本发明提供如下技术方案:In order to solve the above technical problems, the present invention provides the following technical solutions:
一种地下室底板集水坑钢筋网分层预制结构,用于施工底板上的集水坑,包括:在施工现场或者加工厂提前预制的集水坑板底钢筋网以及下部固定有钢筋支架的集水坑板面钢筋网,所述集水坑板底钢筋网呈盆状结构,所述集水坑板底钢筋网铺设于拟建集水坑的垫层或者砖胎模上,所述集水坑板面钢筋网通过所述钢筋支架架设于集水坑板底钢筋网上方,所述集水坑板底钢筋网与集水坑周边底板板底钢筋逐根对应连接,所述集水坑板面钢筋网与集水坑周边底板板面钢筋逐根对应连接。A layered prefabricated structure of reinforcement mesh for a sump pit on a basement floor, which is used for a sump on a construction floor, including: a prefabricated steel mesh at the bottom of a sump pit slab bottom at a construction site or in a processing plant and a collection pit with a steel support fixed at its lower part. The reinforced mesh on the surface of the sump, the reinforced mesh at the bottom of the sump is a basin-shaped structure, and the reinforced mesh at the bottom of the sumps is laid on the cushion layer or brick tire mold of the proposed sump, and the water-collected The reinforced mesh on the surface of the pit plate is erected above the reinforced mesh at the bottom of the sump plate through the steel bar bracket. The surface reinforcement mesh is connected with the surface reinforcement of the bottom plate around the sump correspondingly one by one.
优选的,在上述的地下室底板集水坑钢筋网分层预制结构中,所述集水坑板底钢筋网包括水平底部钢筋网与位于水平底部钢筋网四周的侧部钢筋网,所述侧部钢筋网斜向上设置,所述侧部钢筋网中斜向上的钢筋与集水坑周边底板板底钢筋对应交叉锚固连接。Preferably, in the layered prefabricated structure of the basement floor sump reinforcement mesh, the bottom reinforcement mesh of the sump pit includes a horizontal bottom reinforcement mesh and side reinforcement meshes located around the horizontal bottom reinforcement mesh, and the side portions The reinforcement mesh is arranged obliquely upward, and the obliquely upward reinforcement in the side reinforcement mesh is correspondingly cross-anchored and connected with the bottom reinforcement of the bottom plate around the sump pit.
优选的,在上述的地下室底板集水坑钢筋网分层预制结构中,所述集水坑板面钢筋网包括坑底水平钢筋网、坑壁竖向钢筋网以及坑顶水平钢筋网,所述坑壁竖向钢筋网设置于所述坑底水平钢筋网的四周,所述坑顶水平钢筋网呈“回字形”,坑顶水平钢筋网的内圈与所述坑壁竖向钢筋网的上端口相匹配且固定连接,所述坑顶水平钢筋网的外圈处钢筋与集水坑周边底板板面钢筋逐根对应连接。Preferably, in the layered prefabricated structure of the basement floor sump reinforcement mesh layered above, the sump surface reinforcement mesh includes a horizontal reinforcement mesh at the bottom of the pit, a vertical reinforcement mesh at the pit wall and a horizontal reinforcement mesh at the top of the pit. The vertical steel mesh on the pit wall is arranged around the horizontal steel mesh at the bottom of the pit. The ports are matched and fixedly connected, and the steel bars at the outer ring of the horizontal steel mesh on the top of the pit are connected with the bottom plate surface steel bars around the sump correspondingly one by one.
优选的,在上述的地下室底板集水坑钢筋网分层预制结构中,所述水平底部钢筋网呈矩形,所述钢筋支架包括矩形顶部型钢钢圈与四根竖向角部型钢,所述矩形顶部型钢钢圈的形状和大小与所述集水坑板底钢筋网的所述水平底部钢筋网相对应,所述四根竖向角部型钢固定设置于所述矩形顶部型钢钢圈的四个角下方,所述四根竖向角部型钢的下端设置于所述集水坑板底钢筋网的所述水平底部钢筋网的四个角位置,所述矩形顶部型钢钢圈支撑于所述集水坑板面钢筋网的坑顶水平钢筋网的下表面。Preferably, in the layered prefabricated structure of the basement floor sump reinforcement mesh, the horizontal bottom reinforcement mesh is rectangular, and the reinforcement support includes a rectangular top steel ring and four vertical corner steel rings. The shape and size of the top section steel ring correspond to the horizontal bottom reinforcement mesh of the sump slab bottom reinforcement mesh, and the four vertical corner section steels are fixedly arranged on the four corners of the rectangular top section steel ring. Below the corner, the lower ends of the four vertical corner section steels are set at the four corners of the horizontal bottom reinforcement mesh of the sump slab bottom reinforcement mesh, and the rectangular top section steel rings are supported on the set The lower surface of the pit top horizontal reinforcement mesh of the puddle slab reinforcement mesh.
优选的,在上述的地下室底板集水坑钢筋网分层预制结构中,所述钢筋支架还包括四根竖向中部型钢,所述竖向中部型钢分别设置于所述矩形顶部型钢钢圈的四条边的中部下方。Preferably, in the above-mentioned layered prefabricated structure of reinforced mesh in the basement sump pit, the steel bar support further includes four vertical middle section steels, and the vertical middle section steels are respectively arranged on the four rectangular top section steel rings. below the middle of the edge.
优选的,在上述的地下室底板集水坑钢筋网分层预制结构中,每根竖向中部型钢的下端通过两根斜撑分别连接于所述矩形顶部型钢钢圈上同侧边的两端。Preferably, in the layered prefabricated structure of the basement floor sump reinforcement mesh, the lower end of each vertical middle section steel is respectively connected to the two ends on the same side of the rectangular top section steel ring through two diagonal braces.
优选的,在上述的地下室底板集水坑钢筋网分层预制结构中,还包括若干板顶吊圈,所述板顶吊圈通过连接杆固定于所述竖向角部型钢上,或者通过连接杆固定于所述竖向中部型钢上。Preferably, in the layered prefabricated structure of the basement floor sump reinforcement mesh layered structure, a number of plate top suspension rings are also included, and the plate top suspension rings are fixed on the vertical corner section steel through connecting rods, or connected The rod is fixed on the vertical middle section steel.
