CN106760679A - Building static pressure cell structure and its construction method - Google Patents

Building static pressure cell structure and its construction method Download PDF

Info

Publication number
CN106760679A
CN106760679A CN201710099248.1A CN201710099248A CN106760679A CN 106760679 A CN106760679 A CN 106760679A CN 201710099248 A CN201710099248 A CN 201710099248A CN 106760679 A CN106760679 A CN 106760679A
Authority
CN
China
Prior art keywords
plenum chamber
suspension rod
seat region
static pressure
backboard
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710099248.1A
Other languages
Chinese (zh)
Inventor
王秋江
李学荣
江海新
薛明
张敏
吕豪
梁新利
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
No7 Building Engineering Co Ltd Beijing Urban Construction Group
Original Assignee
No7 Building Engineering Co Ltd Beijing Urban Construction Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by No7 Building Engineering Co Ltd Beijing Urban Construction Group filed Critical No7 Building Engineering Co Ltd Beijing Urban Construction Group
Priority to CN201710099248.1A priority Critical patent/CN106760679A/en
Publication of CN106760679A publication Critical patent/CN106760679A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H1/00Buildings or groups of buildings for dwelling or office purposes; General layout, e.g. modular co-ordination or staggered storeys
    • E04H1/12Small buildings or other erections for limited occupation, erected in the open air or arranged in buildings, e.g. kiosks, waiting shelters for bus stops or for filling stations, roofs for railway platforms, watchmen's huts or dressing cubicles
    • E04H1/125Small buildings, arranged in other buildings
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F13/00Details common to, or for air-conditioning, air-humidification, ventilation or use of air currents for screening
    • F24F13/02Ducting arrangements
    • F24F13/06Outlets for directing or distributing air into rooms or spaces, e.g. ceiling air diffuser
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F13/00Details common to, or for air-conditioning, air-humidification, ventilation or use of air currents for screening
    • F24F13/24Means for preventing or suppressing noise

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Building Environments (AREA)

Abstract

The invention discloses one kind building static pressure cell structure and its construction method, for building static pressure cell structure, building includes auditorium seat region, seat region structural slab and curb girder, structure base slab layer and floor layer;Seat region structural slab is provided with whirlwind outlet with curb girder;Auditorium seat region is arranged on seat region structural slab and curb girder;Structure base slab layer is located at floor layer top;The building static pressure cell structure includes the first plenum chamber and the second plenum chamber;Second plenum chamber is arranged on structure base slab layer top;First plenum chamber be separately positioned on floor layer and structure base slab layer between, and the second plenum chamber top.The effective save space of energy of the invention:Plenum chamber is formed using the smaller space sealing of the Anomalistic space of under-seat, effectively saves space.In addition conventional airduct can also be solved cannot construction problem:Plenum chamber can solve the problems, such as that ladder under-seat ajutage arrangement is more difficult, simplify ventilating system, improve the combination property of ventilating system.

