CN106759552A - One kind simulation calcareous sand ground piling process Particle Breakage pilot model apparatus and its test method - Google Patents

One kind simulation calcareous sand ground piling process Particle Breakage pilot model apparatus and its test method Download PDF

Info

Publication number
CN106759552A
CN106759552A CN201710052465.5A CN201710052465A CN106759552A CN 106759552 A CN106759552 A CN 106759552A CN 201710052465 A CN201710052465 A CN 201710052465A CN 106759552 A CN106759552 A CN 106759552A
Authority
CN
China
Prior art keywords
soil sample
pile
model
soil
chamber
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710052465.5A
Other languages
Chinese (zh)
Other versions
CN106759552B (en
Inventor
肖鹏
肖杨
向佳
冉进瑜
何想
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing University
Original Assignee
Chongqing University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing University filed Critical Chongqing University
Priority to CN201710052465.5A priority Critical patent/CN106759552B/en
Publication of CN106759552A publication Critical patent/CN106759552A/en
Application granted granted Critical
Publication of CN106759552B publication Critical patent/CN106759552B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures

Abstract

Invention provides a kind of simulation calcareous sand ground piling process Particle Breakage pilot model apparatus and its test method.The device includes freeze thawing model casing, kind of refrigeration cycle instrument, pile sinking loading device and reaction frame.Freeze thawing model casing includes refrigerating chamber and soil sample chamber.Soil sample chamber is bolted on inside refrigerating chamber.Using the test method of the device steps such as sample, pile sinking loading, soil sample freezing, sampling defrosting and Parameter analysis are filled including model casing.The present invention can simulate calcareous sand ground in soil compaction during pile driving or the Particle Breakage process of piling process stake bottom and pile peripheral earth, and soil around pile sample is obtained well, can be studied malm and be restrained with evolution isotactic by the Particle Breakage after soil compaction effect, variable density, level.