优选的,在上述的地下室底板集水坑钢筋网分层预制结构中,所述侧部钢筋网的四个角上均设有一个板底吊圈。Preferably, in the layered prefabricated steel mesh structure of the sump pit on the basement floor, four corners of the side steel mesh are provided with a slab bottom suspension ring.
优选的,在上述的地下室底板集水坑钢筋网分层预制结构中,所述集水坑板底钢筋网借助钢筋胎架加工制作,所述钢筋胎架由四组支撑架围合组成,每组支撑架包括至少三对竖向间隔设置的直角三角形钢架与一对平行的条状型钢,每个直角三角形钢架由斜边型钢、水平直角边型钢以及竖向直角边型钢围成,所述直角三角形架的所述斜边型钢靠内设置,每组支撑架中的各个水平直角边型钢通过一对平行的条状型钢连接。Preferably, in the above-mentioned layered prefabricated structure of reinforced mesh in the sump pit on the basement floor, the reinforced mesh at the bottom of the sump pit is processed by means of a steel frame, and the reinforced frame is composed of four sets of supporting frames, each The set of supporting frames includes at least three pairs of right-angled triangular steel frames arranged vertically at intervals and a pair of parallel bar-shaped steel frames. The hypotenuse shaped steel of the right-angled triangular frame is set inside, and each horizontal right-angled shaped steel in each group of support frames is connected by a pair of parallel strip shaped steel.
本发明还公开了一种地下室底板集水坑钢筋网分层预制建造方法,采用如上所述的地下室底板集水坑钢筋网分层预制结构,包括如下步骤:The present invention also discloses a layered prefabricated construction method of reinforced mesh in a sump pit of a basement floor, which adopts the layered prefabricated structure of reinforced mesh in a sump pit of a basement floor as described above, including the following steps:
步骤一,集水坑钢筋网设计;Step 1, sump reinforcement mesh design;
步骤二,集水坑预制钢筋网预制加工,所述集水坑钢筋网包括集水坑板底钢筋网、以及下部固定有钢筋支架的集水坑板面钢筋网;Step 2, prefabricated processing of prefabricated steel mesh in the sump, the steel mesh in the sump includes the steel mesh at the bottom of the sump plate, and the steel mesh on the surface of the sump plate with the reinforcement bracket fixed at the bottom;
步骤三,集水坑预制钢筋网分层吊装与拼装:先吊装集水坑板底钢筋网,再吊装下部固定有钢筋支架的集水坑板面钢筋网,使得集水坑板底钢筋网与集水坑板面钢筋网由下至上依次设置于集水坑内;Step 3, layered hoisting and assembly of the prefabricated steel mesh in the sump pit: first hoist the steel mesh at the bottom of the sump pit, and then hoist the steel mesh on the bottom of the sump pit with the steel bracket fixed at the lower part, so that the steel mesh at the bottom of the sump pit and the steel mesh at the bottom of the sump pit The steel mesh on the surface of the sump is arranged in the sump in sequence from bottom to top;
步骤四,将集水坑板底钢筋网与集水坑周边底板板底钢筋逐根对应连接,将集水坑板面钢筋网与集水坑周边底板板面钢筋逐根对应连接;Step 4: Connect the reinforcement mesh at the bottom of the sump pit with the steel bars at the bottom of the bottom slab around the sump correspondingly, and connect the steel mesh at the bottom of the sump pit with the reinforcement at the bottom of the bottom slab around the sump pit;
步骤五;浇筑带有集水坑的底板混凝土。Step 5: Pouring the concrete of the bottom slab with the sump.
优选的,在上述的地下室底板集水坑钢筋网分层预制建造方法中,所述步骤三之前,在拟建集水坑的垫层或者砖胎模的四个角部画控制线,在吊装过程中利用集水坑板底钢筋网的底部四个角对准垫层上控制线,完成集水坑板底钢筋网精确入坑定位工作。Preferably, in the above-mentioned layered prefabricated construction method of the basement floor sump reinforcement mesh, before the third step, control lines are drawn on the four corners of the pad or brick mold of the sump to be built, and the hoisting During the process, the bottom four corners of the reinforcement mesh at the bottom of the sump pit are aligned with the control line on the cushion layer to complete the precise positioning of the reinforcement mesh at the bottom of the sump pit.
由以上公开的技术方案可知,与现有技术相比,本发明的有益效果如下:As can be seen from the technical solutions disclosed above, compared with the prior art, the beneficial effects of the present invention are as follows:
本发明提供地下室底板集水坑钢筋网分层预制结构及其建造方法,通过分层即分开预制集水坑板底钢筋网以及下部固定有钢筋支架的集水坑板面钢筋网,可以有效减少集水坑内的大量现场钢筋绑扎工作量,提高施工效率,缩短施工工期,而且提前预制有利于提升地下室底板集水坑钢筋网以及集水坑板面钢筋网内钢筋定位及连接精度,解决了集水坑内钢筋绑扎工作条件差,钢筋定位难、施工繁琐的问题。对于超高层或高层而言,能够尽快形成基坑底板可以确保基坑安全及稳定。此外,通过分层即分开预制集水坑板底钢筋网以及下部固定有钢筋支架的集水坑板面钢筋网,避免了预制集水坑板底钢筋网以及集水坑板面钢筋网整体预制在一起所造成的吊装质量过大的问题。The invention provides a layered prefabricated structure and construction method of basement floor sump reinforcement mesh, which can effectively reduce the A large amount of on-site steel binding workload in the sump improves construction efficiency and shortens the construction period, and prefabrication in advance is conducive to improving the positioning and connection accuracy of the reinforcement mesh in the basement floor sump and the reinforcement mesh in the sump surface, which solves the problem of centralized The working conditions of the steel bar binding in the puddle are poor, the positioning of the steel bar is difficult, and the construction is cumbersome. For super high-rise or high-rise buildings, the foundation pit floor can be formed as soon as possible to ensure the safety and stability of the foundation pit. In addition, the prefabricated sump slab bottom reinforcement mesh and the sump slab surface reinforcement mesh with steel brackets fixed at the lower part are separated by layering, which avoids the overall prefabrication of the sump bottom slab reinforcement mesh and sump slab surface reinforcement mesh. The lifting quality caused by the combination is too large.