Description

Building static pressure cell structure and its construction method
Technical field
The invention belongs to plenum chamber construction technique field, more particularly to a kind of building static pressure cell structure and its construction party Method.
Background technology
China's economy constantly flourishes in recent years, and the income level of entire society constantly increases, the culture of the people Life requirement is gradually stepped up, and this facilitates the development of China's cultural undertakings, the newly-built building of many arenas properties in all parts of the country. At present, in order to improve cinema, gymnasium, the air-supply quality in conference hall room, air inlet is set in the bottom at each seat, Reserving hole installs ajutage on the concrete floor of fixed seating, and installing plenum chamber in the lower section of floor forms plenum chamber.
Plenum chamber is a closed space, the certain pressure that can keep the air in it, can make multiple air-out The air-out of mouth becomes uniform, effectively reduces the noise of air conditioning duct system, reducing the kinetic pressure losses of wind system.Plenum chamber air-supply system System not only has the characteristics of air output is big, noise is low, and can make gallery formed a uniform temperature and velocity field and And can avoid producing wind and the strong blowing feeling of generation after brain such that it is able to build a comfortable watching environment to spectators.
The content of the invention
It is an object of the invention to provide one kind building static pressure cell structure and its construction method.
One kind building static pressure cell structure, building includes auditorium seat region, seat region structural slab and curb girder, structure base slab layer And floor layer;Seat region structural slab is provided with whirlwind outlet with curb girder;Auditorium seat region is arranged on seat region structural slab and curb girder On;Structure base slab layer is located at floor layer top;The building static pressure cell structure includes the first plenum chamber and the second plenum chamber;It is described Second plenum chamber is arranged on structure base slab layer top;First plenum chamber is separately positioned on floor layer and structure base slab layer Between, and the second plenum chamber top.
Building static pressure cell structure as described above of the invention, further, first plenum chamber includes:Plenum chamber steelframe, Centrifugally glass-wool plate, galvanized iron sheet and plenum chamber backboard;The centrifugally glass-wool plate is covered in the bottom table of seat region structural slab Face and the side of curb girder;The galvanized iron sheet is covered in centrifugally glass-wool plate surface;The plenum chamber steelframe includes main joist, secondary Keel and suspension rod;The main joist and secondary joist cross-fixing are connected, and main joist is by suspension rod and seat region structural slab or curb girder Connection;Mutual lap seal splicing between the plenum chamber backboard, and it is fixed on the bottom surface and side of plenum chamber steelframe.
Building static pressure cell structure of the invention as described above, further, the plenum chamber backboard includes horizontal bar keel, zinc-plated Iron sheet and centrifugally glass-wool plate;The centrifugally glass-wool plate is arranged in the framework surrounded by horizontal bar keel, galvanized iron sheet cladding In the outside of horizontal bar keel, and leave overlap edge.
Building static pressure cell structure as described above of the invention, further, the suspension rod is angle steel, and the outside of angle steel scribbles pellet Red antirust paint, and angle steel outsourcing heat-insulation layer.
Building static pressure cell structure as described above of the invention, further, building also includes ceiling decoration, fan coil, wind Pipe, fire-fighting spray pipe, fulgurite, ceiling decoration, fan coil, airduct, fire-fighting spray pipe, fulgurite are each attached to the plenum chamber steel On frame.
Building static pressure cell structure as described above of the invention, further, the main joist is 10# channel-section steels, the secondary joist It is L50 × 5 angle steel with suspension rod;The thickness of the galvanized iron sheet is 1mm, and the thickness of the centrifugally glass-wool is 30mm.
Building static pressure cell structure as described above of the invention, further, second plenum chamber includes:Centrifugally glass-wool, Galvanized iron sheet and secondary structure wall;The centrifugally glass-wool plate is covered in the lower surface of seat region structural slab and the side of curb girder Face;The galvanized iron sheet is covered in centrifugally glass-wool plate surface;Centrifugally glass-wool plate is fixed on structure base slab layer by bar for line Upper surface, galvanized iron sheet is covered in centrifugally glass-wool surface and is fixed on structure base slab layer by expansion bolt;Expansion bolt Increase gluing treatment in rubber pad, and hole at hole;Secondary structure wall top is tightly connected with seat region structural slab, below with Structure base slab layer is tightly connected.
As above the construction method of static pressure cell structure is built described in any one, is comprised the following steps:
Step 1, line setting;Drawing is checked, the coverage and its axis chi of plenum chamber are determined according to on-site actual situations It is very little;According to previous level absolute altitude control point, drawn on concrete beam, post and the wall for having poured with spirit level, and eject horizontal line, be used to Control often walks the absolute altitude of operation;