Description

One kind simulation calcareous sand ground piling process Particle Breakage pilot model apparatus and its examination Proved recipe method
Technical field
The present invention relates to civil engineering experimental technique field, more particularly to a kind of simulation calcareous sand ground piling process particle Crushing test model equipment and its test method.
Background technology
China just builds at the Efforts To Develop South Sea, actively realizes the strategic objective of " building ocean power ", and calcareous sand is A kind of subsoil soil for being distributed widely in China South Sea region, it is by a kind of marine organisms origin cause of formation, internal porous gap, shape Irregular Special Rock medium, therefore, the research to calcareous sand helps speed up the process of South Sea construction, with very great Strategic importance.Pile foundation is the method for processing foundation commonly used in engineering construction, and it has high capacity, convenient, cost of constructing Low series of advantages.There is the characteristic that Particle Breakage easily occurs in itself yet with calcareous sand, enter in South Sea calcareous sand area Row pile foundation engineering is built, particularly during prefabricated pile piling, because Impact Load or soil compaction effect cause stake week There is Particle Breakage in the soil body, the Particle Breakage of the soil body matches somebody with somebody the level for changing the soil body, the packing of the soil body, so as to further influence stake The bearing capacity of base, therefore, the Particle Breakage situation of prefabricated pile pile peripheral earth during piling in calcareous sand ground is determined to grinding The bearing capacity of pile foundation for studying carefully calcareous sand ground has very important significance, and to the stress test of stake Soil Interface in existing research Research is less, and the Particle Breakage that pile-soil interaction causes more is studied without special experimental rig.Therefore, it is empty to fill up this In vain, a kind of simulation calcareous sand ground piling process Particle Breakage pilot model apparatus and test method are developed as not allowing at a quarter Slow work.
The content of the invention
Present invention aim to address prefabricated pile cannot be determined in piling process in the pile foundation process of construction of calcareous sand ground The problem of pile peripheral earth Particle Breakage situation, there is provided one kind simulation calcareous sand ground piling process Particle Breakage pilot model apparatus And test method.
The technical scheme used to realize the object of the invention is such, one kind simulation calcareous sand ground piling process Grain crushing test model equipment, including it is fixed on reaction frame and freeze thawing model casing on experimental bench.
The lower surface of the reaction frame top cross-bar is provided with pile sinking loading device.The pile sinking loading device lower end can be with Model Pile is connected, and drives Model Pile along lengthwise movement.Temperature sensor is provided with the Model Pile.
The freeze thawing model casing is arranged in area of reaction frame test center.The freeze thawing model casing includes refrigerating chamber and soil sample Room.
The soil sample chamber is the open rectangular box in upper end.The soil sample chamber is made up of metal heat-conducting material.The soil sample Temperature sensor is equipped with room bottom and inwall.The refrigerating chamber is the rectangular box with top cover.The refrigerating chamber by every Hot material is made.
The soil sample chamber is arranged in the inner chamber of refrigerating chamber.The soil sample chamber bottom is fixedly connected with refrigerating chamber bottom.Institute State and space S is formed between refrigerating chamber and soil sample chamber.Freezing liquid is marked with the space S.The refrigerating chamber passes through metal cooling-pipe Connected with kind of refrigeration cycle instrument.During experiment, freezing liquid is circulated between space S and kind of refrigeration cycle instrument.
One kind simulation calcareous sand ground piling process Particle Breakage pilot model apparatus, it is characterised in that including being fixed on Reaction frame and freeze thawing model casing on experimental bench.
The lower surface of the reaction frame top cross-bar is provided with pile sinking loading device.The pile sinking loading device lower end can be with Model Pile is connected, and drives Model Pile along lengthwise movement.Temperature sensor is provided with the Model Pile.
The freeze thawing model casing is arranged in area of reaction frame test center.The freeze thawing model casing includes refrigerating chamber and soil sample Room.