附图说明Description of drawings
图1为本发明一实施例的地下室底板集水坑钢筋网分层预制结构的结构示意图。Fig. 1 is a structural schematic diagram of a layered prefabricated structure of a basement floor sump reinforcement mesh according to an embodiment of the present invention.
图2为本发明一实施例中集水坑板底钢筋网及钢筋胎架的结构示意图。Fig. 2 is a structural schematic diagram of the reinforcement mesh and the reinforcement frame at the bottom of the sump slab in an embodiment of the present invention.
图3为本发明一实施例中集水坑板面钢筋网的结构示意图(未示出板顶吊圈)。Fig. 3 is a schematic diagram of the structure of the reinforcement mesh on the surface of the sump pit in an embodiment of the present invention (the hanging ring on the top of the slab is not shown).
图4为本发明一实施例中吊装集水坑板底钢筋网时的立体示意图。Fig. 4 is a three-dimensional schematic view of hoisting the reinforcement mesh at the bottom of the sump slab in an embodiment of the present invention.
图5为本发明一实施例中吊装集水坑板底钢筋网时的结构示意图。Fig. 5 is a schematic diagram of the structure when hoisting the reinforcement mesh at the bottom of the sump slab in an embodiment of the present invention.
图6为本发明一实施例中吊装集水坑板面钢筋网时的立体示意图。Fig. 6 is a three-dimensional schematic view of hoisting the reinforcement mesh on the surface of the sump pit in an embodiment of the present invention.
图7为本发明一实施例中吊装集水坑板面钢筋网时的结构示意图。Fig. 7 is a schematic diagram of the structure when hoisting the reinforcement mesh on the surface of the sump pit in an embodiment of the present invention.
图8为本发明一实施例中集水坑板底钢筋网与集水坑周边底板板底钢筋逐根对应连接以及集水坑板面钢筋网与集水坑周边底板板面钢筋逐根对应连接后的结构示意图。Fig. 8 shows the corresponding connection of the steel mesh at the bottom of the sump and the steel bars at the bottom of the bottom of the sump and the corresponding connection of the steel mesh at the bottom of the sump with the reinforcement of the bottom of the bottom of the sump in one embodiment of the present invention. Schematic diagram of the subsequent structure.
图中:100-集水坑预制钢筋网、1-集水坑板底钢筋网、11-水平底部钢筋网、12-侧部钢筋网、13-板底吊圈、2-钢筋支架、21-矩形顶部型钢钢圈、22-竖向角部型钢、23-竖向中部型钢、24-斜撑、3-集水坑板面钢筋网、31-坑底水平钢筋网、32-坑壁竖向钢筋网、33-坑顶水平钢筋网、35-板顶吊圈、4-垫层或者砖胎模、5-集水坑周边底板板底钢筋、6-集水坑周边底板板面钢筋、71-直角三角形钢架、72-条状型钢、8-吊索。In the figure: 100-prefabricated steel mesh for sump, 1-slab bottom steel mesh for sump, 11-horizontal bottom steel mesh, 12-side steel mesh, 13-slab bottom suspension ring, 2-steel support, 21- Rectangular top section steel rim, 22-vertical corner section steel, 23-vertical middle section section steel, 24-diagonal bracing, 3-sump surface reinforcement mesh, 31-pit bottom horizontal reinforcement mesh, 32-pit wall vertical Reinforcement mesh, 33-pit top horizontal reinforcement mesh, 35-slab top suspension ring, 4-cushion layer or brick tire mold, 5-bottom plate bottom reinforcement around sump pit, 6-bottom plate surface reinforcement around sump pit, 71 -Right triangle steel frame, 72-strip steel, 8-sling.
具体实施方式Detailed ways
以下结合附图和具体实施例对本发明作进一步详细说明。根据下面的说明和权利要求书,本发明的优点和特征将更清楚。以下将由所列举之实施例结合附图,详细说明本发明的技术内容及特征。需另外说明的是,附图均采用非常简化的形式且均使用非精准的比例,仅用以方便、明晰地辅助说明本发明实施例的目的。为叙述方便,下文中所述的“上”、“下”与附图的上、下的方向一致,但这不能成为本发明技术方案的限制。The present invention will be described in further detail below in conjunction with the accompanying drawings and specific embodiments. Advantages and features of the present invention will be apparent from the following description and claims. The technical content and features of the present invention will be described in detail below by referring to the illustrated embodiments in conjunction with the accompanying drawings. It should be further noted that all the drawings are in very simplified form and use imprecise scales, and are only used to facilitate and clearly assist the purpose of illustrating the embodiments of the present invention. For the convenience of description, the "up" and "down" described below are consistent with the directions of up and down in the drawings, but this should not be a limitation of the technical solution of the present invention.
