CN106760045A - A kind of form of construction work for building wall system - Google Patents

A kind of form of construction work for building wall system Download PDF

Info

Publication number
CN106760045A
CN106760045A CN201611247307.7A CN201611247307A CN106760045A CN 106760045 A CN106760045 A CN 106760045A CN 201611247307 A CN201611247307 A CN 201611247307A CN 106760045 A CN106760045 A CN 106760045A
Authority
CN
China
Prior art keywords
building block
block brick
latch fitting
brick
type groove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201611247307.7A
Other languages
Chinese (zh)
Other versions
CN106760045B (en
Inventor
林锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Foshan Century Century Building Materials Co Ltd
Original Assignee
Foshan Century Century Building Materials Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Foshan Century Century Building Materials Co Ltd filed Critical Foshan Century Century Building Materials Co Ltd
Priority to CN201611247307.7A priority Critical patent/CN106760045B/en
Publication of CN106760045A publication Critical patent/CN106760045A/en
Application granted granted Critical
Publication of CN106760045B publication Critical patent/CN106760045B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/02Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls built-up from layers of building elements
    • E04B2/04Walls having neither cavities between, nor in, the solid elements
    • E04B2/06Walls having neither cavities between, nor in, the solid elements using elements having specially-designed means for stabilising the position
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/02Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls built-up from layers of building elements
    • E04B2/04Walls having neither cavities between, nor in, the solid elements
    • E04B2/06Walls having neither cavities between, nor in, the solid elements using elements having specially-designed means for stabilising the position
    • E04B2/08Walls having neither cavities between, nor in, the solid elements using elements having specially-designed means for stabilising the position by interlocking of projections or inserts with indentations, e.g. of tongues, grooves, dovetails
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/02Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls built-up from layers of building elements
    • E04B2002/0202Details of connections
    • E04B2002/0243Separate connectors or inserts, e.g. pegs, pins or keys
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/02Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls built-up from layers of building elements
    • E04B2002/0202Details of connections
    • E04B2002/0243Separate connectors or inserts, e.g. pegs, pins or keys
    • E04B2002/0247Strips or bars
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/02Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls built-up from layers of building elements
    • E04B2002/0202Details of connections
    • E04B2002/0243Separate connectors or inserts, e.g. pegs, pins or keys
    • E04B2002/025U-shaped, e.g. brackets

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • Finishing Walls (AREA)

Abstract

A kind of form of construction work for building wall system;Comprise the following steps:First, the installation of same row building block brick, is carried out successively from the bottom up, and since the 3rd piece of building block brick, the installation fixation between every piece of building block brick and previous piece of building block brick is all carried out according to the installation steps between second piece of building block brick and first piece of building block brick;2nd, the building block brick of an adjacent row is installed, and vertical U-type cell body II is installed on the vertical side of mounted adjacent bricks brick row, then installs building block brick successively from the bottom up, and installation steps are identical with the installation steps of above-mentioned same row building block brick;Built wall is turned left from left to right or from the right side and install by column between the vertical metope in two sides.Adjacent bricks brick is inserted in the side plate of both sides by its respective side upper groove, that is, realize the installation between two building block bricks, bonds building block brick and wall or floor without passing through other binding agents again, installs simple and convenient, intensity reliability.