The soil sample chamber is that upper end is open and interior hollow staving.The soil sample chamber is made up of metal heat-conducting material.It is described Temperature sensor is equipped with soil sample chamber bottom and inwall.The refrigerating chamber is the hollow staving with top cover.The refrigerating chamber It is made up of heat-barrier material.
The soil sample chamber is arranged in the inner chamber of refrigerating chamber.The soil sample chamber bottom is fixedly connected with refrigerating chamber bottom.Institute State and space S is formed between refrigerating chamber and soil sample chamber.Freezing liquid is marked with the space S.The refrigerating chamber passes through metal cooling-pipe Connected with kind of refrigeration cycle instrument.During experiment, freezing liquid is circulated between space S and kind of refrigeration cycle instrument.
Further, the pile sinking loading device includes electric loading system device, drive link and Model Pile erecting bed.Wherein, institute State drive link and be arranged on electric loading system device lower section, Model Pile erecting bed is arranged on drive link lower end.The Model Pile erecting bed It is upper that there is air level.The Model Pile erecting bed lower surface has fixed screw-cap.During experiment, the fixed screw-cap of Model Pile insertion In reserved model stake holes, and it is bolted on Model Pile erecting bed by tightening.Electric loading system device drives drive link edge Lengthwise movement, then drives Model Pile motion.
Further, the stake footpath of the Model Pile is 10mm~30mm, and length is 100~300mm;The kind of refrigeration cycle instrument Temperature-control range is between -20 DEG C~80 DEG C.
Further, the length of the soil sample chamber is a, and width is b, is highly c, and wall thickness is d.Wherein, a=400~ 600mm, b=400~600mm, c=500~700mm, d=5~10mm.The refrigerating chamber length is 900mm, and width is 900mmmm, is highly 800mm, and wall thickness is 10mm.
Further, the soil sample chamber and the reserved screw of refrigerating chamber bottom correspondence position.The soil sample chamber and refrigerating chamber pass through Bolt is fixedly connected.
Invention additionally discloses a kind of on above-mentioned simulation calcareous sand ground piling process Particle Breakage pilot model apparatus Test method, comprises the following steps:
1) according to predetermined level is with preparation calcareous sand and is well mixed.
2) calcareous sand soil sample is loaded in soil sample chamber using sand rain method, and appropriate water is poured into according to required saturation degree and formed Calcareous sand soil layer.Wherein, the packed height of calcareous sand soil sample is 300~500mm.
3) model pile verticality is adjusted, Model Pile is fixed on pile sinking loading device lower end.
4) start-up loading device, is pressed into calcareous sand soil layer set depth by Model Pile as requested.
5) cover plate of refrigerating chamber is covered, it is -10 DEG C to set kind of refrigeration cycle instrument temperature, starts kind of refrigeration cycle instrument until soil sample chamber With the temperature sensor temperature stabilization in Model Pile to setting value.
6) kind of refrigeration cycle instrument is closed, the cover plate of refrigerating chamber is opened, the calcium of piles with different footpath and stake bottom scope is taken out with soil sampler Matter sand sample, measures the volume and quality of soil sample, soil sample then is put into baking oven and is toasted 24 hours at 60 DEG C.
7) after soil sample drying, a separating tests is carried out by oscillating sieving machine, can obtain calcareous sand at piles with different footpath point Curve.
Further, the soil sampler is square soil sampler.The square soil sampler is the hollow rectangular of upper and lower side opening Body.This cuboid 20~150mm long, 20~150mm wide, 100~600mm high.The hollow cuboid upper and lower side open-mouth It is respectively provided with sharp metal cutter.
Further, the soil sampler is circular soil sampler.The circular soil sampler is the open hollow circuit cylinder of upper and lower side Body.The internal diameter of this hollow circular cylinder is 39.1~50.1mm, is highly 80~100mm.The hollow circular cylinder upper and lower side is opened Sharp metal cutter is respectively provided with mouthful.
The solution have the advantages that unquestionable:
A. this model equipment can be very good to simulate the piling process of prefabricated pile in calcareous Flooding in Borehole pile foundation engineering, by system SAPMAC method instrument freezes soil sample so as to obtain complete calcareous sand soil sample, and the particle undergone after pile foundation treatment with studying calcareous Flooding in Borehole breaks Broken situation, level effectively solve calcareous sand ground piling pile week and the stake ground soil body with evolution and variable density Experimental study on particle breakage problem;