实施例一Embodiment one
请参阅图1至图8,本实施例公开了一种地下室底板集水坑钢筋网分层预制结构,用于施工底板上的集水坑,包括:在施工现场或者加工厂提前预制的集水坑板底钢筋网1以及下部固定有钢筋支架2的集水坑板面钢筋网3,集水坑板底钢筋网1以及下部固定有钢筋支架2的集水坑板面钢筋网3合称为集水坑预制钢筋网100。所述集水坑板底钢筋网1呈盆状结构,所述集水坑板底钢筋网1铺设于拟建集水坑的垫层或者砖胎模4上,所述集水坑板面钢筋网3通过所述钢筋支架2架设于集水坑板底钢筋网1上方,所述集水坑板底钢筋网1与集水坑周边底板板底钢筋5逐根对应连接,所述集水坑板面钢筋网3与集水坑周边底板板面钢筋6逐根对应连接。Please refer to Fig. 1 to Fig. 8, this embodiment discloses a layered prefabricated structure of basement floor sump reinforcement mesh, which is used for the sump on the construction floor, including: prefabricated water collection at the construction site or processing plant The reinforcement mesh 1 at the bottom of the pit slab and the reinforcement mesh 3 on the surface of the sump slab with the steel support 2 fixed at the lower part, the reinforcement mesh 1 at the bottom of the slab of the sump and the reinforcement mesh 3 at the surface of the sump slab with the steel support 2 fixed at the lower part are collectively referred to as Prefabricated reinforcement mesh 100 for sump pit. The reinforcement mesh 1 at the bottom of the sump is in a basin-like structure, and the reinforcement mesh 1 at the bottom of the sump is laid on the cushion layer or the brick tire mold 4 of the sump to be built, and the reinforcement on the surface of the sump The net 3 is erected above the reinforcement mesh 1 at the bottom of the sump through the steel bar bracket 2, and the reinforcement mesh 1 at the bottom of the sump is connected with the steel bars 5 at the bottom of the bottom of the sump correspondingly one by one. The reinforcement mesh 3 on the surface of the plate is connected correspondingly with the reinforcement bars 6 on the surface of the bottom plate around the sump pit one by one.
本发明提供地下室底板集水坑钢筋网分层预制结构及其建造方法,通过分层即分开预制集水坑板底钢筋网1以及下部固定有钢筋支架2的集水坑板面钢筋网3,可以有效减少集水坑内的大量现场钢筋绑扎工作,提高施工效率,缩短施工工期,能够尽快形成基坑底板,可以确保基坑安全及稳定,对于超高层或高层尤显重要,而且提前预制有利于提升地下室底板集水坑钢筋网以及集水坑板面钢筋网3内钢筋定位及连接精度,从而解决了集水坑内钢筋绑扎工作条件差,钢筋定位难、施工繁琐的问题。此外,通过分层即分开预制集水坑板底钢筋网1以及下部固定有钢筋支架2的集水坑板面钢筋网3,避免了预制集水坑板底钢筋网1以及集水坑板面钢筋网3整体预制在一起所造成的吊装质量过大的问题,提高了施工的安全性。The present invention provides a layered prefabricated structure and a construction method for a basement floor sump reinforcement mesh. By layering, the prefabricated sump slab bottom reinforcement mesh 1 and the sump surface reinforcement mesh 3 fixed with a reinforcement bracket 2 are separated. It can effectively reduce a large number of on-site steel binding work in the sump, improve construction efficiency, shorten the construction period, and can form the foundation pit floor as soon as possible, which can ensure the safety and stability of the foundation pit. It is especially important for super high-rise or high-rise buildings, and prefabrication is beneficial Improve the positioning and connection accuracy of steel reinforcement mesh in the sump pit on the basement floor and reinforcement mesh 3 on the surface of the sump pit, thereby solving the problems of poor binding conditions for reinforcement in the sump pit, difficult reinforcement positioning, and cumbersome construction. In addition, by layering, that is, separating the steel mesh 1 at the bottom of the prefabricated sump slab and the steel mesh 3 on the slab surface of the sump with the steel support 2 fixed at the lower part, it avoids the prefabricated steel mesh 1 at the bottom of the sump slab and the slab surface of the sump pit. The problem of excessive hoisting quality caused by the overall prefabrication of the steel mesh 3 improves the safety of construction.
较佳的,在本实施例的地下室底板集水坑钢筋网分层预制结构中,所述集水坑板底钢筋网1包括水平底部钢筋网11与位于所述水平底部钢筋网11四周的侧部钢筋网12,也就是说,所述集水坑板底钢筋网1由一块水平钢筋网将其四周斜向上弯曲形成,所述侧部钢筋网12斜向上设置,所述侧部钢筋网12中斜向上的钢筋与集水坑周边底板板底钢筋5通过人工对应交叉锚固连接。为了便于吊装集水坑板底钢筋网1,所述侧部钢筋网12的四个角上均设有一个板底吊圈13。Preferably, in the layered prefabricated structure of the basement floor sump reinforcement mesh in this embodiment, the sump slab bottom reinforcement mesh 1 includes a horizontal bottom reinforcement mesh 11 and sides located around the horizontal bottom reinforcement mesh 11. The upper reinforcement mesh 12, that is to say, the bottom reinforcement mesh 1 of the sump plate is formed by bending its surroundings obliquely upwards by a horizontal reinforcement mesh, the side reinforcement mesh 12 is arranged obliquely upward, and the side reinforcement mesh 12 The steel bars slanted upwards are connected with the steel bars 5 at the bottom of the bottom slab around the sump pit through artificial corresponding cross-anchoring. In order to facilitate hoisting of the reinforcement mesh 1 at the bottom of the sump, a bottom suspension ring 13 is provided on the four corners of the side reinforcement mesh 12 .
较佳的,在本实施例的地下室底板集水坑钢筋网分层预制结构中,所述集水坑板面钢筋网3包括坑底水平钢筋网31、坑壁竖向钢筋网32以及坑顶水平钢筋网33,所述坑壁竖向钢筋网32设置于所述坑底水平钢筋网31的四周,所述坑顶水平钢筋网33呈“回字形”,坑顶水平钢筋网33的内圈与所述坑壁竖向钢筋网32的上端口相匹配且固定连接,所述坑顶水平钢筋网33的外圈处钢筋与集水坑周边底板板面钢筋6逐根对应连接。逐根对应连接时,可以通过焊接工艺或者采用直螺纹连接的形式。对于大于16mm的钢筋可以直接采用直螺纹套筒方式连接,在确保连接强度的情况下,提高连接效率。Preferably, in the layered prefabricated structure of the basement floor sump reinforcement mesh in this embodiment, the sump surface reinforcement mesh 3 includes a pit bottom horizontal reinforcement mesh 31, a pit wall vertical reinforcement mesh 32 and a pit top Horizontal reinforced mesh 33, the vertical reinforced mesh 32 of the pit wall is arranged around the horizontal reinforced mesh 31 at the bottom of the pit, the horizontal reinforced mesh 33 on the top of the pit is "back-shaped", and the inner ring of the horizontal reinforced mesh 33 on the pit top It is matched with and fixedly connected to the upper port of the vertical steel mesh 32 on the pit wall, and the steel bars at the outer circle of the horizontal steel mesh 33 on the pit roof are connected with the steel bars 6 on the bottom plate surface around the sump correspondingly one by one. When the corresponding connection is made one by one, it can be connected by welding process or straight thread connection. For steel bars larger than 16mm, it can be directly connected by straight thread sleeve, which can improve the connection efficiency while ensuring the connection strength.