Step 2, the installation of suspension rod;Suspension rod fixed form is installed and curb girder mounting surface two ways under being divided into seat region structural slab; Hanger erection utilizes expansion bolt by Interal fixation below seat plot structure plate under structural slab, and suspension rod is welded and fixed with steel plate; Beam sides hanger erection is fixed on suspension rod is vertical above beam side using expansion bolt;
The installation of step 3, main joist and secondary joist;It is arranged in parallel between main joist, by secondary between adjacent main joist Keel are welded to connect to form entirety;The fastness detection and examination of plenum chamber:50kg weights are placed on keel, 48 is stood small When, main joist, secondary joist and suspension rod are found without deformed damaged, expansion bolt does not have loosening phenomenon;
Step 4, the making of plenum chamber backboard;Plenum chamber backboard is existing by two-layer galvanized iron sheet, centrifugally glass-wool and horizontal bar keel Field is made;When plenum chamber backboard makes, should be processed according to the plenum chamber steelframe grid size at scene;
Step 5, the installation of plenum chamber backboard;The main joist of installation plenum chamber backboard, secondary joist position is being needed to punch, surface is clear Brush coating is carried out to the position that need to be connected after reason is clean, is fixed by pulling rivet afterwards;
Step 6, the insulation on concrete structure is installed with galvanized iron sheet;Centrifugally glass-wool plate is covered under the structural slab of seat region Portion surface and the side of curb girder;Galvanized iron sheet is covered in centrifugally glass-wool plate surface;Centrifugally glass-wool plate is fixed by bar for line In structure base slab layer upper surface, galvanized iron sheet is covered in centrifugally glass-wool surface and is fixed on structure base slab layer by expansion bolt On;Increase gluing treatment in rubber pad, and hole at hole for the expansion bolt;
Step 7, joint treatment;Plenum chamber backboard seam crossing lays sealing strip, and sealing strip lays along plate stitch is elongated;Plenum chamber backboard Sealed with fireproof seal gum after installing;Plenum chamber backboard also lays elongated with the link position of seat region structural slab or curb girder Sealing strip;
Step 8, after the completion of the sealing of the first plenum chamber, plenum chamber outside integral spray fireproof coating.
Preferably, plenum chamber sealing propertytest is also included after step 8 and step is checked and accepted:With by force in plenum chamber backboard Light light irradiation, plenum chamber backboard seam crossing and with seat region structural slab or curb girder wall side junction without printing opacity;Then with height Drum pressure blower fan is blown to plenum chamber, and close to plenum chamber backboard seam, flue gas is without substantially dispelling situation for the cigarette end that will be lighted.
Preferably, in step 2, suspension rod spacing is not more than 1m, and logical line should be drawn when suspension rod is installed, and makes on per pass curb girder Suspension rod keeps on the same line;After installing suspension rod, check suspension rod spacing and position whether accurately, whether bolt fasten, weld Whether seam is qualified;It is to be checked it is qualified after, antirust treatment is carried out to suspension rod with red red antirust paint;To prevent the angle steel in plenum chamber from hanging Bar forms cold bridge, condensation is produced, to all suspension rod outsourcing isothermal holdings in plenum chamber.
The beneficial effects of the invention are as follows:
1st, the comfortableness of audience area is improved:Audience area forms a uniform temperature and velocity field, without blowing feeling, it is to avoid see Crowd produces wind after brain, while noise can be effectively reduced, improves the comfortableness of spectators' event watching.
2nd, sports field environmental requirement is met:Meet indoor various ball and other various physical culture ratios for being required to wind speed Contest item mesh.
3rd, effective save space:Plenum chamber is formed using the smaller space sealing of the Anomalistic space of under-seat, is had The saving space of effect.
4th, solving conventional airduct cannot construction problem:It is more difficult that plenum chamber can solve ladder under-seat ajutage arrangement Problem, simplifies ventilating system, improves the combination property of ventilating system.
5th, comprehensive branch suspension rod:Plenum chamber steelframe solves it as the branch suspension rod of the equipment, pipeline and furred ceiling of other systems His system equipment, pipeline branch suspension rod cannot installation question.
Brief description of the drawings
By the detailed description made in conjunction with the following drawings, of the invention above-mentioned and/or other aspects and advantage will become Become apparent from and be easier to understand, these accompanying drawings are schematical, are not intended to limit the present invention, wherein:
Fig. 1 is the building plenum chamber structural representation of an embodiment of the present invention;
Fig. 2 is the first plenum chamber schematic diagram of an embodiment of the present invention;
Fig. 3 is the plenum chamber steelframe schematic diagram of an embodiment of the present invention;
Fig. 4 is the suspension rod and seat region structural slab connection diagram of an embodiment of the present invention;
Fig. 5 is the suspension rod and curb girder schematic diagram of an embodiment of the present invention;
Fig. 6 is the plenum chamber backboard schematic diagram of an embodiment of the present invention;
Fig. 7 is two pieces of plenum chamber backboard connection diagrams of an embodiment of the present invention;
Fig. 8 is two pieces of plenum chamber backboards connection schematic cross-section of an embodiment of the present invention;
Fig. 9 is that centrifugally glass-wool plate is installed in the lower surface of the seat region structural slab of an embodiment of the present invention and the side of curb girder With galvanized iron sheet schematic diagram;
Figure 10 is that centrifugally glass-wool is installed in the lower surface of the seat region structural slab of an embodiment of the present invention and the side of curb girder Plate and galvanized iron sheet schematic diagram;
Figure 11 is the joint treatment schematic diagram of an embodiment of the present invention;
Figure 12 is the second plenum chamber schematic diagram of an embodiment of the present invention;
Figure 13 is the construction method flow chart of the building static pressure cell structure of an embodiment of the present invention.
In accompanying drawing, the list of parts representated by each label is as follows:
1st, the first plenum chamber, 11, main joist, 12, secondary joist, 13, suspension rod, 14, centrifugally glass-wool plate, 15, galvanized iron sheet, 16, Plenum chamber backboard, 17, steel plate, 18, expansion bolt, 19, horizontal bar keel;
2nd, the second plenum chamber, 21, secondary structure wall, 22, construction hole;
3rd, seat region structural slab and curb girder, 31, seat region structural slab, 32, curb girder, 33, whirlwind outlet;
4th, floor layer;
5th, structure base slab layer;
6th, ajutage;
7th, joint glue.
Specific embodiment
Hereinafter, the embodiment of building static pressure cell structure of the invention and its construction method is described with reference to the accompanying drawings.
The embodiment recorded herein is specific specific embodiment of the invention, for illustrating design of the invention, It is explanatory and exemplary, should not be construed as the limitation to embodiment of the present invention and the scope of the invention.Except what is recorded herein Implement exception, those skilled in the art can also be based on the application claims and specification disclosure of that using aobvious Other technical schemes being clear to, these technical schemes include any obvious using making for the embodiment to recording herein The technical scheme of substitutions and modifications.
The accompanying drawing of this specification is schematic diagram, aids in illustrating design of the invention, it is schematically indicated the shape of each several part And its correlation.Note that for the ease of clearly showing the structure of each part of the embodiment of the present invention, between each accompanying drawing Do not drawn according to identical ratio.Identical reference marker is used to represent identical part.
Fig. 1 shows the building static pressure cell structure of an embodiment of the present invention, and building includes auditorium seat region, seat region knot Structure plate and curb girder 3, structure base slab layer 5 and floor layer 4;Seat region structural slab is provided with whirlwind outlet 33 with curb girder 3;Auditorium's seat Area is arranged on seat region structural slab and curb girder 3;Structure base slab layer 5 is located at the top of floor layer 4;Building static pressure cell structure includes the One plenum chamber 1 and the second plenum chamber 2;Second plenum chamber 2 is arranged on 5 top of structure base slab layer;First plenum chamber 1 is separately positioned on Floor layer 4 and structure base slab layer 5 between, and the second plenum chamber 2 top.The plenum chamber of ajutage 6 and first, the second plenum chamber Full air-treatment unit is delivered to plenum chamber by connection, ajutage, is further exported by whirlwind and is entered auditorium seat region.
Fig. 2 is first plenum chamber of an embodiment of the present invention, and first plenum chamber 1 includes:Plenum chamber steelframe, centrifugation glass Glass cotton plate 14, galvanized iron sheet 15 and plenum chamber backboard 16;Centrifugally glass-wool plate 14 is covered in the bottom table of seat region structural slab 31 Face and the side of curb girder 32;Galvanized iron sheet 15 is covered in the surface of centrifugally glass-wool plate 14;As shown in figure 3, plenum chamber steelframe includes Main joist 11, secondary joist 12 and suspension rod 13;Main joist 11 and the cross-fixing of secondary joist 12 are connected, main joist 11 by suspension rod 13 with Seat region structural slab or curb girder are connected(As shown in Figure 4 and Figure 5);Mutual lap seal splicing between plenum chamber backboard 16, and it is solid It is scheduled on the bottom surface and side of plenum chamber steelframe(As shown in figure 11).
In the plenum chamber backboard of an embodiment of the present invention, as shown in Fig. 6, Fig. 7 and Fig. 8, plenum chamber backboard 16 includes Horizontal bar keel 19, galvanized iron sheet 15 and centrifugally glass-wool plate 14;Centrifugally glass-wool plate 14 is arranged on what is surrounded by horizontal bar keel 19 In framework, galvanized iron sheet 15 is coated on the outside of horizontal bar keel 19, and leaves overlap edge.
In a kind of preferred embodiment, suspension rod 13 is angle steel, and the outside of angle steel scribbles red red antirust paint, and outside angle steel Bag heat-insulation layer.Building also include ceiling decoration, fan coil, airduct, fire-fighting spray pipe, fulgurite, ceiling decoration, fan coil, Airduct, fire-fighting spray pipe, fulgurite are each attached on plenum chamber steelframe.Main joist 11 is 10# channel-section steels, and secondary joist 12 and suspension rod 13 are L50 × 5 angle steel;The thickness of galvanized iron sheet 15 is 1mm, and the thickness of centrifugally glass-wool is 30mm.