B. this model equipment can use cooperatively different soil samplers, can be very good to obtain the calcareous sand at piles with different footpath Sample, so as to preferably study the Particle Breakage of calcareous Flooding in Borehole with the situation of change in stake footpath;
C. this model equipment simulates different packings, different saturation calcareous sand ground, different-diameter, difference as needed Pile-type and different pile sinking loading speeds can be provided, applicability is wide.
Brief description of the drawings
Fig. 1 is model equipment structural representation;
Fig. 2 is freeze thawing model casing operating diagram;
Fig. 3 is freeze thawing mold box configuration schematic diagram;
Fig. 4 is heavy dress loading device structural representation;
Fig. 5 is square sampler structure schematic diagram;
Fig. 6 is circular sampler structure schematic diagram.
In figure:Space S, refrigerating chamber 1, top cover 101, soil sample chamber 2, calcareous sand soil layer 3, soil sampler 4, Model Pile 5, freezing liquid 7th, pile sinking loading device 8, electric loading system device 801, drive link 802, Model Pile erecting bed 803, air level 8031, fixed spiral Cap 8032, reaction frame 9, kind of refrigeration cycle instrument 10, experimental bench 11, metal cooling-pipe 12.
Specific embodiment
With reference to embodiment, the invention will be further described, but should not be construed above-mentioned subject area of the invention only It is limited to following embodiments.Without departing from the idea case in the present invention described above, according to ordinary skill knowledge and used With means, various replacements and change are made, all should included within the scope of the present invention.
Embodiment 1:
The present embodiment provides a kind of simulation calcareous sand ground piling process Particle Breakage pilot model apparatus, including is fixed on Reaction frame 9 and freeze thawing model casing on experimental bench 11.
Referring to Fig. 1, the lower surface of the top cross-bar of the reaction frame 9 is provided with pile sinking loading device 8.The pile sinking loading dress Putting 8 lower ends can be connected with Model Pile 5, drive Model Pile 5 along lengthwise movement.The pile sinking loading device 8 can provide constant adding Speed and constant pressure are carried, to simulate knocking pile sinking and static pressure pile-sinking.Temperature sensor is provided with the Model Pile 5.
The freeze thawing model casing is arranged in the area of test center of reaction frame 9, i.e. freeze thawing model casing is placed on pile sinking loading device 8 Lower section, and freeze thawing model casing is aligned with the center of pile sinking loading device 8.The freeze thawing model casing includes refrigerating chamber 1 and soil sample chamber 2。
Referring to Fig. 2 and Fig. 3, the soil sample chamber 2 is that upper end is open and interior hollow rectangular box.The soil sample chamber 2 is by gold Category Heat Conduction Material is made.Temperature sensor is equipped with the bottom of the soil sample chamber 2 and inwall.The refrigerating chamber 1 is with top cover 101 hollow, rectangular casing.The refrigerating chamber 1 is made up of heat-barrier material.
The soil sample chamber 2 is arranged in the inner chamber of refrigerating chamber 1.The soil sample chamber 2 and the bottom correspondence position of refrigerating chamber 1 are reserved Screw.The soil sample chamber 2 and refrigerating chamber 1 are bolted to connection.Space S is formed between the refrigerating chamber 1 and soil sample chamber 2. Freezing liquid 7 is marked with the space S.The refrigerating chamber 1 is connected by metal cooling-pipe 12 with kind of refrigeration cycle instrument 10.During experiment, Freezing liquid 7 is circulated between space S and kind of refrigeration cycle instrument 10, and cold is freezed to provide in space S.
Embodiment 2:
The present embodiment provides a kind of simulation calcareous sand ground piling process Particle Breakage pilot model apparatus, including is fixed on Reaction frame 9 and freeze thawing model casing on experimental bench 11.
The lower surface of the top cross-bar of the reaction frame 9 is provided with pile sinking loading device 8.The lower end of pile sinking loading device 8 Can be connected with Model Pile 5, drive Model Pile 5 along lengthwise movement.The pile sinking loading device 8 can provide constant loading speed and Constant pressure, to simulate knocking pile sinking and static pressure pile-sinking.Temperature sensor is provided with the Model Pile 5.
The freeze thawing model casing is arranged in the area of test center of reaction frame 9, i.e. freeze thawing model casing is placed on pile sinking loading device 8 Lower section, and freeze thawing model casing is aligned with the center of pile sinking loading device 8.The freeze thawing model casing includes refrigerating chamber 1 and soil sample chamber 2。
The soil sample chamber 2 is that upper end is open and interior hollow staving.The soil sample chamber 2 is made up of metal heat-conducting material.Institute State and be equipped with temperature sensor on the bottom of soil sample chamber 2 and inwall.The refrigerating chamber 1 is the hollow staving with top cover 101.It is described Refrigerating chamber 1 is made up of heat-barrier material.
The soil sample chamber 2 is arranged in the inner chamber of refrigerating chamber 1.The soil sample chamber 2 and the bottom correspondence position of refrigerating chamber 1 are reserved Screw.The soil sample chamber 2 and refrigerating chamber 1 are bolted to connection.Space S is formed between the refrigerating chamber 1 and soil sample chamber 2. Freezing liquid 7 is marked with the space S.The refrigerating chamber 1 is connected by metal cooling-pipe 12 with kind of refrigeration cycle instrument 10.During experiment, Freezing liquid 7 is circulated between space S and kind of refrigeration cycle instrument 10, and cold is freezed to provide in space S.
Embodiment 3:
The present embodiment provides a kind of simulation calcareous sand ground piling process Particle Breakage pilot model apparatus, including is fixed on Reaction frame 9 and freeze thawing model casing on experimental bench 11.
Referring to Fig. 1, the lower surface of the top cross-bar of the reaction frame 9 is provided with pile sinking loading device 8.
Referring to Fig. 4, the pile sinking loading device 8 includes electric loading system device 801, drive link 802 and Model Pile erecting bed 803.Wherein, the drive link 802 is arranged on the lower section of electric loading system device 801, and Model Pile erecting bed 803 is arranged on drive link 802 lower ends.The electric loading system device is that stress-strain controls formula, it is possible to provide constant loading speed and constant pressure, with Simulation knocking pile sinking and static pressure pile-sinking.The lower surface of Model Pile erecting bed 803 has fixed screw-cap 8032.Model Pile 5 is inserted In entering the reserved model stake holes of fixed screw-cap 8032, and it is bolted on Model Pile erecting bed 803 by tightening.The mould Also there is air level 8031 on type stake erecting bed 803, to ensure the perpendicularity of model sunk pile.The stake footpath of the Model Pile 5 is 10mm, length is 100mm.Temperature sensor is provided with the Model Pile 5.During experiment, electric loading system device 801 drives transmission Bar 802 then drives Model Pile 5 along lengthwise movement along lengthwise movement.
The freeze thawing model casing is arranged in the area of test center of reaction frame 9, i.e. freeze thawing model casing is placed on pile sinking loading device 8 Lower section, and freeze thawing model casing is aligned with the center of pile sinking loading device 8.The freeze thawing model casing includes refrigerating chamber 1 and soil sample chamber 2。
Referring to Fig. 2 and Fig. 3, the soil sample chamber 2 is the open rectangular box in upper end.The soil sample chamber 2 is by metal heat-conducting material Material is made.Temperature sensor is equipped with the bottom of the soil sample chamber 2 and inwall.The refrigerating chamber 1 is the rectangle with top cover 101 Casing.The refrigerating chamber 1 is made up of heat-barrier material.
The soil sample chamber 2 is arranged in the inner chamber of refrigerating chamber 1.The bottom of the soil sample chamber 2 is fixed with the bottom of refrigerating chamber 1 and is connected Connect.Space S is formed between the refrigerating chamber 1 and soil sample chamber 2.Freezing liquid 7 is marked with the space S.The refrigerating chamber 1 is by gold Category cooling tube 12 is connected with kind of refrigeration cycle instrument 10.During experiment, freezing liquid 7 is circulated between space S and kind of refrigeration cycle instrument 10, Freeze cold to provide in space S.
What deserves to be explained is, in the present embodiment, the length of soil sample chamber 2 is 500mm, and width is 400mm, is highly 600mm, Wall thickness is 10mm.The length of refrigerating chamber 1 is 900mm, and width is 900mmmm, is highly 800mm, and wall thickness is 10mm.Kind of refrigeration cycle instrument 10 temperature-control range is between -20 DEG C~80 DEG C.
Embodiment 4:
The present embodiment discloses a kind of on simulating the piling process Particle Breakage experiment of calcareous sand ground described in embodiment 1 or 2 The test method of model equipment, comprises the following steps:
1) according to predetermined level is with preparation calcareous sand and is well mixed.
2) calcareous sand soil sample is loaded in soil sample chamber 2 using sand rain method, and appropriate water shape is poured into according to required saturation degree Into calcareous sand soil layer 3.Wherein, the packed height of calcareous sand soil sample 3 is 300~500mm.
3) perpendicularity of Model Pile 5 is adjusted, Model Pile 5 is fixed on the lower end of pile sinking loading device 8.