优选的,在集水坑板面钢筋网3中,所述坑底水平钢筋网31与所述水平底部钢筋网11均呈矩形,所述钢筋支架2包括矩形顶部型钢钢圈21与四根竖向角部型钢22,所述矩形顶部型钢钢圈21的形状和大小与所述集水坑板底钢筋网1的所述水平底部钢筋网11相对应,所述四根竖向角部型钢22固定设置于所述矩形顶部型钢钢圈21的四个角下方,所述四根竖向角部型钢22的下端设置于所述集水坑板底钢筋网1的所述水平底部钢筋网11的四个角位置,所述矩形顶部型钢钢圈21支撑于所述集水坑板面钢筋网3的坑顶水平钢筋网33的下表面。Preferably, in the reinforcement mesh 3 on the surface of the sump pit, the horizontal reinforcement mesh 31 at the bottom of the pit and the horizontal bottom reinforcement mesh 11 are both rectangular, and the reinforcement support 2 includes a rectangular top shaped steel ring 21 and four vertical To the corner shaped steel 22, the shape and size of the rectangular top shaped steel ring 21 correspond to the horizontal bottom reinforced mesh 11 of the sump bottom steel mesh 1, and the four vertical corner shaped steel 22 It is fixedly arranged under the four corners of the rectangular top steel ring 21, and the lower ends of the four vertical corner steel rings 22 are arranged on the horizontal bottom steel mesh 11 of the bottom steel mesh 1 of the sump pit. At the four corners, the rectangular top shaped steel ring 21 is supported on the lower surface of the pit top horizontal steel mesh 33 of the sump surface steel mesh 3 .
较佳的,为了提高钢筋支架2的强度,实现对集水坑板面钢筋网3更加稳定的支撑,所述钢筋支架2还包括四根竖向中部型钢23,所述竖向中部型钢23分别设置于所述矩形顶部型钢钢圈21的四条边的中部下方。每根竖向中部型钢23的下端通过两根斜撑24分别连接于所述矩形顶部型钢钢圈21上同侧边的两端。Preferably, in order to improve the strength of the steel bar support 2 and realize a more stable support for the reinforcement mesh 3 on the surface of the sump pit, the steel bar support 2 also includes four vertical middle section steels 23, and the vertical middle section steel sections 23 are respectively It is arranged below the middle part of the four sides of the rectangular top shaped steel ring 21 . The lower end of each vertical middle section steel 23 is respectively connected to the two ends of the same side on the rectangular top section steel ring 21 through two diagonal braces 24 .
较佳的,为了便于吊装集水坑板面钢筋网3,在本实施例的中,还包括若干板顶吊圈35,所述板顶吊圈35通过连接杆固定于所述竖向角部型钢22上,或者通过连接杆固定于所述竖向中部型钢23上。Preferably, in order to facilitate the hoisting of the steel mesh 3 on the surface of the sump pit, in this embodiment, a number of plate top hanging rings 35 are also included, and the plate top hanging rings 35 are fixed to the vertical corners through connecting rods. on the section steel 22, or be fixed on the vertical middle section section steel 23 by connecting rods.
较佳的,为了提高集水坑板底钢筋网1的制作精度和制作效率,在本实施例的地下室底板集水坑钢筋网分层预制结构中,所述集水坑板底钢筋网1借助钢筋胎架加工制作,所述钢筋胎架由四组支撑架围合组成,每组支撑架包括至少三对竖向间隔设置的直角三角形钢架71与一对平行的条状型钢72,每个直角三角形钢架71由斜边型钢、水平直角边型钢以及竖向直角边型钢围成,所述直角三角形架的所述斜边型钢靠内设置,每组支撑架中的各个水平直角边型钢通过一对平行的条状型钢72连接。其中斜边型钢与集水坑板底钢筋网1的侧部钢筋网12的斜率相同,用于平稳支撑集水坑板底钢筋网1的侧部钢筋网12,实现集水坑板底钢筋网1与水平底部钢筋网11的精确定位,以及集水坑板底钢筋网1快速预制。Preferably, in order to improve the manufacturing accuracy and manufacturing efficiency of the steel mesh 1 at the bottom of the sump pit, in the layered prefabricated structure of the steel mesh at the bottom of the basement sump according to this embodiment, the steel mesh 1 at the bottom of the sump pit is The reinforced tire frame is processed and manufactured, and the reinforced tire frame is composed of four sets of support frames, each set of support frames includes at least three pairs of right-angled triangle steel frames 71 arranged at vertical intervals and a pair of parallel strip shaped steel 72, each The right-angled triangle steel frame 71 is surrounded by hypotenuse section steel, horizontal section steel and vertical section steel. A pair of parallel bar shaped steel 72 is connected. The slope of the hypotenuse section steel is the same as that of the side reinforcement mesh 12 of the bottom reinforcement mesh 1 of the sump pit, which is used to stably support the side reinforcement mesh 12 of the bottom reinforcement mesh 1 of the sump pit to realize the reinforcement mesh at the bottom of the sump pit. 1 and the precise positioning of the horizontal bottom reinforcement mesh 11, and the rapid prefabrication of the sump slab bottom reinforcement mesh 1.