Figure 12 is the second plenum chamber schematic diagram of an embodiment of the present invention, and the second plenum chamber 2 includes:Centrifugally glass-wool, Galvanized iron sheet 15 and secondary structure wall 21;Secondary structure wall is provided with construction hole 22;Centrifugally glass-wool plate 14 is covered in seat region The lower surface of structural slab and the side of curb girder;Galvanized iron sheet 15 is covered in the surface of centrifugally glass-wool plate 14;Such as Fig. 9 and Figure 10 institutes Show, centrifugally glass-wool plate 14 is fixed on 5 upper surface of structure base slab layer by bar for line, galvanized iron sheet 15 is covered in centrifugally glass-wool Surface is simultaneously fixed on structure base slab layer 5 by expansion bolt 18;Increase at the hole of expansion bolt 18 and beaten in rubber pad, and hole Glue treatment;The top of secondary structure wall 21 is tightly connected with seat region structural slab, is tightly connected with structure base slab layer 5 below.
In the above-described embodiments, the first plenum chamber is by the space of auditorium seat region bottom, plenum chamber steelframe and quiet Pressure chamber back plate seals are formed;Second plenum chamber utilizes the civil engineering structure of ladder seat bottom(Structure base slab layer and secondary structure wall) Sealing is formed, that is, take full advantage of existing civil engineering structure(Structure base slab layer), also ensure that room under auditorium seat region Head room.
Figure 13 shows a kind of construction method of the building static pressure cell structure of embodiment, comprises the following steps:
Step 1, line setting;Drawing is checked, the coverage and its axis chi of plenum chamber are determined according to on-site actual situations It is very little;According to previous level absolute altitude control point, drawn on concrete beam, post and the wall for having poured with spirit level, and eject horizontal line, be used to Control often walks the absolute altitude of operation;
Step 2, the installation of suspension rod 13;The fixed form of suspension rod 13 is divided into seat region structural slab and installs and the mounting surface two of curb girder 32 for 31 times The mode of kind;Suspension rod 13 is installed steel plate 17 is fixed on below the structural slab of seat region using expansion bolt 18 under structural slab, suspension rod 13 It is welded and fixed with steel plate;Beam sides suspension rod 13 is installed and is fixed on suspension rod 13 is vertical on beam side using expansion bolt 18 Face;
In step 2, the spacing of suspension rod 13 is not more than 1m, and logical line should be drawn when suspension rod 13 is installed, and makes the suspension rod 13 on per pass curb girder Keep on the same line;After installing suspension rod 13, check the spacing of suspension rod 13 and position whether accurately, whether bolt fasten, weld Whether seam is qualified;It is to be checked it is qualified after, antirust treatment is carried out to suspension rod 13 with red red antirust paint;To prevent the angle steel in plenum chamber Suspension rod 13 forms cold bridge, condensation is produced, to the outsourcing isothermal holding of all suspension rods 13 in plenum chamber.
Step 3, the installation of main joist 11 and secondary joist 12;Main joist arranged in parallel between main joist 11, adjacent It is welded to connect to form entirety by secondary joist 12 between 11;The fastness detection and examination of plenum chamber:50kg is placed on keel Weight, stands 48 hours, finds main joist, secondary joist and suspension rod without deformed damaged, and expansion bolt does not have loosening phenomenon;
Step 4, the making of plenum chamber backboard 16;Plenum chamber backboard 16 passes through two-layer galvanized iron sheet 15, centrifugally glass-wool and backboard The field fabrication of keel 19 is formed;When plenum chamber backboard 16 makes, should be processed according to the plenum chamber steelframe grid size at scene;
Step 5, the installation of plenum chamber backboard 16;Beaten the main joist 11 of installation plenum chamber backboard 16, the position of secondary joist 12 is needed Hole, brush joint glue 7 is carried out after removing surface is clean to the position that need to be connected, and is fixed by pulling rivet afterwards;
Step 6, the insulation on concrete structure is installed with galvanized iron sheet 15;Centrifugally glass-wool plate 14 is covered in seat region structural slab Lower surface and curb girder side;Galvanized iron sheet 15 is covered in the surface of centrifugally glass-wool plate 14;Centrifugally glass-wool plate 14 passes through Bar for line is fixed on 5 upper surface of structure base slab layer, and galvanized iron sheet 15 is covered in centrifugally glass-wool surface and by expansion bolt 18 It is fixed on structure base slab layer 5;Increase gluing treatment in rubber pad, and hole at the hole of expansion bolt 18;
Step 7, joint treatment;The seam crossing of plenum chamber backboard 16 lays sealing strip, and sealing strip lays along plate stitch is elongated;Plenum chamber is carried on the back Plate 16 is sealed after installing with fireproof seal gum;Plenum chamber backboard 16 is also applied with the link position of seat region structural slab or curb girder If elongated sealing strip;
Step 8, after the completion of the first plenum chamber 1 is sealed, plenum chamber outside integral spray fireproof coating.
Step 9, plenum chamber sealing propertytest and examination step:High light light irradiation, the plenum chamber back of the body are used in plenum chamber backboard Plate seam crossing and with seat region structural slab or curb girder wall side junction without printing opacity;Then sent to plenum chamber with high pressure blower Wind, close to plenum chamber backboard seam, flue gas is without substantially dispelling situation for the cigarette end that will be lighted.
Each technical characteristic of above-mentioned disclosure is not limited to disclosed and further feature combination, and those skilled in the art are also Other combinations between each technical characteristic can be carried out according to the purpose of invention, is defined by the purpose for realizing the present invention.

Claims (10)

1. a kind of building static pressure cell structure, building include auditorium seat region, seat region structural slab and curb girder, structure base slab layer and Floor layer;Characterized in that, seat region structural slab is provided with whirlwind outlet with curb girder;Auditorium seat region is arranged on seat plot structure On plate and curb girder;Structure base slab layer is located at floor layer top;The building static pressure cell structure is quiet including the first plenum chamber and second Pressure chamber;Second plenum chamber is arranged on structure base slab layer top;First plenum chamber is separately positioned on floor layer and structure Between backplane level, and the second plenum chamber top.
2. it is according to claim 1 to build static pressure cell structure, it is characterised in that first plenum chamber includes:Plenum chamber Steelframe, centrifugally glass-wool plate, galvanized iron sheet and plenum chamber backboard;The centrifugally glass-wool plate is covered under the structural slab of seat region Portion surface and the side of curb girder;The galvanized iron sheet is covered in centrifugally glass-wool plate surface;The plenum chamber steelframe includes main dragon Bone, secondary joist and suspension rod;The main joist and secondary joist cross-fixing are connected, main joist by suspension rod and seat region structural slab or Curb girder is connected;Mutual lap seal splicing between the plenum chamber backboard, and it is fixed on the bottom surface and side of plenum chamber steelframe.
3. it is according to claim 2 to build static pressure cell structure, it is characterised in that the plenum chamber backboard includes backboard dragon Bone, galvanized iron sheet and centrifugally glass-wool plate;The centrifugally glass-wool plate is arranged in the framework surrounded by horizontal bar keel, galvanized iron Suitcase overlays on the outside of horizontal bar keel, and leaves overlap edge.
4. it is according to claim 3 to build static pressure cell structure, it is characterised in that the suspension rod is angle steel, the outside of angle steel Scribble red red antirust paint, and angle steel outsourcing heat-insulation layer.
5. it is according to claim 4 to build static pressure cell structure, it is characterised in that building also includes ceiling decoration, fan unit Pipe, airduct, fire-fighting spray pipe, fulgurite, ceiling decoration, fan coil, airduct, fire-fighting spray pipe, fulgurite are each attached to described quiet On pressure chamber steelframe.
6. it is according to claim 4 to build static pressure cell structure, it is characterised in that the main joist is 10# channel-section steels, described time Keel and suspension rod are L50 × 5 angle steel;The thickness of the galvanized iron sheet is 1mm, and the thickness of the centrifugally glass-wool is 30mm.
7. the building static pressure cell structure according to claim any one of 1-6, it is characterised in that the second plenum chamber bag Include:Centrifugally glass-wool, galvanized iron sheet and secondary structure wall;The centrifugally glass-wool plate is covered in the bottom table of seat region structural slab Face and the side of curb girder;The galvanized iron sheet is covered in centrifugally glass-wool plate surface;Centrifugally glass-wool plate is fixed by bar for line In structure base slab layer upper surface, galvanized iron sheet is covered in centrifugally glass-wool surface and is fixed on structure base slab layer by expansion bolt On;Increase gluing treatment in rubber pad, and hole at hole for the expansion bolt;Secondary structure wall top and the sealing of seat region structural slab Connection, is tightly connected with structure base slab layer below.
8. the construction method of static pressure cell structure is built described in any one of claim 1-7, it is characterised in that comprised the following steps:
Step 1, line setting;Drawing is checked, the coverage and its axis chi of plenum chamber are determined according to on-site actual situations It is very little;According to previous level absolute altitude control point, drawn on concrete beam, post and the wall for having poured with spirit level, and eject horizontal line, be used to Control often walks the absolute altitude of operation;
Step 2, the installation of suspension rod;Suspension rod fixed form is installed and curb girder mounting surface two ways under being divided into seat region structural slab; Hanger erection utilizes expansion bolt by Interal fixation below seat plot structure plate under structural slab, and suspension rod is welded and fixed with steel plate; Beam sides hanger erection is fixed on suspension rod is vertical above beam side using expansion bolt;
The installation of step 3, main joist and secondary joist;It is arranged in parallel between main joist, by secondary between adjacent main joist Keel are welded to connect to form entirety;The fastness detection and examination of plenum chamber:50kg weights are placed on keel, 48 is stood small When, main joist, secondary joist and suspension rod are found without deformed damaged, expansion bolt does not have loosening phenomenon;
Step 4, the making of plenum chamber backboard;Plenum chamber backboard is existing by two-layer galvanized iron sheet, centrifugally glass-wool and horizontal bar keel Field is made;When plenum chamber backboard makes, should be processed according to the plenum chamber steelframe grid size at scene;
Step 5, the installation of plenum chamber backboard;The main joist of installation plenum chamber backboard, secondary joist position is being needed to punch, surface is clear Brush coating is carried out to the position that need to be connected after reason is clean, is fixed by pulling rivet afterwards;
Step 6, the insulation on concrete structure is installed with galvanized iron sheet;Centrifugally glass-wool plate is covered under the structural slab of seat region Portion surface and the side of curb girder;Galvanized iron sheet is covered in centrifugally glass-wool plate surface;Centrifugally glass-wool plate is fixed by bar for line In structure base slab layer upper surface, galvanized iron sheet is covered in centrifugally glass-wool surface and is fixed on structure base slab layer by expansion bolt On;Increase gluing treatment in rubber pad, and hole at hole for the expansion bolt;
Step 7, joint treatment;Plenum chamber backboard seam crossing lays sealing strip, and sealing strip lays along plate stitch is elongated;Plenum chamber backboard Sealed with fireproof seal gum after installing;Plenum chamber backboard also lays elongated with the link position of seat region structural slab or curb girder Sealing strip;
Step 8, after the completion of the sealing of the first plenum chamber, plenum chamber outside integral spray fireproof coating.
9. it is according to claim 8 building static pressure cell structure construction method, it is characterised in that also wrap after step 8 Include plenum chamber sealing propertytest and check and accept step:Use high light light irradiation in plenum chamber backboard, plenum chamber backboard seam crossing and With seat region structural slab or curb girder wall side junction without printing opacity;Then blown to plenum chamber with high pressure blower, by what is lighted Close to plenum chamber backboard seam, flue gas is without substantially dispelling situation for cigarette end.
10. it is according to claim 8 building static pressure cell structure construction method, it is characterised in that in step 2, suspension rod Spacing is not more than 1m, and logical line should be drawn when suspension rod is installed, and the suspension rod on per pass curb girder is kept on the same line;Install and hang After bar, check suspension rod spacing and position whether accurately, bolt whether fasten, weld seam it is whether qualified;It is to be checked it is qualified after, with pellet it is red Antirust paint carries out antirust treatment to suspension rod;To prevent the angle steel suspension rod in plenum chamber from forming cold bridge, condensation being produced, in plenum chamber All suspension rod outsourcing isothermal holdings.
CN201710099248.1A 2017-02-23 2017-02-23 Building static pressure cell structure and its construction method Pending CN106760679A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710099248.1A CN106760679A (en) 2017-02-23 2017-02-23 Building static pressure cell structure and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710099248.1A CN106760679A (en) 2017-02-23 2017-02-23 Building static pressure cell structure and its construction method