Description

A kind of form of construction work for building wall system
Technical field
The present invention relates to build wall system field, more particularly to a kind of form of construction work for building wall system.
Background technology
Traditional brick body mounting means is that brick body is fixed on wall using cement and mortar, and this mode program is complicated, Masterful technique operative is needed, using substantial amounts of cement and mortar, waste of materials, and brick body are fixed together with wall, After on wall, it is impossible to carry out it is secondary use, when house is fitted up again, brick body, cement and mortar will be as substantial amounts of Building waste;On the other hand, due to cement and mortar quality weight, test is caused for building supporting power.
The content of the invention
In order to overcome in the prior art, brick body installation is complicated, need skilled worker to operate, brick body can not be reused, wall Weigh big defect, it is reusable the invention provides a kind of rational in infrastructure, easy to use, ceramic tile and installation matter can be improved Amount builds wall system and its form of construction work with efficiency.
It is that, up to this purpose, the present invention uses following technical scheme:
A kind of form of construction work for building wall system;Comprise the following steps:
First, the installation of same row building block brick, is carried out successively from the bottom up, wherein:1) first piece of building block brick is installed, vertical Vertical U-type cell body I is installed, the notch of the vertical U-type cell body I is outside on metope;In the level joined with the vertical metope Horizontally U-shaped cell body I is installed, the notch of the horizontally U-shaped cell body I is upward, and its side end face props up the vertical U type groove on ground The outer face of the avris plate of body I, the vertical U-type cell body I and horizontally U-shaped cell body I form 90 degree of right angles;By first piece of building block brick Card holding trough in adjacent flank side surface and bottom side inserts the vertical U-type cell body I and the fixation of horizontally U-shaped cell body I respectively;
2) second piece of building block brick is installed, horizontally U-shaped cell body II, the horizontal U is installed in first piece of upper side of building block brick The notch of type groove body II is upward, and its end side surface props up the outer face of the avris plate of the vertical U-type cell body I;
One side plate of L-type corner brace is placed in the horizontally U-shaped cell body II, with the side plate in the another of 90 degree of angles Side plate is posted by the bottom land of vertical U-type cell body I, then by fixing bolt is separately fixed at two side plates of L-type corner brace respectively In vertical U-type cell body I and horizontally U-shaped cell body II;
Card holding trough on second piece of building block brick adjacent bottom side and flank side surface is inserted into the vertical U-type cell body I respectively It is fixed with horizontally U-shaped cell body II;
3) since the 3rd piece of building block brick, the installation between every piece of building block brick and previous piece of building block brick is fixed all according to second Installation steps between block building block brick and first piece of building block brick are carried out;
2nd, the building block brick of an adjacent row is installed, and vertical U-type is installed on the vertical side of mounted adjacent bricks brick row Cell body II, then building block brick is installed successively from the bottom up, installation steps are identical with the installation steps of above-mentioned same row building block brick;
Built wall is turned left from left to right or from the right side and install by column between the vertical metope in two sides.
Preferably, also including gating operation, the position by gating operation to needing to install door body on built wall is entered Row is left a blank, and the gating operation is comprised the following steps:
A) the right and left for the position of leaving a blank for installing door body in the planning of built wall is respectively mounted left side building block brick row and the right side Side building block brick row, the left side building block brick row and right side building block brick row are respectively by some building block bricks, U-type groove body and L-type corner brace Arranged by with each adjacent building block brick, installed upwards successively according to step one (2) and step one (3), to obtain height and institute The left side building block brick row that the height of the door body that need to be installed is suitable are arranged with right side building block brick, and left side building block brick row and right side building block brick The horizontal range for arranging interval is suitable with the width of door body;
B) it is described by lintel U-type groove body across the upper side for being fixed on the left side building block brick row and right side building block brick row The opening upwards of lintel U-type groove body, and the high order end that is arranged with the left side building block brick of its length and right side building block brick row is most right Horizontal range between end is suitable;
C) up continue that building block brick row are installed successively since lintel U-type groove body, connect until with ceiling, mounting means It is identical with step one (2) and step one (3), the weight of building block brick between door body and ceiling is born in the middle part of lintel U-type groove body.
Preferably, wall most left upper end is built or installation site that most upper right side is last block building block brick, last block Building block brick is comprised the following steps when installing:1) side by lower section building block brick by wall is consolidated by the stretchable clamp of locking U-type groove body I Vertical metope is scheduled on, the stretchable locking U-type groove body I vertically extends;By it is left right building block brick by stretchable locking U-type groove body II is fixed with building block brick below, and the stretchable locking U-type groove body II is horizontally extending;
The stretchable locking U-type groove body I and stretchable locking U-type groove body II include the first latch fitting and the second latch fitting, The section of the first latch fitting is U-shaped, first latch fitting and the second latch fitting can be inserted into the card holding trough of building block brick with the product Woodbox clamp is fixed;
Second latch fitting is mutually placed in first latch fitting, and the direction that second latch fitting extends along end is slidably drawn For first latch fitting;First latch fitting is provided with limiting section, and second latch fitting is provided with card division, and the card division cocker is butted on In the limiting section, second latch fitting by the setting of the card division and the limiting section it is irreversible spacing and can pull out in First latch fitting;
2) last block building block brick is put into its installation site;
3) the second latch fitting of stretchable locking U-type groove body I is pulled out upwards, inserts the card of last block building block brick flank side surface It is locked with last block building block brick in tankage;By stretchable locking U-type groove body II to the left right pull-out, insert last block It is locked with last block building block brick in the card holding trough of building block brick downside.
Preferably, the U-shaped section in section of second latch fitting;First latch fitting is mutual with the bottom surface of the second latch fitting Contact, the elongated end of second latch fitting protrudes from the end of first latch fitting;
The limiting section of some mounting holes and projection is arranged in the bottom surface of first latch fitting;
The bottom surface of second latch fitting is provided with the card division and mounting groove, and the mounting groove is used for mounting hole described in empty avoiding, The mounting groove is located at the middle part of the bottom surface of second latch fitting, and it is opened along the axis direction of the bottom surface of second latch fitting If at least provided with 2,2 card divisions are respectively positioned at the both sides of the mounting groove for the card division;
The base of the side wall of the elongated end of second latch fitting is provided with push rod, and the push rod is used to pull out second lock Part.
Preferably, the two side of first latch fitting is respectively arranged with mounting groove in vertical direction, outside its two side The base on surface is provided with the extension slot of horizontal direction fluting, and the inwall of the mounting groove is horizontally arranged to be provided with some limits Position portion, the bottom of first latch fitting is provided for the mounting hole of lock ground or lock wall;
The plate face of second latch fitting is provided with the card division, and second latch fitting is provided with two, second latch fitting point It is not installed in the mounting groove, and its card division for setting is limited in mounting groove in some limiting sections, second latch fitting One edges of boards are located at the bottom of the mounting groove, and its another edges of boards is provided with concordant portion, and the concordant portion protrudes from the mounting groove, And the width B in concordant portion described in its both sides is equal to the width of first latch fitting;
Second latch fitting can draw from the end of the mounting groove and remove, and the card division of second latch fitting receives described spacing The limitation in portion, when the previous limiting section is crossed in the card division, second latch fitting can not be moved the card division inversely Again it is stuck in the previous limiting section;
Also include push rod, the push rod is provided with 2, two push rods be each passed through the extension slot be connected to it is described The bottom of the side wall of the second latch fitting;Second latch fitting is moved along the extension slot by the push rod and is dragged out the peace Tankage.
Preferably, last block building block brick is put into it and pacified by last block building block brick by sucker suction by mobile sucker Holding position.
Preferably, the building block brick is slim hexahedron structure, and two larger faces are surface, and four less faces are side Face, each described side is provided with two card holding troughs and a middle part projection, and the card holding trough runs through the whole side, it is described in Portion's projection is the platform between two card holding troughs;
