CN106786167A - 一种输电线路冰灾优化决策方法及其系统 - Google Patents

一种输电线路冰灾优化决策方法及其系统 Download PDF

Info

Publication number
CN106786167A
CN106786167A CN201710076179.2A CN201710076179A CN106786167A CN 106786167 A CN106786167 A CN 106786167A CN 201710076179 A CN201710076179 A CN 201710076179A CN 106786167 A CN106786167 A CN 106786167A
Authority
CN
China
Prior art keywords
transmission line
ice
electricity
degree
covering
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710076179.2A
Other languages
English (en)
Other versions
CN106786167B (zh
Inventor
陆佳政
郭俊
李波
方针
熊蔚立
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Hunan Electric Power Co Ltd
Disaster Prevention and Mitigation Center of State Grid Hunan Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Hunan Electric Power Co Ltd
Disaster Prevention and Mitigation Center of State Grid Hunan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Hunan Electric Power Co Ltd, Disaster Prevention and Mitigation Center of State Grid Hunan Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201710076179.2A priority Critical patent/CN106786167B/zh
Publication of CN106786167A publication Critical patent/CN106786167A/zh
Application granted granted Critical
Publication of CN106786167B publication Critical patent/CN106786167B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/02Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

本发明提供了一种输电线路冰灾优化决策方法及其系统,可制定电网输电线路冰灾应急处置策略,提高电网输电线路冰灾应急处理的效果和效益。本发明包括:获取输电线路覆冰厚度和一段时间内的覆冰增长厚度;根据输电线路覆冰厚度和输电线路覆冰增长厚度结合输电线路设计冰厚计算得到输电线路覆冰程度,根据输电线路电压等级和输电线路断面重要程度获取输电线路重要程度,根据输电线路配置的融冰装备、输电线路制定的融冰方案和输电线路电压等级获取输电线路融冰难度系数;根据输电线路的覆冰程度筛选需要融冰的输电线路,综合输电线路覆冰程度、输电线路重要程度和输电线路融冰难度系数对需要融冰的输电线路进行优先级排序,按优先级顺序开展融冰。