4) start-up loading device, is pressed into the set depth of calcareous sand soil layer 3 by Model Pile 5 as requested.
5) cover plate 101 of refrigerating chamber 1 is covered, it is -10 DEG C to set kind of refrigeration cycle instrument temperature, starts kind of refrigeration cycle instrument until soil Temperature sensor temperature stabilization in specimen chamber 2 and Model Pile 5 is to setting value.
6) kind of refrigeration cycle instrument is closed, the cover plate of refrigerating chamber 1 is opened, piles with different footpath and stake bottom scope is taken out with soil sampler 4 Calcareous sand soil sample, measures the volume and quality of soil sample, soil sample then is put into baking oven and is toasted 24 hours at 60 DEG C.Wherein, institute Soil sampler 4 is stated for square soil sampler.Referring to Fig. 6, the square soil sampler is the open hollow cuboid of upper and lower side.This length Cube 100mm long, 70mm wide, 200mm high.The hollow cuboid upper and lower side open-mouth is respectively provided with sharp metal cutter.
7) after soil sample drying, a separating tests is carried out by oscillating sieving machine, can obtain calcareous sand at piles with different footpath point Curve.
Embodiment 5:
The present embodiment discloses a kind of on simulating the piling process Particle Breakage experiment of calcareous sand ground described in embodiment 1 or 2 The test method of model equipment, comprises the following steps:
1) according to predetermined level is with preparation calcareous sand and is well mixed.
2) calcareous sand soil sample is loaded in soil sample chamber 2 using sand rain method, and appropriate water shape is poured into according to required saturation degree Into calcareous sand soil layer 3.Wherein, the packed height of calcareous sand soil sample 3 is 300~500mm.
3) perpendicularity of Model Pile 5 is adjusted, Model Pile 5 is fixed on the lower end of pile sinking loading device 8.
4) start-up loading device, is pressed into the set depth of calcareous sand soil layer 3 by Model Pile 5 as requested.
5) cover plate 101 of refrigerating chamber 1 is covered, it is -10 DEG C to set kind of refrigeration cycle instrument temperature, starts kind of refrigeration cycle instrument until soil Temperature sensor temperature stabilization in specimen chamber 2 and Model Pile 5 is to setting value.
6) kind of refrigeration cycle instrument is closed, the cover plate of refrigerating chamber 1 is opened, piles with different footpath and stake bottom scope is taken out with soil sampler 4 Calcareous sand soil sample, measures the volume and quality of soil sample, soil sample then is put into baking oven and is toasted 24 hours at 60 DEG C.Wherein, institute It is circular soil sampler to state soil sampler.Referring to Fig. 5, the circular soil sampler is the open hollow circular cylinder of upper and lower side.In this The internal diameter of hollow cylinder is 39.1mm, is highly 80mm.The hollow circular cylinder upper and lower side open-mouth is respectively provided with sharp metal Cutting knife.
7) after soil sample drying, a separating tests is carried out by oscillating sieving machine, can obtain calcareous sand at piles with different footpath point Curve.
Embodiment 6:
The present embodiment discloses a kind of on simulating calcareous sand ground piling process Particle Breakage test model described in embodiment 3 The test method of device, comprises the following steps:
1) according to predetermined level is with preparation calcareous sand and is well mixed.
2) calcareous sand soil sample is loaded in soil sample chamber 2 using sand rain method, and appropriate water shape is poured into according to required saturation degree Into calcareous sand soil layer 3.Wherein, the packed height of calcareous sand soil sample 3 is 300~500mm.
3) during Model Pile 5 to be inserted the preformed hole of the lower end screw-cap 6 of pile sinking loading device 8, after the adjustment perpendicularity of Model Pile 5 Model Pile 5 is fixed by bolt.
4) start-up loading device, is pressed into the set depth of calcareous sand soil layer 3 by Model Pile 5 as requested.
5) cover plate 101 of refrigerating chamber 1 is covered, it is -10 DEG C to set kind of refrigeration cycle instrument temperature, starts kind of refrigeration cycle instrument until soil Temperature sensor temperature stabilization in specimen chamber 2 and Model Pile 5 is to setting value.
6) kind of refrigeration cycle instrument is closed, the cover plate of refrigerating chamber 1 is opened, piles with different footpath and stake bottom scope is taken out with soil sampler 4 Calcareous sand soil sample, measures the volume and quality of soil sample, soil sample then is put into baking oven and is toasted 24 hours at 60 DEG C.
7) after soil sample drying, a separating tests is carried out by oscillating sieving machine, can obtain calcareous sand at piles with different footpath point Curve.