The U-type groove body is metal material, and it includes trough floor and two avris plates, and avris plate is individually fixed in described in two The two ends of the trough floor, and the upper end of avris plate described in two gathers to the inside of the U-type groove body, the trough floor is provided with Through the mounting hole of its upper and lower two plate face;
The avris plate inserts the card holding trough, to realize the fixation of the U-type groove body and building block brick.
Preferably, the corner of the building block brick is fixed by L-type corner brace with the corner of adjacent bricks brick;
The L-type corner brace includes two side plates, and two side plates are vertically fixed by respective one end and form 90 degree Angular structure;The side plate is provided with the fixed via through its upper and lower two plate face;The width of the side plate and the U-type groove body Width it is suitable so that the side plate can be just put into the U-type groove body;
U-type groove body described in two is installed on the orthogonal two sides of the building block brick, two sides of the L-type corner brace respectively Plate is attached at the orthogonal two sides of the building block brick respectively, and the lateral surface of two side plates is attached at the U-type groove The madial wall of body.
Preferably, the middle part projection length direction two ends, be designed with corner brace erecting bed;The corner brace erecting bed Formed towards the inner recess of the building block brick by the upper end of the middle part projection so that the L-type corner brace when mounted, its side The madial wall of plate is affixed on the corner brace erecting bed, and the lateral wall of the side plate is in the same plane with the side of building block brick.
Preferably, the length of the biside plate of the L-type corner brace is unequal.
It is U-shaped with building block brick is wall constructed or during floor, first matching used U-type groove body is arranged on wall or floor Two avris plates of cell body extend to the direction away from wall or floor, and the card holding trough of building block brick side is inserted into U-type groove body Two avris plates.After being installed near the building block brick on wall side, then building block brick is spliced successively with building block brick by U-type groove body Installation forms metope, and in the installation process of building block brick and building block brick, mode is similar to above, and U-type groove body is fixed therein On the side of one building block brick, two avris plates of U-type groove body extend to adjacent side, and adjacent bricks brick passes through its respective side upper groove In insertion both sides side plate, that is, the installation between two building block bricks is realized, without passing through other binding agents again by building block brick and wall Or floor bonds, simple and convenient, intensity reliability is installed.
Brief description of the drawings
Fig. 1 present invention builds the scheme of installation of each building block brick in wall;
Fig. 2 is the installation procedure figure of building block brick 1-1 and building block brick 1-2 in the present invention;
Fig. 3 is the scheme of installation of L-type corner brace in the present invention;
Fig. 4 is the partial sectional view of one embodiment of stretchable locking U-type groove body in the present invention;
Fig. 5 is the top view of one embodiment of stretchable locking U-type groove body in the present invention;
Fig. 6 is the partial sectional view of another embodiment of stretchable locking U-type groove body in the present invention;
Fig. 7 is the top view of another embodiment of stretchable locking U-type groove body in the present invention;
Fig. 8 is the stereogram of one embodiment of building block brick in the present invention;
Fig. 9 is the clamping structure schematic diagram of one embodiment of U-type groove body and building block brick in the present invention;
Figure 10 is the stereogram of one embodiment of U-type groove body in the present invention;
Figure 11 is the stereogram of one embodiment of L-type corner brace in the present invention;
Figure 12 is the structural representation of one embodiment of mounting hole and fixed via in the present invention.
Wherein:Building block brick 1, building block brick 1-1, building block brick 1-2, building block brick 1-3, building block brick 1-4, building block brick 1-5, building block brick 1-6, building block brick 1-7, building block brick 1-8, building block brick 1-9, building block brick 1-10, building block brick 1-11, building block brick 1-12, building block brick 1- 13, building block brick 1-18, building block brick 1-19, building block brick 1-20, building block brick 1-21, building block brick 1-22, building block brick 1-23, building block brick 1- 24, card holding trough 11, middle part projection 12, corner brace erecting bed 13 locks groove 14;Fixing bolt 2;
U-type groove body 3, vertical U-type cell body I 301, horizontally U-shaped cell body I 311, horizontally U-shaped cell body II 312, trough floor 31, side Side plate 32, mounting hole 33;
L-type corner brace 4, side plate 41, installation through-hole 42;
Stretchable locking U-type groove body 5, the first latch fitting 51, limiting section 511, mounting hole 512, mounting groove 513, extension slot 514, mounting hole 515;Second latch fitting 52, elongated end 5201, card division 521, mounting groove 522, concordant portion 523;
Push rod 6, breach 7, lintel U-type groove body 8, diameter through hole 91, minor diameter through hole 92, installation step 93.
Specific embodiment
Further illustrate technical scheme below in conjunction with the accompanying drawings and by specific embodiment.
As shown in Figures 1 and 2, a kind of form of construction work for building wall system;Comprise the following steps:
First, the installation of same row building block brick, is carried out successively from the bottom up, wherein:1) first piece of building block brick 1-1 is installed, Vertical U-type cell body I 301 is installed on vertical metope, the notch of the vertical U-type cell body I 301 is outside;With the vertical metope Horizontally U-shaped cell body I 311 is installed, the notch of the horizontally U-shaped cell body I 311 is upward, and its side end face on the level ground of handing-over Prop up the outer face of the avris plate of the vertical U-type cell body I 301, the vertical U-type cell body I 301 and horizontally U-shaped cell body I 311 Form 90 degree of right angles;Card holding trough in first piece of building block brick adjacent flank side surface and bottom side is inserted into the vertical U-type respectively Cell body I 301 and horizontally U-shaped cell body I 311 are fixed;
2) second piece of building block brick is installed, horizontally U-shaped cell body II 311, the water is installed in first piece of upper side of building block brick The notch of flat U-type groove body II 311 is upward, and its end side surface props up the outer face of the avris plate of the vertical U-type cell body I 301;
One side plate of L-type corner brace 4 is placed in the horizontally U-shaped cell body II 311, is in 90 degree of angles with the side plate Another side plate is posted by the bottom land of vertical U-type cell body I 301, then passes through fixing bolt 2 respectively by two side plates of L-type corner brace 4 point It is not fixed in vertical U-type cell body I and horizontally U-shaped cell body II;
Card holding trough on second piece of building block brick adjacent bottom side and flank side surface is inserted into the vertical U-type cell body I respectively It is fixed with horizontally U-shaped cell body II;
3) since the 3rd piece of building block brick, the installation between every piece of building block brick and previous piece of building block brick is fixed all according to second Installation steps between block building block brick and first piece of building block brick are carried out;
2nd, the building block brick of an adjacent row is installed, and vertical U-type is installed on the vertical side of mounted adjacent bricks brick row Cell body II, then building block brick is installed successively from the bottom up, installation steps are identical with the installation steps of above-mentioned same row building block brick;
Built wall is turned left from left to right or from the right side and install by column between the vertical metope in two sides.
Also include gating operation, the position by gating operation to needing to install door body on built wall is left a blank, The gating operation is comprised the following steps:
A) the right and left for the position of leaving a blank for installing door body in the planning of built wall is respectively mounted left side building block brick row and the right side Side building block brick row, the left side building block brick row and right side building block brick row are respectively by some building block bricks, U-type groove body and L-type corner brace Arranged by with each adjacent building block brick, installed upwards successively according to step one (2) and step one (3), to obtain height and institute The left side building block brick row that the height of the door body that need to be installed is suitable are arranged with right side building block brick, and left side building block brick row and right side building block brick The horizontal range for arranging interval is suitable with the width of door body;
B) it is described by lintel U-type groove body across the upper side for being fixed on the left side building block brick row and right side building block brick row The opening upwards of lintel U-type groove body, and the high order end that is arranged with the left side building block brick of its length and right side building block brick row is most right Horizontal range between end is suitable;
C) up continue that building block brick row are installed successively since lintel U-type groove body, connect until with ceiling, mounting means It is identical with step one (2) and step one (3).
Build the mounting means of last block building block brick in wall system;Built wall most upper right side is last block building block brick 1- 24 installation site, last block building block brick 1-24 comprises the following steps when installing:1) side by lower section building block brick by wall leads to Cross the stretchable clamp of locking U-type groove body I and be fixed on vertical metope, the stretchable locking U-type groove body I vertically extends;Will It is left right building block brick fixed with building block brick below by stretchable locking U-type groove body II, this is stretchable to lock U-type groove body II is horizontally extending;
As shown in Fig. 4 to Fig. 7, the stretchable locking U-type groove body I and stretchable locking U-type groove body II include first The latch fitting 52 of latch fitting 51 and second, the section of the first latch fitting 51 is U-shaped, and the latch fitting 52 of first latch fitting 51 and second can be inserted into Fixed with the clamp of the building block brick 1 in the card holding trough 11 of building block brick 1;