Description

一种输电线路冰灾优化决策方法及其系统
技术领域
本发明属于电气工程领域,尤其涉及一种输电线路冰灾优化决策方法及其系统。
背景技术
冰灾是当前威胁电网输电线路安全稳定运行的最重要的灾害,近年来,随着全球气候变化,冰冻灾害频发,冰灾严重时持续时间长、影响范围大,对电网输电线路造成的破坏十分巨大。
当前的电网冰灾应急处置多依靠人工经验决策,难以达到最优的处置效果。
因此,本发明提出了一种输电线路冰灾优化决策方法及其系统,可综合考虑覆冰监测、覆冰预测、输电线路重要程度等多要素,制定最优的应急处置策略,确保在电网覆冰灾害条件下的冰灾及时高效处置,有力保障电网安全稳定运行。
发明内容
本发明的目的在于提供一种输电线路冰灾优化决策方法及其系统,以解决依靠人工经验决策难以达到最优的处置效果的现有技术问题。
为实现上述目的,本发明提供了一种输电线路冰灾优化决策方法,包括以下步骤:
获取实时输电线路覆冰厚度和一段时间内的输电线路覆冰增长厚度。
根据输电线路覆冰厚度和输电线路覆冰增长厚度结合输电线路设计冰厚计算得到输电线路的覆冰程度,根据输电线路电压等级和输电线路断面重要程度获取输电线路重要程度,根据输电线路配置的融冰装备、输电线路制定的融冰方案和输电线路电压等级获取输电线路融冰难度系数。
根据输电线路的覆冰程度筛选需要融冰的输电线路,综合输电线路覆冰程度、输电线路重要程度和输电线路融冰难度系数对需要融冰的输电线路进行优先级排序,按优先级顺序开展融冰。
与上述方法相对应的,本发明还提供了一种输电线路冰灾优化决策系统,包括以下步骤:
采集模块:用于获取实时输电线路覆冰厚度和一段时间内的输电线路覆冰增长厚度。
计算模块:用于根据输电线路覆冰厚度和输电线路覆冰增长厚度结合输电线路设计冰厚计算得到输电线路的覆冰程度,根据输电线路电压等级和输电线路断面重要程度获取输电线路重要程度,根据输电线路配置的融冰装备、输电线路制定的融冰方案和输电线路电压等级获取输电线路融冰难度系数。
决策模块:用于根据输电线路的覆冰程度筛选需要融冰的输电线路,综合输电线路覆冰程度、输电线路重要程度和输电线路融冰难度系数对需要融冰的输电线路进行优先级排序,按优先级顺序开展融冰。
本发明具有以下有益效果:
本发明制定了一套电网冰灾应急处置策略,有效提高电网冰灾应急处置的效果和效益,解决了传统依靠人工经验决策难以达到最优处置效果的技术问题。
综合考虑输电线路覆冰程度、输电线路重要程度和输电线路融冰难度系数等多要素对需要融冰的输电线路进行优先级排序,制定的优先级排序为最优应急处置策略,确保在电网覆冰灾害条件下保障电网安全稳定的运行。
本发明所据原理清晰,操作性强,实用性强。
下面将参照附图,对本发明作进一步详细的说明。
附图说明
构成本申请的一部分的附图用来提供对本发明的进一步理解,本发明的示意性实施例及其说明用于解释本发明,并不构成对本发明的不当限定。在附图中:
图1是本发明优选实施例的一种输电线路冰灾优化决策流程图。
具体实施方式
以下结合附图对本发明的实施例进行详细说明,但是本发明可以由权利要求限定和覆盖的多种不同方式实施。
实施例1:
如图1所示,本发明提供了一种输电线路冰灾优化决策方法,包括以下步骤:
S1:获取实时输电线路覆冰厚度观测数据和一段时间内的输电线路覆冰增长厚度。可通过输电线路覆冰自动监测装置和/或人工哨覆冰观测站获取每条输电线路的覆冰厚度R;可采用输电线路覆冰预警系统获取输电线路覆冰增长厚度ΔR;
S2:根据输电线路覆冰厚度和输电线路覆冰增长厚度结合输电线路设计冰厚计算得到输电线路的覆冰程度,根据输电线路电压等级和输电线路断面重要程度获取输电线路重要程度,根据输电线路配置的融冰装备、输电线路制定的融冰方案和输电线路电压等级获取输电线路融冰难度系数。输电线路重要程度可以通过输电线路重要程度计算表获取;输电线路融冰难度系数可以通过输电线路融冰难度系数表获取。输电线路重要程度计算表和输电线路融冰难度系数表如下:
表1输电线路重要程度计算表
表2输电线路融冰难度系数
S3:根据输电线路的覆冰程度筛选需要融冰的输电线路,综合输电线路覆冰程度、输电线路重要程度和输电线路融冰难度系数对需要融冰的输电线路进行优先级排序,按优先级顺序开展融冰。
进一步地,S1中提到的一段时间内的输电线路覆冰增长厚度一般为实时观测覆冰厚度后24小时增长的覆冰厚度,在知道实时观测覆冰厚度、24小时增长的覆冰厚度和输电线路设计冰厚的条件下,可以通过
求得各输电线路的覆冰程度。其中,R0为输电线路设计冰厚,R为输电线路实时覆冰厚度观测数据,ΔR为未来24小时内输电线路覆冰增长厚度。