Publications (1)

Publication Number Publication Date
CN106760679A true CN106760679A (en) 2017-05-31

Family

ID=58959941

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710099248.1A Pending CN106760679A (en) 2017-02-23 2017-02-23 Building static pressure cell structure and its construction method

Country Status (1)

Country Link
CN (1) CN106760679A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107503529A (en) * 2017-08-31 2017-12-22 温州市大众城建监理有限公司 One kind building static pressure cell structure and its construction method

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201724361U (en) * 2009-11-02 2011-01-26 世纪良基(北京)科技发展有限公司 Formaldehyde-free environment-friendly soundproofing static pressure tank
CN202166160U (en) * 2011-07-14 2012-03-14 深圳市洪涛装饰股份有限公司 Theatre plenum box sound-insulation and heat-preservation structure
CN104088481A (en) * 2014-07-18 2014-10-08 北京城建建设工程有限公司 Sandwich composite glass fiber reinforced plastic plenum chamber for auditorium and construction method thereof
CN204063476U (en) * 2014-08-27 2014-12-31 中建七局第四建筑有限公司 Armored concrete air supply plenum chamber
WO2016033770A1 (en) * 2014-09-04 2016-03-10 冯新林 Method for construction of suspended rhombic aluminum veneer shading curtain wall for exhibition hall
CN105972802A (en) * 2016-05-25 2016-09-28 上海市安装工程集团有限公司 Vibration isolation noise reduction type air conditioner system for floating building and installation method thereof
CN206503384U (en) * 2017-02-23 2017-09-19 北京城建七建设工程有限公司 Build static pressure cell structure
CN107503529A (en) * 2017-08-31 2017-12-22 温州市大众城建监理有限公司 One kind building static pressure cell structure and its construction method
CN207006487U (en) * 2017-05-16 2018-02-13 深圳市深装总装饰股份有限公司 A kind of Movie House floor with under-floor air distribution air-conditioning system
CN209355446U (en) * 2018-11-12 2019-09-06 中信建筑设计研究总院有限公司 A kind of seat air supply static pressure case apparatus
CN110645696A (en) * 2019-10-09 2020-01-03 北京城建七建设工程有限公司 Heating and ventilation static pressure box structure and construction method thereof
CN210486028U (en) * 2019-10-09 2020-05-08 北京城建七建设工程有限公司 Static pressure box structure below grandstand ladder
CN113175245A (en) * 2021-05-22 2021-07-27 中建一局集团第一建筑有限公司 Stand seat air supply static pressure box and construction method thereof

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201724361U (en) * 2009-11-02 2011-01-26 世纪良基(北京)科技发展有限公司 Formaldehyde-free environment-friendly soundproofing static pressure tank
CN202166160U (en) * 2011-07-14 2012-03-14 深圳市洪涛装饰股份有限公司 Theatre plenum box sound-insulation and heat-preservation structure
CN104088481A (en) * 2014-07-18 2014-10-08 北京城建建设工程有限公司 Sandwich composite glass fiber reinforced plastic plenum chamber for auditorium and construction method thereof
CN204063476U (en) * 2014-08-27 2014-12-31 中建七局第四建筑有限公司 Armored concrete air supply plenum chamber
WO2016033770A1 (en) * 2014-09-04 2016-03-10 冯新林 Method for construction of suspended rhombic aluminum veneer shading curtain wall for exhibition hall
CN105972802A (en) * 2016-05-25 2016-09-28 上海市安装工程集团有限公司 Vibration isolation noise reduction type air conditioner system for floating building and installation method thereof
CN206503384U (en) * 2017-02-23 2017-09-19 北京城建七建设工程有限公司 Build static pressure cell structure
CN207006487U (en) * 2017-05-16 2018-02-13 深圳市深装总装饰股份有限公司 A kind of Movie House floor with under-floor air distribution air-conditioning system
CN107503529A (en) * 2017-08-31 2017-12-22 温州市大众城建监理有限公司 One kind building static pressure cell structure and its construction method
CN209355446U (en) * 2018-11-12 2019-09-06 中信建筑设计研究总院有限公司 A kind of seat air supply static pressure case apparatus
CN110645696A (en) * 2019-10-09 2020-01-03 北京城建七建设工程有限公司 Heating and ventilation static pressure box structure and construction method thereof
CN210486028U (en) * 2019-10-09 2020-05-08 北京城建七建设工程有限公司 Static pressure box structure below grandstand ladder
CN113175245A (en) * 2021-05-22 2021-07-27 中建一局集团第一建筑有限公司 Stand seat air supply static pressure box and construction method thereof

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
曹旭明: "国家体育馆看台区空调均衡下送风施工技术", 《安装》 *
曾涛等: "《体育建筑设计手册》", 31 August 2001, 中国建筑工业出版社 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107503529A (en) * 2017-08-31 2017-12-22 温州市大众城建监理有限公司 One kind building static pressure cell structure and its construction method

Similar Documents

Publication Publication Date Title
CN102352661A (en) Fish scale curtain wall system
CN206503384U (en) Build static pressure cell structure
CN105783123B (en) A kind of suspended ceiling device for strengthening the heat exchange of radiation cooling/heating supply top plate
CN106760679A (en) Building static pressure cell structure and its construction method
CN101581122B (en) Cast-in-place hollow floor with hidden protecting fume exhaust ductwork
CN107763759A (en) A kind of building in the style of the ancients air-conditioner outdoor unit concealed structure
CN210486028U (en) Static pressure box structure below grandstand ladder
CN205971329U (en) Rail vehicle wind channel roof skeleton modular structure
CN110645696A (en) Heating and ventilation static pressure box structure and construction method thereof
CN104088481B (en) The construction method of the composite glass fiber reinforced plenum chamber of a kind of auditorium sandwich
Saroglou et al. Façades
CN208291224U (en) Bottom air return way system is sent at a kind of slim bottom for subway
CN203755506U (en) Ribbon curtain wall structure
CN206094383U (en) Subway station ventilating air conditioniner environment control system
CN112253209B (en) Self-adaptive ventilation structure for tunnel construction
CN209686688U (en) Floor piece ventilation duct structure and aeration structure
CN215336887U (en) Wall-attached air supply device with double flow guide plates
Siry Frank Lloyd Wright's innovative approach to environmental control in his buildings for the SC Johnson Company
CN203961350U (en) The composite glass fiber reinforced plenum chamber of a kind of auditorium sandwich
CN209355446U (en) A kind of seat air supply static pressure case apparatus
Hanam Development of an open source hourly building energy modeling software tool
CN113446691A (en) Wall-attached air supply device with double flow guide plates and air supply method thereof
CN113175245A (en) Stand seat air supply static pressure box and construction method thereof
CN109629689B (en) Green dome for building
CN201416225Y (en) Cast-in-situ open web building roof with hidden protection exhaustsmoke conduit system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170531