Second latch fitting 52 is mutually placed in first latch fitting 51, and the direction that second latch fitting 52 extends along end can Slip is pulled out in first latch fitting 51;First latch fitting 51 is provided with limiting section 511, and second latch fitting 52 is provided with card division 521, the cocker of the card division 521 is butted in the limiting section 511, and second latch fitting 52 passes through the card division 521 and limiting section 511 setting is irreversible spacing and can pull out in first latch fitting 51;
2) last block building block brick 1-24 is put into its installation site;
3) the second latch fitting 52 of stretchable locking U-type groove body I is pulled out upwards, inserts last block building block brick 1-24 avris It is locked with last block building block brick 1-24 in the card holding trough in face;By stretchable locking U-type groove body II to the left right pull-out, insert It is locked with last block building block brick 1-24 in the card holding trough for entering last block building block brick 1-24 downsides.
As shown in Figures 4 and 5, one embodiment of the stretchable structure of locking U-type groove body 5:Second latch fitting 52 The U-shaped section in section;First latch fitting 51 contacts with each other with the bottom surface of the second latch fitting 52, the extension of second latch fitting 52 End 5201 protrudes from the end of first latch fitting 51;
The limiting section 511 of some mounting holes 512 and projection is arranged in the bottom surface of first latch fitting 51;
The bottom surface of second latch fitting 52 is provided with the card division 521 and mounting groove 522, and the mounting groove 522 is used for empty avoiding The mounting hole 512, the mounting groove 522 is located at the middle part of the bottom surface of second latch fitting 52, and it is along second latch fitting The axis direction of 52 bottom surface opens up, and at least provided with 2,2 card divisions 521 are located at the peace respectively for the card division 521 The both sides of tankage 522;
The base of the side wall of the elongated end 5201 of second latch fitting 52 is provided with push rod 6, and the push rod 6 is described for pulling out Second latch fitting 52.
The lower section building block brick is fixed by stretchable locking U-type groove body 5 with vertical metope, the stretchable locking U-type groove Body 5 vertically extends;It is described it is left right building block brick consolidate with building block brick below also by stretchable locking U-type groove body 5 Fixed, the stretchable locking U-type groove body 5 is horizontally extending;
By it is left the card holding trough of downside of right building block brick be installed in the first latch fitting of the stretchable locking U-type groove body 5 51, the card holding trough of the flank side surface of the lower section building block brick is also installed in first of the stretchable locking U-type groove body 5 on vertical metope After latch fitting 51, last block building block brick is spliced in its installation site, then by with it is left right building block brick clamp it is stretchable Second latch fitting 52 of locking U-type groove body 5 by push rod 6 to the right Zola go out, and be embedded on last block building block brick 1-24 bottom side Card holding trough in, then the second latch fitting 52 with the stretchable locking U-type groove body 5 of the lower section building block brick clamp is passed through into push rod 6 Pull out upwards, and embedded last block building block brick is by the card holding trough in the flank side surface of wall side, by two stretchable locking U Second latch fitting 52 of type groove body 5 is embedded in the inside groove of last block building block brick the splicing peace for realizing last block building block brick respectively Dress, and realize the second latch fitting 52 relative to first by the limiting section 511 and card division 521 that are set in stretchable locking U-type groove body 5 Irreversible restriction after the pull-out of latch fitting 51, it is ensured that the firm installation capability of the second latch fitting 52, i.e., it is U-shaped by 1 stretchable locking Cell body 5 is that the splicing being capable of achieving between connected brick plate is installed, it is adaptable to the seamless installation for building last block brick plate in wall system, behaviour It is convenient simple to make, and can realize seamless spliced between brick plate.
In the present embodiment, the upper well width A in the U-shaped section of second latch fitting 52 is slightly larger than or equal to the described first lock The upper well width in the U-shaped section of part 51.Applying certain pressure by the side wall to the second latch fitting 52 can be by the second latch fitting 52 press-ins are placed in the first latch fitting 1, and the side wall of the second the first latch fitting 51 of latch fitting 52 pairs has certain pressure, can make the second latch fitting 52 Embedded installation it is more firm.
As shown in FIG. 6 and 7, second embodiment of the stretchable structure of locking U-type groove body 5:First latch fitting 51 Two side is respectively arranged with mounting groove 513 in vertical direction, and the base of the outer surface of its two side is provided with horizontal direction and opens The extension slot 514 of groove, the inwall of the mounting groove 513 is horizontally arranged to be provided with some limiting sections 511, first latch fitting 51 bottom is provided for the mounting hole 515 of lock ground or lock wall;
The plate face of second latch fitting 52 is provided with the card division 521, and second latch fitting 52 is provided with two, described second Latch fitting 52 is respectively arranged in mounting groove 513, and its card division 521 for setting is limited in some limiting sections 511 in mounting groove 513 Interior, an edges of boards of second latch fitting 52 are located at the bottom of the mounting groove 513, and its another edges of boards is provided with concordant portion 523, institute State concordant portion 523 and protrude from the mounting groove 513, and the width B in concordant portion 523 described in its both sides is equal to first latch fitting 51 Width;
Second latch fitting 52 can draw from the end of the mounting groove 513 and remove, and second latch fitting 52 card division 521 Limited by the limiting section 511, when the previous limiting section 511 is crossed in the card division 521, second latch fitting 52 is not Can inversely move and the card division 521 is stuck in the previous limiting section 511 again;
Also include push rod 6, the push rod 6 is provided with 2, and two push rods 6 are each passed through the extension slot 514 and connect In the bottom of the side wall of second latch fitting 52;Second latch fitting 52 moved along the extension slot 514 by the push rod 6 and Dragged out the mounting groove 513.
By it is left the card holding trough of downside of right building block brick be installed in the first latch fitting of the stretchable locking U-type groove body 5 51, the card holding trough of the flank side surface of the lower section building block brick is also installed in first of the stretchable locking U-type groove body 5 on vertical metope After latch fitting 51, last block building block brick is spliced in its installation site, then by with it is left right building block brick clamp it is stretchable Second latch fitting 52 of locking U-type groove body 5 by push rod 6 to the right Zola go out, and be embedded in the card on last block building block brick bottom side In tankage, then will be upward by push rod 6 with the second latch fitting 52 of the stretchable locking U-type groove body 5 of the lower section building block brick clamp Pull out, and embedded last block building block brick is by the card holding trough in the flank side surface of wall side, by two stretchable locking U-type grooves Second latch fitting 52 of body 5 is embedded in the inside groove of last block building block brick respectively realizes that the splicing of last block building block brick is installed, And realize the second latch fitting 52 relative to the first lock by the limiting section 511 and card division 521 that are set in stretchable locking U-type groove body 5 Irreversible restriction after the pull-out of part 51, it is ensured that the firm installation capability of the second latch fitting 52, i.e., by 1 stretchable locking U-type groove Body 5 is that the splicing being capable of achieving between connected brick plate is installed, it is adaptable to the seamless installation for building last block brick plate in wall system, operation It is convenient simple, and can realize seamless spliced between brick plate.Concordant portion 523 is provided with, is its folder after two piece of second latch fitting 2 is pulled out Tight width is consistent with the clip slot width of the first latch fitting 1, and the card holding trough of last block brick plate is carried out by two piece of second latch fitting 52 Embedding folder is installed, it is ensured that to last block brick plate with it is left right building block brick, lower section building block brick be respectively provided with good steadiness.
Last block building block brick is put into its installation position by last block building block brick 1-24 by sucker suction by mobile sucker Put, easy to operate, accurate positioning.
As shown in Fig. 8 to Figure 10, in the technical program, the building block brick 1 is slim hexahedron structure, two larger faces It is surface, four less faces are side, and each described side is provided with two card holding troughs 11 and a middle part projection 12, the card Tankage 11 runs through the whole side, and the middle part projection 12 is the platform between two card holding troughs 11;
The U-type groove body 3 is metal material, and it includes trough floor 31 and two avris plates 32,32 points of avris plate described in two The two ends of the trough floor 31 are not fixed on, and the upper end of avris plate 31 described in two is gathered to the inside of the U-type groove body 3, institute State trough floor 31 and be provided with mounting hole 33 through its upper and lower two plate face;
As shown in figure 9, the avris plate 32 inserts the card holding trough 11, to realize the U-type groove body 3 and building block brick 1 It is fixed.
Because the thickness of the avris plate 32 of U-type groove body 3 is suitable with the groove width of card holding trough 11, the inner stuffing of building block brick 1 contains There are cement, the frictional force after the insertion card holding trough 11 of avris plate 32 of U-type groove body 3 between both side walls so that U-type groove body 3 and product The stuck fixation of woodbox 1;Further, since metal is flexible, and avris plate 31 described in two inside from upper end to the U-type groove body 3 Gather, U-type groove body 3 is snapped in when in two card holding troughs 11 of building block brick 1, two avris plates 31 of U-type groove body 3 can be supportted by force Open, in the presence of in metallic elastic is replied, avris plate 31 can be attached and clamped in the card holding trough 11 of building block brick 1 again, improved and fixed Stability.
As shown in Figure 9, it is preferred that the bottom of the card holding trough 11 is provided with locking groove 14, and locking groove 14 is by clamp The bottom end face of groove 11 is recessed to be formed downwards, the thickness of slab of the thickness of slab less than its fixing end of the free end of the avris plate 32 so that The free end of the avris plate 32 is fixed after snapping in the locking groove 14.
The card holding trough 11 of building block brick 1 designs thickness in pairs, and outer thickness is larger, the inside it is narrower, and with U-type groove Quite, what is be so just more prone to when building block brick is inserted in the side of U-type groove body can be with stuck fixation for wall wide.
As shown in figure 11, the L-type corner brace 4 includes two side plates 41, and two side plates 41 are hung down by respective one end The straight fixed angular structure for forming 90 degree;The side plate 41 is provided with the fixed via through its upper and lower two plate face;The side plate 41 width is suitable with the width of the U-type groove body 3 so that the side plate 41 can be just put into the U-type groove body 3;By L When type corner brace 4 fixes the corner of building block brick 4, side plate 41 is fixed on when in the trough floor 31 of U-type groove body 3 by fixing bolt, groove The side wall of base plate 31 is contacted with the madial wall of U-type groove body 3, and the friction that contact is produced defines relative motion between the two, carries The stability of height assembling.
U-type groove body 3 described in two is installed on the orthogonal two sides of the building block brick 1, the two of the L-type corner brace 4 respectively Individual side plate 41 is attached at the orthogonal two sides of the building block brick 1 respectively, and the lateral surface of two side plates 41 is attached at The madial wall of the U-type groove body 3.
At the two ends of the length direction of the middle part projection 12, corner brace erecting bed 13 is designed with;The corner brace erecting bed 13 Formed towards the inner recess of the building block brick 1 by the upper end of the middle part projection 12 so that the L-type corner brace 4 when mounted, The madial wall of its side plate 41 is affixed on the corner brace erecting bed 13, and the lateral wall of the side plate 41 is in same with the side of building block brick 1 In one plane.
The length of the biside plate 41 of the L-type corner brace 4 is unequal.The adjacent side of same building block brick 1 passes through two U respectively Type groove body 3 is installed, vertically-mounted in such as Fig. 3 and two U-type groove bodies 3 that are horizontally mounted, and two groove width specification phases of U-type groove body 3 Deng (being easy to volume production, improve production efficiency).Vertically-mounted U-type groove body 3 inserts the card holding trough 11 of the left surface of building block brick 1, is based on The equal factor of groove width, the U-type groove body 3 being horizontally mounted just props up the right-hand end of vertically-mounted U-type groove body 3, L-type corner brace 4 One end be fixed in vertically-mounted U-type groove body 3, the other end is fixed in the U-type groove body 3 being horizontally mounted, and due to two U Type groove body 3 cannot be superimposed, so L-type corner brace 4 occurs hanging section C as shown in Figure 3, in order to ensure L-type corner brace 4 in building block brick The equal length extended on 1 each side, so two side plate length of L-type corner brace 4 are unequal, with the length difference between biside plate Compensate the length of " hanging section ", compact mounting structure.
In addition, the mounting hole 33 on U-type groove body 3 in the technical program, the fixed via 42 in L-type corner brace 4, be all by The stepped throughhole of diameter through hole 91 and the composition of minor diameter through hole 92, as shown in Figure 10 and Figure 12, the top nut of fixing bolt 2 Height is suitable with the height of diameter through hole 91, and the screw rod lower end of fixing bolt 2 pierces the type groove of building block brick or building block brick When fixed, the lower surface of the top nut of fixing bolt 2 props up installation step 93, and whole nut is hidden in diameter through hole 91, is made Fixing bolt 2 upper surface it is non-bulging in side plate 41 and the plate face of trough floor 32, be easy to the type of adjacent bricks brick or building block brick The superposition of groove, more compact structure.
Preferably, screw thread, i.e. diameter through hole 91 and minor diameter through hole 92 are designed with mounting hole 33 and fixed via 42 Screw thread is inside both provided with, the skew in bolt occurred level all directions is limited by its spiral helicine lines, improve the steady of installation It is qualitative.
In the present embodiment, by being built wall and being specifically described this by what 24 pieces of building block bricks (1-1~1-24) were built up in Fig. 1 Leave the position for installing door body, and 24 pieces of peaces of building block brick (1-1~1-24) in the technical scheme of invention, the centre that the institute builds wall Dress order carried out successively according to the numbering in Fig. 1, finally give 5 row building block bricks row, be respectively building block brick row I (building block brick 1-1, Building block brick 1-2, building block brick 1-3, building block brick 1-4, building block brick 1-5), building block brick row II (building block brick 1-10, building block brick 1-11, product Woodbox 1-12, building block brick 1-13, building block brick 1-18, building block brick 1-19), building block brick row III (building block brick 1-20, building block brick 1-21), Building block brick row IV (building block brick 1-14, building block brick 1-15, building block brick 1-16, building block brick 1-17, building block brick 1-22, building block brick 1- 23), building block brick row V (building block brick 1-6, building block brick 1-7, building block brick 1-8, building block brick 1-9, building block brick 1-24).
Built wall is from building block brick row I (building block brick 1-1, building block brick 1-2, building block brick 1-3, building block brick 1-4, building block brick 1- 5) start to install:
As shown in Figures 2 and 3, building block brick 1-1 is first installed, installs perpendicular on the vertical metope in the left side of building block brick row I first Straight U-type groove body I 301, the notch of vertical U-type cell body I 301 is outside;Water is installed on the level ground joined with vertical metope again Flat U-type groove body I 311, the notch of horizontally U-shaped cell body I 311 is upward, and its left end face props up the avris of vertical U-type cell body I 301 The outer face of plate.No matter whether flat metope is, and vertical U-type cell body I 301 is when mounted, it is necessary to keep absolute plumbness (to put down Row is in plummet direction);No matter whether flat level ground is, and horizontally U-shaped cell body I 311 is when mounted, it is necessary to protect absolute level State (on the basis of horizontal line), vertical U-type cell body I 301 and horizontally U-shaped cell body I 311 are when mounted by instruments such as level meters Determine respective position, it is ensured that vertical U-type cell body I 301 and horizontally U-shaped cell body I 311 form 90 degree of right angle.Will be perpendicular to water The U-type groove body that horizontal line is installed is defined as vertical U-type cell body, and the vertical U-type cell body that will be installed for each building block brick row is according to row number It is respectively designated as the U-type groove body that vertical U-type cell body I 301, vertical U-type cell body II, vertical U-type cell body III ... will be horizontally mounted Horizontally U-shaped cell body is defined as, the horizontally U-shaped cell body installed for each building block brick is named as horizontal U according to the numbering of building block brick Type groove body I 311, horizontally U-shaped cell body II 312, horizontally U-shaped cell body III ...
The height of vertical U-type cell body I 301 is suitable with the height for installing its vertical wall, vertical U-type cell body I 301 and water After the installation of flat U-type groove body I 311, the card holding trough in building block brick 1-1 adjacent flank side surface and bottom side is inserted described respectively Stuck fixation after vertical U-type cell body I 301 and horizontally U-shaped cell body I 311.
After building block brick 1-1 installations, building block brick 1-2 is then installed, horizontally U-shaped is installed in the upper side of building block brick 1-1 Cell body II 312, upwards, its left end side props up the avris plate of vertical U-type cell body I 301 to the notch of horizontally U-shaped cell body II 312 Outer face;
One side plate of L-type corner brace 4 is placed in the horizontally U-shaped cell body II 312, is in 90 degree of angles with the side plate Another side plate is posted by the bottom land of vertical U-type cell body I 301, then passes through fixing bolt respectively by two side plates difference of L-type corner brace It is fixed in vertical U-type cell body I 301 and horizontally U-shaped cell body II 312;
Card holding trough on building block brick 1-12 adjacent bottom side and flank side surface is inserted into the He of horizontally U-shaped cell body II 312 respectively It is fixed in vertical U-type cell body I 301;
To building block brick 1-5 since building block brick 1-2, the installation between every piece of building block brick and previous piece of building block brick is fixed and all pressed Carried out according to the installation steps between building block brick 1-1 and building block brick 1-2, until building block brick row I (1-1,1-2,1-3,1-4,1-5) peace Install into.