进一步地,S3中根据覆冰程度筛选需要融冰的输电线路为选择覆冰程度大于70%的输电线路进行融冰决策。把所有输电线路的覆冰程度进行统计,优选出所有覆冰程度大于70%的输电线路作为电网冰灾防治决策候选方案。
进一步地,采用TOPSIS(Technique for Order Preference by Similarity toan Ideal Solution)方法进行优先级排序,计算各候选方案的优劣排序值,排序值Yii越大的越优先安排开展融冰,优先级排序的计算公式如下:
其中,为输电线路覆冰程度最大值;为输电线路重要程度最大值;为输电线路融冰难度系数最大值;为输电线路覆冰程度最小值;为输电线路重要程度最小值;为输电线路融冰难度系数最小值;Yi为第i个候选方案的TOPSIS排序值;m为候选方案的个数;为第i个候选方案与理论最优候选方案的欧式距离;为第i个候选方案与理论最劣候选方案的欧式距;V为输电线路融冰方案决策矩阵;Si1为第i个候选方案的输电线路覆冰程度;Ii2为第i个候选方案的输电线路重要程度;Hi3为第i个候选方案的输电线路融冰难度系数。实际覆冰中并不是每个电压等级的线路都会有覆冰,这里的重要程度最大值和重要程度最小值是指所有覆冰线路中线路重要程度的最大值和最小值。候选方案的个数即为输电线路条数。
综上,本实施列公开的一种输电线路冰灾优化决策方法,综合考虑输电线路覆冰程度、输电线路重要程度和输电线路融冰难度系数等多要素对需要融冰的输电线路进行优先级排序,制定的优先级排序为最优应急处置策略,有效提高电网冰灾应急处置的效果和效益,确保在电网覆冰灾害条件下保障电网安全稳定的运行。
与上述方法实施例相对应的,下述实施例还公开一种用于执行上述方法的配套系统,该系统包括以下模块:
采集模块:用于获取实时输电线路覆冰厚度和一段时间内的输电线路覆冰增长厚度。
计算模块:用于根据输电线路覆冰厚度和输电线路覆冰增长厚度结合输电线路设计冰厚计算得到输电线路的覆冰程度,用于根据输电线路电压等级和输电线路断面重要程度获取输电线路重要程度,根据输电线路融冰装备、输电线路融冰方案和输电线路电压等级获取输电线路融冰难度系数;
决策模块:用于根据输电线路的覆冰程度筛选需要融冰的输电线路,综合输电线路覆冰程度、输电线路重要程度和输电线路融冰难度系数对需要融冰的输电线路进行优先级排序,按优先级顺序开展融冰。
本实施例公开的本实施列公开的一种输电线路冰灾优化决策方法,综合考虑输电线路覆冰程度、输电线路重要程度和输电线路融冰难度系数等多要素对需要融冰的输电线路进行优先级排序,制定的优先级排序为最优应急处置策略,有效提高电网冰灾应急处置的效果和效益,确保在电网覆冰灾害条件下保障电网安全稳定的运行。
实施例2:
基于输电线路覆冰自动监测装置和人工哨覆冰观测站获取每条线路的覆冰厚度R,具体为:500kV输电线路A覆冰厚度为15mm、220kV输电线路B覆冰厚度为12mm、110kV输电线路C覆冰厚度为8mm、35kV输电线路D覆冰厚度为3mm。采用输电线路覆冰预测预警系统,计算未来24h每条输电线路覆冰增长厚度ΔR。输电线路A未来24h覆冰增长厚度为5mm,输电线路B未来24h覆冰增长厚度为3mm,输电线路C未来24h覆冰增长厚度为3mm,输电线路D未来24h覆冰增长厚度为4mm。输电线路A设计冰厚为25mm,输电线路B设计冰厚为20mm,输电线路C设计冰厚为15mm,输电线路D设计冰厚为10mm。通过
计算得到输电线路A覆冰程度为80%,输电线路B覆冰程度为75%,输电线路C覆冰程度为73%,输电线路D覆冰程度为70%。
综合考虑输电线路配备的融冰装备及融冰方案制定情况,分析输电线路融冰难度系数为:输电线路A融冰难度系数为0.2,输电线路B融冰难度系数为0.5,输电线路C融冰难度系数为0.6,输电线路D融冰难度系数为0.4。
采用TOPSIS方法计算各候选方案的优劣排序值,排序值Yi越大的优先安排开展融冰,计算得到各输电线路的排序值分别为:输电线路A排序值为0.67,输电线路B排序值为0.54,输电线路C排序值为0.43,输电线路D排序值为0.19。由此可知融冰的先后次序为:输电线路A、输电线路B、输电线路C、输电线路D。
以上所述仅为本发明的优选实施例而已,并不用于限制本发明,对于本领域的技术人员来说,本发明可以有各种更改和变化。凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。