实施例二Embodiment two
请继续参阅图1至图8,本实施例还公开了一种地下室底板集水坑钢筋网分层预制建造方法,采用如实施例一所述的地下室底板集水坑钢筋网分层预制结构,包括如下步骤:Please continue to refer to Fig. 1 to Fig. 8, this embodiment also discloses a layered prefabricated construction method of reinforced mesh in the basement sump pit, adopting the layered prefabricated structure of the reinforced mesh in the basement sump pit as described in the first embodiment, Including the following steps:
步骤一,集水坑钢筋网设计。集水坑钢筋网设计,包括确定集水坑及坑边钢筋预制的范围、预制钢筋网(即集水坑钢筋网,包括集水坑板底钢筋网1以及下部固定有钢筋支架2的集水坑板面钢筋网3)下料与排布、钢筋支架2设计与排布、钢筋网吊钩设计与验算、钢筋网吊装验算等。其中需综合考虑塔吊吊装能力、集水坑内钢筋绑扎难度、坑内整体钢筋网预制、预制钢筋网与周边钢筋连接、钢筋网胎架制作难易程度等方面综合考虑预制钢筋网的范围;预制钢筋网下料与排布包括预制钢筋下料计算、钢筋空间排布等,并建立预制钢筋网的三维模型等;满足预制钢筋网自身的稳定及受力要求,进行钢筋支架2设计与布置;此外,为满足钢筋网整体吊装需求,需提前在深化设计阶段额外布置吊钩,进行钢筋网吊装验算,为满足钢筋网吊装刚度及强度需求,需额外布置附加钢筋等。Step 1, sump reinforcement mesh design. The design of the sump reinforcement mesh includes determining the scope of the prefabrication of the sump pit and the reinforcement around the pit, the prefabricated reinforcement mesh (that is, the sump pit reinforcement mesh, including the bottom reinforcement mesh 1 of the sump pit and the water collection pit with the reinforcement bracket 2 fixed at the bottom 3) Cutting and arrangement of reinforced mesh on pit slab surface, design and arrangement of reinforced support 2, design and checking calculation of steel mesh hook, checking calculation of steel mesh hoisting, etc. Among them, it is necessary to comprehensively consider the range of prefabricated steel mesh in terms of the hoisting capacity of the tower crane, the difficulty of binding steel bars in the sump, the prefabrication of the overall steel mesh in the pit, the connection between the prefabricated steel mesh and the surrounding steel bars, and the difficulty of making the steel mesh tire frame; Cutting and arrangement include prefabricated reinforcement blanking calculation, reinforcement spatial arrangement, etc., and establishment of 3D model of prefabricated reinforcement mesh, etc.; to meet the stability and force requirements of prefabricated reinforcement mesh itself, design and layout of reinforcement support 2; in addition, In order to meet the overall hoisting requirements of the steel mesh, it is necessary to arrange additional hooks in the detailed design stage in advance, and carry out the hoisting calculation of the steel mesh. In order to meet the rigidity and strength requirements of the steel mesh hoisting, additional reinforcement is required.
步骤二,集水坑预制钢筋网100预制加工,所述集水坑钢筋网包括集水坑板底钢筋网1、以及下部固定有钢筋支架2的集水坑板面钢筋网3。钢筋网加工包括钢筋网胎架设计与制作,钢筋网成型工艺、钢筋网精度控制等。其中为满足集水坑钢筋网预制需求,需在项目现场或加工厂设计并制作一个钢筋网高精度制作胎架,胎架外形及尺寸需根据预制钢筋网外形及尺寸确定。在项目现场或加工工厂先进行搭设钢筋网胎架,进行板底钢筋网的预制加工,如图2;搭设钢筋支架2,进行集水坑板面钢筋网3的预制加工,如图3所示。此外,在钢筋网加工过程中,需严格控制胎架的加工精度、单根钢筋的下料及安装精度等。Step 2: The sump prefabricated reinforcement mesh 100 is prefabricated and processed, and the sump pit reinforcement mesh includes the sump bottom reinforcement mesh 1 and the sump surface reinforcement mesh 3 with the reinforcement support 2 fixed at the bottom. Reinforced mesh processing includes the design and manufacture of reinforced mesh tire frames, the forming process of reinforced mesh, the precision control of reinforced mesh, etc. Among them, in order to meet the prefabrication requirements of the sump reinforcement mesh, it is necessary to design and manufacture a steel mesh high-precision tire frame on the project site or in the processing plant. The shape and size of the tire frame need to be determined according to the shape and size of the prefabricated steel mesh. At the project site or in the processing factory, first set up the steel mesh tire frame to prefabricate the steel mesh at the bottom of the slab, as shown in Figure 2; set up the steel bar support 2, and carry out the prefabrication of the steel mesh 3 on the surface of the sump pit, as shown in Figure 3 . In addition, in the process of steel mesh processing, it is necessary to strictly control the processing accuracy of the tire frame, the blanking and installation accuracy of a single steel bar, etc.
步骤三,集水坑预制钢筋网100分层吊装与拼装:先吊装集水坑板底钢筋网1,再吊装下部固定有钢筋支架2的集水坑板面钢筋网3,使得集水坑板底钢筋网1与集水坑板面钢筋网3由下至上依次设置于集水坑内。具体的,集水坑预制钢筋网100分层吊装与拼装,包括钢筋网吊装方案确定、集水坑板底钢筋网1于集水坑内精确定位、集水坑板底钢筋网1与集水坑板面钢筋网3拼装。其中需提前根据塔吊吊装能力确定集水坑底板钢筋网1的大小及重量,以兼顾吊装能力及尽量预制的原则进行;制定预制钢筋网分层吊装专项方案,并制定相应的应急措施等,先吊装板底钢筋网,如图4、5所示,后吊装集水坑板面钢筋网3及下部钢筋支架2,如图6、7所示。Step 3, layered hoisting and assembling of prefabricated reinforcement mesh 100 in the sump: first hoist the reinforcement mesh 1 at the bottom of the sump slab, and then hoist the reinforcement mesh 3 on the surface of the sump slab with the reinforcement bracket 2 fixed at the lower part, so that the sump slab The bottom reinforcement mesh 1 and the sump surface reinforcement mesh 3 are sequentially arranged in the sump from bottom to top. Specifically, the prefabricated steel mesh 100 in the sump is hoisted and assembled in layers, including the determination of the hoisting scheme of the steel mesh, the precise positioning of the steel mesh 1 at the bottom of the sump pit in the sump, the reinforcement mesh 1 at the bottom of the sump pit Panel steel mesh 3 assembled. Among them, it is necessary to determine the size and weight of the reinforcement mesh 1 on the sump floor according to the hoisting capacity of the tower crane in advance, so as to take into account the hoisting capacity and the principle of prefabrication as much as possible; formulate a special plan for layered hoisting of prefabricated reinforcement meshes, and formulate corresponding emergency measures, etc., first Hoist the reinforcement mesh at the bottom of the slab, as shown in Figures 4 and 5, and then hoist the reinforcement mesh 3 on the surface of the sump pit and the lower reinforcement support 2, as shown in Figures 6 and 7.
优选的,在上述的地下室底板集水坑钢筋网分层预制建造方法中,所述步骤三之前,在拟建集水坑的垫层或者砖胎模4的四个角部画控制线,在吊装过程中利用集水坑板底钢筋网1的底部四个角对准垫层上控制线,完成集水坑板底钢筋网1精确入坑定位工作。也就是说,在集水坑内垫层四角部或四边中线画控制线,在吊装过程中板底钢筋网四角部钢筋对准垫层上控制线,完成板底钢筋网精确入坑定位工作。利用塔吊将集水坑板面钢筋网3与其下部钢筋支架2整体吊装入坑,可利用下部钢筋支架2进行精确定位。Preferably, in the above-mentioned layered prefabricated construction method of the basement floor sump reinforcement mesh, before the step 3, control lines are drawn on the four corners of the cushion layer of the sump to be built or the brick tire mold 4, and the During the hoisting process, the bottom four corners of the steel mesh 1 at the bottom of the sump pit are aligned with the control line on the cushion layer to complete the precise positioning of the steel mesh 1 at the bottom of the sump pit. That is to say, draw the control line at the four corners or the center line of the four sides of the cushion in the sump, and during the hoisting process, the steel bars at the four corners of the steel mesh at the bottom of the slab are aligned with the control line on the cushion, and the precise positioning of the steel mesh at the bottom of the slab is completed. Utilize the tower crane to integrally hoist the reinforced mesh 3 on the surface of the sump pit and its lower steel support 2 into the pit, and the lower steel support 2 can be used for precise positioning.
步骤四,将集水坑板底钢筋网1与集水坑周边底板板底钢筋5逐根对应连接,将集水坑板面钢筋网3与集水坑周边底板板面钢筋6逐根对应连接。预制钢筋网与周边底板钢筋连接包括利用焊接或套筒连接方式逐根将预制钢筋网四边与周边底板钢筋进行连接,可利用焊接工艺进行钢筋连接或大于16mm的钢筋直接采用直螺纹套筒连接,如图8所示。Step 4: Connect the reinforcement mesh 1 at the bottom of the sump pit with the steel bars 5 at the bottom of the bottom slab around the sump correspondingly, and connect the reinforcement mesh 3 at the bottom of the sump with the steel bars 6 at the bottom of the bottom of the sump. . The connection between the prefabricated steel mesh and the surrounding bottom plate reinforcement includes connecting the four sides of the prefabricated steel mesh with the surrounding bottom plate steel bars one by one by welding or sleeve connection. The welding process can be used to connect the steel bars or the steel bars larger than 16mm can be directly connected by straight thread sleeves. As shown in Figure 8.
步骤五;浇筑带有集水坑的底板混凝土。Step 5: Pouring the concrete of the bottom slab with the sump.
本发明的地下室底板集水坑钢筋网分层预制建造方法,通过在项目现场或加工厂提前分层预制集水坑板底及板面钢筋网,利用塔吊将集水坑板底钢筋网1及集水坑板面钢筋网分别吊装入坑,在坑内拼装成整体,放置于集水坑的垫层或砖胎模上,人工连接预制钢筋网与周边底板钢筋,最终浇筑混凝土的施工工艺,由于分层即分开预制集水坑板底钢筋网1以及下部固定有钢筋支架2的集水坑板面钢筋网3,可以有效减少集水坑内的大量现场钢筋绑扎工作,提高施工效率,缩短施工工期,能够尽快形成基坑底板,可以确保基坑安全及稳定,而且提前预制有利于提升集水坑板底钢筋网1以及集水坑板面钢筋网3内钢筋定位及连接精度,从而解决了集水坑内钢筋绑扎工作条件差,钢筋定位难、施工繁琐的问题。此外,通过分层即分开预制集水坑板底钢筋网1以及下部固定有钢筋支架2的集水坑板面钢筋网3,避免了预制集水坑板底钢筋网1以及集水坑板面钢筋网3整体预制在一起所造成的吊装质量过大的问题,提高了施工的安全性。The layered prefabrication construction method of the reinforcement mesh of the sump pit of the basement floor of the present invention is to prefabricate the bottom of the sump pit and the reinforcement mesh on the surface of the sump by layering in advance at the project site or in the processing plant, and use the tower crane to place the bottom reinforcement mesh 1 and the bottom of the sump pit. The reinforcement mesh on the surface of the sump pit is hoisted into the pit separately, assembled into a whole in the pit, placed on the cushion layer or brick tire form of the sump pit, the prefabricated reinforcement mesh and the surrounding bottom plate reinforcement are manually connected, and the construction process of finally pouring concrete is due to Layering means separating the prefabricated sump slab bottom reinforcement mesh 1 and the sump slab surface reinforcement mesh 3 with the steel support 2 fixed at the lower part, which can effectively reduce a large number of on-site reinforcement work in the sump pit, improve construction efficiency, and shorten the construction period , the foundation pit floor can be formed as soon as possible, which can ensure the safety and stability of the foundation pit, and the prefabrication in advance is conducive to improving the positioning and connection accuracy of the reinforcement mesh 1 at the bottom of the sump pit and the reinforcement mesh 3 on the surface of the sump pit, thus solving the problem of centralized The working conditions of the steel bar binding in the puddle are poor, the positioning of the steel bar is difficult, and the construction is cumbersome. In addition, by layering, that is, separating the steel mesh 1 at the bottom of the prefabricated sump slab and the steel mesh 3 on the slab surface of the sump with the steel support 2 fixed at the lower part, it avoids The problem of excessive hoisting quality caused by the overall prefabrication of the steel mesh 3 improves the safety of construction.