After the installation of building block brick row I (1-1,1-2,1-3,1-4,1-5), building block brick row V (1-6,1- are then carried out 7th, 1-8,1-9,1-24) installation, wherein building block brick 1-24 be entirely last block of built wall install building block brick, then peace During dress building block brick row V, building block brick 1-6, building block brick 1-7, building block brick 1-8 and building block brick 1-9, building blocks are first installed successively in order The installation site of brick 1-24 is left a blank.When building block brick 1-6, building block brick 1-7, building block brick 1-8 and building block brick 1-9 are installed, step and product The installation of woodbox row I is identical, first vertical U-type cell body V is vertically mounted on the vertical metope on the right side of building block brick V, its notch To the left, the vertical distance and between the top of vertical U-type cell body V and ceiling be two pieces of upper and lower setting height(from bottom)s of building block brick and; Horizontally U-shaped cell body V is horizontally arranged on level ground (horizontally U-shaped cell body V is parallel with sea level), and its notch is upward, vertical U Type groove body V and horizontally U-shaped cell body V form 90 degree of right angles.After U-type groove body installation, by the adjacent bottom sides of building block brick 1-6 Insert fixed in horizontally U-shaped cell body V and vertical U-type cell body V respectively with the card holding trough in flank side surface;Since building block brick 1-7 The installation of building block brick 1-8 is up arrived, it is identical with the mounting means between building block brick 1-2 and building block brick 1-1.
The position of door body installation is left between building block brick row II and building block brick row IV, the installation of this two row building block brick is all divided into Carry out twice, what is first carried out is left side building block brick row (building block brick 1-10, building block brick 1-11, the building block brick suitable with door height 1-12, building block brick 1-13) and right side building block brick row (building block brick 1-14, building block brick 1-15, building block brick 1-16, building block brick 1-17), If it is required that left side building block brick row and the height of right side building block brick row can not be obtained by the installation of monoblock building block brick, need The height of its uppermost one piece of building block brick is carried out into part cutting, makes the building block brick installed after cutting and building block brick below The height suitable with door body is gathered out in superposition together.
Wherein, the installation of left side building block brick row (building block brick 1-10, building block brick 1-11, building block brick 1-12, building block brick 1-13) Mounting means with each building block brick in building block brick row I is identical, and first vertical U-type cell body II is vertically mounted on the right side of building block brick I In flank side surface, to the right, and vertical U-type cell body II is suitable with the height of building block brick I for its notch;The level of horizontally U-shaped cell body II 312 is pacified On level ground (horizontally U-shaped cell body II 312 is parallel with sea level), its notch upwards, vertical U-type cell body II and horizontal U Type groove body II 312 forms 90 degree of right angles.After U-type groove body installation, by building block brick 1-10 adjacent bottom side and flank side surface Card holding trough insert in horizontally U-shaped cell body II 312 and vertical U-type cell body II fixed respectively, since building block brick 1-11 up to The installation of building block brick 1-13, it is identical with the mounting means between building block brick 1-2 and building block brick 1-1;
The installation on right side building block brick row (building block brick 1-14, building block brick 1-15, building block brick 1-16, building block brick 1-17) and left side The installation of building block brick row is identical, and first vertical U-type cell body IV is vertically mounted in the flank side surface in the left side of building block brick V, its notch to A left side, and vertical U-type cell body IV top and ceiling between vertical distance be one piece of height of building block brick;Horizontally U-shaped cell body IV is horizontally arranged on level ground (horizontally U-shaped cell body IV is parallel with sea level), and its notch is upward, the He of vertical U-type cell body IV Horizontally U-shaped cell body IV forms 90 degree of right angles.After U-type groove body installation, by building block brick 1-14 adjacent bottom side and flank side surface On card holding trough insert in horizontally U-shaped cell body IV and vertical U-type cell body IV fixed respectively, up to product since building block brick 1-15 The installation of woodbox 1-17, it is identical with the mounting means between building block brick 1-2 and building block brick 1-1.
Left side building block brick row (building block brick 1-10, building block brick 1-11, building block brick 1-12, building block brick 1-13) and right side building block brick After row (building block brick 1-14, building block brick 1-15, building block brick 1-16, building block brick 1-17) installation, by lintel U-type groove body across solid It is scheduled on the upper side of left side building block brick row and right side building block brick row, the opening upwards of lintel U-type groove body, and its length and the left side Horizontal range between the high order end of side building block brick row and the low order end of right side building block brick row is suitable.
After lintel U-type groove body installation, next the building block brick row between lintel U-type groove body and ceiling are installed, it is left The installation of building block brick row (building block brick 1-18, building block brick 1-19) above the building block brick row of side, first puts a side plate of L-type corner brace Put in lintel U-type groove body, be posted by the bottom land of vertical U-type cell body II in another side plate of 90 degree of angles with the side plate, then divide Two side plates of L-type corner brace are not separately fixed in vertical U-type cell body II and lintel U-type groove body by fixing bolt;Will product Card holding trough in woodbox 1-18 adjacent flank side surface and bottom side inserts the vertical U-type cell body II and lintel U-type groove body respectively Stuck fixation afterwards.The installation of follow-up building block brick 1-19, it is identical with the mounting means of building block brick 1-2 with building block brick 1-1.
After the installation of building block brick row (building block brick 1-18, building block brick 1-19) above left side building block brick row, start to Right building blocks row (building block brick 1-20, building block brick 1-21) installed between door body and ceiling.Building blocks row between door body and ceiling The width of door body installed as needed of columns it is actual determine, can be a row, or multiple row.If the reality of door body Width can not be arranged by the installation of monoblock building block brick and obtained, then need for the building block brick row of its rightmost side all to enter line width and cut Cut, the building block brick installed after cutting is superimposed together with the building block brick of its left and gather out the width suitable with door body.Building block brick 1- The mounting means of 20 and building block brick 1-21 is identical with the mounting means of building block brick 1-2 with building block brick 1-1.
After building blocks row installation between door body and ceiling, what is then installed is the building blocks above the building block brick row of right side Brick arranges (building block brick 1-22, building block brick 1-23), is first hung down on the right side of building block brick row (building block brick 1-20, building block brick 1-21) It is straight that vertical U-type cell body III 303 is installed, then a side plate of L-type corner brace is placed in lintel U-type groove body, it is in 90 with the side plate Another side plate for spending angle is posted by the bottom land of vertical U-type cell body III 303, then passes through fixing bolt respectively by the two of L-type corner brace Individual side plate is separately fixed in vertical U-type cell body III 303 and lintel U-type groove body;By building block brick 1-22 adjacent flank side surface and bottom Card holding trough on side inserts stuck fixation after the vertical U-type cell body III 303 and lintel U-type groove body 8 respectively.
Building block brick 1-9 is the lower section building block brick of last block building block brick 1-24, and building block brick 1-23 is last block building block brick The left building block brick of 1-24, the installation of this two pieces of building block bricks will coordinate the installation of last block building block brick 1-24 to carry out.First will product Woodbox 1-9 is fixed on vertical metope, stretchable locking U-type groove body I by the side of wall by the stretchable clamp of locking U-type groove body I Up it is vertically mounted on vertical metope along vertical U-type cell body V, the stretchable locking U-type groove body I vertically extends; Stretchable locking U-type groove body II is horizontally arranged at the upper side of building block brick 1-22, the notch of stretchable locking U-type groove body II to On, extend along horizontal direction;
The stretchable locking U-type groove body I and stretchable locking U-type groove body II include the first latch fitting 51 and the second latch fitting 52, the section of the first latch fitting 51 is U-shaped, and the latch fitting 52 of first latch fitting 51 and second can be inserted into the card holding trough of building block brick 1 Fixed with the clamp of the building block brick 1 in 11;
Second latch fitting 52 is mutually placed in first latch fitting 51, and the direction that second latch fitting 52 extends along end can Slip is pulled out in first latch fitting 51;First latch fitting 51 is provided with limiting section 511, and second latch fitting 52 is provided with card division 521, the cocker of the card division 521 is butted in the limiting section 511, and second latch fitting 52 is by the card division 521 and the limit The setting in position portion 511 is irreversible spacing and can pull out in first latch fitting 51;
Then, last block building block brick 1-24 is put into its installation site;By the second lock of stretchable locking U-type groove body I Part is pulled out upwards, inserts solid with last block building block brick 1-24 lockings in the card holding trough 11 of last block building block brick 1-24 flank side surface It is fixed;Stretchable locking U-type groove body II is pulled out to the right, insert in the card holding trough of last block building block brick 1-24 downsides with it is last One piece of building block brick 1-24 is locked.
Know-why of the invention is described above in association with specific embodiment.These descriptions are intended merely to explain of the invention Principle, and can not by any way be construed to limiting the scope of the invention.Based on explanation herein, the technology of this area Personnel associate other specific embodiments of the invention by would not require any inventive effort, these modes fall within Within protection scope of the present invention.