Claims (9)

1. it is a kind of to simulate calcareous sand ground piling process Particle Breakage pilot model apparatus, it is characterised in that including being fixed on reality The reaction frame (9) and freeze thawing model casing tested on platform (11);
The lower surface of reaction frame (9) top cross-bar is provided with pile sinking loading device (8);Under the pile sinking loading device (8) End can be connected with Model Pile (5), drive Model Pile (5) along lengthwise movement;Temperature sensor is provided with the Model Pile (5);
The freeze thawing model casing is arranged in area of reaction frame (9) test center;The freeze thawing model casing includes refrigerating chamber (1) and soil sample Room (2);
The soil sample chamber (2) is the open rectangular box in upper end;The soil sample chamber (2) is made up of metal heat-conducting material;The soil Temperature sensor is equipped with specimen chamber (2) bottom and inwall;The refrigerating chamber (1) is the rectangular box with top cover (101);Institute Refrigerating chamber (1) is stated to be made up of heat-barrier material;
The soil sample chamber (2) is arranged in the inner chamber of refrigerating chamber (1);Soil sample chamber (2) bottom is fixed with refrigerating chamber (1) bottom Connection;Space (S) is formed between the refrigerating chamber (1) and soil sample chamber (2);Freezing liquid (7) is marked with the space (S);It is described Refrigerating chamber (1) is connected by metal cooling-pipe (12) with kind of refrigeration cycle instrument (10);During experiment, freezing liquid (7) is in space (S) and system SAPMAC method instrument is circulated between (10).
2. it is a kind of to simulate calcareous sand ground piling process Particle Breakage pilot model apparatus, it is characterised in that including being fixed on reality The reaction frame (9) and freeze thawing model casing tested on platform (11);
The lower surface of reaction frame (9) top cross-bar is provided with pile sinking loading device (8);Under the pile sinking loading device (8) End can be connected with Model Pile (5), drive Model Pile (5) along lengthwise movement;Temperature sensor is provided with the Model Pile (5);
The freeze thawing model casing is arranged in area of reaction frame (9) test center;The freeze thawing model casing include the refrigerating chamber (1) and The soil sample chamber (2);
The soil sample chamber (2) is for upper end is open and interior hollow staving;The soil sample chamber (2) is made up of metal heat-conducting material;Institute State and be equipped with temperature sensor on soil sample chamber (2) bottom and inwall;The refrigerating chamber (1) is the Hollow barrel with top cover (101) Body;The refrigerating chamber (1) is made up of heat-barrier material;
The soil sample chamber (2) is arranged in the inner chamber of refrigerating chamber (1);Soil sample chamber (2) bottom is fixed with refrigerating chamber (1) bottom Connection.Space (S) is formed between the refrigerating chamber (1) and soil sample chamber (2);Freezing liquid (7) is marked with the space (S);It is described Refrigerating chamber (1) is connected by metal cooling-pipe (12) with kind of refrigeration cycle instrument (10);During experiment, freezing liquid (7) is in space (S) and system SAPMAC method instrument is circulated between (10).
3. one kind according to claim 1 and 2 simulates calcareous sand ground piling process Particle Breakage pilot model apparatus, its It is characterised by:The pile sinking loading device (8) includes electric loading system device (801), drive link (802) and Model Pile erecting bed (803);Wherein, the drive link (802) is arranged on electric loading system device (801) lower section, and Model Pile erecting bed (803) is arranged on Drive link (802) lower end;There is air level (8031) on the Model Pile erecting bed (803);The Model Pile erecting bed (803) Lower surface is fixed with fixed screw-cap (8032);In the reserved model stake holes of the fixed screw-cap (8032) of Model Pile (5) insertion, and It is bolted on Model Pile erecting bed (803) by tightening;During experiment, electric loading system device (801) drives drive link (802) Along lengthwise movement, Model Pile (5) motion is then driven.
4. the one kind according to claim 1,2 or 3 simulates calcareous sand ground piling process Particle Breakage pilot model apparatus, It is characterized in that:The stake footpath of the Model Pile (5) is 10mm~30mm, and length is 100~300mm;The kind of refrigeration cycle instrument (10) temperature-control range is between -20 DEG C~80 DEG C.
5. one kind according to claim 1 simulates calcareous sand ground piling process Particle Breakage pilot model apparatus, and it is special Levy and be:The length of the soil sample chamber (2) is a, and width is b, is highly c, and wall thickness is d;Wherein, a=400~600mm, b= 400~600mm, c=500~700mm, d=5~10mm;Refrigerating chamber (1) length is 900mm, and width is 900mmmm, high It is 800mm to spend, and wall thickness is 10mm.
6. one kind according to claim 1 and 2 simulates calcareous sand ground piling process Particle Breakage pilot model apparatus, its It is characterised by:The soil sample chamber (2) and the reserved screw of refrigerating chamber (1) bottom correspondence position;The soil sample chamber (2) and refrigerating chamber (1) it is bolted to connection.
7. a kind of examination on simulating calcareous sand ground piling process Particle Breakage pilot model apparatus described in claim 1 or 2 Proved recipe method, it is characterised in that:Comprise the following steps:
1) according to predetermined level is with preparation calcareous sand and is well mixed;
2) calcareous sand soil sample is loaded in soil sample chamber (2) using sand rain method, and appropriate water is poured into according to required saturation degree and formed Calcareous sand soil layer (3);Wherein, the packed height of calcareous sand soil sample (3) is 300~500mm;
3) perpendicularity of adjustment Model Pile (5), Model Pile (5) is fixed on the lower end of pile sinking loading device (8);
4) start-up loading device, is pressed into calcareous sand soil layer (3) set depth by Model Pile (5) as requested;
5) cover plate (101) of refrigerating chamber (1) is covered, it is -10 DEG C to set kind of refrigeration cycle instrument temperature, starts kind of refrigeration cycle instrument until soil Temperature sensor temperature stabilization in specimen chamber (2) and Model Pile (5) is to setting value;
6) kind of refrigeration cycle instrument is closed, the cover plate of refrigerating chamber (1) is opened, piles with different footpath and stake bottom scope is taken out with soil sampler (4) Calcareous sand soil sample, measures the volume and quality of soil sample, soil sample then is put into baking oven and is toasted 24 hours at 60 DEG C;
7) after soil sample drying, a separating tests is carried out by oscillating sieving machine, can obtain a component curve of calcareous sand at piles with different footpath.
8. a kind of test method according to claim 7, it is characterised in that:The soil sampler (4) is square soil sampler;Institute It is the open hollow cuboid of upper and lower side to state square soil sampler;This cuboid 20~150mm long, 20~150mm wide are high 100~600mm;The hollow cuboid upper and lower side open-mouth is respectively provided with sharp metal cutter.
9. a kind of test method according to claim 7, it is characterised in that:The soil sampler is circular soil sampler;It is described Circular soil sampler is the open hollow circular cylinder of upper and lower side;The internal diameter of this hollow circular cylinder is 39.1~50.1mm, height It is 80~100mm;The hollow circular cylinder upper and lower side open-mouth is respectively provided with sharp metal cutter.
CN201710052465.5A 2017-01-24 2017-01-24 A kind of simulation calcareous sand ground piling process Particle Breakage pilot model apparatus and its test method Active CN106759552B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710052465.5A CN106759552B (en) 2017-01-24 2017-01-24 A kind of simulation calcareous sand ground piling process Particle Breakage pilot model apparatus and its test method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710052465.5A CN106759552B (en) 2017-01-24 2017-01-24 A kind of simulation calcareous sand ground piling process Particle Breakage pilot model apparatus and its test method

Publications (2)

Publication Number Publication Date
CN106759552A true CN106759552A (en) 2017-05-31
CN106759552B CN106759552B (en) 2018-12-18

Family

ID=58941572

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710052465.5A Active CN106759552B (en) 2017-01-24 2017-01-24 A kind of simulation calcareous sand ground piling process Particle Breakage pilot model apparatus and its test method

Country Status (1)

Country Link
CN (1) CN106759552B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20050074297A1 (en) * 2003-10-02 2005-04-07 Stoetzer Erwin Emil Method and test setup for determining the bearing behaviour of displacement piles
CN104316391A (en) * 2014-10-10 2015-01-28 同济大学 Freezing and thawing test model device and method of simulating artificial ground freezing method
CN104515734A (en) * 2014-12-16 2015-04-15 广西科技大学 Visualization simulator and simulation method for tubular pile vertical static test
CN104913977A (en) * 2015-06-18 2015-09-16 兰州交通大学 Indoor frozen soil model pile static force loading experimental device and method
CN205617449U (en) * 2016-04-18 2016-10-05 青岛理工大学 Vertical force device of simulation static pile pile sinking process
CN106245691A (en) * 2016-09-28 2016-12-21 中国科学院武汉岩土力学研究所 Calcareous sand sound load Multifunctional pile base model test apparatus

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20050074297A1 (en) * 2003-10-02 2005-04-07 Stoetzer Erwin Emil Method and test setup for determining the bearing behaviour of displacement piles
CN104316391A (en) * 2014-10-10 2015-01-28 同济大学 Freezing and thawing test model device and method of simulating artificial ground freezing method
CN104515734A (en) * 2014-12-16 2015-04-15 广西科技大学 Visualization simulator and simulation method for tubular pile vertical static test
CN104913977A (en) * 2015-06-18 2015-09-16 兰州交通大学 Indoor frozen soil model pile static force loading experimental device and method
CN205617449U (en) * 2016-04-18 2016-10-05 青岛理工大学 Vertical force device of simulation static pile pile sinking process
CN106245691A (en) * 2016-09-28 2016-12-21 中国科学院武汉岩土力学研究所 Calcareous sand sound load Multifunctional pile base model test apparatus

Also Published As

Publication number Publication date
CN106759552B (en) 2018-12-18

Similar Documents

Publication Publication Date Title
US4955237A (en) Method and apparatus for measurement of in-situ horizontal stress by freezing of the ground in-situ
Othman et al. Laboratory testing to evaluate changes in hydraulic conductivity of compacted clays caused by freeze-thaw: State-of-the-art
Singh et al. Undisturbed sampling of saturated sands by freezing
CN106592651B (en) A kind of cement mixing method model test apparatus of reducing
CN108732057A (en) Ring shear test equipment and its test method under a kind of soil body Frozen-thawed cycled and weathering environment
CN109270243A (en) Frozen-soil Blasting model assay systems and its test method
CN108362727A (en) Visualize two-way frost heave experimental bench
CN113295495A (en) Device and method for manufacturing frozen soil sample with high ice content
CN106442035B (en) Device and method for manufacturing direct shear test sample of concrete-frozen soil contact surface
CN209495911U (en) A kind of sample preparation device of Frozen-soil Blasting model test
CA2958615A1 (en) Method and means for treatment of soil
JP2020090842A (en) Methane hydrate mixed simulated ground, methane hydrate simulated ground, methane hydrate excavation simulated experimental equipment, methane hydrate mixed simulated ground manufacturing method, and methane hydrate simulated ground manufacturing method
Liu et al. A slurry consolidation method for reconstitution of triaxial specimens
CN106759552B (en) A kind of simulation calcareous sand ground piling process Particle Breakage pilot model apparatus and its test method
Swan et al. Characteristics of Chicago Blue Clay Subjected to a Freeze–Thaw Cycle
CN106124275B (en) A kind of production method and device of seabed gassiness bury
CN107476353A (en) The model test apparatus and method of anchor slab foundation anti-pulling performance in hydrate heat exploitation
CN114858847B (en) Test device and method for simulating development process of frost heaving induced cracks of lining structure
CN114112842A (en) Saturated frozen soil permeability coefficient measuring system under temperature gradient
CN209495910U (en) A kind of Frozen-thawed cycled SHPB test sample preparation device
Saowapakpiboon et al. Comparison on the performance of prefabricated vertical drain (PVD) preloading combined with and without vacuum and heat
Collins In Situ Testing and its Application to Foundation Analysis in Fine-Grained Unsaturated Soils
Villeneuve Laboratory Testing for Adfreeze Bond of Sand on Model Steel Piles
Konrad Sampling of saturated and unsaturated sands by freezing
Zhao et al. Effects of temperature gradients on elastic modulus and compression strength of the saturated frozen clay

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant