CN106802845A - A kind of power consumption test method and system based on mobile terminal - Google Patents

A kind of power consumption test method and system based on mobile terminal Download PDF

Info

Publication number
CN106802845A
CN106802845A CN201710013223.5A CN201710013223A CN106802845A CN 106802845 A CN106802845 A CN 106802845A CN 201710013223 A CN201710013223 A CN 201710013223A CN 106802845 A CN106802845 A CN 106802845A
Authority
CN
China
Prior art keywords
test
mobile terminal
power consumption
time
control terminal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710013223.5A
Other languages
Chinese (zh)
Inventor
古启才
吴兆云
赖燕铭
石雷
吴泽威
宋彬
胡亚军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huizhou TCL Mobile Communication Co Ltd
Original Assignee
Huizhou TCL Mobile Communication Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huizhou TCL Mobile Communication Co Ltd filed Critical Huizhou TCL Mobile Communication Co Ltd
Priority to CN201710013223.5A priority Critical patent/CN106802845A/en
Publication of CN106802845A publication Critical patent/CN106802845A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F11/00Error detection; Error correction; Monitoring
    • G06F11/22Detection or location of defective computer hardware by testing during standby operation or during idle time, e.g. start-up testing
    • G06F11/2268Logging of test results
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F11/00Error detection; Error correction; Monitoring
    • G06F11/22Detection or location of defective computer hardware by testing during standby operation or during idle time, e.g. start-up testing
    • G06F11/2273Test methods

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Theoretical Computer Science (AREA)
  • Computer Hardware Design (AREA)
  • Quality & Reliability (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Telephone Function (AREA)
  • Mobile Radio Communication Systems (AREA)

Abstract

The invention discloses a kind of power consumption test method and system based on mobile terminal, method includes:The default test command information that acquisition for mobile terminal control terminal sends, and it is simultaneously synchronous to obtain the time of control terminal;The default test command information of mobile terminal parsing, the default test command information according to parsing carries out power consumption test, and the power consumption response data of recording test time and mobile terminal is simultaneously uploaded to control terminal;Control terminal obtains testing time and the power consumption response data that mobile terminal is returned, and shows and stores.The automatic test of the achievable mobile terminal power consumption test of the present invention, is significantly reduced the workload of engineer, improves testing efficiency, reduces human cost, reduces Project-developing cost.

Description

A kind of power consumption test method and system based on mobile terminal
Technical field
The present invention relates to technical field of mobile terminals, more particularly to a kind of power consumption test method based on mobile terminal and it is System.
Background technology
As the performance of mobile terminal is continued to optimize, power problemses are of crucial importance.Each of mobile terminal R&D and production Stage and each important version are required for carrying out up to a hundred test cases carrying out power consumption test.In the prior art, it is mobile whole The power consumption test at end needs to carry out the progressively test of each single item manually, and usual wheel test needs to complete for more than 2 days.With hardware The increase in stage, the increase of version, this causes greatly waste to manpower effectiveness, and the time spends excessive, and manpower effectiveness is low, and And manual test data are unstable, cannot also power consumption test be carried out to many mobile terminals.
Therefore, prior art has yet to be improved and developed.
The content of the invention
In view of the deficiencies in the prior art, present invention aim at provide a kind of power consumption test method based on mobile terminal and System, it is intended to which solving the power consumption test of mobile terminal in the prior art needs to carry out the progressively test of each single item manually, time flower Take excessive, the low technical problem of manpower effectiveness.
Technical scheme is as follows:
A kind of power consumption test method based on mobile terminal, wherein, method includes step:
The default test command information that A, acquisition for mobile terminal control terminal send, and it is simultaneously synchronous to obtain the time of control terminal;
B, the default test command information of mobile terminal parsing, the default test command information according to parsing carry out power consumption test, remember The power consumption response data of record testing time and mobile terminal is simultaneously uploaded to control terminal;
C, control terminal obtain testing time and the power consumption response data that mobile terminal is returned, and show and store.
The described power consumption test method based on mobile terminal, wherein, step is also included before the step A:
The IP advance to the mobile terminal to be tested of S, control terminal, Current Voltage test address, test command information set Put.
The described power consumption test method based on mobile terminal, wherein, the step A specifically includes step:
A1, control terminal timing send default test command information to the corresponding mobile terminals of IP for pre-setting by network;
When A2, acquisition for mobile terminal preset test command information and parse test item and test in default test command information Between;
The time of A3, acquisition for mobile terminal control terminal, and the time of mobile terminal is synchronized with the time of control terminal.
The described power consumption test method based on mobile terminal, wherein, the step B specifically includes step:
B1, control terminal sending power consumption response data acquisition instructions to the corresponding power consumption in default Current Voltage test address are gathered Instrument;
The default different test item sequence numbers of B2, mobile terminal enquiry relation table corresponding with test response of step, obtains default survey The corresponding response operation of examination item, is configured according to the response operation for obtaining to mobile terminal, obtains default test item start-stop Time;
B3, according to carrying out power consumption test, power consumption acquisition instrument to mobile terminal between at the beginning of the default test item beginning and ending time Collection mobile terminal to the power consumption response data of test item and be uploaded to control terminal;
B4, when detect test item test after the completion of, record test the end time, will test the time started and the end time upload To control terminal.
The described power consumption test method based on mobile terminal, wherein, the step C specifically includes step:
C1, control terminal obtain the test time started that the power consumption response data and mobile terminal of the collection of power consumption acquisition instrument are uploaded And the end time, after power consumption response data is processed with the test beginning and ending time, generation data form is displayed in control terminal and deposits Storage.
A kind of power consumption test system based on mobile terminal, wherein, system includes:
Instruction is obtained and time synchronized module, for the default test command information that acquisition for mobile terminal control terminal sends, and The time for obtaining control terminal is simultaneously synchronous;
Test module, for the default test command information of mobile terminal parsing, the default test command information according to parsing is carried out The power consumption response data of power consumption test, recording test time and mobile terminal is simultaneously uploaded to control terminal;
Display and memory module, testing time and the power consumption response data that mobile terminal is returned, display are obtained for control terminal And store.
The described power consumption test system based on mobile terminal, wherein, the system also includes:
Module is pre-set, for control terminal IP, Current Voltage test address, test in advance to the mobile terminal to be tested Command information is configured.
The described power consumption test system based on mobile terminal, wherein, the instruction is obtained and included with time synchronized module:
Instruction sending unit, default test command information to IP pairs for pre-setting is sent for control terminal timing by network The mobile terminal answered;
Instruction resolution unit, presets test command information and parses the survey in default test command information for acquisition for mobile terminal Examination item and the testing time;
Time synchronized unit, for the time of acquisition for mobile terminal control terminal, and by the time of mobile terminal and control terminal Time synchronize.
The described power consumption test system based on mobile terminal, wherein, the test module is specifically included:
Acquisition instructions transmitting element, tests for control terminal sending power consumption response data acquisition instructions to default Current Voltage The corresponding power consumption acquisition instrument in address;
Inquiry and setting unit, for the default different test item sequence numbers of mobile terminal enquiry pass corresponding with test response of step It is table, obtains the corresponding response operation of default test item, mobile terminal is configured according to the response operation for obtaining, obtains pre- If the test item beginning and ending time;
Test cell, for according to carrying out power consumption test, work(to mobile terminal between at the beginning of the default test item beginning and ending time Consumption acquisition instrument collection mobile terminal to the power consumption response data of test item and be uploaded to control terminal;
Record and uploading unit, for after the completion of test item test is detected, record to test the end time, when test is started Between and the end time be uploaded to control terminal.
The described power consumption test system based on mobile terminal, wherein, the display is with memory module specifically for control Terminal obtains the test time started and end time that the power consumption response data and mobile terminal of the collection of power consumption acquisition instrument are uploaded, After power consumption response data is processed with the test beginning and ending time, generation data form is displayed in control terminal and stores.
The invention provides a kind of power consumption test method and system based on mobile terminal, the achievable mobile terminal of the present invention The automatic test of power consumption test, is significantly reduced the workload of engineer, improves testing efficiency, reduces human cost, reduces Project-developing cost, by the automatic test of instrument, improves the unstability of manual testing, realizes that autoreport is exported, Many mobile terminal power consumptions can be supported while being tested.
Brief description of the drawings
Fig. 1 is a kind of flow chart of the preferred embodiment of power consumption test method based on mobile terminal of the invention.
Fig. 2 is that a kind of framework of the concrete application embodiment of power consumption test method based on mobile terminal of the invention is illustrated Figure.
Fig. 3 is a kind of flow chart of the concrete application embodiment of power consumption test method based on mobile terminal of the invention.
Fig. 4 is a kind of principle of work and power frame of the preferred embodiment of power consumption test system based on mobile terminal of the invention Figure.
Specific embodiment
To make the purpose of the present invention, technical scheme and effect clearer, clear and definite, below to the present invention further specifically It is bright.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, it is not intended to limit the present invention.
Present invention also offers a kind of flow chart of the preferred embodiment of the power consumption test method based on mobile terminal, such as Shown in Fig. 1, method includes step:
The default test command information that S100, acquisition for mobile terminal control terminal send, and it is simultaneously same to obtain the time of control terminal Step;
S200, the default test command information of mobile terminal parsing, the default test command information according to parsing carry out power consumption test, The power consumption response data of recording test time and mobile terminal is simultaneously uploaded to control terminal;
S300, control terminal obtain testing time and the power consumption response data that mobile terminal is returned, and show and store.
During specific implementation, as shown in Fig. 2 control terminal is the computer for being installed as automating power consumption test software, calculate Machine includes Ethernet interface and GPIB capture cards, and the Ethernet interface of its Computer passes through AP routers or interchanger and movement Terminal is attached, and the preferential use Agilent power supply test instrument of the instrument of power consumption test, and Agilent tester passes through USB sets up with mobile terminal and is connected, and Agilent power supply test instrument is by GPIB data wires and the GPIB capture cards of computer Set up connection.General purpose interface bus(General-Purpose Interface Bus, GPIB)It is that a kind of equipment and computer connect The bus for connecing.Most of desk-top instruments are connected with computer by GPIB lines and gpib interface.Computer can control to survey simultaneously The multiple mobile terminals of examination, each mobile terminal corresponds to different IP respectively, and Agilent power supply test instrument is with mobile terminal one by one Correspondence, so as to ensure that data acquisition results are corresponded.
Mobile terminal power consumption test application program can be installed in step S100 on mobile terminal, and obtain the survey of control terminal Examination command information, and it is synchronous with the time holding of control terminal.Wherein control terminal is designated as computer or PC ends.
In step S200 in different test items, according to default time start by set date WIFI, it is responsible for and PC ends is referred to Order interaction, so as to the response for realizing different testing procedures is processed;After director data interaction is finished, then WIFI is closed;When reaching To after pre-conditioned, then power consumption test is carried out, and record test beginning and ending time point.Tester is built by gpib bus The many Agilent power supply test instruments of default different address numbering, using USB data line, connect mobile terminal, carry out in real time The collection of Current Voltage.
Control terminal automation power consumption test software, obtains the data of GPIB capture cards in step S300, is located in real time Reason, real-time voltage current waveform display, database purchase, and by wireless WIFI, real-time control different mobile terminal, according to Default test item carries out click response, realizes power consumption automatic test.
In further embodiment, step is also included before step S100:
The IP advance to the mobile terminal to be tested of S, control terminal, Current Voltage test address, test command information set Put.
During specific implementation, control terminal presets the IP of the mobile terminal for needing test, presets corresponding Agilent voltage Address, presets the testing time that test sequence number and each test item need.
In further embodiment, step S100 specifically includes step:
It is corresponding mobile whole to the IP for pre-setting that S101, control terminal regularly send default test command information by network End;
When S102, acquisition for mobile terminal preset test command information and parse test item and test in default test command information Between;
The time of S103, acquisition for mobile terminal control terminal, and the time of the time of mobile terminal and control terminal is carried out together Step.
During specific implementation, set and start timer Wifi_timer, open WIFI, connect default AP (router or Person's interchanger), the command information for waiting PC ends to be obtained to be sent by network;Into time status are waited, if in default wait Interior to obtain data, then time-out, carries out restarting timer Wifi_timer;If successfully obtaining PC ends command information, According to the command information for obtaining, the test information such as the test item sequence number and the testing time that are currently needed for carrying out are parsed, and obtain Take and the synchronous PC ends time, make mobile terminal time and PC ends time consistency.
Further, step S200 specifically includes step:
S201, control terminal sending power consumption response data acquisition instructions to the corresponding power consumption in default Current Voltage test address are adopted Collection instrument;
The default different test item sequence numbers of S202, mobile terminal enquiry relation table corresponding with test response of step, obtains default The corresponding response operation of test item, is configured according to the response operation for obtaining to mobile terminal, obtains default test item and rises Only time;
S203, according to carrying out power consumption test, power consumption Acquisition Instrument to mobile terminal between at the beginning of the default test item beginning and ending time Device collection mobile terminal to the power consumption response data of test item and be uploaded to control terminal;
S204, when detect test item test after the completion of, record test the end time, will test the time started and the end time on Reach control terminal.
During specific implementation, the corresponding response operation of preset test item is obtained;Preset in advance different test item sequence numbers and The corresponding relation table of test response of step, from the test sequence number for obtaining, obtains the response operation that needs are set, and sets mobile whole Hold, upload last round of test beginning and ending time T1, T2, and close WIFI, point T1 between recording at the beginning of currently testing carries out power consumption Test, judges whether the testing time reaches;
If reaching, judge it is current whether last test sequence number;If it is not, then record the current test end time, into next Wheel test;If last test sequence number, then prompting test is completed, and records the current test end time, and WIFI is uploaded; End is exited,
If not up to, continuing to test, reached until the testing time.
Further, step S300 specifically includes step:
When the test that the power consumption response data and mobile terminal that S301, control terminal obtain the collection of power consumption acquisition instrument are uploaded starts Between and the end time, by power consumption response data with test the beginning and ending time treatment after, generation data form be displayed in control terminal simultaneously Storage.
During specific implementation, specifically, control terminal opens thread 1, is responsible for treatment and control mobile terminal;Thread 2 is opened, It is responsible for obtaining the voltage x current information of Agilent;Thread 1 and the particular content of thread 2 are as follows:Obtain the Agilent electricity of preset address Piezoelectricity stream information, real time record, real-time processing carries out waveform and shows, and form is stored, and regularly sends default letter by network Designated terminal is ceased, and timing is monitored and specifies IP, is obtained the beginning and ending time point of mobile terminal test and is recorded;Detect test knot Shu Hou, according to the beginning and ending time of different test items, exports last list data and stores.
A kind of specific embodiment is as follows:At PC ends, NI companies ComponentWorks++ plug-in units are installed, Agilent is installed PCI-GPIB capture card function libraries, based on the automation power consumption test software of VC++ exploitations, pre-set different power consumption tests Testing time, according to default Agilent power supply address, default mobile terminal IP obtains the electricity of different mobile terminal in real time Current voltage, carries out database purchase, the output of form.
Agilent power end, presets corresponding address, and pre-set output voltage is tested.
In mobile terminal, the machine IP is set, mobile terminal power consumption test application program APK is installed;Application program timing is supervised Reception is listened to be instructed from PC ends, test sequence number of the instruction comprising the test item for needing to carry out, testing time, the switching of test item refers to Order;Application program the time, carries out different click responses according to different test sequence numbers.Application program is subtracted in PC end datas The electric current I1 of IDEL.Due to I1 as little as 1ma, thumping majority test item is omitted to be disregarded.
Present invention also offers a kind of flow chart of the concrete application embodiment of the power consumption test method based on mobile terminal, As shown in figure 3, method includes step:
S10, beginning;
S20, opening timing device wifi-timer;
S30, opening WIFI, the default AP of connection;
S40, etc. PC to be obtained send command information, judge whether time-out, if so, then perform step S50, if it is not, then performing step Rapid S20;
The test such as S50, parsing test item sequence number and testing time information, obtains and the synchronous PC ends time;
The corresponding response operation of the preset test item of S60, acquisition;
S70, setting mobile terminal, upload last round of test beginning and ending time T1, T2, and close WIFI;
S80, record current point in time T1, carry out power consumption test;
S90, judge whether the testing time reaches, if so, step S91 is then performed, if it is not, then performing step S80;
S91, judge whether last test item, if so, step S92 is then performed, if it is not, then performing step S94;
S92, prompting test are completed, and exited;
S93, last lower testing time point T3 is recorded, and uploaded by WIFI;
S94, record current point in time T2, and carry out next round test;
S95, end.
From above method embodiment, the invention provides a kind of power consumption test method based on mobile terminal, PC ends Automation power consumption test software is installed, according to default Agilent voltage address, different electrical power gathered data, real-time processing is obtained Display storage;According to default test item sequence number and testing time, IP is preset, control instruction is transmitted by wireless WIFI, in real time Control different mobile terminal;In different test items, according to default time start by set date WIFI, it is responsible for and PC ends is instructed Interaction, so as to the response for realizing different testing procedures is processed;After director data interaction is finished, then WIFI is closed;When reaching After pre-conditioned, then power consumption test is carried out, and record test beginning and ending time point, realize the automatic of mobile terminal power consumption test Change test, be significantly reduced the workload of engineer, improve testing efficiency, reduce human cost, reduce Project-developing cost;It is logical The automatic test of instrument is crossed, the unstability of manual testing is improve, realizes that autoreport is exported;Realize many shiftings of support Dynamic power consumption of terminal is tested simultaneously.
In the exemplary embodiment, device can be by one or more application specific integrated circuits(ASIC), data signal Processor(DSP), digital signal processing appts(DSPD), PLD(PLD), field programmable gate array (FPGA), controller, microcontroller, microprocessor or other electronic components realize, for performing the above method.
In the exemplary embodiment, a kind of non-provisional computer-readable recording mediums including instructing are additionally provided, for example Including the memory for instructing, above-mentioned instruction can be by the computing device of device completing the above method.For example, the non-transitory Computer-readable recording medium can be ROM, random access memory(RAM), CD-ROM, tape, floppy disk and optical data storage Equipment etc..
The invention provides a kind of functional schematic block diagram of the preferred embodiment of the power consumption test system based on mobile terminal, As shown in figure 4, wherein, system includes:
Instruction is obtained and time synchronized module 100, for the default test command information that acquisition for mobile terminal control terminal sends, And it is simultaneously synchronous to obtain the time of control terminal;Specifically as described in embodiment of the method.
Test module 200, for the default test command information of mobile terminal parsing, the default test according to parsing instructs letter Ceasing carries out power consumption test, and the power consumption response data of recording test time and mobile terminal is simultaneously uploaded to control terminal;Specific such as side Described in method embodiment.
Display and memory module 300, testing time and the power consumption number of responses that mobile terminal is returned are obtained for control terminal According to showing and store;Specifically as described in embodiment of the method.
The described power consumption test system based on mobile terminal, wherein, the system also includes:
Module is pre-set, for control terminal IP, Current Voltage test address, test in advance to the mobile terminal to be tested Command information is configured;Specifically as described in embodiment of the method.
The described power consumption test system based on mobile terminal, wherein, the instruction is obtained and included with time synchronized module:
Instruction sending unit, default test command information to IP pairs for pre-setting is sent for control terminal timing by network The mobile terminal answered;Specifically as described in embodiment of the method.
Instruction resolution unit, in the default test command information of acquisition for mobile terminal and the default test command information of parsing Test item and the testing time;Specifically as described in embodiment of the method.
Time synchronized unit, for the time of acquisition for mobile terminal control terminal, and by the time of mobile terminal and controls The time of terminal synchronizes;Specifically as described in embodiment of the method.
The described power consumption test system based on mobile terminal, wherein, the test module is specifically included:
Acquisition instructions transmitting element, tests for control terminal sending power consumption response data acquisition instructions to default Current Voltage The corresponding power consumption acquisition instrument in address;Specifically as described in embodiment of the method.
Inquiry and setting unit, it is corresponding with test response of step for the default different test item sequence numbers of mobile terminal enquiry Relation table, obtain the corresponding response operation of default test item, mobile terminal is configured according to the response operation for obtaining, obtain Take the default test item beginning and ending time;Specifically as described in embodiment of the method.
Test cell, for according to carrying out power consumption survey to mobile terminal between at the beginning of the default test item beginning and ending time Examination, power consumption acquisition instrument collection mobile terminal to the power consumption response data of test item and be uploaded to control terminal;Specific such as side Described in method embodiment.
Record and uploading unit, for after the completion of test item test is detected, the record test end time, test being opened Time beginning and end time are uploaded to control terminal;Specifically as described in embodiment of the method.
The described power consumption test system based on mobile terminal, wherein, the display is with memory module specifically for control Terminal obtains the test time started and end time that the power consumption response data and mobile terminal of the collection of power consumption acquisition instrument are uploaded, After power consumption response data is processed with the test beginning and ending time, generation data form is displayed in control terminal and stores;Specific such as side Described in method embodiment.
In sum, the present invention proposes a kind of power consumption test method and system based on mobile terminal, and method includes:Move Dynamic terminal obtains the default test command information that control terminal sends, and it is simultaneously synchronous to obtain the time of control terminal;Mobile terminal The default test command information of parsing, the default test command information according to parsing carries out power consumption test, recording test time and shifting The power consumption response data of dynamic terminal is simultaneously uploaded to control terminal;Control terminal obtains testing time and the power consumption that mobile terminal is returned Response data, shows and stores.The automatic test of the achievable mobile terminal power consumption test of the present invention, is significantly reduced engineer Workload, improve testing efficiency, reduce human cost, reduce Project-developing cost, by the automatic test of instrument, improve The unstability of manual testing, realizes that autoreport is exported, and can support many mobile terminal power consumptions while being tested.
It should be appreciated that application of the invention is not limited to above-mentioned citing, and for those of ordinary skills, can To be improved according to the above description or converted, all these modifications and variations should all belong to the guarantor of appended claims of the present invention Shield scope.

Claims (10)

1. a kind of power consumption test method based on mobile terminal, it is characterised in that method includes step:
The default test command information that A, acquisition for mobile terminal control terminal send, and it is simultaneously synchronous to obtain the time of control terminal;
B, the default test command information of mobile terminal parsing, the default test command information according to parsing carry out power consumption test, remember The power consumption response data of record testing time and mobile terminal is simultaneously uploaded to control terminal;
C, control terminal obtain testing time and the power consumption response data that mobile terminal is returned, and show and store.
2. the power consumption test method based on mobile terminal according to claim 1, it is characterised in that before the step A Also include step:
The IP advance to the mobile terminal to be tested of S, control terminal, Current Voltage test address, test command information set Put.
3. the power consumption test method based on mobile terminal according to claim 2, it is characterised in that the step A is specific Including step:
A1, control terminal timing send default test command information to the corresponding mobile terminals of IP for pre-setting by network;
When A2, acquisition for mobile terminal preset test command information and parse test item and test in default test command information Between;
The time of A3, acquisition for mobile terminal control terminal, and the time of mobile terminal is synchronized with the time of control terminal.
4. the power consumption test method based on mobile terminal according to claim 3, it is characterised in that the step B is specific Including step:
B1, control terminal sending power consumption response data acquisition instructions to the corresponding power consumption in default Current Voltage test address are gathered Instrument;
The default different test item sequence numbers of B2, mobile terminal enquiry relation table corresponding with test response of step, obtains default survey The corresponding response operation of examination item, is configured according to the response operation for obtaining to mobile terminal, obtains default test item start-stop Time;
B3, according to carrying out power consumption test, power consumption acquisition instrument to mobile terminal between at the beginning of the default test item beginning and ending time Collection mobile terminal to the power consumption response data of test item and be uploaded to control terminal;
B4, when detect test item test after the completion of, record test the end time, will test the time started and the end time upload To control terminal.
5. the power consumption test method based on mobile terminal according to claim 4, it is characterised in that the step C is specific Including step:
C1, control terminal obtain the test time started that the power consumption response data and mobile terminal of the collection of power consumption acquisition instrument are uploaded And the end time, after power consumption response data is processed with the test beginning and ending time, generation data form is displayed in control terminal and deposits Storage.
6. a kind of power consumption test system based on mobile terminal, it is characterised in that system includes:
Instruction is obtained and time synchronized module, for the default test command information that acquisition for mobile terminal control terminal sends, and The time for obtaining control terminal is simultaneously synchronous;
Test module, for the default test command information of mobile terminal parsing, the default test command information according to parsing is carried out The power consumption response data of power consumption test, recording test time and mobile terminal is simultaneously uploaded to control terminal;
Display and memory module, testing time and the power consumption response data that mobile terminal is returned, display are obtained for control terminal And store.
7. the power consumption test system based on mobile terminal according to claim 6, it is characterised in that the system is also wrapped Include:
Module is pre-set, for control terminal IP, Current Voltage test address, test in advance to the mobile terminal to be tested Command information is configured.
8. the power consumption test system based on mobile terminal according to claim 7, it is characterised in that the instruction obtain with Time synchronized module includes:
Instruction sending unit, default test command information to IP pairs for pre-setting is sent for control terminal timing by network The mobile terminal answered;
Instruction resolution unit, presets test command information and parses the survey in default test command information for acquisition for mobile terminal Examination item and the testing time;
Time synchronized unit, for the time of acquisition for mobile terminal control terminal, and by the time of mobile terminal and control terminal Time synchronize.
9. the power consumption test system based on mobile terminal according to claim 8, it is characterised in that the test module tool Body includes:
Acquisition instructions transmitting element, tests for control terminal sending power consumption response data acquisition instructions to default Current Voltage The corresponding power consumption acquisition instrument in address;
Inquiry and setting unit, for the default different test item sequence numbers of mobile terminal enquiry pass corresponding with test response of step It is table, obtains the corresponding response operation of default test item, mobile terminal is configured according to the response operation for obtaining, obtains pre- If the test item beginning and ending time;
Test cell, for according to carrying out power consumption test, work(to mobile terminal between at the beginning of the default test item beginning and ending time Consumption acquisition instrument collection mobile terminal to the power consumption response data of test item and be uploaded to control terminal;
Record and uploading unit, for after the completion of test item test is detected, record to test the end time, when test is started Between and the end time be uploaded to control terminal.
10. the power consumption test system based on mobile terminal according to claim 9, it is characterised in that the display with deposit The test that storage module is uploaded specifically for power consumption response data and mobile terminal that control terminal obtains the collection of power consumption acquisition instrument Time started and end time, after power consumption response data is processed with the test beginning and ending time, generation data form is displayed in control Terminal is simultaneously stored.
CN201710013223.5A 2017-01-09 2017-01-09 A kind of power consumption test method and system based on mobile terminal Pending CN106802845A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710013223.5A CN106802845A (en) 2017-01-09 2017-01-09 A kind of power consumption test method and system based on mobile terminal

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710013223.5A CN106802845A (en) 2017-01-09 2017-01-09 A kind of power consumption test method and system based on mobile terminal

Publications (1)

Publication Number Publication Date
CN106802845A true CN106802845A (en) 2017-06-06

Family

ID=58984363

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710013223.5A Pending CN106802845A (en) 2017-01-09 2017-01-09 A kind of power consumption test method and system based on mobile terminal

Country Status (1)

Country Link
CN (1) CN106802845A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110650237A (en) * 2019-09-11 2020-01-03 捷开通讯(深圳)有限公司 Power consumption testing device and system
CN112345823A (en) * 2020-10-20 2021-02-09 深圳市新国都支付技术有限公司 Power consumption testing method, device and system and storage medium
CN114167132A (en) * 2022-02-10 2022-03-11 为准(北京)电子科技有限公司 Power consumption detection method and device of wireless terminal, electronic equipment and storage medium

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103179241A (en) * 2013-03-08 2013-06-26 百度在线网络技术(北京)有限公司 Method and system for automatically testing power consumption of mobile terminal
CN103439560A (en) * 2013-08-12 2013-12-11 中科创达软件股份有限公司 Method and system for testing current of mobile phone terminal wirelessly and automatically
CN104468915A (en) * 2013-09-24 2015-03-25 卓望数码技术(深圳)有限公司 Device for testing mobile terminal and system for testing mobile terminals
CN105785113A (en) * 2014-12-25 2016-07-20 展讯通信(上海)有限公司 System and method for automatically testing power consumption
CN105791497A (en) * 2014-12-25 2016-07-20 展讯通信(上海)有限公司 Automatic testing system of power consumption of mobile terminal and working method of automatic testing system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103179241A (en) * 2013-03-08 2013-06-26 百度在线网络技术(北京)有限公司 Method and system for automatically testing power consumption of mobile terminal
CN103439560A (en) * 2013-08-12 2013-12-11 中科创达软件股份有限公司 Method and system for testing current of mobile phone terminal wirelessly and automatically
CN104468915A (en) * 2013-09-24 2015-03-25 卓望数码技术(深圳)有限公司 Device for testing mobile terminal and system for testing mobile terminals
CN105785113A (en) * 2014-12-25 2016-07-20 展讯通信(上海)有限公司 System and method for automatically testing power consumption
CN105791497A (en) * 2014-12-25 2016-07-20 展讯通信(上海)有限公司 Automatic testing system of power consumption of mobile terminal and working method of automatic testing system

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110650237A (en) * 2019-09-11 2020-01-03 捷开通讯(深圳)有限公司 Power consumption testing device and system
CN112345823A (en) * 2020-10-20 2021-02-09 深圳市新国都支付技术有限公司 Power consumption testing method, device and system and storage medium
CN112345823B (en) * 2020-10-20 2024-06-18 深圳市新国都支付技术有限公司 Power consumption testing method, device, system and storage medium
CN114167132A (en) * 2022-02-10 2022-03-11 为准(北京)电子科技有限公司 Power consumption detection method and device of wireless terminal, electronic equipment and storage medium
CN114167132B (en) * 2022-02-10 2022-04-29 为准(北京)电子科技有限公司 Power consumption detection method and device of wireless terminal, electronic equipment and storage medium

Similar Documents

Publication Publication Date Title
CN107632219A (en) A kind of automatic switching test system and its method of testing
CN106802845A (en) A kind of power consumption test method and system based on mobile terminal
CN104298224A (en) Automatic vehicle-mounted electronic control unit CAN bus communication testing device and system
TW201248395A (en) Power supply test system and method
CN112014788B (en) Load identification module detection method based on wave recording file playback
CN105629180A (en) Test method, test device and controller
CN104932479A (en) Automatic test method and system
CN104572422A (en) Memory monitoring achievement method based on startup and shutdown of Linux system
CN108304326B (en) Automatic testing system and method for android intelligent terminal
CN109857095A (en) A kind of off-line detection system and method for domain controller
CN102164196A (en) Automatic mobile phone current testing method
CN114325458B (en) Test method, system, device, equipment and storage medium of switching power supply
CN109032864A (en) A kind of method and system of NVMe SSD hot plug test
CN101287264A (en) Method, system and control device for measuring standby/call current of mobile phone
CN113590401B (en) CPE equipment multifunctional test method, CPE equipment multifunctional test device, computer equipment and storage medium
WO2016188077A1 (en) Burn-in test method and device
CN104198788A (en) VNA (Vector Network Analyzer) multiplexing instrument and method
CN113626306A (en) Jenkins-based BMC automatic testing method and device
CN113407469A (en) Parameter configuration method and device, storage medium and electronic device
CN105391833B (en) A kind of internal storage data loss test system and method based on mobile terminal
CN111949538A (en) Data analysis method, equipment and system
CN103439560A (en) Method and system for testing current of mobile phone terminal wirelessly and automatically
CN104239202A (en) Non-Root testing method and system of interactive intelligent equipment
CN111103495A (en) Automatic test system and method for field debugging of cross-interval relay protection equipment
CN106980561B (en) Power-on and power-off test system and method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170606