Claims (10)

1. a kind of form of construction work for building wall system, it is characterised in that:Comprise the following steps:
First, the installation of same row building block brick, is carried out, 1 successively from the bottom up) first piece of building block brick is first installed, on vertical metope Vertical U-type cell body I is installed, the notch of the vertical U-type cell body I is outside;On the level ground joined with the vertical metope Horizontally U-shaped cell body I is installed, the notch of the horizontally U-shaped cell body I is upward, and its side end face props up the vertical U-type cell body I The outer face of avris plate, the vertical U-type cell body I and horizontally U-shaped cell body I form 90 degree of right angles;First piece of building block brick is adjacent Flank side surface and bottom side on card holding trough insert the vertical U-type cell body I and the fixation of horizontally U-shaped cell body I respectively;
2) second piece of building block brick is installed, horizontally U-shaped cell body II, the horizontally U-shaped groove is installed in first piece of upper side of building block brick The notch of body II is upward, and its end side surface props up the outer face of the avris plate of the vertical U-type cell body I;
One side plate of L-type corner brace is placed in the horizontally U-shaped cell body II, with the side plate in 90 degree of another side plates of angle It is posted by the bottom land of vertical U-type cell body I, then two side plates of L-type corner brace is separately fixed at by vertical U by fixing bolt respectively In type groove body I and horizontally U-shaped cell body II;
Card holding trough on second piece of building block brick adjacent bottom side and flank side surface is inserted into the vertical U-type cell body I and water respectively It is fixed in flat U-type groove body II;
3) since the 3rd piece of building block brick, the installation between every piece of building block brick and previous piece of building block brick is fixed all according to second piece of product Installation steps between woodbox and first piece of building block brick are carried out;
2nd, the building block brick of an adjacent row is installed, and vertical U-type cell body is installed on the vertical side of mounted adjacent bricks brick row II, then building block brick is installed successively from the bottom up, installation steps are identical with the installation steps of above-mentioned same row building block brick;
Built wall is turned left from left to right or from the right side and install by column between the vertical metope in two sides.
2. the form of construction work for building wall system according to claim 1, it is characterised in that:Also include gating operation, by setting Position of the door operation to needing to install door body on built wall is left a blank, and the gating operation is comprised the following steps:
A) the right and left for the position of leaving a blank for installing door body in the planning of built wall is respectively mounted left side building block brick row and right side product Woodbox is arranged, and the left side building block brick row and right side building block brick row are relied on by some building block bricks, U-type groove body and L-type corner brace respectively With each adjacent building block brick row, installed upwards successively according to step one (2) and step one (3), to obtain height and required peace The left side building block brick row that the height of the door body of dress is suitable are arranged with right side building block brick, and between left side building block brick row and right side building block brick are arranged Every horizontal range it is suitable with the width of door body;
B) by lintel U-type groove body across the upper side for being fixed on the left side building block brick row and right side building block brick row, the lintel U Between the opening upwards of type groove body, and the low order end of the high order end and right side building block brick row of its length and left side building block brick row Horizontal range it is suitable;
C) up continue to install successively building block brick row since lintel U-type groove body, connect until with ceiling, mounting means and step Rapid one (2) and step one (3) it is identical, the weight of building block brick between door body and ceiling is born in the middle part of lintel U-type groove body.
3. wall mounting means according to claim 2, it is characterised in that:Built wall most left upper end or most upper right side is The installation site of last block building block brick, last block building block brick is comprised the following steps when installing:1) lower section building block brick is leaned on into wall Side vertical metope is fixed on by the stretchable clamp of locking U-type groove body I, the stretchable locking U-type groove body I is vertically Extend;By it is left right building block brick fixed with building block brick below by stretchable locking U-type groove body II, the stretchable locking U Type groove body II is horizontally extending;
The stretchable locking U-type groove body I and stretchable locking U-type groove body II include the first latch fitting and the second latch fitting, first The section of latch fitting is U-shaped, first latch fitting and the second latch fitting can be inserted into the card holding trough of building block brick with the building block brick Clamp is fixed;
Second latch fitting is mutually placed in first latch fitting, second latch fitting extend along end direction slidably pull out in First latch fitting;First latch fitting is provided with limiting section, and second latch fitting is provided with card division, and the card division cocker is butted on described In limiting section, second latch fitting is irreversible spacing by the setting of the card division and the limiting section and can pull out in described First latch fitting;
2) last block building block brick is put into its installation site;
3) the second latch fitting of stretchable locking U-type groove body I is pulled out upwards, inserts the card holding trough of last block building block brick flank side surface It is interior to be locked with last block building block brick;By stretchable locking U-type groove body II to the left right pull-out, insert last block building blocks It is locked with last block building block brick in the card holding trough of brick downside.
4. the form of construction work for building wall system according to claim 3, it is characterised in that:The section of second latch fitting is in U Font section;First latch fitting contacts with each other with the bottom surface of the second latch fitting, and the elongated end of second latch fitting protrudes from described The end of the first latch fitting;
The limiting section of some mounting holes and projection is arranged in the bottom surface of first latch fitting;
The bottom surface of second latch fitting is provided with the card division and mounting groove, and the mounting groove is used for mounting hole described in empty avoiding, described Mounting groove is located at the middle part of the bottom surface of second latch fitting, and it is opened up along the axis direction of the bottom surface of second latch fitting, At least provided with 2,2 card divisions are respectively positioned at the both sides of the mounting groove for the card division;
The base of the side wall of the elongated end of second latch fitting is provided with push rod, and the push rod is used to pull out second latch fitting.
5. the form of construction work for building wall system according to claim 3, it is characterised in that:The two side of first latch fitting exists Mounting groove is respectively arranged with vertical direction, the base of the outer surface of its two side is provided with the extension slot of horizontal direction fluting, The inwall of the mounting groove is horizontally arranged to be provided with some limiting sections, the bottom of first latch fitting be provided for lock ground or Lock the mounting hole of wall;
The plate face of second latch fitting is provided with the card division, and second latch fitting is provided with two, and second latch fitting is pacified respectively Loaded in the mounting groove, and its card division for setting is limited in mounting groove in some limiting sections, a plate of second latch fitting Side is located at the bottom of the mounting groove, and its another edges of boards is provided with concordant portion, and the concordant portion protrudes from the mounting groove, and its The width B in concordant portion described in both sides is equal to the width of first latch fitting;
Second latch fitting can draw from the end of the mounting groove and remove, and the limiting section is received in the card division of second latch fitting Limitation, when the previous limiting section is crossed in the card division, second latch fitting can not be moved inversely by the card division again It is stuck in the previous limiting section;
Also include push rod, the push rod is provided with 2, and two push rods are each passed through the extension slot and are connected to described second The bottom of the side wall of latch fitting;Second latch fitting is moved along the extension slot by the push rod and is dragged out the installation Groove.
6. the form of construction work for building wall system according to claim 3, it is characterised in that:Last block building block brick is inhaled by sucker It is attached, last block building block brick is put into by its installation site by mobile sucker.
7. the form of construction work for building wall system according to claim 1, it is characterised in that:The building block brick is slim hexahedron Structure, two larger faces are surface, and four less faces are side, and each described side is provided with two card holding troughs and one Portion's projection, the card holding trough runs through the whole side, and the middle part projection is the platform between two card holding troughs;
The U-type groove body is metal material, and it includes trough floor and two avris plates, and avris plate described in two is individually fixed in described The two ends of trough floor, and the upper end of avris plate described in two gathers to the inside of the U-type groove body, the trough floor is provided with and runs through The mounting hole of its upper and lower two plate face;
The avris plate inserts the card holding trough, to realize the fixation of the U-type groove body and building block brick.
8. the form of construction work for building wall system according to claim 7, it is characterised in that:The corner of the building block brick passes through L Type corner brace is fixed with the corner of adjacent bricks brick;
The L-type corner brace includes two side plates, and two side plates vertically fix the angular of 90 degree of formation by respective one end Structure;The side plate is provided with the fixed via through its upper and lower two plate face;The width of the width of the side plate and the U-type groove body Degree is suitable so that the side plate can be just put into the U-type groove body;
U-type groove body described in two is installed on the orthogonal two sides of the building block brick, two side plates point of the L-type corner brace respectively The orthogonal two sides of the building block brick are not attached at, and the lateral surface of two side plates is attached at the U-type groove body Madial wall.
9. the form of construction work for building wall system according to claim 7, it is characterised in that:In the length side of the middle part projection To two ends, be designed with corner brace erecting bed;The corner brace erecting bed is by the upper end of the middle part projection towards the building block brick Inner recess is formed so that when mounted, the madial wall of its side plate is affixed on the corner brace erecting bed, the side to the L-type corner brace The lateral wall of plate is in the same plane with the side of building block brick.
10. the form of construction work for building wall system according to claim 8 or claim 9, it is characterised in that:The both sides of the L-type corner brace The length of plate is unequal.
CN201611247307.7A 2016-12-29 2016-12-29 A kind of form of construction work for building wall system Expired - Fee Related CN106760045B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611247307.7A CN106760045B (en) 2016-12-29 2016-12-29 A kind of form of construction work for building wall system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611247307.7A CN106760045B (en) 2016-12-29 2016-12-29 A kind of form of construction work for building wall system

Publications (2)

Publication Number Publication Date
CN106760045A true CN106760045A (en) 2017-05-31
CN106760045B CN106760045B (en) 2019-04-23

Family

ID=58929403

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611247307.7A Expired - Fee Related CN106760045B (en) 2016-12-29 2016-12-29 A kind of form of construction work for building wall system

Country Status (1)

Country Link
CN (1) CN106760045B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108978959A (en) * 2018-09-27 2018-12-11 彭国洪 Frame shape glass assembles the wall of casting foamed cement

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN86102682A (en) * 1986-03-19 1987-11-11 费尔南德斯·纳瓦罗·洛伦索 Method and process for constructing a flexible building or the like
CN1189561A (en) * 1997-01-27 1998-08-05 环境建筑技术有限公司 Building construction method
CA2254003C (en) * 1997-12-12 2006-07-18 Bradley S. Dressler Holder for adjustable positioning of reinforcing rods
CN2883533Y (en) * 2006-02-22 2007-03-28 王建国 Building-block bricks
CN200975039Y (en) * 2006-06-02 2007-11-14 孙林柱 Wall structural formed by multifunctional shaped building blocks
CN201137234Y (en) * 2007-07-13 2008-10-22 邝文达 Building block brick and its splicing structure
CN101775858A (en) * 2004-07-07 2010-07-14 汪荣勋 Wall body structure formed by building block
US8800230B2 (en) * 2005-06-22 2014-08-12 Daniel O'Connor Stacking masonry block system with transition block and utility groove running therethrough
CN203961052U (en) * 2014-07-07 2014-11-26 刁铁城 A kind of new type block wall body structure
WO2015192764A1 (en) * 2014-06-18 2015-12-23 段炼山 Hollow building block and wall built by using same

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN86102682A (en) * 1986-03-19 1987-11-11 费尔南德斯·纳瓦罗·洛伦索 Method and process for constructing a flexible building or the like
CN1189561A (en) * 1997-01-27 1998-08-05 环境建筑技术有限公司 Building construction method
CA2254003C (en) * 1997-12-12 2006-07-18 Bradley S. Dressler Holder for adjustable positioning of reinforcing rods
CN101775858A (en) * 2004-07-07 2010-07-14 汪荣勋 Wall body structure formed by building block
US8800230B2 (en) * 2005-06-22 2014-08-12 Daniel O'Connor Stacking masonry block system with transition block and utility groove running therethrough
CN2883533Y (en) * 2006-02-22 2007-03-28 王建国 Building-block bricks
CN200975039Y (en) * 2006-06-02 2007-11-14 孙林柱 Wall structural formed by multifunctional shaped building blocks
CN201137234Y (en) * 2007-07-13 2008-10-22 邝文达 Building block brick and its splicing structure
WO2015192764A1 (en) * 2014-06-18 2015-12-23 段炼山 Hollow building block and wall built by using same
CN203961052U (en) * 2014-07-07 2014-11-26 刁铁城 A kind of new type block wall body structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108978959A (en) * 2018-09-27 2018-12-11 彭国洪 Frame shape glass assembles the wall of casting foamed cement

Also Published As

Publication number Publication date
CN106760045B (en) 2019-04-23

Similar Documents

Publication Publication Date Title
US10837166B2 (en) Building structure and construction method for same
CN101573495B (en) Novel building and construction method and device thereof
CN103541463B (en) Wallboard and shear wall allowing floor location provided with post-pouring belt comprising same and construction method for shear wall
CN207392526U (en) A kind of concrete light hollow wall panel connection structure
CN104631631A (en) Method and structure for fixedly sealing seam between infill wall and beam or board
CN106760045A (en) A kind of form of construction work for building wall system
US3130500A (en) Masonry guides
RU156105U1 (en) LIGHTHOUSE MOUNTING DEVICE
CN113502944A (en) PC exterior wall cladding structure and construction process thereof
CN106522413B (en) Build the mounting means of last block building block brick in wall system
CN101985857B (en) Method and structure for mounting high and large space clean room
CN205804710U (en) A kind of universal body of wall top installation component
CN213508961U (en) Cement concrete prefabricated part assembly structure
CN210858012U (en) Building templates link for civil engineering
CN213980025U (en) Thermal insulation building block for thermal insulation layer transformed from old city
CN204475514U (en) A kind of building structure
CN203546945U (en) Wallboard and shear wall with post-cast strip at floor position composed of wallboard
CN206844335U (en) A kind of anti-vibration house external wall structure
CN214786150U (en) Light gauge steel gypsum board furred ceiling false keel interval control device
RU121828U1 (en) CONSTRUCTION MODULE
CN206360147U (en) A kind of building block brick and build wall system using it
RU2597650C1 (en) Formwork shield frame
CN216515659U (en) Geotechnical engineering investigation is with rectangle supporting device
KR200494014Y1 (en) Fireproof cladding assembly for easy construction
CN204475512U (en) A kind of main house body structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190423

CF01 Termination of patent right due to non-payment of annual fee