上述描述仅是对本发明较佳实施例的描述,并非对本发明范围的任何限定,本发明领域的普通技术人员根据上述揭示内容做的任何变更、修饰,均属于权利要求书的保护范围。The above description is only a description of the preferred embodiments of the present invention, and does not limit the scope of the present invention. Any changes and modifications made by those of ordinary skill in the field of the present invention based on the above disclosures shall fall within the protection scope of the claims.
Claims (7)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201611246113.5A CN106638645B (en) | 2016-12-29 | 2016-12-29 | Basement bottom board catch pit steel mesh is layered precast construction and method of construction |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201611246113.5A CN106638645B (en) | 2016-12-29 | 2016-12-29 | Basement bottom board catch pit steel mesh is layered precast construction and method of construction |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN106638645A CN106638645A (en) | 2017-05-10 |
| CN106638645B true CN106638645B (en) | 2018-12-18 |
Family
ID=58837114
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201611246113.5A Expired - Fee Related CN106638645B (en) | 2016-12-29 | 2016-12-29 | Basement bottom board catch pit steel mesh is layered precast construction and method of construction |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN106638645B (en) |
Families Citing this family (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107891510B (en) * | 2017-12-11 | 2023-10-17 | 安徽海龙建筑工业有限公司 | Split prefabricated part toilet mold and molding process thereof |
| CN111021361A (en) * | 2019-12-20 | 2020-04-17 | 中国建筑第八工程局有限公司 | Installation construction method of foundation pit bottom plate reinforcing steel bars |
| CN112359874A (en) * | 2020-11-18 | 2021-02-12 | 中建八局第三建设有限公司 | Construction method of basement sump structure |
| CN115030205B (en) * | 2022-06-07 | 2024-04-26 | 上海城建市政工程(集团)有限公司 | Integrated rapid construction method for raft, water collecting well and elevator shaft of deep foundation pit |
| CN116556431A (en) * | 2023-05-29 | 2023-08-08 | 中建八局第四建设有限公司 | How to make a basement sump |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN201176598Y (en) * | 2007-12-28 | 2009-01-07 | 浙江环宇建设集团有限公司 | Foundation slab reinforced bar caging over subway tunnel |
| CN104712146A (en) * | 2013-12-12 | 2015-06-17 | 中国核工业第五建设有限公司 | Steel bar binding construction method in wall body construction |
| CN105952061A (en) * | 2016-06-24 | 2016-09-21 | 东南大学 | Prefabricated shear wall reinforcement cage member and column reinforcement cage member as well as manufacturing and assembling methods thereof |
| CN206418512U (en) * | 2016-12-29 | 2017-08-18 | 上海建工四建集团有限公司 | Basement bottom board catch pit bar-mat reinforcement is layered precast construction |
-
2016
- 2016-12-29 CN CN201611246113.5A patent/CN106638645B/en not_active Expired - Fee Related
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN201176598Y (en) * | 2007-12-28 | 2009-01-07 | 浙江环宇建设集团有限公司 | Foundation slab reinforced bar caging over subway tunnel |
| CN104712146A (en) * | 2013-12-12 | 2015-06-17 | 中国核工业第五建设有限公司 | Steel bar binding construction method in wall body construction |
| CN105952061A (en) * | 2016-06-24 | 2016-09-21 | 东南大学 | Prefabricated shear wall reinforcement cage member and column reinforcement cage member as well as manufacturing and assembling methods thereof |
| CN206418512U (en) * | 2016-12-29 | 2017-08-18 | 上海建工四建集团有限公司 | Basement bottom board catch pit bar-mat reinforcement is layered precast construction |
Also Published As
| Publication number | Publication date |
|---|---|
| CN106638645A (en) | 2017-05-10 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN106638645B (en) | Basement bottom board catch pit steel mesh is layered precast construction and method of construction | |
| CN106522372B (en) | A kind of hybrid integrated house and construction method | |
| CN103452350B (en) | Assembling electronic workshop and construction method thereof | |
| CN108049666B (en) | A kind of echelon installation method of super plane multilayer steel truss electronic workshop steel construction | |
| CN105201107A (en) | Construction method for stacked plate type shear wall of underground garage | |
| CN204001652U (en) | The portable exterior wall operating platform of fabricated shear wall structure | |
| CN104234305A (en) | Reinforced concrete prefabricated part plate with reserved holes in vertical and transverse directions | |
| CN106836255B (en) | Integral prefabricated structure and construction method of reinforcement mesh in sump pit of basement floor | |
| CN102888894A (en) | Structure and construction method for steel frame building with inner cylinder, outer frame and shape like Chinese character 'hui' | |
| CN202577571U (en) | Structure of inner barrel-outer frame clip-shaped steel framework building | |
| CN202064281U (en) | Slip form frame | |
| CN102975278A (en) | Mold system and prefabrication method for architectural prefabricated parts | |
| CN116122579B (en) | Hoisting method for bidirectional bending dome bracket | |
| CN105951683A (en) | Construction method for corbel steel reinforcements of gate pier | |
| CN206956752U (en) | The assembly of steel cofferdam coxopodite and suspension system | |
| CN206418512U (en) | Basement bottom board catch pit bar-mat reinforcement is layered precast construction | |
| CN111364642A (en) | A prefabricated energy-consuming shear wall system and its construction method | |
| CN102251679B (en) | Construction method | |
| CN213204438U (en) | Semi-prefabricated and semi-cast-in-place building component | |
| CN206418513U (en) | The integral prefabricated structure of basement bottom board catch pit bar-mat reinforcement | |
| CN203654454U (en) | Upper-lower-layer prefabricated balcony slabs, and support connecting structures therebetween and beams | |
| CN107965193A (en) | Diameter Silo structure roof construction method | |
| CN102704399B (en) | Reinforcement binding and jointing operating room and reinforcement binding and jointing method | |
| CN208802765U (en) | A self-elevating high-rise modular building hoisting equipment | |
| CN114250975A (en) | A wellbore hydraulic integrated distribution platform for building construction |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20181218 |