Claims (10)

1.一种输电线路冰灾优化决策方法,其特征在于,包括以下步骤:
获取实时输电线路覆冰厚度和一段时间内的输电线路覆冰增长厚度;
根据输电线路覆冰厚度和输电线路覆冰增长厚度结合输电线路设计冰厚计算得到输电线路的覆冰程度,根据输电线路电压等级和输电线路断面重要程度获取输电线路重要程度,根据输电线路配置的融冰装备、输电线路制定的融冰方案和输电线路电压等级获取输电线路融冰难度系数;
根据所述输电线路的覆冰程度筛选需要融冰的输电线路,综合输电线路覆冰程度、输电线路重要程度和输电线路融冰难度系数对需要融冰的输电线路进行优先级排序,按优先级顺序开展融冰。
2.根据权利要求1所述的一种输电线路冰灾优化决策方法,其特征在于,所述一段时间为未来24小时,所述覆冰程度S的计算公式:
S = R + Δ R R 0
其中,R0为输电线路设计冰厚,R为输电线路实时覆冰厚度观测数据,ΔR为未来24小时内输电线路覆冰增长厚度。
3.根据权利要求1所述的一种输电线路冰灾优化决策方法,其特征在于,所述根据覆冰程度筛选需要融冰的输电线路为选择覆冰程度大于70%的输电线路。
4.根据权利要求1所述的一种输电线路冰灾优化决策方法,其特征在于,采用TOPSIS方法进行优先级排序。
5.根据权利要求4所述的一种输电线路冰灾优化决策方法,其特征在于,计算所述优先级排序的公式为:
V = v 11 v 12 v 13 v 21 v 22 v 23 . . . . . . . . . v i 1 v i 2 v i 3 = S 11 I 12 H 13 S 21 I 22 H 23 . . . . . . . . . S i 1 I i 2 H i 3 , i = 1 , 2 , ... , m
v 1 + = m a x { v i 1 | i = 1 , 2 , ... , m }
v 2 + = m a x { v i 2 | i = 1 , 2 , ... , m }
v 3 + = m a x { v i 3 | i = 1 , 2 , ... , m }
v 1 - = m i n { v i 1 | i = 1 , 2 , ... , m }
v 2 - = m i n { v i 2 | i = 1 , 2 , ... , m }
v 3 - = m i n { v i 3 | i = 1 , 2 , ... , m }
L i + = Σ j = 1 3 ( v i j - v j + ) 2 , i = 1 , 2 , ... , m
L i - = Σ j = 1 3 ( v i j - v j - ) 2 , i = 1 , 2 , ... , m
Y i = L i - L i + + L i - , i = 1 , 2 , ... , m
其中,为输电线路覆冰程度最大值;为输电线路重要程度最大值;为输电线路融冰难度系数最大值;为输电线路覆冰程度最小值;为输电线路重要程度最小值;为输电线路融冰难度系数最小值;Yi为第i个候选方案的TOPSIS排序值;m为候选方案的个数;为第i个候选方案与理论最优候选方案的欧式距离;为第i个候选方案与理论最劣候选方案的欧式距离;V为输电线路融冰方案决策矩阵;Si1为第i个候选方案的输电线路覆冰程度;Ii2为第i个候选方案的输电线路重要程度;Hi3为第i个候选方案的输电线路融冰难度系数。
6.一种输电线路冰灾优化决策系统,其特征在于,包括以下模块:
采集模块:用于获取实时输电线路覆冰厚度观测数据和一段时间内的输电线路覆冰增长厚度;
计算模块:用于根据输电线路覆冰厚度和输电线路覆冰增长厚度结合输电线路设计冰厚计算得到输电线路的覆冰程度,根据输电线路电压等级和输电线路断面重要程度获取输电线路重要程度,根据输电线路配置的融冰装备、输电线路制定的融冰方案和输电线路电压等级获取输电线路融冰难度系数;
决策模块:用于根据所述输电线路的覆冰程度筛选需要融冰的输电线路,综合输电线路覆冰程度、输电线路重要程度和输电线路融冰难度系数对需要融冰的输电线路进行优先级排序,按优先级顺序开展融冰。
7.根据权利要求6所述的一种输电线路冰灾优化决策系统,其特征在于,所述一段时间为未来24小时,所述计算模块采用的覆冰厚度的计算公式:
S = R + Δ R R 0
其中,R0为输电线路设计冰厚,R为输电线路实时覆冰厚度观测数据,ΔR为未来24小时内输电线路覆冰增长厚度。
8.根据权利要求6所述的一种输电线路冰灾优化决策系统,其特征在于,所述决策模块中所述根据覆冰程度筛选需要融冰的输电线路为选择覆冰程度大于70%的输电线路。
9.根据权利要求6所述的一种输电线路冰灾优化决策系统,其特征在于,所述决策模块采用TOPSIS方法进行优先级排序。
10.根据权利要求9所述的一种输电线路冰灾优化决策系统,其特征在于,计算所述决策模块中优先级排序的公式为:
V = v 11 v 12 v 13 v 21 v 22 v 23 . . . . . . . . . v i 1 v i 2 v i 3 = S 11 I 12 H 13 S 21 I 22 H 23 . . . . . . . . . S i 1 I i 2 H i 3 , i = 1 , 2 , ... , m
v 1 + = m a x { v i 1 | i = 1 , 2 , ... , m }
v 2 + = m a x { v i 2 | i = 1 , 2 , ... , m }
v 3 + = m a x { v i 3 | i = 1 , 2 , ... , m }
v 1 - = m i n { v i 1 | i = 1 , 2 , ... , m }
v 2 - = m i n { v i 2 | i = 1 , 2 , ... , m }
v 3 - = m i n { v i 3 | i = 1 , 2 , ... , m }
L i + = Σ j = 1 3 ( v i j - v j + ) 2 , i = 1 , 2 , ... , m
L i - = Σ j = 1 3 ( v i j - v j - ) 2 , i = 1 , 2 , ... , m
Y i = L i - L i + + L i - , i = 1 , 2 , ... , m
其中,为输电线路覆冰程度最大值;为输电线路重要程度最大值;为输电线路融冰难度系数最大值;为输电线路覆冰程度最小值;为输电线路重要程度最小值;为输电线路融冰难度系数最小值;Yi为第i个候选方案的TOPSIS排序值;m为候选方案的个数;为第i个候选方案与理论最优候选方案的欧式距离;为第i个候选方案与理论最劣候选方案的欧式距;V为输电线路融冰方案决策矩阵;Si1为第i个候选方案的输电线路覆冰程度;Ii2为第i个候选方案的输电线路重要程度;Hi3为第i个候选方案的输电线路融冰难度系数。
CN201710076179.2A 2017-02-13 2017-02-13 一种输电线路冰灾优化决策方法及其系统 Active CN106786167B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710076179.2A CN106786167B (zh) 2017-02-13 2017-02-13 一种输电线路冰灾优化决策方法及其系统

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710076179.2A CN106786167B (zh) 2017-02-13 2017-02-13 一种输电线路冰灾优化决策方法及其系统

Publications (2)

Publication Number Publication Date
CN106786167A true CN106786167A (zh) 2017-05-31
CN106786167B CN106786167B (zh) 2018-06-29

Family

ID=58956366

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710076179.2A Active CN106786167B (zh) 2017-02-13 2017-02-13 一种输电线路冰灾优化决策方法及其系统

Country Status (1)

Country Link
CN (1) CN106786167B (zh)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107330189A (zh) * 2017-06-29 2017-11-07 国网湖南省电力公司 一种临近网格温度分层细化预测方法和系统
CN107492885A (zh) * 2017-08-23 2017-12-19 国网山东省电力公司经济技术研究院 一种确定极端条件下基本电网框架的方法
CN109214675A (zh) * 2018-08-28 2019-01-15 华北电力大学 一种输电线路覆冰风险评估方法
CN109631774A (zh) * 2018-12-12 2019-04-16 云南电网有限责任公司带电作业分公司 一种无人机双目视觉线路覆冰测量系统
CN110490485A (zh) * 2019-08-27 2019-11-22 国网湖南省电力有限公司 一种基于动态数据的在线融冰排序算法及系统
CN111047177A (zh) * 2019-12-06 2020-04-21 国网湖南省电力有限公司 一种输电线路覆冰多源监测预警方法及系统
CN112580863A (zh) * 2020-12-08 2021-03-30 国网湖南省电力有限公司 电网密集输电通道线路队列直流融冰排序优化方法
CN113283725A (zh) * 2021-05-14 2021-08-20 国电南瑞科技股份有限公司 一种融冰策略效果评估方法、系统、存储介质及计算设备
CN114386625A (zh) * 2021-12-07 2022-04-22 贵州电网有限责任公司 一种电网输电线路停电融冰方案智能编制系统

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01202110A (ja) * 1988-02-05 1989-08-15 Hitachi Ltd 送電線の氷雪除去方法および装置
CN103778305A (zh) * 2014-02-27 2014-05-07 南京工程学院 基于k-VNN和LS-SVM的输电线路覆冰建模方法
CN104166761A (zh) * 2014-08-13 2014-11-26 南京理工大学 一种基于遗传算法的输电线路机械除冰次序优化方法

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01202110A (ja) * 1988-02-05 1989-08-15 Hitachi Ltd 送電線の氷雪除去方法および装置
CN103778305A (zh) * 2014-02-27 2014-05-07 南京工程学院 基于k-VNN和LS-SVM的输电线路覆冰建模方法
CN104166761A (zh) * 2014-08-13 2014-11-26 南京理工大学 一种基于遗传算法的输电线路机械除冰次序优化方法

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
周晓雨 等: "考虑电网安全风险的融冰序列决策", 《电力自动化设备》 *
徐勋建 等: "基于TOPSIS的电网融冰决策技术IDSS研究", 《湖南大学学报(自然科学版)》 *
杨铭 等: "电力系统冰灾智能决策方法研究", 《电力信息化》 *
陈亮 等: "基于加权平均组合评价法的电网直流融冰计划决策", 《电网技术》 *

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107330189B (zh) * 2017-06-29 2021-03-09 国网湖南省电力有限公司 一种临近网格温度分层细化预测方法和系统
CN107330189A (zh) * 2017-06-29 2017-11-07 国网湖南省电力公司 一种临近网格温度分层细化预测方法和系统
CN107492885A (zh) * 2017-08-23 2017-12-19 国网山东省电力公司经济技术研究院 一种确定极端条件下基本电网框架的方法
CN109214675B (zh) * 2018-08-28 2021-12-07 华北电力大学 一种输电线路覆冰风险评估方法
CN109214675A (zh) * 2018-08-28 2019-01-15 华北电力大学 一种输电线路覆冰风险评估方法
CN109631774A (zh) * 2018-12-12 2019-04-16 云南电网有限责任公司带电作业分公司 一种无人机双目视觉线路覆冰测量系统
CN110490485A (zh) * 2019-08-27 2019-11-22 国网湖南省电力有限公司 一种基于动态数据的在线融冰排序算法及系统
CN111047177A (zh) * 2019-12-06 2020-04-21 国网湖南省电力有限公司 一种输电线路覆冰多源监测预警方法及系统
CN112580863A (zh) * 2020-12-08 2021-03-30 国网湖南省电力有限公司 电网密集输电通道线路队列直流融冰排序优化方法
CN112580863B (zh) * 2020-12-08 2023-12-01 国网湖南省电力有限公司 电网密集输电通道线路队列直流融冰排序优化方法
CN113283725A (zh) * 2021-05-14 2021-08-20 国电南瑞科技股份有限公司 一种融冰策略效果评估方法、系统、存储介质及计算设备
CN113283725B (zh) * 2021-05-14 2022-08-09 国电南瑞科技股份有限公司 一种融冰策略效果评估方法、系统、存储介质及计算设备
CN114386625A (zh) * 2021-12-07 2022-04-22 贵州电网有限责任公司 一种电网输电线路停电融冰方案智能编制系统

Also Published As

Publication number Publication date
CN106786167B (zh) 2018-06-29

Similar Documents

Publication Publication Date Title
CN106786167B (zh) 一种输电线路冰灾优化决策方法及其系统
CN103778575B (zh) 变压器状态评估方法及系统
CN100578488C (zh) 电网雷害分布确定方法
Chuansheng et al. Safety evaluation of smart grid based on AHP-entropy method
CN105068149B (zh) 一种基于多信息综合的输变电设备雷电监测和预报方法
CN104063750B (zh) 基于改进ahp‑反熵权的电力系统受灾影响的预测方法
Liu et al. Health assessment and prediction of overhead line based on health index
CN107742040A (zh) 一种基于topsis和最优组合权重的输电线路综合风险评估方法
CN107436162B (zh) 一种电网线路舞动发生预测方法和系统
CN106780141A (zh) 一种基于流形学习的输电线路检修计划优化方法及系统
CN102521497A (zh) 电网运行风险处理方法与系统
CN105069709A (zh) 基于专家经验的电网调度操作过程准动态风险评估方法
CN105095668B (zh) 基于亚洲极涡因子的电网覆冰长期预报方法
CN106548294A (zh) 一种基于飞行数据的着陆操作绩效评价方法及装置
Dokic et al. Risk assessment of a transmission line insulation breakdown due to lightning and severe weather
CN105184490B (zh) 电网调度操作过程风险辅助预控系统
CN105354768A (zh) 输变电设备状态的评估方法和系统
CN107274634B (zh) 一种输电线路沿线降水次生地质灾害告警计算方法及系统
CN109635440A (zh) 一种架空输电线路覆冰闪络跳闸概率计算方法
CN104361535A (zh) 一种输电线路覆冰状态评估方法
CN117614137A (zh) 基于多源数据融合的配电网优化系统
CN105096003B (zh) 基于最短路径算法和0/1决策的输电线路融冰决策方法
CN114545097B (zh) 一种基于多要素动态权重算法的雷电预警研判方法
Yuan et al. Research on fusion algorithm of lightning strike trip warning for mountain transmission lines
CN106124089A (zh) 基于灰色理论的高压开关柜在线测温方法

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant